Feasibility Study Federal Inspection Service Facility at Long Beach Airport

Similar documents
3 MEETING OF THE ECONOMIC DEVELOPMENT COMMISSION

Austin-Bergstrom International Airport Master Plan Update

Airport Master Plan Update

Appendix D. FIS Facility Siting Alternatives

Tampa International Airport Master Plan Update. December 12, 2012

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

Table of Contents. Master Plan March 2014 TOC i Spokane International Airport

Love Field Modernization Program Update: Master Planning Recommendations

Alternatives. Introduction. Range of Alternatives

? 0-? WA", ilp. Y ON 1Z Cond 1 0 AIRPORT COMMISSIONERS BOARD REPORT TO THE Los Angeles World Airports 0*1-

SAN JOSE CAPITAL OF SILICON VALLEY

FORECASTING FUTURE ACTIVITY

Scoping Meeting LAX Landside Access Modernization Program

Presented by Long Beach City Attorney s Office Michael Mais, Assistant City Attorney February 17, 2015

AIRPORT MASTER PLAN FOR. charles B. WHEELER DOWNTOWN AIRPORT KANSAS CITY, MISSOURI

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3

Chapter 1 EXECUTIVE SUMMARY

SAN JOSÉ INTERNATIONAL AIRPORT

LAS VEGAS. Rosemary A. Vassiliadis Clark County Director of Aviation MCCARRAN INTERNATIONAL AIRPORT UDPATE

ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS

Preliminary Draft Budget FY Airline Rates and Charges. Sea-Tac International Airport

Economic Impact of Kalamazoo-Battle Creek International Airport

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

COMMENT PERIOD INTRODUCTION

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES

COUNTY OF ORANGE, CALIFORNIA AIRPORT REVENUE BONDS, SERIES 2009 A & B ANNUAL REPORT FOR FISCAL YEAR ENDED JUNE 30, 2013

CITY OF HOUSTON INTEROFFICE CORRESPONDENCE FROM: DATE: SUBJECT: The passenger traffic for each of the airlines for the previous 5 years.

Chapter 1 Introduction and Project Overview

The Economic Impacts of the Open Skies Initiative: Past and Future

ECONOMIC IMPACT STUDY OF CALIFORNIA AIRPORTS

Financial Proposal for Gwinnett County Airport Briscoe Field

MASTER PLAN UPDATE GRANT NUMBER

OFFICE OF THE AUDITOR

IRREGULAR OPERATIONS AIRPORT CONTINGENCY PLAN

The Law of Noise Regulation Daniel S. Reimer

Chapter 1 Introduction and Project Overview

Los Angeles Business Travel Association

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018

Nantucket Memorial Airport Commission. Master Plan Workshop. October 26, 2012

Greater Orlando Aviation Authority Orlando International Airport One Jeff Fuqua Boulevard Orlando, Florida Memorandum TO: FROM:

Planning, Development and Environment Committee

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257

FY 2018 Rates, Fees, and Charges Year End Reconciliation. Finance Department P.O. Box DFW Airport, Texas

Terminal Space and Ratemaking

Amended & Restated Lease of Terminal Building Premises (Airport Use & Lease Agreement)

msp macnoise.com MSP Noise Oversight Committee (NOC) November 17, 2010

Economic Impact of Aviation in Arizona

Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport

EXHIBIT E to Signatory Airline Agreement for Palm Beach International Airport RATE AND FEE SCHEDULE

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport


a p 0.4 f Ai RPORT COMMISSIONERS Meeting Date: \ Sk 0 /1ci / 1/1'/V BOARD..ii REPORT TO THE -...r "V:4'

Greater Orlando Aviation Authority Board Meeting. Wednesday, January 17, 2018

BOARD ITO Aide REPORT TO THE AIRPORT COMMISSIONERS

The Economic Impact of Emirates in the United States. Prepared by:

Casper/Natrona County International Airport Master Plan Update Technical Advisory Committee Meeting Two - October 14th, :30 PM

Fort McMurray International Airport


STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

AIRPORT NOISE AND CAPACITY ACT OF 1990

Finance and Implementation

The Economic Impact of Travel in Minnesota Analysis

City of Monett, Missouri. Pride and Progress. Airport Master Plan Update. for the Monett Municipal Airport

AGENCY SCOPING MEETING

Chapter 9: Financial Plan Draft

GSP TERMINAL IMPROVEMENT PROGRAM PRESS KIT

WELCOME! FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT 14 CFR PART 150 NOISE AND LAND USE COMPATIBILITY STUDY

Sunshine Coast Airport Master Plan September 2007

ESTIMATION OF ECONOMIC IMPACTS FOR AIRPORTS IN HAWTHORNE, EUREKA, AND ELY, NEVADA

TABLE OF CONTENTS. Washington Aviation System Plan Update July 2017 i

The San Diego Region s Air Transportation Future

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway

Alternatives Analysis EXECUTIVE SUMMARY

AIRPORT MASTER PLAN UPDATE

Abstract. Introduction

INTERNAL AUDIT REPORT

DOWNTOWN SAN JOSÉ AIRSPACE & DEVELOPMENT CAPACITY STUDY (PROJECT CAKE) STEERING COMMITTEE MEETING #7. Draft. November 13, 2018

Exhibit H: Statement of Overriding Considerations

Forecast and Overview

MASTER PLAN GEORGE BUSH INTERCONTINENTAL AIRPORT/HOUSTON. Houston Airport System Houston, Texas DRAFT TECHNICAL REPORT.

SERVING CALIFORNIA S COMMERCIAL AIRPORTS

Lake Tahoe Airport Master Plan

STANDARD RATES AND FEES AT BALTIMORE/WASHINGTON INTERNATIONAL THURGOOD MARSHALL (BWI MARSHALL) AIRPORT

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906

TRACK: B TERMINAL/LANDSIDE

BNA Master Plan Update Community Advisory Committee Meeting No. 5

JOHN WAYNE AIRPORT SECURITY

FLL Master Plan Update Technical Advisory Committee (TAC) Briefing #1. September 28, 2016

Federal Aviation Administration. Airport Land Use Compatibility Advisory Circular ACI-NA / FAA. FAA HQ Washington, DC March 27, 2013

Fort Lauderdale Hollywood International Airport

PUBLIC NOTICE. Table 1 Projects Proposed by Amendment

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES

SouthwestFloridaInternational Airport

The Economic Impact of the 2015 ASICS Los Angeles Marathon. September 2015

SUBJECT: DOWNTOWN AIRSPACE AND DEVELOPMENT CAPACITY STUDY REPORT FINDINGS AND RECOMMENDATIONS DATE: January 10, 2019

The Economic Impact of Tourism in Walworth County, Wisconsin. July 2013

Transcription:

Feasibility Study Federal Inspection Service Facility at Long Beach Airport 13 December 2016 Long Beach City Council PLEASE NOTE: The information, analysis, assessments and opinions contained in this presentation are intended for general evaluation purposes only. This document is intended for use only by its specified client and is NOT intended for use, reliance or in making financial/investment decisions by outside parties.

What is an FIS Facility? A Federal Inspection Services (FIS) Facility is a single facility that serves as the base of operations for U.S. Customs and Border Protection (CBP), immigration, and agriculture operations All aircraft flying to the U.S. from foreign countries must be cleared by CBP The FIS Facility unifies both passenger processing and baggage processing for safe and efficient flow of passengers and goods into the U.S. 2

Why are we here? Request by JetBlue to seek creation of a US Customs Facility City Council authorized a Feasibility Study and RFQ issued Jacobs selected to perform Study Study released October 4 th, 2016 Present findings of the Study 3

Outreach Community Meeting #1 March 30, 2016 Community Meeting #2 April 20, 2016 Jacobs received comment cards, emails, and conducted an economic impact survey Airport Advisory Commission October 20, 2016 Economic Development Commission October 25, 2016 City Council presentation December 13, 2016 4

Scope of Study Market Analysis Environmental Compliance Assessment Economic Impact Analysis FIS Facility Siting Alternatives Financial Feasibility Security Risk Assessment 5

Feasibility Study Overview Is there demand? Environmental clearances? What is the economic impact? Can it fit? How much will it cost? Who will pay for it? Does it increase security risks? 6

Feasibility Study Overview Long Beach Airport Noise Compatibility Ordinance One of the strictest in the world Long Beach Municipal Code Chapter 16.43 21 year old law, codified in 1995 Consistently reaffirmed by City Council Limits aircraft noise, not routes Study considered Noise Ordinance limits as a given 7

FAA Legal Opinion Letters dated 05-27-15 and 10-18-16 affirm that an FIS Facility will not negatively impact the Noise Ordinance, specifically: Will not affect the conclusion in the FAA letter of April 30, 2003, that the Long Beach Noise Ordinance is exempt from ANCA review; [T]he FAA does not find an issue of current noncompliance under ANCA or the City s grant assurances. Concerns that the introduction of international service consistent with the current noise ordinance would undermine that ordinance or cause a change in the FAA s position toward it are unwarranted. 8

Feasibility Study Findings: Market Analysis 9

Findings: Market Analysis LGB is located within a competitive Southern California Market Passenger traffic is up throughout the Southern California Market International Growth is outpacing Domestic within Southern California 10

Findings: Market Analysis Forecasted international demand is approximately 379,000 annual FIS arriving passengers, following a three year ramp up period 11

Findings: Market Analysis 2006 2015 Slot Utilization: 32.5 per day (79%) Unused allocation could provide for international activity Within the existing slot allocation, forecast international activity: 6 out of 50 daily air carrier flights (12%) in Year One 8 out of 50 daily air carrier flights (16%) in Year Four General Aviation forecasted impacts: improved efficiency of airspace and incremental reduction in emissions 12

Findings: Market Analysis Year DOMESTIC INTERNATIONAL TOTAL 2002 551,899,643 82% 118,704,850 18% 670,604,493 2003 583,293,766 83% 117,569,855 17% 700,863,621 Historical Passenger Distribution US DOT Statistics (2002 through May 2016) 2004 629,769,616 82% 133,940,075 18% 763,709,691 2005 657,261,487 82% 143,588,422 18% 800,849,909 2006 658,362,620 81% 149,740,591 19% 808,103,211 2007 679,185,450 81% 156,324,972 19% 835,510,422 2008 651,710,182 80% 158,111,711 20% 809,821,893 2009 618,067,255 80% 149,749,333 20% 767,816,588 Domestic: 80% International: 20% 2010 629,537,593 80% 157,940,463 20% 787,478,056 2011 638,247,667 80% 163,887,126 20% 802,134,793 2012 642,289,482 79% 170,838,576 21% 813,128,058 2013 645,677,554 78% 179,290,049 22% 824,967,603 2014 662,826,955 78% 188,690,254 22% 851,517,209 LGB will not become a 100% International Airport 2015 696,016,894 78% 200,491,818 22% 896,508,712 2016 286,808,375 78% 78,858,882 22% 365,667,257 TOTAL 9,230,954,539 80% 2,267,726,977 20% 11,498,681,516 13

Findings: Market Analysis Current & Past Activity LGB is served by four U.S. passenger airlines providing nonstop flights to 13 destinations (including seasonal service to Anchorage): American Airlines Delta Air Lines JetBlue Airways Southwest Airlines 14

Findings: Market Analysis Probable International Destinations Most probable international destinations that fit within JetBlue s network Forecasted that 6 8 of these destinations would be considered by JetBlue Destinations based on type of aircraft and facility constraints 15

Findings: Market Analysis Probable International Destinations Most probable international destinations that fit within JetBlue s network Forecasted that 6 8 of these destinations would be considered by JetBlue Destinations based on type of aircraft and facility constraints 16

Findings: Market Analysis International flights must operate within the constraints of the Noise Ordinance There is a market at LGB for international flights to/from southern destinations Estimated market is 6 to 8 flights per day totaling approximately 379,000 annual arriving passengers 17

Feasibility Study Findings: Economic Impact Analysis 18

Findings: Economic Impact Analysis Economic Impact Analysis used results from a 2016 tenant survey The analysis identified the economic impacts of LGB and the potential contribution of an FIS Facility Annual economic contribution of LGB and its tenants (pre-fis) is approximately 45,000 jobs and $10.3 billion in output 19

Findings: Economic Impact Analysis Non local purchases Non local labor (commuters) Savings Non local purchases Non local labor (commuters) Savings Direct Effect (e.g., new jobs, operational expenditures) Non Local Purchases (not applied to multipliers) Local Purchases Multiplier Effect Inter Industry Purchases Labor Income Spending Indirect Impact Induced Impact Direct + Indirect + Induced Total Impact Note: Diagram is illustrative and is intended to provide an overview of Input Output modeling, not a full representation of model inputs and structure. Source: AKRF, Inc. May 2013 20

Findings: Economic Impact Analysis FIS Annual Long Beach Economic Impact Community request to identify specific local benefits to Long Beach Statistical analysis applied to estimate local benefits and supplement regional economic analysis in the Study Local benefits are expressed as a range Results in the same conclusions as more detailed study and just as accurate for purpose of making business decision 21

Findings: Economic Impact Analysis FIS Annual Long Beach Economic Impact Range Economic impact likely greater than mean due to customer base Annual Impact of FIS: $20M to $60M 22

Findings: Economic Impact Analysis FIS Annual Long Beach Economic Impact Estimate Item Regional Impact (2) Study Appendix C Source Table Local Impact (3) Existing Annual Impact (Before FIS) Employment Output Employment Output Existing LGB 2015 (LGB Only Non Capital Expenditures) 171 $49,381,607 Table 2, airport only, no tenants 22 $8,318,128 Existing LGB 2015 (LGB Only Planned Capital Expenditures) 184 $30,894,450 Table 3, airport only, no tenants 34 $5,296,228 Existing LGB 2015 (Airport + Tenants) 44,772 $10,261,165,625 Table 5 LESS Tables 2 and 3 6,240 $1,776,527,660 Total Existing LGB 2015 (Airport + Tenants) 45,127 $10,341,441,682 6,296 $1,790,142,016 FIS Option 1 Impact (1) FIS Option 1 (One time, Capital) 253 $38,840,444 Table 7 47 $6,658,408 FIS Option 1 (Ongoing Facility O&M) 5 $867,153 Table 13 1 $137,196 FIS Operations (Airlines, Government, and Suppliers) 353 $35,654,059 Tables 16 and 17 80 $6,961,621 International Visitors (Steady State, Year 4+) 1,396 $185,610,476 Table 20 179 $31,265,318 Total FIS Ongoing Impact (4) 1,754 $222,131,688 260 $38,364,135 Footnotes (1) FIS Option 1 used for analysis only. This is neither an endorsement nor recommendation of a preferred alternative. (2) Regional impact values from IMPLAN analysis for Los Angeles and Orange Counties (total of direct, indirect and induced). (3) Local impact values are 28% of direct regional impacts based on 2016 tenant survey in study plus 3.6% of indirect and induced impacts based on population for City of Long Beach compared to Los Angeles and Orange Counties in 2015. (4) Ongoing Impact of FIS calculated for Year 4 and beyond following establishment of international service. Ongoing impact does not include one time capital expenditure to construct the FIS Facility. 23

Findings: Economic Impact Analysis Economic Impact Summary Long Beach Airport (pre-fis) Approx. 45,000 jobs and $10.3 billion in regional output Estimated 6,300 jobs and $1.8 billion in local output Potential FIS Facility construction (Option 1) Approx. 250 jobs and $38 million in one-time regional output Estimated 47 jobs and $6.7 million in one-time local output Potential FIS Facility operations Approx. 350 jobs and $36 million in annual regional output Estimated 80 jobs and $7 million in annual local output 24

Findings: Economic Impact Analysis Economic Impact Summary International travelers Estimated 30% of annual international passengers are visitors to the U.S. Estimated visitor spending equals $104 million per year Economic impact multiplier effect of international travelers spending Approx. 1,400 jobs and $186 million in annual regional output Estimated 179 jobs and $31 million in annual local output Potential Total FIS Ongoing Impact Approx. 1,750 jobs and $222 million in annual regional output Estimated 260 jobs and $20 $60 million in annual local output 25

Feasibility Study Findings: Environmental Compliance 26

Findings: Environmental Compliance Environmental Clearance Requires Compliance with State and Federal Regulations (CEQA & NEPA) California Environmental Quality Act (CEQA) Under some scenarios the FIS Facility could be accommodated within the impact envelope contemplated in the 2006 Terminal Area Improvement Project Final Environmental Impact Report (FEIR) No. 37-03 (State Clearinghouse No. 2003091112). National Environmental Protection Act (NEPA) Categorical Exclusion may be appropriate documentation in some scenarios pursuant to NEPA. Coordination with CBP and FAA on the type of NEPA documentation to be required as part of the project development process. 27

Findings: Environmental Compliance CEQA Environmental Impact Reports evaluate the following: I. Aesthetics II. Agricultural and Forestry Resources III. Air Quality IV. Biological Resources V. Cultural Resources VI. Geology and Soils VII. Greenhouse Gas Emissions VIII.Hazards and Hazardous Material IX. Hydrology and Water Quality X. Land Use and Planning XI. Mineral Resources XII. Noise XIII.Population and Housing XIV.Public Services XV. Recreation XVI.Transportation/Traffic XVII.Utilities and Service Systems 28

Findings: Environmental Compliance Conducted review of FEIR No. 37-03 Original FEIR consultant, Kathleen Brady from BonTerra Psomas, was retained to perform the review Feasibility Study does not constitute CEQA compliance. An environmental assessment will be preformed if and when the City determines to proceed with a Project Feasibility Study determined that in some scenarios no additional environmental impacts would be generated FEIR No. 37-03: 52 air carrier + 25 commuter daily flights = 5.28 MAP Forecast Activity: 50 air carrier + 3 commuter daily flights = 4.28 MAP 29

Findings: Environmental Compliance Functional Areas Evaluated Within FEIR No. 37-03: Holdrooms Concession Area Passenger Security Screening Baggage Security Screening Baggage Claim Devices Baggage Service Office Office Space Ticketing Facilities Airline Gates Aircraft Parking Positions Vehicular Parking Traffic and Pedestrian Circulation Restrooms 30

Findings: Environmental Compliance FEIR 37-03 Certified June 30, 2006 by City Council Evaluated 102,850 square feet of terminal facilities April 24, 2007 City Council Action Authorized 89,995 square feet of terminal facilities Phase I Improvements Completed 73,769 square feet of terminal facilities Remaining Terminal Improvements (under FEIR 37-03) 8,600 square feet of terminal facility removals 37,681 square feet of terminal facilities remaining 31

Feasibility Study Findings: Facility Siting Alternatives 32

Findings: Facility Siting Alternatives Three (3) conceptual options prepared Simulated flight schedule 6 to 8 daily international arrivals Demand peak: 255 passengers per hour Sized based on CBP Airport Technical Design Standards (ATDS) Options evaluated for feasibility only Preferred Project to be determined, but all are feasible 33

Findings: Facility Siting Alternatives Option 1 35,051 Gross Square Feet $21,558,000 CONCEPTUAL MASSING DIAGRAM FOR ILLUSTRATIVE PURPOSES ONLY 34

Findings: Facility Siting Alternatives Option 2 30,672 Gross Square Feet $17,335,000 CONCEPTUAL MASSING DIAGRAM FOR ILLUSTRATIVE PURPOSES ONLY 35

Findings: Facility Siting Alternatives Option 3 28,406 Gross Square Feet $20,353,000 CONCEPTUAL MASSING DIAGRAM FOR ILLUSTRATIVE PURPOSES ONLY 36

Feasibility Study Findings: Financial Feasibility 37

Findings: Financial Feasibility No City of Long Beach General Fund Dollars support the Airport No General Fund Dollars or Tax Payer Dollars would be used to construct or operate an FIS Facility Per FAA Regulations, Airport revenues can only be used for Airport activities Airport revenues cannot be used to pay for City services not related to the Airport 38

Findings: Financial Feasibility LGB could commit up to $3 million of Passenger Facility Charges (PFC) Balance of capital costs could be funded directly by JetBlue Airways as primary user of the FIS Facility FIS Facility charges would be approximately $13 per FIS arriving passenger in Year One (reflecting start-up costs) and then approximately $6 per FIS arriving passenger for the next ten years FIS Facility charges within range of comparable California airports Ultimate financing plan would be negotiated by all parties The potential FIS Facility would be financially feasible 39

Findings: Financial Feasibility Airport LGB SNA SAN OAK FAT PHX FIS Fees FIS Capital Charge: $3.52 to $4.65 per FIS arriving passenger FIS Net Operating Charge: $9.00 per FIS arriving passenger (Year One) and approximately $1.35 to $2.48 per FIS arriving passenger (Years Two through Ten) Effective fee of $6.80 (2016) per FIS arriving passenger based upon allocated costs and FIS square footage $2.00 per arriving international seat $10.00 per arriving international passenger $12.00 per deplaned passenger using the FIS facility Fee per FIS arriving passenger: $1.30 (2016); $2.55 (2017) & $4.00 (2018) Per aircraft turn fee: $430 (2016); $562.70 (2017) & $662 (2018) The potential FIS Facility would be financially feasible as this fee level is in the range of FIS charges at comparable airports 40

Feasibility Study Findings: Security Risk Assessment 41

Findings: Security Risk Assessment Study examined potential for additional risk The FIS Facility would not increase the risks to LGB and the Long Beach community CBP on-site presence provides additional protection Elimination of risk is seldom possible, and LGB currently commits significant resources to provide protection for the traveling public Regardless of the addition of international service, the risks to LGB will continue to be managed with a robust security operation 42

Next Steps City Council decision whether or not to move forward with next steps for an FIS Facility at the Long Beach Airport City Council Action tentatively scheduled for January 24, 2017 43

Feasibility Study Federal Inspection Service Facility at Long Beach Airport Copyright December 12, 2016