Wintershall K10-B Decommissioning Case Study Sven Vandamme, Scaldis Salvage & Marine Contractors
SVEN VANDAMME PROJECT ENGINEER
01. COMPANY PROFILE 02. ING TRACK RECORD 03. SITE VISIT 04. PREPARATION PHASE 2013 05. PREPARATION PHASE 2014 06. REMOVAL PHASE I 07. REMOVAL PHASE II 08. DISPOSAL YARD 09. TECHNICAL QUERIES 10. LESSONS LEARNT 11. EXECUTION 01. ING TRACK RECORD
01. COMPANY PROFILE
RAMBIZ 3000 02. 01. TECHNICAL COMPANY SPECIFICATION PROFILE
RAMBIZ 4000 01. COMPANY PROFILE
02. ING TRACK RECORD
Project : REM platform Location : North Sea, NL Execution : 2007 Weight : 1000 T 02. ING TRACK RECORD
Project : Welland 54/1A Platform Location : North Sea, UK Execution : 2011 Weight : 970 T 01. 02. ING TRACK WORKS RECORD
Project : Camelot Location : North Sea, UK Execution : 2012 Weight : 1100 T (Topside) : 670 T (Jacket) 01. 02. ING TRACK WORKS RECORD
Project : Draugen FLP Location : Stord, Norway Execution : 2014 Weight : 300 T (Topside) : 4000 T (Column) 01. 02. ING TRACK WORKS RECORD
Project : K10-B Location : North Sea, NL Execution : 2014 01. 02. ING TRACK WORKS RECORD
03. SITE VISIT
01. 03. 03. SITE VISIT OFFSHORE SITE VISIT WORKS REMOVAL PHASE CONDUCTORS
01. 03. 03. SITE VISIT SITE VISIT WORKS
01. 03. 03. SITE VISIT SITE VISIT WORKS
04. PREPARATION PHASE 2013
01. 04. 02. PREPARATION PHASE PREPARATION 2013 WORKS PHASE 2013 ROV SURVEY ROV SURVEY
01. 04. 02. PREPARATION PHASE PREPARATION 2013 WORKS PHASE 2013 TRUNNIONS PP TRUNNION INSTALLATION
01. 04. 02. PREPARATION PHASE PREPARATION 2013 WORKS PHASE 2013 MPI / UT LP MPI / UT
01. 04. 02. PREPARATION PHASE PREPARATION 2013 WORKS PHASE 2013 WORK PLATFORMS WORK PLATFORM INSTALLATION
01. 04. 02. PREPARATION PHASE PREPARATION 2013 WORKS PHASE 2013 SPIDER DECK REPAIR SPIDER WH DECK REPAIR
05. PREPARATION PHASE 2013 2014
01. 05. 02. PREPARATION PHASE PREPARATION 2014 WORKS PHASE 2014 SPIDER DECK REPAIR SPIDER PP DECK REPAIR
01. 05. 02. PREPARATION PHASE PREPARATION 2014 WORKS PHASE 2014 TRUNNIONS LQ TRUNNIONS INSTALLATION
01. 05. 02. PREPARATION PHASE PREPARATION 2014 WORKS PHASE 2014 CONDUCTOR CLEANING CONDUCTOR CLEANING
01. 05. 02. PREPARATION PHASE PREPARATION 2014 WORKS PHASE 2014 WORK PLATFORMS WORK PLATFORM INSTALLATION
01. 05. 02. PREPARATION PHASE PREPARATION 2014 WORKS PHASE 2014 ASBESTOS REMOVAL ASBESTOS REMOVAL
06. REMOVAL PHASE I
Phase I Phase I - B Phase II 1. Vent boom 2. Bridge 3. WH upper deck 4. Conductors (11) 5. WH lower deck 6. WH leg extensions 7. WH jacket 8. Living quarters 9. PP main deck 10.PP leg extensions 11.PP jacket 01. 06. 03. REMOVAL PHASE OFFSHORE I WORKS REMOVAL PHASE
1. Vent boom 01. 06. 03. REMOVAL PHASE OFFSHORE I WORKS REMOVAL PHASE VENT BOOM
1. Vent boom 2. Bridge 01. 06. 03. REMOVAL PHASE OFFSHORE I WORKS REMOVAL PHASE BRIDGE
1. Vent boom 2. Bridge 3. WH upper deck Calculated Weighted : 835 t : 620 t 01. 06. 03. REMOVAL PHASE OFFSHORE I WORKS REMOVAL PHASE WH UPPER DECK
1. Vent boom 2. Bridge 3. WH upper deck 4. Conductors (11) 01. 06. 03. REMOVAL PHASE OFFSHORE I WORKS REMOVAL PHASE CONDUCTORS
1. Vent boom 2. Bridge 3. WH upper deck 4. Conductors (9) 01. 06. 03. REMOVAL PHASE OFFSHORE I WORKS REMOVAL PHASE CONDUCTORS
1. Vent boom 2. Bridge 3. WH upper deck 4. Conductors (9) 5. WH lower deck Calculated Weighted : 140 t : 160 t 01. 06. 03. REMOVAL PHASE OFFSHORE I WORKS REMOVAL PHASE WH LOWER DECK
1. Vent boom 2. Bridge 3. WH upper deck 4. Conductors (9) 5. WH lower deck 6. WH leg extensions 01. 06. 03. REMOVAL OFFSHORE PHASE REMOVAL I WORKS PHASE WH LEG EXTENSIONS
1. Vent boom 2. Bridge 3. WH upper deck 4. Conductors (9) 5. WH lower deck 6. WH leg extensions 7. WH jacket 01. 06. 03. REMOVAL PHASE OFFSHORE I WORKS REMOVAL PHASE WH JACKET
1. Vent boom 2. Bridge 3. WH upper deck 4. Conductors (9) 5. WH lower deck 6. WH leg extensions 7. WH jacket 01. 06. 03. REMOVAL PHASE OFFSHORE I WORKS REMOVAL PHASE WH JACKET
1. Vent boom 2. Bridge 3. WH upper deck 4. Conductors (9) 5. WH lower deck 6. WH leg extensions 7. WH jacket 01. 06. 03. REMOVAL PHASE OFFSHORE I WORKS REMOVAL PHASE WH JACKET
1. Vent boom 2. Bridge 3. WH upper deck 4. Conductors (9) 5. WH lower deck 6. WH leg extensions 7. WH jacket 8. Living quarters Calculated Weighted : 500 t : 520 t 01. 06. 03. REMOVAL PHASE OFFSHORE I WORKS REMOVAL PHASE LQ
1. Vent boom 2. Bridge 3. WH upper deck 4. Conductors 5. WH lower deck 6. WH leg extensions 7. WH jacket 8. Living quarters Calculated Weighted : 1220 t : 1000 t 01. 06. 03. REMOVAL PHASE OFFSHORE I WORKS REMOVAL PHASE WH JACKET
1. Vent boom 2. Bridge 3. WH upper deck 4. Conductors 5. WH lower deck 6. WH leg extensions 7. WH jacket 8. Living quarters 01. 06. 03. REMOVAL PHASE OFFSHORE I WORKS REMOVAL PHASE WH JACKET
07. REMOVAL PHASE II
1. Vent boom 2. Bridge 3. WH upper deck 4. Conductors 5. WH lower deck 6. WH leg extensions 7. WH jacket 8. Living quarters 9. PP main deck Calculated Weighted : 1810 t : 1850 t 01. 07. 03. REMOVAL PHASE OFFSHORE II WORKS REMOVAL PHASE PP MAIN DECK
1. Vent boom 2. Bridge 3. WH upper deck 4. Conductors 5. WH lower deck 6. WH leg extensions 7. WH jacket 8. Living quarters 9. PP main deck 10.PP leg extensions 01. 07. 03. REMOVAL PHASE II OFFSHORE WORKS REMOVAL PHASE PP LEG EXTENSIONS
1. Vent boom 2. Bridge 3. WH upper deck 4. Conductors 5. WH lower deck 6. WH leg extensions 7. WH jacket 8. Living quarters 9. PP main deck 10.PP leg extensions 11.PP jacket Calculated Weighted : 1220 t : 930 t 01. 07. 03. REMOVAL PHASE OFFSHORE II WORKS REMOVAL PHASE PP JACKET
08. DISPOSAL YARD
01. 08. 02. DISPOSAL YARD PREPARATION WORKS PHASE 2014 TRUNNIONS INSTALLATION
01. 08. 02. DISPOSAL YARD PREPARATION WORKS PHASE 2014 TRUNNIONS INSTALLATION
09. TECHNICAL QUERIES
01. 09. 02. TECHNICAL QUERIES PREPARATION WORKS PHASE 2014 TRUNNIONS INSTALLATION
01. 09. 02. TECHNICAL QUERIES PREPARATION WORKS PHASE 2014 BARGE PREPARATIONS
01. 09. 02. TECHNICAL QUERIES PREPARATION WORKS PHASE 2014 BARGE PREPARATIONS
01. 09. 03. TECHNICAL OFFSHORE QUERIES REMOVAL WORKS PHASE WH LEG EXTENSIONS
01. 09. 03. TECHNICAL OFFSHORE QUERIES REMOVAL WORKS PHASE WH LEG EXTENSIONS
01. 09. 03. TECHNICAL OFFSHORE QUERIES REMOVAL WORKS PHASE WH LEG EXTENSIONS
01. 09. 03. TECHNICAL OFFSHORE QUERIES REMOVAL WORKS PHASE WH LEG EXTENSIONS
10. LESSONS LEARNT
01. 10. 02. LESSONS LEARNT PREPARATION WORKS PHASE 2014 BARGE PREPARATIONS
01. 10. 03. LESSONS OFFSHORE LEARNT REMOVAL WORKS PHASE WH LEG EXTENSIONS
01. 10. 03. LESSONS OFFSHORE LEARNT REMOVAL WORKS PHASE WH LEG EXTENSIONS
11. EXECUTION
1. Preparation phase 2013 : 16 days 2. Preparation phase 2014 : 14 days 3. Removal phase I (Vent boom, Bridge, WH upper deck, Conductors (11), WH lower deck, WH leg extensions (6), Living quarters, WH jacket) Mob/Demob : 3 days Sailing : 4 days Working days : 10,5 days Wow : 11 days 4. Removal phase II (PP main deck, PP leg extensions (6), PP jacket) Mob/Demob : 2 days Sailing : 4 days Working days : 3 days Wow : 5 days 01. 11. 02. EXECUTION PREPARATION WORKS PHASE 2014 BARGE PREPARATIONS
Scaldis Marine Contractors NV Sven Vandamme THANK YOU Project Engineer Noorderlaan 133 box 31 2030 Antwerp, Belgium Sven.vandamme@scaldis-smc.com www.scaldis-smc.com