John Hart Generating Station Replacement Project. October 2018 Community Construction Update Report #64

Similar documents
Guide to the L. F. Manis Photographs

Guide to the L. F. Manis Photographs

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF JANUARY 25, 2011

ENLOE HYDROELECTRIC PROJECT FERC PROJECT NO PUBLIC SAFETY PLAN. Final

Pumped Storage Schemes & imported hydroelectricity

Minnesota Power Renewable Energy (& Engineering) for the 21 st Century

STATEMENT OF QUALIFICATIONS

Seven Wonders of the Modern World

EPCG is seated at the address no 2 Vuka Karadžića St. in Nikšić

Lake Chelan Operations

Guide to the Virginia "Teddy" Fenton Photograph Collection on the Hoover Dam and Boulder City, Nevada

TORONTO TRANSIT COMMISSION REPORT NO.

Status. Agreement announced: June 2004 Completed: Value for Money Report. released: Nov 2004 *CCPPP: Financing Award Agreement announced:

Proposal to Redevelop Lower Kananaskis River-Barrier Lake. Bow Valley Provincial Park

Canada and New Brunswick fund 74 projects to improve water and wastewater systems across the province

Keeyask Generation Project. Project Description. Supporting Volume. Environmental Impact Statement

1. TITLE OF THE PROJECT HYDROPOWER SYSTEM UPPER HORIZONS. 2. SECTOR Energy

Ronan Delaney. DELANEY_RONAN_AVIATION_JUN_2018.DOCX

2006 ANNUAL GENERAL MEETING

2018 Goldwedge Mines Inc. Licence of Occupation Management Plan. Photo: xxxx. Goldwedge Mines Inc.

2 August 23-25, 2017 Banff, AB: Board of Governors Strategic Retreat. 7 November 7-9, 2017

MANITOBA METIS FEDERATION MATRIX SOLUTIONS INC. PARTNERSHIP INDIGENOUS CONSTRUCTION MONITORING

The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands.

Toyostove Error Code EE 2 (EE 6)

Kurobegawa No.4 Power Plant Toyama Prefecture, Japan (Asia)

Greyhound Canada Transportation ULC

Cofferdam Performance Hurricanes Harvey & Irma

Prequalified Service Provider Registry

Evaluation of the amendment proposal for "converted paper" products

Long water shutdown scheduled for Tuesday, September 18

Guide to the Boulder City 31ers Photograph Collection

Kinder Morgan Canada Trans Mountain Pipeline Expansion Project

South of Fraser Transportation Priorities March 2017 Engagement

Vancouver Island Rail

Splash of Colour - Community Art Program North West Region. Expression of Interest 2018

SAMSON CREE NATION MATRIX SOLUTIONS INC. PARTNERSHIP ABORIGINAL CONSTRUCTION MONITORING

INFORMATION ONLY. Subject: Metrolinx Presentation Date: June 22, 2015

Monitoring Report No. 278

2014 floods in Serbia

During Construction. Full Resident and Non-Resident Services. Contract Administration and Construction Supervision of Groundside and Airside Projects

Engineering Branch Selection Associate Professor Bill Wong Deputy Head & Director of Teaching Department of Civil Engineering Monash University

Misinterpreted Engine Situation

STRABAG SE Successful in Eastern Europe

Leeds Grenville Economic Development Summit Thousand Islands International Bridge Outlook

Alberta Tourism Market Monitor

CREATING CONNECTIONS IN THE TOWN OF GRIMSBY PUBLIC MEETING NOVEMBER 21, 2017

RW Bruhn Bridge and Approaches Project

BOULDER CREEK CATTLE FENCING FOR KOKANEE HABITAT ENHANCEMENT 2010

Alberta Tourism Market Monitor

Rail /Trail Service Plan & Infrastructure Upgrade Project 14 April 2018

SAMSON CREE NATION MATRIX SOLUTIONS INC. PARTNERSHIP ABORIGINAL CONSTRUCTION MONITORING

Appalachian Power Company Smith Mountain Hydroelectric Project FERC No Debris Management Plan

Proposal to Redevelop Lower Kananaskis River-Barrier Lake. Bow Valley Provincial Park. Frequently Asked Questions

It has been quiet during the past few weeks. I suppose it has been Christmas and people have other things on their mind.

Day of Mourning. April 28, 2017

SAMSON CREE NATION MATRIX SOLUTIONS INC. PARTNERSHIP ABORIGINAL CONSTRUCTION MONITORING

Alberta Tourism Market Monitor

Public-Private Partnerships (P3) for Social Infrastructure. Alberta Schools Alternative Procurement (ASAP Team) Alberta Infrastructure

Endless investment opportunities in public infrastructure and services Carlos Herrera Investors Servicing Director

UNITED STATES DEPARTMENT OF THE INTERIOR BUREAU OF RECLAMATION REGION 4 SALT LAKE CITY, UTAH. May 29, 1958

Rotorua. newzealand.com. argentina. Market information about our Visitors and our Active Considerers

San Antonio's River Walk Behind the scenes tour or did you know?

Hydro-Electric Schemes Compliance Report June June 2013

APPENDIX IV MINOR HOCKEY ZONES

Proposal for the Development of Bus Stops

I T N E T R E N R A N T A I T ON O AL A L A R A R R I R VA V L A S L S A N A D N D D E D PA

PPP in the Canadian Roads Sector Presentation to PIARC Technical Committee A.2

Virginia Beach City Case Study

MUNICIPALITY OF KINCARDINE

John Dennison fonds. Original inventory (1985, 1998) Revised by Erwin Wodarczak (2004) University of British Columbia Archives

Agenda. Introduction YYC. Looking Ahead in 2014

RE: Visitor experience and safety improvements Temporary delays and closures in Banff and Kootenay national parks in 2018

The Government s Aviation Strategy Transport for the North (TfN) response

Alberta Tourism Market Monitor

BILFINGER SE NUCLEAR ENERGY PROJECTS: WE MAKE IT WORK FROM ENGINEERING AND TECHNOLOGY TO FABRICATION, CONSTRUCTION AND SERVICES

PASSENGER TRANSPORTATION BRANCH MINISTRY OF TRANSPORTATION AND INFRASTRUCTURE LICENCE. Passenger Transportation Licence COPY

4 VIVA PHASE 2 YONGE STREET - Y2, AND HIGHWAY 7 - H3 CORRIDORS PRELIMINARY ENGINEERING UPDATE

Lake Margaret: Conservation of a 1914 Tasmanian Hydro-Electric Power Scheme

FINAL REPORT AIC PAPUA NEW GUINEA ACCIDENT INVESTIGATION COMMISSION SHORT SUMMARY REPORT

RESEARCH AND PLANNING FORT STEELE HERITAGE TOWN VISITOR STUDY 2007 RESULTS. May 2008

Let s Fly. Fort McMurray Airport Authority

ANNUAL GENERAL MEETING

Available On-Board Technologies For Runway Excursions Prevention

Toronto Pearson February 2019 Briefing. February 19, 2019

Updated on November 28, 2016

Committee. Presentation Outline

EDMONTON HISTORIAN LAUREATE

ASSET MANAGEMENT AND AUTOMATION: ANDRITZ DIGITAL SOLUTIONS AND CASE STUDIES

Electric System Serving Pierce County Current system and future investments. Janet Olsen Steve Botts

Ballybane homes Boston scientific, HP, APC and many more large companies with limited room for expansion

Outlıne of the Presentatıon

Cherokee And The Concow Dam

new with purpose PARADISE A Vulnerable white-eye species and the largest tortoise in the world on an ultra-luxe private tropical island

PETROLEUM INDUSTRY ORAL HISTORY PROJECT TRANSCRIPT

Electric System Serving Pierce County Current system and future investments

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE PUBLIC WORKS AND UTILITIES DEPARTMENT

Grade Crossing Regulations

AUGUST 2017 GNSS REVIEW. Survey Economics Chances of success. Mobile Mapping Airport scanning. Stag s Leap Winery Pre-construction plan

Tourism Snapshot A focus on the markets in which the CTC and its partners are active

Roadside Management Manual

Transcription:

John Hart Generating Station Replacement Project October 2018 Community Construction Update Report #64 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 Twitter: @Puntledge Email: steve.watson@bchydro.com

Project Status General update: Oct 1: Old John Hart Generator #4 was permanently shut down; Oct 11: Old John Hart Generator #2 and #6 were shut down powerhouse operations shut down and operations transferred to the new facility. End of an era; Generator #1 officially commissioned October 25; Testing of new public warning (siren) warning system along the river; Significant demobilization on site with trailers being emptied and removed; Powerhouse, service bay and mezzanine electrical work including lighting, receptacles, terminations and groundings; Fire suppression system installation ongoing; Initial clean-up work in old generating station; begins; and Preparation for removal of the penstocks. On October 11, BC Hydro permanently shut down the last two generators in the old generating station. An end of an era.

Project Schedule Ongoing: Training; Last generator to be officially commissioned in early November; Water bypass facility to be fully automated (currently operating in manual mode) in early November; Nov: Finishing touches on powerhouse completed; Nov Dec: Demobilization of construction crews and equipment; Nov Feb 2019: Woodstave penstock removal; Feb/March 2019: Removal of old surge towers begins; and March/April: Turbines and generators from old powerhouse removed and facility is deconstructed. The final construction report, for November-December, will be issued on December 19. There will then be some periodic John Hart decommissioning reports issued in 2019. Good view of the surge towers, substation and old generating station. Work to remove the three penstocks, or pipes, and two of the three surge towers, along with the old powerhouse to be removed down to the ground level, will begin next month through next summer.

John Hart Project Underground Site Map 4

John Hart dam and the new water intake works. 5

FMI and NCE who are leading the decommissioning works, have undertaken a huge broom clearing effort along the penstock corridor and around construction areas. This is to prepare those sites for removal of old structures and the rehabilitation work following. The final permitting for the extensive decommissioning work is in process with Ministry of Environment and Forest, Lands and Natural Resources. New surge tank. Service tunnel entrance to the underground powerhouse. Main access tunnel entrance to the powerhouse. 6

On a foggy day, the service tunnel entrance. 7

8 John Hart powerhouse area, with office complex in the background.

9 Powerhouse view from the top of the office complex.

10 Generator #1.

11 Generator #2.

Service tunnel entry. Generator #3. 12

13 View from the generator floor of the powerhouse.

14 View from the mezzanine area of the powerhouse.

Siren system tests begin: In late October the new public warning system for the John Hart hydroelectric facility went into early testing. The plan is to replace the old 360 degree air raid siren sound with a whooping sound that is more directional, with the sirens facing upstream or downstream of the canyon or river. The first siren tests occurred at the dam and near Elk Falls. The new sound may create some confusion as to what the sound means, so the project communicated out to the Campbell River community. The siren tests down by the powerhouse and by the old pulp and paper mill water intake below Second Island may take place at the end of November. The plan is to have the new system in place by the end of the year. Until then, the old system will remain in place to ensure public safety notification of sudden water flow changes. The new siren system will be more reliable and up to current public safety guidelines. Water flow changes down Elk Falls Canyon or below the generating station can take place at any time, and it s imperative that we have a good siren system in place to properly warn people downstream. The work is part of the final components of the John Hart project. Photo: New siren placed near Elk Falls. 15

Old Generator 4 Permanently Shut Down 16

<Heli pic of substation TBC Friday> 17

18

<Oct 11> Generator 6 and 2 operating at 5 MW prior to being shutdown on October 11. 19

<Oct 11> 20 View of the celebration event. Pic courtesy of Mary Ruth Harris at Shaw TV.

<Oct 11> BC Hydro staff and Power Pioneers were on hand to recall the 71 years of nostalgia of the facility. 21

<Oct 11> BC Hydro s Stephen Watson, involved in communications with the Campbell River community for almost 19 years, reflects on the John Hart facility and the staff that kept it operating all these years. 22

<Oct 11> Senior Field Manager, Neal Dermody, discusses the passion and commitment of the staff at John Hart, and staff from around the province, that were able to keep the facility running until today. 23

Shutting Down Generator 6 Greg Remfert, a staff member in Campbell River, was drawn by lottery to pull the lever to signal the shutdown of Generator 6. 24

<Oct 11> BC Hydro s Regional Manager, Fawn Hollard, pulls the level to Generator 2 as staff and Power Pioneers look on. This was when the powerhouse sounds went quiet and the vibrations stopped. A surreal moment. 25

<Oct 11> 26 No more water outflow out of the old tailrace. Water flows now come out of the tunnel outlet to the top right on the photo.

<Oct 11> BC Hydro staff and Power Pioneers gather for a group picture once the generators were shut down. 27

People Profile Andy Brown About Andy Background: Andy was born, raised and educated in Australia and shortly after graduating from the University of Adelaide, took off on a round-the-world excursion. As his trip neared its end in Edmonton in 1974, he met his wife and laid down roots. His two sons still live in Edmonton. Now, he calls Courtenay home, although he still considers himself an Aussie at heart. Home: With the bulk of his career with Alberta Transportation, Andy managed the construction and maintenance of rural highways before moving into the private sector in 2006 in Calgary, focusing on two of the Stoney Trail (Calgary ring road) P3 projects. Working with SNC-Lavalin on one of those projects led to the John Hart project opportunity. Hobbies: When he s not working, Andy s main interest is travelling to off-thebeaten-path locations, from one coast of Canada to the other, and other stops like Iceland and Zambia. His aim in retirement is to explore the outback areas of his home country Australia. Andy is also part of the BMW car club of Canada and owns two of them; one practical, the other his toy. Photography has always been an interest, but he s not yet given over to the intricacies of today s cameras in the digital world. Project Responsibility: As Technical Director for InPower BC, Andy s role on the John Hart project is to liaise between the project site and InPower/SNC-Lavalin s Vancouver/Montreal offices during the construction phase, observing the work in progress and assisting proactively with any contractual issues that have arisen or could become a concern. Being on-site allows InPower BC to be an active and visible part of the team delivering this very important project. I ve always worked on big projects aboveground and the chance to work on this project underground was too big for me to let it go. It s been more interesting than I could have imagined.

Construction Point Of Interest Each month, BC Hydro and InPower BC will provide a construction fact, occurrence, or situation. Decommissioning With the new John Hart facility now operating, the project team is turning it s eyes to the decommissioning and removal of the old infrastructure, including the generating station, penstocks and two of the three surge towers. Pictures on right taken prior to 2011. Below is how it s generally planned to roll out. October 2018-February 2019: Powerhouse cleaned/prepped for demo; First of three turbine-generators in the powerhouse dismantled and removed; Water intake at the reservoir plugged/decommissioned; Woodstave penstock removal begins; and Surge Tower 3 comes down/removed. March-August 2019: Final three turbines-generators dismantled and removed; Powerhouse taken down; Penstock wood and steel removal completed; Contaminated soils disposed off site at approved facilities; and Surge Tower 2 comes down and is removed.