Community Weekly Update for September 8- September 14, 2012 A Love Note from Me to You Dear Neighbors, Please be advised that we have a scheduled closure of our Preferential Runway 13R/31L (Denton) Friday Sept. 7th at 11 p.m. until Saturday Sept. 8th at 7 a.m. for maintenance. There is a slight chance for thunderstorms in the forecast for Friday evening and Saturday morning. We will coordinate the scheduled maintenance based on permitting weather conditions. We are excited about the progress and changes that are taking place here at Dallas Love Field and we want you to be excited as well! If you are interested in some area that we are currently monitoring for our quarterly meetings of the LFEAC or if you have some particular interest in a time frame to be monitored, please let me know and I will try to accommodate that suggestion. -Ms. Courtenay Shorter Construction Updates Contents Runway Closures Airport Diagram Airport Operations Report Pg.2 Pg.2 Pg.3 Pg.4 & 5 Want to get involved? The Love Field Environmental Advisory Council (LFEAC) meets once every quarter. Please join us for round-table discussion and updates!!! Upcoming LFEAC Meetings: October 11, 2012 January 10, 2013 April 11, 2013 The Love Field Modernization Project (LFMP) is steadily underway. For more information and updates about the LFMP please visit: http://www.lovefieldmodernizationprogram.com/ Everyday Environmental Tip Buy local products as often as possible. By choosing local products, you can reduce gas consumption, pollution, and the impact made on the environment.
Construction Activities Runway Safety Area (RSA) In order to meet current FAA requirements, modifications to RWY 13L/31R must be made to have the appropriate amount of safety area (1,000 feet) at the north end of the runway. In order for the Runway Safety Area (RSA) Project to begin construction, it is necessary for construction elements to be completed on Taxiway Bravo to allow the Love Field Modernization Program (LFMP) to remain on schedule. Portions of Taxiway Bravo are expected to be closed beginning July 1, 2012 through December 31, 2012. Because both projects can not be done concurrently, construction of the RSA Project will not begin until early 2013. If you would like to learn more about the LFMP please visit: http://www.dallas-lovefield.com/pdf/lfmp_newsletter_0412.pdf Water Main Replacement DWU has contracted with Atkins Brothers Construction to install a 48 water line around Love Field from the Shorecrest Weiss Street intersection to approximately the 8000 block of Lemmon Ave. All work will be competed in phases. Construction has begun and is still on schedule to be completed by November 2012. Shorecrest is closed to traffic between Webb Chapel and Lemmon as work on the water line continues.. Runway Closures Scheduled Runway Closures for Routine Maintenance RWY 13R/31L (Denton) will be closed Friday September 7, 2012 at 11 p.m. until Saturday September 8, 2012 at 7 a.m. for maintenance. Ongoing Airfield Closures TWY B will be closed for construction from TWY B5 to 500ft NW of TWY B1, through December 2012. TWYs B3, B4 and M will be closed for construction through December 2012. TWY B5 from TWY D to TWY B, is currently closed for construction and will remain closed through December 2012. *Please see the airport diagram on the next page for the locations of runways and taxiways. Page 2 Weekly Update for September 8 September 14, 2012
Airport Diagram Page 3 Weekly Update for September 8 September 14, 2012
Airport Operations Report Total Operations for the Week of September 8 September 14, 2012 13L / 31R (Lemmon) 13R / 31L (Denton) Aug 26 Sept 1 Total Day Total Weekly Operations for July 29-August 4, 2012 Day Arrivals 639 91 Arrivals 949 136 Commercial 13L / 31R 73 (Lemmon) 10 Commercial 13R / 31L 752 (Denton) 107 GA 377 54 GA 147 21 Other July 29 August 4 189 Total 27 Day Other 50 Total 7 Day Departures Arrivals 524567 75 81 Departures Arrivals 927 945 132 135 Commercial Commercial 53 52 8 7 Commercial Commercial 765 805 109 115 GA GA 300313 43 45 GA GA 122 109 17 16 Other 202 29 Other 31 4 Other 171 24 Other 40 6 Departures 486 69 Departures 912 130 Annual Comparison Commercial 25 4 Commercial 754 108 GA 256 37 GA 118 17 RWY 13L/31R Lemmon Ave. Other 205 29 Other 40 6 TOTAL ARRIVALS TOTAL DEPARTURES 2011 (Aug 26 Sept 1) * 2012 (Aug 26 Sept 1) 0 100 200 300 400 500 600 700 OPERATIONS * On August 27, 2011 RWY 13R/31L (Denton) was closed from 6am until 2pm and RWY 13L/31R (Lemmon) was closed from 2pm until 4pm. * On August 28, 2011 RWY 13L/31R (Lemmon) was closed from 7am until 12pm. Page 4 Weekly Update for September 8-September 14, 2012
Airport Operations Report (Continued) RWY 13R/31L Denton Rd. TOTAL ARRIVALS TOTAL DEPARTURES 2011 (Aug 26 Sept 1) * 2012 (Aug 26 Sept 1) 0 200 400 600 800 1000 OPERATIONS * On August 27, 2011 RWY 13R/31L ( Denton) was closed from 6am until 2pm and RWY 13L/31R (Lemmon) was closed from 2pm until 4pm. * On August 28, 2011 RWY 13L/31R (Lemmon) was closed from 7am until 12pm. Community Weekly Update September 8 September 14, 2012 Visit us at www.dallas-lovefield.com/ For questions or concerns please contact: Courtenay Shorter Aircraft Noise Coordinator City of Dallas-Department of Aviation Phone: 214-670-6673