Review Advisory Committee October 9, 2008 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground) Park & Ride Facility Direct Connection to the Pasadena Metro $898.8 million On-Time/Within Budget Opens in 2009
Louise Martinez Beloved RAC Member Rest In Peace 1923-2008
Overall Construction Progress ACTIVITY 2008 2009 2010 J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J Major Construction Activities Trackwork 1st/Boyle & 1st/Soto 1st/Alameda 1st/Utah Indiana 3rd/Ford 3rd/Mednik Pomona/Atlantic Station Architecture and Site Finishes Boyle Heights/Mariachi Plaza & Soto Stations Little Tokyo/Arts District Station Pico/Aliso Station Indiana Station Maravilla Station East LA Civic Station Atlantic Station Third Party Interfaces 1st Street Bridge Widening LAUSD Re-Build Ramona Opportunity High School Systems Installation & Testing/ Pre-Revenue Systems Installation & Integration Testing (Phases I & II) Pre-Revenue Operations Revenue Operations Date
Overall Construction Progress Construction began in July 2004. As of October 2008, the Project is over 89% complete. The Contractor has worked over 3.5 million hours without a lost-time accident. Trackwork installation along the entire six-mile alignment is complete. Construction of the two underground stations at 1st/Boyle and 1st/Soto is 83% complete. Construction of the six at-grade stations is 63% complete. Systems installation is 76% complete.
101 Freeway Light Rail Transit Bridge Union Station View looking southwest from Union Station towards Downtown Los Angeles. The tie-in to the Pasadena tracks was completed in September 2008. Installation of all the trackwork along the entire six-mile alignment is complete.
Light Rail Transit Stations LittleTokyo/ Arts District Pico/Aliso Boyle Heights/ Mariachi Plaza 1st/Soto Maravilla Indiana Station East Los Angeles Civic Center Pomona/Atlantic
At-Grade Station Construction 1 st /Alameda and 1 st /Utah Little Tokyo/Arts District Station - Northeast corner of 1st/Alameda. Pico/Aliso Station View east near 1 st /Utah towards Boyle Heights. Construction of the At-Grade stations along the west side of the alignment includes concrete sitework, canopy installation and systems installation.
Underground Station Construction 1 st /Boyle and 1 st /Soto Boyle Heights/Mariachi Plaza - Northeast corner of 1st/Boyle where the station entrance is being constructed adjacent to the Mariachi Plaza Kiosko. Soto Station Interior work in the underground rooms progresses as work on the station entrance structures above continues.
Underground Station Construction Boyle Heights/Mariachi Plaza Station Station entrance stairs are being constructed from the plaza to the mezzanine levels. Escalators are being installed to connect the various underground levels. Elevators will be installed within the next few months.
At-Grade Station Construction Indiana Station Maravilla Station Construction of the stations from 1st/Indiana and along 3rd Street in East Los Angeles is well underway where the erection of canopies and the installation architectural finishes has begun. East LA Civic Center Station Pomona/Atlantic Station
Surface Work and Street Restoration New crosswalks are being constructed at the 1 st Street and Lorena Street intersection near the east tunnel portal. The portion of the jogging path that was impacted by construction along the north side of 1 st Street between Lorena Street and Fresno Street has been replaced.
Surface Work and Street Restoration Final paving and striping is occurring along 3 rd Street where the track guideway has been completed. The U-Channel track guideway and barrier walls on 3 rd Street between Marianna Avenue and Downey Road have been completed.
Community Relations
City of Baltimore Tour with the RAC Metro hosted a Community Workshop between guests from the City of Baltimore and Eastside community Review Advisory Committee (RAC) members. City of Baltimore elected officials, community and business leaders asked Eastside community Review Advisory Committee members to share their experiences on the Metro Eastside Extension Project.
City of Baltimore Tour with the RAC Guests from the City of Baltimore and Eastside community Review Advisory Committee (RAC) members arrived at the future Boyle Heights/Mariachi Plaza Station after a tour of the Project. Guests received underground safety training and construction attire and equipment before going underground to tour the station and tunnels.
City of Baltimore Tour with the RAC
Community Relations Mitigation Mitigating construction related impacts. Coordinating construction activities to minimize disruptions. Notification of traffic detours and related activities through construction notices. Filing field reports for physical damages to the Contractor. Working with local businesses to promote them as part of the opening of the Metro Eastside Extension. Community Relations Field Office 1505 1st Street Los Angeles, CA 90033 MGLEE HOTLINE (213) 922 2259 www.metro.net/eastside
Community Relations Mitigation Mariachi Directory Now Available! Public Libraries Local Chambers of Commerce Offices of Elected Officials For a complete list of locations: www.mothersofeastla.com www.boyleheightschamber.com www.boyleheightsnc.com www.elacoc.com