RECONSTRUCT/REHABILITATE TRANSIENT APRON AND TAXIWAY 'A' PHASING PLAN - PHASE 1
|
|
- Gyles Maxwell
- 5 years ago
- Views:
Transcription
1 PHASING PLAN - PHASE 1 2 Weeks PHASE 1 SCOPE OF WORK Phase 1 consists of the reconstruction of a portion of Taxiway 'A' and the crack seal and seal coat of the North Apron. The portion of Taxiway 'A' to be reconstructed is located between Taxilane 1 and Taxilane 4, along the east edge of the Transient Apron. All of this work shall be outside of the Taxiway 'D' Object Free Area. In addition access will be provided to all hangars located on Taxilanes 1-3 via Taxilane 4. Approximate Dates: October 16 - October 27 NOTAM will be issued prior to the start of Phase 1 The construction area shall be delineated with low level barricades and all aircraft currently located on the North Apron shall be temporarily relocated to the Transient Ramp during this Phase.
2 PHASING PLAN - PHASE 2 3 Weeks PHASE 2 SCOPE OF WORK Phase 2 consists of the reconstruction of Taxiway 'D' from the east side of the Papillon Apron to the intersection of Taxiway 'D' and Taxiway 'A'. Runway '9-27' will remain open and maintain standard operations during Phase 2. As part of Phase 2 there will be a temporary taxiway marked onto the existing Transient Apron north of the closed portion of Taxiway 'D'. This will allow access to Taxiway 'A' and Taxilanes 1 through 4. Approximate Dates: October 30 - November 20 NOTAM will be issued prior to the start of Phase 2 The construction area shall be delineated with low level barricades.
3 PHASING PLAN - PHASE 3 8 Days Approximate Dates: November 13 - November 20 PHASE 3 SCOPE OF WORK Phase 3 consists of the reconstruction of the east end of Taxiway 'D' and a portion of Taxiway 'A'. This phase also includes the crack seal and seal coat of Taxiway 'A', south of the existing Fuel Farm. This work shall be completed over a five (5) consecutive day duration in conjunction with Phase 2. Runway '9-27' will remain open and operational during Phase 3, however aircraft traffic will be required to back taxi on the Runway as a portion of Taxiway 'A' will be closed. Access to all hangars on Taxilane 4 will be provided via Taxilane 3. The Contractor will be allowed to work inside the Runway Object Free Area but no work will be performed within the Runway Safety Area. RUNWAY '9-27' Shall be open for Arrivals only NOTAM will be issued prior to the start of Phase 3 This construction area shall be delineated with low level barricades and a taxiway closure marker shall be placed at the intersection of Runway '9-27' and Taxiway 'A'.
4 PHASING PLAN - PHASE 4 3 Weeks PHASE 4 SCOPE OF WORK Phase 4 consists of the reconstruction of the eastern half of the Transient Apron west of Taxiway 'A' and north of Taxiway 'D'. All work in this phase shall be outside of the Taxiway 'A' and Taxiway 'D' Object Free Area. The construction in this area shall be delineated with low level barricades. The contractor will be required to provide pedestrian access to the buildings at all times. In addition, the contractor will be required to install temporary fencing during this phase to maintain a secure perimeter as the new security fence is installed. Approximate Dates: November 21 - December 12 NOTAM will be issued prior to the start of Phase 4
5 PHASING PLAN - PHASE 5 3 Weeks PHASE 5 SCOPE OF WORK Phase 5 consists of the reconstruction of the western half of the Transient Apron north of Taxiway 'D' and on the east side of the City Apron, all work in this area shall be outside of Taxiway 'D' Object Free Area. The construction in this area shall be delineated with low level barricades. Approximate Dates: December 13 - January 04 NOTAM will be issued prior to the start of Phase 5
6 PHASING PLAN - PHASE 6 8 Days Max PHASE 6 SCOPE OF WORK Phase 6 consists of the crack seal and seal coat of the City Apron and the section of Taxiway 'D' located adjacent to the City Apron. The City Apron and a portion of Taxiway 'D' shall be closed during this phase. Runway '9-27' will remain open and operational during Phase 3, however aircraft traffic may be required to back taxi on Runway '9-27' to gain access to east side of the airfield. The Construction in this area shall be delineated with low level barricades. Approximate Dates: January 04 - January 11 RUNWAY '9-27' Shall be open for Arrivals only NOTAM will be issued prior to the start of Phase 6
Planning & Development Group
Planning & Development Group LAX Airside Technical Committee Meeting January 9, 2018 Mark Vicelja, P.E. 1 Airside Element Projects LAX AIRSIDE ELEMENT PROJECTS CONSTRUCTION SCHEDULE (as of January 1, 2018)
More informationSan Bernardino International Airport Authority Ramp Joint Seal Replacement & Pavement Repair Project
San Bernardino International Airport Authority Ramp Joint Seal Replacement & Pavement Repair Project Construction Safety and Phasing Plan 1601 E. Third St. San Bernardino, California 92408 As an authorized
More informationSan Bernardino International Airport Authority Building 795
San Bernardino International Airport Authority Building 795 Construction Safety and Phasing Plan 1601 E. Third St. San Bernardino, California 92408 As an authorized representative of, (Company) I (Name
More informationJACIP-AIRPORT PROJECT DETAIL REPORT August 15, 2007
JACIP-AIRPORT PROJECT DETAIL REPORT August 15, 27 11242 1 of 14 Sponsor: City of Naples Airport Authority NPIAS No.: 12-53 Sponsor ID: 122 Airport ID: APF Site No.: 3379.*A 11242 Airport Project ID: 1
More informationChapter 5 Airport Development Alternatives
Chapter 5 Airport Development Alternatives Introduction CHAPTER 5 AIRPORT DEVELOPMENT ALTERNATIVES JUNE 2013-1 Evaluation Process No-Action Alternative CHAPTER 5 AIRPORT DEVELOPMENT ALTERNATIVES JUNE 2013-2
More informationAddendum - Airport Development Alternatives (Chapter 6)
Bowers Field Addendum - Airport Development Alternatives (Chapter 6) This addendum to the Airport Development Alternatives chapter includes the preferred airside development alternative and the preliminary
More informationPunta Gorda Airport Master Plan Update
Punta Gorda Airport Master Plan Update Draft Executive Summary Prepared for: The Charlotte County Airport Authority January 2018 Charlotte County Airport Authority James Herston, Chair Robert D. Hancik,
More informationICAO Standards. Airfield Information Signs. ICAO Annex 14, 4th Edition Aerodrome Design and Operations
ICAO Standards Airfield Information Signs ICAO Annex 14, 4th Edition Aerodrome Design and Operations Federal Aviation Administration U.S. Department of Transportation February 2004 ICAO Standards This
More informationTONOPAH AIRPORT REHABILITATE TAXIWAY B AND AIRCRAFT APRON
REHABILITATE TAXIWAY B AND AIRCRAFT APRON AIP NO. 3-32-0019-16 PWP-NY-2018-148 NYE COUNTY, NEVADA MARCH 16, 2018 N 376 Coaldale 265 Silver Peak 6 95 Tonopah TONOPAH AIRPORT Goldfield Warm Springs 6 E to
More informationLos Angeles International Airport (LAX) Airside $907M
Los Angeles International Airport (LAX) $3,948M Airside $907M Airfield Electrical Systems Rehabilitation Bradley West Core Renovation, East Ramp and Concourse Demolition Imperial Terminal Aircraft Parking
More informationCHICO MUNICIPAL AIRPORT NON-MOVEMENT AREA DRIVER TRAINING PROGRAM
CHICO MUNICIPAL AIRPORT NON-MOVEMENT AREA DRIVER TRAINING PROGRAM Introduction In an effort to provide the safest and most efficient operating environment for tenants and users of the Chico Municipal Airport
More informationDallas/Fort Worth International Airport Winter Weather Season Kick-Off Meeting
Dallas/Fort Worth International Airport Winter Weather Season Kick-Off Meeting 10.27.16 Dallas/Fort Worth International Airport Winter Weather Season Kick-Off Meeting Agenda Welcome / Introductions DFW
More information10.1 INTRODUCTION NORTH PERRY AIRPORT MASTER PLAN UPDATE SECTION 10: CAPITAL IMPROVEMENT PROGRAM
10.1 INTRODUCTION Based on the findings from the Facility Requirements and the combined plan recommended in the Alternative Analysis, a capital improvement program for North Perry Airport has been developed
More informationAviation Planning in Maine and Our Region. Stacie Haskell Aviation Coordinator & Study Manager Maine Department of Transportation April 27, 2011
Aviation Planning in Maine and Our Region Stacie Haskell Aviation Coordinator & Study Manager Maine Department of Transportation April 27, 2011 Overview The National Aviation System Maine s Economic Dependence
More informationBeginning balance available for Priority I Projects: $1,737,029
2016 COAR Grant Cycle Priority I Projects Airport Name Project Name Requested Grant Amount Match % of Grant Match Total Project Cost or Total FAA Grant Match Amount required RUNNING TOTAL (Available Balance)
More informationBuchanan Field. Airport Planning Program. Steering Committee. December 14, Master Plan FAR Part 150 Noise Study Strategic Business Plan
Airport Planning Program Master Plan FAR Part 150 Noise Study Strategic Business Plan Steering Committee December 14, 2006 Airport Planning Program Master Plan FAR Part 150 Noise Study Strategic Business
More informationNotice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application
July 3, 2018 Notice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application The City of Kansas City (City), Missouri through its Aviation Department ( the Department
More informationLakeland International Airport
Lakeland International Airport Sun n Fun Contractor & Volunteer Safety Briefing Updated 1/16/18 Airport Statistics 85 Tenants 1,000 people work here 126,000 aircraft operations annually. Why are we here?
More informationAIRFIELD OPERATIONAL INSTRUCTION 26 GENERAL AVIATION OPERATIONS
AIRFIELD OPERATIONAL INSTRUCTION 26 GENERAL AVIATION OPERATIONS Return to Contents Page Liverpool John Lennon Airport 0 20161012LJAAOI26V6.0pdf AIRFIELD OPERATIONAL INSTRUCTION 26 GENERAL AVIATION OPERATIONS
More informationAirside Construction Safety: The Human Factor
Airside Construction Safety: The Human Factor Presented by The Massachusetts Port Authority Houssam H. Sleiman, P.E., CCM Director, Capital Programs and Environmental Affairs September 25, 2010 ACI-NA
More informationGround Vehicle Operations Training READING REGIONAL AIRPORT
Ground Vehicle Operations Training READING REGIONAL AIRPORT October 22, 2014 Airport Operations Area (AOA) Movement Areas Non-Movement Areas Non-Movement Area Markings Never cross solid line with out ATC
More informationMELBOURNE AIRPORT AUTHORITY B R I E F REGULAR MEETING of March 23, :30 AM MELBOURNE INTERNATIONAL AIRPORT BOARD ROOM
MELBOURNE AIRPORT AUTHORITY B R I E F REGULAR MEETING of March 23, 2011 8:30 AM MELBOURNE INTERNATIONAL AIRPORT BOARD ROOM Pledge of Allegiance ACTION ITEMS APPROVAL OF MINUTES of the Regular Meeting of
More informationAviation Summit Design and Construction Services
Aviation Summit 2017 Design and Construction Services Agenda: Terminal 3 Modernization PHX Sky Train Stage 2 Terminal 4 S1 Concourse & Apron Other Capital Program Projects Terminal 3 Modernization Processor
More informationMOST aircraft need a runway for landing and takeout.
38th Annual Concrete Paving Workshop Upcoming Airport Projects January 17, 2017 MOST aircraft need a runway for landing and takeout. 1 Airport Improvement Program AIP Eligibility The federal AIP grants
More informationIRELAND AERONAUTICAL INFORMATION SERVICE IRISH AVIATION AUTHORITY BALLYCASEY CROSS SHANNON CO. CLARE Tel Fax
IRELAND AERONAUTICAL INFORMATION SERVICE IRISH AVIATION AUTHORITY BALLYCASEY CROSS SHANNON CO. CLARE Tel +353 61 703750 Fax +353 61 366245 DUBLIN AIRPORT (EIDW) RUNWAY 10/28 UPGRADE PHASE 1 AND PHASE 2
More informationPART F SECTION 2 RESPONSIBILITIES AND ACTIONS
F-2-1 AIRPORT OPERATIONS MANUAL AIRFIELD OPERATIONS 31 January 2011 PART F SECTION 2 RESPONSIBILITIES AND ACTIONS 1. Overview 1.1 This section outlines the responsibilities and actions of the airport organizations
More informationCHAPTER 3 ALTERNATIVES CONSIDERED
CHAPTER 3 ALTERNATIVES CONSIDERED 3.0 ALTERNATIVES The 2010 Stevensville Airport Master Plan contained five (5) airside development options designed to meet projected demands. Each of the options from
More informationRef. AIM Para AOPA Air Safety Foundation Supported by the FAA Ref. AIM Para Supported by the FAA
ILS Critical Area Holding Position Sign: ATC may hold you at this sign, on a taxiway, when the instrument landing system is being used at the airport. Aircraft taxiing beyond this point may interfere with
More informationPREFERRED PLAN Kahului Airport Master Plan and Noise Compatibility Program Update
PREFERRED PLAN Kahului Airport Master Plan and Noise Compatibility Program Update AIRPORTS DIVISION DEPARTMENT OF TRANSPORTATION March 13, 2012 AGENDA Introduction Purpose and Meeting Objectives Kahului
More informationCHAPTER 4: ALTERNATIVES
MSP Long Term Comprehensive Plan Update Metropolitan Airports Commission 4.1 INTRODUCTION CHAPTER 4: ALTERNATIVES Several alternatives were developed and evaluated based on their capability to meet the
More informationAirport Master Plan Open House Front Range Airport February 23, 2017
Airport Master Plan Open House Front Range Airport February 23, 2017 MASTER PLAN PROCESS AND OVERVIEW MASTER PLAN ELEMENTS The Master Plan is a 20-year plan to understand the needs of current and future
More informationChapter 4.0 Alternatives Analysis
Chapter 4.0 Alternatives Analysis Chapter 1 accumulated the baseline of existing airport data, Chapter 2 presented the outlook for the future in terms of operational activity, Chapter 3 defined the facilities
More informationMeeting Notes Public Open House
Meeting Notes Public Open House, 5:30-8:00 pm Fairbanks Pipeline Training Center, 3605 Cartwright Court, Fairbanks, Alaska= Agenda: Open House: 30 minutes Presentation: 45 minutes Question and Answers:
More information2018 Airport Master Plan Overview of Development Concepts. Greg Ballentine (WSP)
2018 Airport Master Plan Overview of Development Concepts Greg Ballentine (WSP) Thank You Stakeholder and community consultation has included discussions with over 40 stakeholder groups including airport
More informationAdvisory Circular CT
(CAA logo, name of the country, etc.) Advisory Circular CT-42-009 SUBJECT: Airport Movement Area and Related Facilities Maintenance DATE: MM/YYYY ASSOCIATED RULES According with (name of the country) Civil
More informationPavement Strength Analysis Prepared by Molzen Corbin September 2016
Pavement Strength Analysis Prepared by Molzen Corbin September 2016 The Santa Fe Municipal Airport was originally constructed in 1941. It was constructed by the military as a B-24 bomber training base.
More informationMASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4
MASTER PLAN UPDATE Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT Meeting #4 December 14, 2017 Today s Agenda o Welcome o Introductions o Progress update o Alternatives analysis
More informationprint materials visit information on free live seminars, online courses, and
The AOPA Air Safety Foundation is dedicated to making flying easier and safer for general aviation pilots. For information on free live seminars, online courses, and print materials visit. ILS Critical
More informationPlanned Procurement Opportunities Report. June 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationYolo County Airport. ALP Narrative Report. April Prepared by Mead & Hunt, Inc. for the County of Yolo, California
Yolo County Airport ALP Narrative Report April 2016 Prepared by Mead & Hunt, Inc. for the County of Yolo, California Yolo County Airport ALP Narrative Report Prepared for the County of Yolo Mindi Nunes,
More information6.4 Aviation AVIATION FACILITIES AND SERVICES
2035 Transportation Plan 6.4 Aviation This chapter describes existing aviation facilities and services in Placer County and projected needs. This chapter also discusses potential aviation issues related
More informationCollier County Airport Authority. Joint Automated Capital Improvement Program
Collier County Airport Authority Joint Automated Capital Improvement Program Joint Automated Capital Improvement Program (JACIP) What is the JACIP? Financial planning process supported by Web-based computer
More informationBremerton National Airport Airport Master Plan Project Update February 12, 2013
Bremerton National Airport Airport Master Plan Project Update February 12, 2013 Project Team Century West Engineering Northwest firm founded in 1969 500+ airport projects completed throughout the Pacific
More informationJWN Runway Safety Area Project Summer 2015 Closure
JWN Runway Safety Area Project Summer 2015 Closure March 2015 Welcome and Overview Doug Kreulen, Chief Operating Officer Robert Ramsey, P. E., A.A.E. Chief Engineer Overview Purpose of Closure Concurrent
More informationP U B L I C N O T I C E. MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application C-00-MBS
P U B L I C N O T I C E MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application 10-07-C-00-MBS INTRODUCTION: This Public Notice is issued as part of a Federal Aviation
More informationHollaway Consulting Engineers, LLC Statement of Qualifications
Deliberate, Strategic, Connected.Delivering tangible solutions for aviation design and construction management. Hollaway Consulting Engineers, LLC Statement of Qualifications Professional Experience Sheri
More informationPublic Notice July 14, 2017
Public Notice July 14, 2017 PROPOSED IMPLEMENTATION OF PFC 13 NOTICE TO AIR CARRIERS AND CONSULTATION MEETING Implementation of PFC On June 14, 2017 the Omaha Airport Authority provided written notice
More informationCONSTRUCTION SAFETY AND PHASING PLAN (CSPP)
TECHNICAL SPECIFICATIONS DENVER INTERNATIONAL AIRPORT DIVISION 1 GENERAL REQUIREMENTS 2019 ANNUAL AIRFIELD PAVEMENT REHABILITATION SECTION CONSTRUCTION SAFETY AND PHASING PLAN CONTRACT NO. 201947110 CONSTRUCTION
More informationInauguration 2017 Dulles Tower
Inauguration 2017 Dulles Tower Presented to: IAD Users By: IAD Staff, Management and NATCA Date:1/3/2017 General Information Inauguration takes place Friday, January 20, 2017 at 1200 (noon) local. The
More informationYakima Air Terminal/McAllister Field Airport Master Plan Update
Yakima Air Terminal/McAllister Field Airport Master Plan Update City of Yakima Work Session July 9, 2013 Meeting Goals Summarize the master plan recommendations. Discuss the decision-making process used
More informationKSBP HIGH. San Luis County Rgnl Airport San Luis Obispo, California, United States
Diagram #1: Runway 29 Departure Guide All Aircraft Categories / Runway 29 p. 1 of 8 Diagram #2: Runway 11 Departure Guide All Aircraft Categories / Runway 11 p. 2 of 8 NOISE ABATEMENT PROCEDURES by Whispertrack
More informationPUBLIC NOTICE FOR PROPOSED COLLECTION OF PASSENGER FACILITY CHARGES AT COLORADO SPRINGS AIRPORT
PUBLIC NOTICE FOR PROPOSED COLLECTION OF PASSENGER FACILITY CHARGES AT COLORADO SPRINGS AIRPORT Date of Public Notice: 8/15/2016 In accordance with the requirements of Section 158.24 of Federal Aviation
More informationFinancial Plan/Capital Improvements - DRAFT 6-1
The analyses completed in previous chapters evaluated development needs at McKinney National Airport (TKI or Airport) over the next 20 years, based on forecast activity, facility requirements, safety standards,
More informationPFC NOTICE AND OPPORTUNITY FOR PUBLIC COMMENT ST. THOMAS CYRIL E. KING AIRPORT SEPTEMBER 26, 2018
PFC NOTICE AND OPPORTUNITY FOR PUBLIC COMMENT ST. THOMAS CYRIL E. KING AIRPORT SEPTEMBER 26, 2018 Table of Contents Section Page I. Overview 2 II. Notice and Opportunity for Public Comment 3 III. Application
More informationLake Tahoe Airport Master Plan
Lake Tahoe Airport Master Plan City Council Briefing October 20, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development
More informationCAPITAL IMPROVEMENT PROGRAM LEE S SUMMIT AIRPORT
CAPITAL IMPROVEMENT PROGRAM 2007-2011 LEE S SUMMIT AIRPORT AIRPORT Pg. No. Project Yrs. 1 Air Traffic Control Tower 2,000 - - - - - - 2,000 2 Develop East Terminal Area 1,10 177,7 4,97 - - - 9,877 Land
More informationLake Tahoe Airport Master Plan Public Meeting March 16, 2015
Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development plans
More informationAWP ACIP DATA SHEET. $100,000 $5,263 $105,263 Access Road Project
Fiscal Year 2011 Approved P Airport Layout Plan (ALP) Diagram Update 75,000 3,947 78,947 D Design Electrical, and Pavement Improvements 75,000 3,947 78,947 Include Construction Safety Plans E Environmental
More informationCorrection to Council Resolution No , dated June 25, Please add the following correction as part of the permanent record:
1410 Memorandum 9 DATE October 20, 2014 CITY OF DALLAS TO Rosa Rios City Secretary SUBJECT Correction to Council Resolution No. 14-1030, dated Please add the following correction as part of the permanent
More informationAppendix B PAVEMENT CONDITION AND HISTORY
Appendix B PAVEMENT CONDITION AND HISTORY The Sunport maintains a pavement management program (PMP) in order monitor the condition of pavements and to plan for repair/replacement in a timely manner. The
More informationPUBLIC NOTICE ***************************** New Castle Airport. Intention to File a Passenger Facility Charge (PFC) Application
PUBLIC NOTICE ***************************** New Castle Airport Intention to File a Passenger Facility Charge (PFC) Application The Delaware River & Bay Authority (DRBA), the sponsor of the New Castle Airport
More informationOctober 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION
October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION The Master Plan Process Inventory Of Existing Conditions Complete. Forecasts Of Aviation Demand Complete. Facility Requirements Complete.
More informationCasper/Natrona County International Airport Master Plan Update Technical Advisory Committee Meeting Two - October 14th, :30 PM
Casper/Natrona County International Airport Master Plan Update Technical Advisory Committee Meeting Two - October 14th, 2014 1:30 PM Casper/Natrona County International Airport Master Plan Update Policy
More informationTable of Contents. Overview Objectives Key Issues Process...1-3
Table of Contents Chapter One Introduction Overview...1-1 Objectives...1-1 Key Issues...1-2 Process...1-3 Chapter Two Inventory of Existing Conditions Airport Setting...2-1 Locale...2-1 Airport Surroundings...2-5
More informationStakeholders Meeting
Stakeholders Meeting for the Expansion of Runway 9R-27L, Terminal 4 Gate Relocation and Land Acquisition for Runway 9R-27L September 22, 2011 Stakeholders Meeting AGENDA Introduction FLL Airport Improvements
More informationDallas Love Field Community Weekly Update
. DALLAS LOVE FIELD COMMUNITY WEEKLY UPDATE August 22 28, 2015 Dallas Love Field Community Weekly Update Crazy little thing called Love Field By: Lanre Olaniyan IN THIS ISSUE Announcements Dalfort Aerospace
More informationNON MOVEMENT AREA DRIVERS TRAINING
NON MOVEMENT AREA DRIVERS TRAINING Introduction Introduction The Federal Aviation Administration (FAA) and the Transportation Security Administration (TSA) have instituted rules and regulations requiring
More informationMELBOURNE AIRPORT AUTHORITY B R I E F REGULAR MEETING of April 27, :30 AM MELBOURNE INTERNATIONAL AIRPORT BOARD ROOM
MELBOURNE AIRPORT AUTHORITY B R I E F REGULAR MEETING of April 27, 2011 8:30 AM MELBOURNE INTERNATIONAL AIRPORT BOARD ROOM Pledge of Allegiance ACTION ITEMS APPROVAL OF MINUTES of the Regular Meeting of
More informationGENERAL AVIATION AIRPORT RULES AND REGULATIONS
GENERAL AVIATION AIRPORT RULES AND REGULATIONS GA WEST MINETA SAN JOSE INTERNATIONAL AIRPORT (CITY OF SAN JOSE) GENERAL AVIATION AIRPORT ACCESS CONTROL SYSTEM INSTRUCTION SHEET The following information
More informationCommunity Noise Consortium Meeting (CNC)
Community Noise Consortium Meeting (CNC) September 13, 2018 Meeting Title or Type / Month Day, Year Safety Restrooms: Outside the door you entered on the left. Emergency Exit: Door through which you entered
More informationAnn Arbor Municipal Airport Ann Arbor, MI Date of Latest ALP ACIP Airport Code - A Airport Identifier - ARB
MICHIGAN AIRPORT DEVELOPMENT PROGRAM AIP CAPITAL IMPROVEMENT PLAN 20102019 FEDERAL/STATE/LOCAL Ann Arbor, MI Date of Latest ALP 2008 ACIP Airport Code A Airport Identifier ARB Prepared by: MDOTAERO Sponsor:
More informationMilton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.
Milton GeneralAviationAirport PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton. Existing Facilities Peter Prince Airport is served by one runway, Runway 18/36, 3,700 feet
More information8 Aviation Support. 8.1 Aerodrome Rescue and Fire Fighting Services. 8.2 Aircraft Refuelling. 8.3 Air Cargo
8 Aviation Support 8.1 Aerodrome Rescue and Fire Fighting Services CASA mandates that a permanent Aerodrome Rescue and Fire Fighting Service (ARFFS) is established for domestic aerodromes when more than
More informationMajor Runway/Taxiway Maintenance Work Bangalore International Airport (Devanahalli) (08 MAR 2012 TO 04 MAY 2012)
AIRAC AIP SUPPLEMENT TEL: 91-11-24632950 Extn: 2219/2233 AFS : VIDDYXAX FAX : 91-11-24615508 Email: gmais@aai.aero INDIA AERONAUTICAL INFORMATION SERVICE AIRPORTS AUTHORITY OF INDIA RAJIV GANDHI BHAVAN
More information5. Facility Requirements
5. Facility Requirements The purpose of this chapter is to compare existing airfield and adjacent landside facilities with the Airport operations and aircraft forecasts developed in the previous chapter
More informationST. CLAIR COUNTY INTERNATIONAL AIRPORT MINIMUM STANDARDS
Introduction ST. CLAIR COUNTY INTERNATIONAL AIRPORT MINIMUM STANDARDS In order to encourage and ensure the economic health of, and the orderly operation of aviation and related activities at the St. Clair
More information7/1/2014. Class II Driver s License Information and Study Guide
7/1/2014 Class II Driver s License Information and Study Guide TABLE OF CONTENTS I. INTRODUCTION Purpose... 1 General Requirements... 1 Policy Statement... 1 Authority... 2 Procedures For Obtaining an
More informationGeneral Aviation Master Plan Update
Peter O. Knight Airport Public Meeting #2 Peter O. Knight Airport Agenda Welcome and Introductions HCAA System of Airports Purpose of Public Meetings Master Plan Status Update Next Steps Q & A 2 Our System
More informationChapter Seven COST ESTIMATES AND FUNDING A. GENERAL
Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL This chapter delineates the recommended 2005 2024 Sussex County Airport Capital Improvement Program (CIP). It further identifies probable construction
More informationBrunswick Executive Airport. Airport Safety Program
Brunswick Executive Airport Airport Safety Program Why Runway Incursions FY 14 FY 13 FY 12 FY 11 1 st Quarter 298 273 226 215 2 nd Quarter 258 287 267 246 3 rd Quarter 359 328 352 257 4 th Quarter 349
More informationNOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019
NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019 The City of Atlanta is providing an opportunity for public comment until April 25, 2019 related to the
More informationOPERATIONAL ADVICE NOTICE (OAN) OAN 07 / 2018 MAN-TP AIRSIDE SURVEYS
OAN 07 / 2018 MAN-TP AIRSIDE SURVEYS OAN REF:- 07/2018 DATE OF ISSUE:- 19/01/18 EFFECTIVE DATE:- 28/01/18 MANUAL REFERENCE(S):- N A EXPIRY DATE:- 30/03/18 PLEASE ENSURE THIS INFORMATION IS PROMULGATED
More informationDallas Love Field Community Weekly Update
DALLAS LOVE FIELD COMMUNITY WEEKLY UPDATE March 7-March 13, 2015 Dallas Love Field Community Weekly Update SNOW DAY AT DALLAS LOVE FIELD! IN THIS ISSUE A Love Note from Me to You by Ms. Courtenay Shorter
More informationWestover Metropolitan Airport Master Plan Update
Westover Metropolitan Airport Master Plan Update June 2008 INTRODUCTION Westover Metropolitan Airport (CEF) comprises the civilian portion of a joint-use facility located in Chicopee, Massachusetts. The
More informationCHAPTER 3 AIRPORT FACILITY REQUIREMENTS
CHAPTER 3 AIRPORT FACILITY REQUIREMENTS 3.1 Introduction The existing runway and taxiway system at Skyhaven Airport provides more than adequate operational capacity to accommodate future peak hour and
More informationAERODROME MARKINGS AND SIGNALIZATION
1. Introduction AERODROME MARKINGS AND SIGNALIZATION This article will present the main aerodrome markings and signalization on runways and taxiways. 2. Runway Markings This chapter will show the runway
More informationLopez Island Airport Master Plan Update. Public Meeting June 15, 2017
Lopez Island Airport Master Plan Update Public Meeting June 15, 2017 Master Plan Update Team Reid Middleton/Everett, WA Shannon Kinsella, Project Manager Melania Haagsma, Project Engineer Mead & Hunt/Tulsa,
More informationRunway Incursions 3 Markings
Session Visual Aids Runway Incursions 3 Markings 3.12.2 A runway-holding position shall be established: a) on the taxiway, at the intersection of a taxiway and a runway; and b) at an intersection of a
More informationPART H SECTION 3 GENERAL REQUIREMENTS AND PROCEDURES GOVERNING THE EXECUTION OF WORKS ON OR ADJACENT TO AIRSIDE OPERATIONAL AREAS
H-3-1 PART H SECTION 3 GENERAL REQUIREMENTS AND PROCEDURES GOVERNING THE EXECUTION OF WORKS ON OR ADJACENT TO AIRSIDE OPERATIONAL AREAS 1. Regulations 1.1 These requirements are intended to ensure that
More informationAlternatives Analysis EXECUTIVE SUMMARY
Alternatives Analysis EXECUTIVE SUMMARY Alternative development plans were created as part of the Master Plan for Harrisburg International Airport. The aim is to provide sufficient capacity for projected
More informationRules and Regulations
APPENDIX 1 LOW-VISABILITY OPERATIONS/SURFACE MOVEMENT GUIDANCE AND CONTROL SYSTEM (LVO/SMGCS) PLAN TABLE OF CONTENTS TITLE PAGE 1.0 INTRODUCTION 2 2.0 DEFINITIONS 3 3.0 FACILITIES, SERVICES AND EQUIPMENT
More information8.0 AIRPORT LAYOUT PLANS
8.0 AIRPORT LAYOUT PLANS This chapter presents a detailed graphic and narrative description of the selected development concept for General Mitchell International Airport (MKE). The plans package presented
More informationHow to be Prepared for an Airport Emergency and What to Look for When Inspecting Your Airfield
How to be Prepared for an Airport Emergency and What to Look for When Inspecting Your Airfield David Decoteau, A.A.E., C.A.E. Hayward Executive Airport Job of Airport Operations Commercial vs GA Airfield
More informationSECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES
SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES 5.1 INTRODUCTION This section investigates Airfield Development Alternatives, generalized Land Use Alternatives, and more detailed General Aviation Alternatives.
More informationLOGAN - CACHE AIRPORT AUTHORITY BOARD MEETING MAY 4, 2016 MINUTES
LOGAN - CACHE AIRPORT AUTHORITY BOARD MEETING MAY 4, 2016 MINUTES The Logan-Cache Airport Authority Board convened in a regular session on May 4, 2016 at 7:30 a.m. in the Cache County Historic Courthouse,
More informationChapter 4 Airport Facility Requirements
Chapter 4 Airport Facility Requirements Introduction CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-1 Organization of Materials CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-2 RPZ - ROAD RPZ - NON-AIRPORT
More informationPlanned Procurement Opportunities Report. March 2017
HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the
More informationDriving Training Class. Presented by: Lancaster Airport Authority
Driving Training Class Presented by: Lancaster Airport Authority Driving is a Privilege Driving on the airport, airport apron and ramps is a privilege and can be revoked at anytime for any reason. Violations
More informationFORECASTING FUTURE ACTIVITY
EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver
More informationREQUEST FOR COMPETITIVE SEALED PROPOSALS AIRPORT MANAGEMENT SERVICES MARV SKIE/LINCOLN COUNTY AIRPORT
REQUEST FOR COMPETITIVE SEALED PROPOSALS AIRPORT MANAGEMENT SERVICES MARV SKIE/LINCOLN COUNTY AIRPORT March 26, 2019 LINCOLN COUNTY BOARD OF COMMISSIONERS 104 N. MAIN, STE. 110 CANTON, SD 57013-1703 (605)764-5732
More information