1 Wellesley Station Second Exit and Automatic Entrance Public Open House Tuesday, September 23, 2014 Central YMCA 20 Grosvenor Street 1

2 What are Second Exits? Second exits serve three functions: As a primary exit if the main exit is blocked in an emergency As an additional exit in an emergency As a convenience to customers Castle Frank Second Exit Dufferin Station Second Exit September 23, 2014 Wellesley Station Second Exit and Automatic Entrance 2

3 Second Exits Considerations Effective second exits must provide: A fast way out of the station Convenience to encourage day-to-day use and familiarity in an emergency Integration into the neighbourhood Woodbine Station Second Exit (Under Construction) 3

4 Second Exits Background Most subway stations have more than one exit All new TTC stations are built with at least two exits 2002 Fire & Life Safety Assessment Study identified 14 priority stations needing a second exit TTC voluntary program retrofitting existing stations to provide an additional way out in case of emergency and to improve customer convenience In 2009, the TTC Board approved an automatic entrance, to be combined with the second exit at Wellesley Station 4

5 Status of Second Exit Program 14 stations identified as priority: Broadview, Castle Frank, Dufferin and Pape complete Wellesley planning complete Woodbine under construction 8 to be planned: Dufferin Station Second Exit Chester, College, Donlands, Dundas, Dundas West, Greenwood, Museum and Summerhill Pape Station Second Exit 5

6 Background Wellesley Station Second Exit Second Exit and Automatic Entrance Project Second Exit Former Proposal Construction of a second exit was slated to start in January 2012 at 15 Dundonald Street property Opportunity arose to work with a developer to connect the Second Exit into a future development Yonge St 15 Dundonald Street Existing Entry/Exit Wellesley Station Second Exit / Entrance Current Proposal 17 Dundonald Street Wellesley St E at 17 Dundonald 6

7 Site Plan New Staircase New Staircase New Exit/Entrance Dundonald Street City Sidewalk Yonge Street Laneway Laneway Bus Driveway 15 Dundonald Street e Bus Driveway 17 Dundonald Street 24 Storey Building Existing Path Legend New Concourse Level (Below Grade) Sliding Door Existing Main Entrance to Wellesley Station Wellesley Street East Platform and Track Level (Below Grade) 7

8 New Exit/Entrance Concourse Level Southbound Stair Midlanding Northbound Stair Midlanding Southbound Stair Northbound Stair Corridor Access Corridor Sounthbound Platform Sounthbound Track Northbound Track Northbound Platform Property Line Proposed Future Connection and Exit/Entrance 17 Dundonald Legend New Concourse Level (Below Grade) Platform and Track Level (Below Grade) 8

9 Proposed Development at 17 Dundonald Street A developer has proposed that the second exit and automatic entrance be housed within the new condominium development at 17 Dundonald Coordination is ongoing between the development and the Second Exit and Automatic Entrance project Existing property at 17 Dundonald Conceptual rendering of 17 Dundonald with Wellesley Station second exit/automatic entrance integration after completion of TTC & Developer's construction 9

10 TTC Construction Schedule TTC Construction is scheduled to begin in Fall 2014 Work will require a full road closure in front of 15 Dundonald Street The construction is scheduled to be completed in Spring 2017 The opening of the new exit/entrance will be coordinated with the condominium development completion 10

11 Traffic Management North Pedestrian Path Maintained Road Closure James Canning Gardens Southbound Tracks Below Grade Northbound Tracks Below Grade Outline of Concourse Level Below Grade Two-way traffic to Yonge Street during construction Outline of Proposed Construction Fence Dundonald Street Two-way traffic to Church Street during construction City Sidewalk Yonge Street Driveway Access to 15 Dundonald Maintained No street parking on Dundonald for duration of construction 15 Dundonald 17 Dundonald 19 Dundonald Back Laneway Maintained Southbound Tracks Below Grade Northbound Tracks Below Grade Platform Level Below Grade Pedestrian Walkway Closed Bus Driveway Wellesley Station Bus Driveway To Church Street Existing Main Entrance to Wellesley Station Wellesley Street East September 23, 2014 Wellesley Station Second Exit and Automatic Entrance 11

12 What to Expect During Construction Community: TTC Contractor will comply with City noise bylaws Monday to Friday 7:00 am to 7:00 pm Saturday 9:00 am to 7:00 pm Work outside these hours will be very limited and only when essential Sequence work in phases to reduce impact to the community Provide standard dust mitigation measures 12

13 What to Expect During Construction Community: Sewer line and water line will be relocated in the early stages of the project A few hours of water disruption will be required for 15 Dundonald residents - advanced notice will be provided 13

14 What to Expect During Construction Vehicular Traffic: Street to be closed to vehicular traffic in front of 15 Dundonald TTC Service: No impact to Wellesley Station subway or bus services Dundonald will become a two-way street for duration of project Driveway Access to 15 Dundonald Maintained North pedestrian path maintained Road Closure Street parking removed to accommodate two lanes of traffic in Construction Zone Dundonald St each direction Laneway access west of 15 Dundonald Yonge Street Proposed Hoarding 15 Dundonald 17 Dundonald 19 Dundonald Street property will be maintained Pedestrians: The pedestrian walkway between Back Laneway Maintained Pedestrian Walkway Closed Wellesley and Dundonald will be closed for duration of the project Wellesley Station Wellesley Street East An east-west pedestrian pathway on the north side of Dundonald Street will be maintained as best as possible. Sidewalk closures may be required during the beginning phases of the project.* Wellesley Station Second Exit and Automatic Entrance 14

15 Contact Us Contact Us Web: projects.ttc.ca Phone: TTY: Fax: Mail: Devin Horne Senior Community Liaison Officer 1900 Yonge Street 2nd Floor Toronto, ON Public Input Please fill out a comment sheet and provide us with your thoughts on the Wellesley Station Second Exit and automatic entrance project This presentation will be available at projects.ttc.ca Please submit your comments by September 30 to devin.horne@ttc.ca Planned TTC Project Schedule Fall 2014 Begin TTC Construction Spring 2017 Complete TTC Construction Thank you for your participation! 15

St. Clair West Station Easier Access Project Community Update Open House

St. Clair West Station Easier Access Project Community Update Open House St. Clair West Station Easier Access Project Community Update Open House 1 Easier Access Program Wide Committed to making all 69 stations accessible by 2025 31 stations completed - almost halfway there

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: SUBJECT: Resubmitted December 19, 2012 November 21, 2012 MODERNIZING THE TTC A NEW APPROACH TO COMMUNICATIONS, COMMUNITY

More information

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED STAFF REPORT ACTION REQUIRED PLANNING AND CONSULTATION PROCESS FOR SECOND EXITS CHESTER STATION UPDATE Date: September 28, 2015 To: From: TTC Board Chief Executive Officer Summary Staff reported to the

More information

Ossington Station Easier Access Project - Construction & Public Art Concept Update

Ossington Station Easier Access Project - Construction & Public Art Concept Update Ossington Station Easier Access Project Construction & Public Art Concept Update Open House College/Shaw Library 1 Easier Access Program Wide Committed to making all stations accessible by 2025 34 stations

More information

Chester Station Second Exit Project Community Meeting April 9, Consultation Summary Report

Chester Station Second Exit Project Community Meeting April 9, Consultation Summary Report Chester Station Second Exit Project Community Meeting April 9, 2014 Consultation Summary Report TABLE OF CONTENTS 1. INTRODUCTION... 3 1.1 BACKGROUND... 3 1.2 EVENT PROMOTION... 3 1.3 CONSULTATION PROCESS...

More information

As the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required.

As the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required. REPORT FOR ACTION Construction Staging Area - 81 Bay Street Date: December 11, 2017 To: Toronto and East York, Community Council From: Acting Director, Transportation Services Toronto and East York District

More information

MEETING DATE: February 17, 2010 SUBJECT: ACTION ITEM TORONTO TRANSIT COMMISSION REPORT NO. ACCESSIBLE TRANSIT SERVICES PLAN: 2009 STATUS REPORT

MEETING DATE: February 17, 2010 SUBJECT: ACTION ITEM TORONTO TRANSIT COMMISSION REPORT NO. ACCESSIBLE TRANSIT SERVICES PLAN: 2009 STATUS REPORT TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: February 17, 2010 SUBJECT: ACCESSIBLE TRANSIT SERVICES PLAN: 2009 STATUS REPORT ACTION ITEM RECOMMENDATION It is recommended that the Commission forward

More information

WORKING WITH BIAS ON TTC PROJECTS

WORKING WITH BIAS ON TTC PROJECTS WORKING WITH BIAS ON TTC PROJECTS David Nagler Manager Community Relations, TTC November 17, 2015 TABIA-CITY meeting Nov, 17, 2015 November 17, 2015 1 OVERVIEW 1. Working with BIAs on major construction

More information

LESLIE BARNS & CONNECTION TRACK. Construction Liaison Group Meeting #6 January 30, 2014

LESLIE BARNS & CONNECTION TRACK. Construction Liaison Group Meeting #6 January 30, 2014 LESLIE BARNS & CONNECTION TRACK Construction Liaison Group Meeting #6 January 30, 2014 Construction Liaison Group Jan 30 2014 1 OVERVIEW HAPPY BELATED NEW YEAR Works to Date Underground Utilities Bell

More information

Woodbine Station Easier Access Project Public Open House January 27, :30 pm 8:30 pm Consultation Summary Report

Woodbine Station Easier Access Project Public Open House January 27, :30 pm 8:30 pm Consultation Summary Report Woodbine Station Easier Access Project Public Open House January 27, 2014 6:30 pm 8:30 pm Consultation Summary Report Danforth Mennonite Church 2174 Danforth Ave Prepared by Lito Romano February 18, 2014

More information

Meeting Purpose & Summary: On January 31, 2018, the TTC hosted the fourth meeting of the Greenwood Second Exit Local Working Group (LWG).

Meeting Purpose & Summary: On January 31, 2018, the TTC hosted the fourth meeting of the Greenwood Second Exit Local Working Group (LWG). Greenwood Station Second Exit Local Working Group (LWG) Meeting #4 January 31, 2018 St David s Church Basement 6:30 p.m. - 9:00 p.m. Meeting Purpose & Summary: On January 31, 2018, the TTC hosted the fourth

More information

Main Street Station Upgrades

Main Street Station Upgrades Main Street Station Upgrades Public Meeting Hope United Church 1 Main Street Station Upgrades Bus diversions Planned improvements Construction staging Pedestrian flows 2 Main Street Station Aerial Bar

More information

Construction Staging Area 19 Western Battery Road

Construction Staging Area 19 Western Battery Road REPORT FOR ACTION Construction Staging Area 19 Western Battery Road Date: December 6, 2017 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York

More information

Construction Staging Area Blue Jays Way (357 King Street West)

Construction Staging Area Blue Jays Way (357 King Street West) REPORT FOR ACTION Construction Staging Area Blue Jays Way (357 King Street West) Date: June 8, 2018. To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto

More information

LESLIE BARNS & CONNECTION TRACK. Leslieville BIA Meeting May 2, 2014

LESLIE BARNS & CONNECTION TRACK. Leslieville BIA Meeting May 2, 2014 LESLIE BARNS & CONNECTION TRACK Leslieville BIA Meeting May 2, 2014 1 OVERVIEW Communications Queen/Leslie Intersection Closure Overview Next Steps - Coordination of TTC Track Upgrades (Queen streetcar

More information

Construction Staging Area 197 Redpath Avenue

Construction Staging Area 197 Redpath Avenue REPORT FOR ACTION Construction Staging Area 197 Redpath Avenue Date: January 31, 2017 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York District

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: November 18, 2013 SUBJECT: YONGE-EGLINTON AND EGLINTON WEST INTERCHANGE STATIONS METROLINX EGLINTON CROSSTOWN LIGHT RAIL TRANSIT PROJECT

More information

6:00 am, June 22 to 6:00 am June 25, 2018 Wood Street, Between Church St and a point approx 200 ft east of Church St. lane)

6:00 am, June 22 to 6:00 am June 25, 2018 Wood Street, Between Church St and a point approx 200 ft east of Church St. lane) Pride Toronto invites you to celebrate with us, and over 1 million people, at this year s Pride Festival from Friday June 22nd to Sunday June 24th, 2018. As one of the largest Pride festivals in the world,

More information

LESLIE BARNS & CONNECTION TRACK. Project Update Construction and Traffic Management Consultation

LESLIE BARNS & CONNECTION TRACK. Project Update Construction and Traffic Management Consultation LESLIE BARNS & CONNECTION TRACK Project Update Construction and Traffic Management Consultation PRESENTATION SUMMARY Part 1 Brief Project Update (New Streetcars & Streetscape Improvements) Part 2 Construction

More information

Construction Staging Adelaide Street West

Construction Staging Adelaide Street West REPORT FOR ACTION Construction Staging Adelaide Street West Date: October 6, 2016 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York District

More information

KING STREET PILOT STUDY PUBLIC MEETING

KING STREET PILOT STUDY PUBLIC MEETING KING STREET PILOT STUDY PUBLIC MEETING 2017.02.13 PUBLIC WORK with GEHL STUDIO / NEW YORK SWERHUN ASSOCIATES SAM SCHWARTZ CONSULTING LLC STARTING POINTS 17 1 - TRANSIT FIRST! Transit service is beyond

More information

The Point Roundabout Improvement Scheme

The Point Roundabout Improvement Scheme The Point Roundabout Improvement Scheme Background and Existing Situation The junction of North Wall Quay, East Wall Road and the East Link Bridge, also known as the Point roundabout, is located in the

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: March 26, 2014 SUBJECT: KENNEDY INTERCHANGE STATION: METROLINX EGLINTON CROSSTOWN LIGHT RAIL TRANSIT PROJECT - PRELIMINARY CONCEPT

More information

Union Station Queens Quay Transit Link Study

Union Station Queens Quay Transit Link Study Welcome Union Station in 1899. Image: City of Toronto Archives Union Station today. Image: Camil Rosiak Activity along Queens Quay. Image: Waterfront Toronto For more information or to comment, visit toronto.ca/waterfronttransit

More information

Hospital Link Project Project Update Winter 2018

Hospital Link Project Project Update Winter 2018 Hospital Link Project Project Update Winter 2018 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction of the Hospital Link facility is open

More information

Route 29 Solutions Projects

Route 29 Solutions Projects Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement

More information

Crystal City Station Improvements. Project Overview. Table 2: North Entrance. Table 1: South Entrance. 20th St. S 18th St. S.

Crystal City Station Improvements. Project Overview. Table 2: North Entrance. Table 1: South Entrance. 20th St. S 18th St. S. Table 1: South Entrance Table 2: North Entrance 20th St. S 18th St. S Proposed Second Entrance Crystal Drive Existing Station Location Platform Future 4 th Track Future New Airport Connection (by others)

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: March 30, 2012 SUBJECT: TTC SERVICE TO GEORGE BROWN COLLEGE WATERFRONT CAMPUS ACTION ITEM: RECOMMENDATIONS It is recommended

More information

KING STREET TRANSIT PILOT

KING STREET TRANSIT PILOT KING STREET TRANSIT PILOT Update toronto.ca/kingstreetpilot #kingstreetpilot HIGHLIGHTS TRANSIT RIDERSHIP TRANSIT CAPACITY To respond to this growth in ridership, the TTC has increased the capacity of

More information

SOUTHBOUND YONGE STREET TO EASTBOUND HIGHWAY 401 F L Y -UNDER

SOUTHBOUND YONGE STREET TO EASTBOUND HIGHWAY 401 F L Y -UNDER SOUTHBOUND YONGE STREET TO EASTBOUND HIGHWAY 401 F L Y -UNDER Proposal to Eliminate Traffic Gridlock in South North York Centre Area With Southbound Yonge Street to Eastbound Highway 401 Fly-UNDER A much

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 29, 2009 SUBJECT: TORONTO-YORK SPADINA SUBWAY EXTENSION PROJECT STEELES WEST STATION APPROVAL OF CONCEPTUAL DESIGN

More information

Spadina Avenue which would include two new underground stations located at Yonge Street and at University Avenue.

Spadina Avenue which would include two new underground stations located at Yonge Street and at University Avenue. TORONTO TRANSIT COMMISSION REPORT No S7 MEETING DATE June 4, 1968 FROM: General Manager Subway Construction Date June 3, 1968 Subject: QUEEN STREET SUBWAY FOR STREETCAR OPERATION The Commission, at its

More information

York Region Rapid Transit Corporation Board of Directors. Mary-Frances Turner, President

York Region Rapid Transit Corporation Board of Directors. Mary-Frances Turner, President Meeting of the Board of Directors On June 9, 2011 To: From: Subject: Ref: York Region Rapid Transit Corporation Board of Directors Mary-Frances Turner, President Spadina Subway Project Update YORK-#3369547

More information

NFTA Access Enhancement Study for Canalside and Cobblestone Alternatives Discussion. Alternative A South Park Avenue

NFTA Access Enhancement Study for Canalside and Cobblestone Alternatives Discussion. Alternative A South Park Avenue Alternative A South Park Avenue Alternative A Summary Alternative A extends Metro Rail service around the foot of Main Street east along South Park Avenue to serve a new station platform located along

More information

ARRIVAL AND DEPARTURE FROM PEARSON INTERNATIONAL AIRPORT

ARRIVAL AND DEPARTURE FROM PEARSON INTERNATIONAL AIRPORT ARRIVAL AND DEPARTURE FROM PEARSON INTERNATIONAL AIRPORT By Taxi Your hotel name and address should be enough for the cab driver to get you where you need to go. Note: many of the taxis charge a flat rate

More information

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED STAFF REPORT ACTION REQUIRED 2015 Accessibility Plan Status Report Date: March 26, 2015 To: From: TTC Board Chief Executive Officer Summary This report describes, in detail, how the TTC is meeting, or

More information

List of Our Ongoing Noise and Vibration Monitoring Projects

List of Our Ongoing Noise and Vibration Monitoring Projects List of Our Ongoing Noise and Vibration Monitoring Projects Project 1: Name of Project: Geotechnical Instrumentation and Monitoring Plan- Segment 1- Keelesdale Station Client: Metrolinx-Eglinton Crosstown

More information

Director, Community Planning, Toronto and East York District

Director, Community Planning, Toronto and East York District STAFF REPORT October 31, 2005 To: From: Subject: Toronto and East York Community Council Director, Community Planning, Toronto and East York District Final Report OPA and Rezoning Application 05 132450

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018

Crenshaw/LAX Transit Project Construction Update Community Meeting. November 15, 2018 Crenshaw/LAX Transit Project Construction Update Community Meeting November 15, 2018 Project Overview Walsh Shea Corridor Constructors (WSCC) Main Line & Stations Contractor Hensel Phelps Herzog (HPH)

More information

Long water shutdown scheduled for Tuesday, September 18

Long water shutdown scheduled for Tuesday, September 18 Thank you for your interest in the Center City Connector Streetcar. In this weekly update, you ll find information about ongoing construction for the 1st phase of utility work in Pioneer Square. Utility

More information

N. Central St. & W. Jackson Ave. Streetscape Projects

N. Central St. & W. Jackson Ave. Streetscape Projects N. Central St. & W. Jackson Ave. Streetscape Projects October 13, 2016 Meeting Overview North Central Street City of Knoxville KUB History & Vision Plan Timing Project Area Overview Schedule Communications

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: February 2, 2011 SUBJECT: TORONTO-YORK SPADINA SUBWAY EXTENSION PROJECT STEELES WEST STATION APPROVAL OF FINAL DESIGN, FINISHES

More information

Construction Staging Area 700 Bay Street - Elizabeth Street and Walton Street

Construction Staging Area 700 Bay Street - Elizabeth Street and Walton Street REPORT FOR ACTION Construction Staging Area 700 Bay Street - Elizabeth Street and Walton Street Date: March 7, 2017 To: Toronto and East York Community Council From: Acting Director, Transportation Services,

More information

York Region Rapid Transit Corporation. City of Vaughan Committee of the Whole June 1, 2016

York Region Rapid Transit Corporation. City of Vaughan Committee of the Whole June 1, 2016 York Region Rapid Transit Corporation City of Vaughan Committee of the Whole June 1, 2016 0 Agenda Future rapid transit projects > Yonge North Subway Extension [YNSE] > Regional Express Rail [RER] Current

More information

Improving Directional Signage for TTC Services at Pearson Airport

Improving Directional Signage for TTC Services at Pearson Airport For Action Improving Directional Signage for TTC Services at Pearson Airport Date: May 8, 2018 To: TTC Board From: Executive Director Corporate Communications Summary This report outlines the signage and

More information

1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET

1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET Report No. 3 of the Regional Council Meeting of March 28, 2013 1 PROJECT STATUS UPDATE 2 ND CONCESSION FROM BRISTOL ROAD TO DOANE ROAD TOWNS OF EAST GWILLIMBURY AND NEWMARKET The recommends: 1. Receipt

More information

12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization

12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization REPORT FOR ACTION 12, 14 and 16 York Street - Amendments to Section 16 Agreement and Road Closure Authorization Date: April 27, 2018 To: Toronto and East York Community Council From: Senior Strategic Director,

More information

Chicago St. Louis High-Speed Rail. Braidwood Construction. Local Officials Briefing August 7, 2014

Chicago St. Louis High-Speed Rail. Braidwood Construction. Local Officials Briefing August 7, 2014 Chicago St. Louis High-Speed Rail Braidwood Construction Local Officials Briefing August 7, 2014 1 Chicago-St. Louis Corridor Goals and Benefits» Reduction in travel time by about an hour» Enhanced reliability»

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: May 1, 2012 SUBJECT: LRT PROJECTS IN TORONTO - STATUS REPORT INFORMATION ITEM RECOMMENDATION It is recommended that the Commission

More information

June-December TBD, to be coordinated with Accessibility Ramps Project

June-December TBD, to be coordinated with Accessibility Ramps Project TTC Updates St. Clair Coordinated Projects TTC is coordinating various accessibility and infrastructure improvement projects along the St. Clair streetcar route which are expected to begin this summer.

More information

WHO IS METROLINX?

WHO IS METROLINX? CROSSTOWN LRT WHO IS METROLINX? Construction of the Eglinton Crosstown LRT Line Background In September 2008, Metrolinx launched a regional transportation plan a 25-year, $50 billion plan -- to coordinate

More information

YORK UNIVERSITY BUSWAY SERVICE CHANGES

YORK UNIVERSITY BUSWAY SERVICE CHANGES Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: April 27, 2009 SUBJECT: YORK UNIVERSITY BUSWAY SERVICE CHANGES ACTION ITEM RECOMMENDATIONS It is recommended that the Commission:

More information

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk STAGE 1 Viaduct removal, deck replacement on the River Bridge, and approach of the Chicago River Bridge north to Roscoe) Maintain local access roadways - 1 lane in each direction A signed alternate route

More information

Ridership Growth Strategy (RGS) Status Update

Ridership Growth Strategy (RGS) Status Update For Information Ridership Growth Strategy (RGS) Status Update Date: July 10, 2018 To: TTC Board From: Deputy Chief Executive Officer Summary The TTC s Ridership Growth Strategy (RGS), with all its components,

More information

1 Metrolinx overview. Mission We connect our communities. Vision Getting you there better, faster and easier

1 Metrolinx overview. Mission We connect our communities. Vision Getting you there better, faster and easier Mission We connect our communities Vision Getting you there better, faster and easier Values Play as a team Think forward Serve with passion 1 Metrolinx overview go transit, up express, presto Serve a

More information

Bloor Street West Rezoning Application for a Temporary Use By-law Final Report

Bloor Street West Rezoning Application for a Temporary Use By-law Final Report STAFF REPORT ACTION REQUIRED 3741 3751 Bloor Street West Rezoning Application for a Temporary Use By-law Final Report Date: June 12, 2007 To: From: Wards: Reference Number: Etobicoke York Community Council

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF JANUARY 25, 2011

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF JANUARY 25, 2011 Item 1, Report No. 1, of the Priorities and Key Initiatives Committee, which was adopted without amendment by the Council of the City of Vaughan on January 25,. 1 RAPID TRANSIT UPDATE TORONTO-YORK SPADINA

More information

582 Church St. 580 Church St Bay St. 558 Yonge St.

582 Church St. 580 Church St Bay St. 558 Yonge St. 1,324sf in basement 1,324sf on ground flr 1,324sf on 2nd flr 649sf on 3rd flr 1 582 Church St. - Net mid $60 s per sf - Excellent fully fixture restaurant - Huge patio fronting on Church St corner; 2 other

More information

BILLY BISHOP TORONTO CITY AIRPORT 2018 MASTER PLAN UPDATE

BILLY BISHOP TORONTO CITY AIRPORT 2018 MASTER PLAN UPDATE BILLY BISHOP TORONTO CITY AIRPORT 2018 MASTER PLAN UPDATE City of Toronto Local Issues & Initiatives Bryan Bowen City Planning Waterfront Secretariat June 25, 2018 PRESENTATION OUTLINE BACKGROUND: ISSUES

More information

Dufferin Jog Elimination Project

Dufferin Jog Elimination Project Project Project Status Update November 14 2007 Project History Planning Alternatives Criteria Measured Project Benefits Structural Configurations Considered Structural Design Considerations The Preferred

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Revised: March/13 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: March 26, 2014 SUBJECT: UNION PRECINCT STATUS REPORT UPDATE ON CONSTRUCTION INFORMATION ITEM RECOMMENDATION It is recommended that

More information

Neighbourhood Committee NDG - Westmount. September 12, 2016

Neighbourhood Committee NDG - Westmount. September 12, 2016 Neighbourhood Committee NDG - Westmount September 12, 2016 2 Presentation Outline Requests from the committee members Feedback on previous questions Work update and hindrance of the Turcot Project Ministry

More information

NEW. 750 Yonge St. 582 Church St. 580 Church St. 56 Wellesley St.W.

NEW. 750 Yonge St. 582 Church St. 580 Church St. 56 Wellesley St.W. 1 750 Yonge St. 4,500sf on ground flr + basement - Net Rent: $100/sf - TMI: $40/sf - Frontage: 30ft - Amazing signage opportunity right on Yonge St - Steps from the Yonge & Bloor intersection + Subway

More information

Town of Markham Yonge and Steeles Corridor Study and City of Vaughan Yonge Street Area Study

Town of Markham Yonge and Steeles Corridor Study and City of Vaughan Yonge Street Area Study STAFF REPORT ACTION REQUIRED Town of Markham Yonge and Steeles Corridor Study and City of Vaughan Yonge Street Area Study Date: August 14, 2009 To: From: Wards: Reference Number: North York Community Council

More information

77 McDonnell-Lindbergh - Monday thru Friday NORTHBOUND Effective: March 18, Shopping Center North County. Shopping Center Washington &

77 McDonnell-Lindbergh - Monday thru Friday NORTHBOUND Effective: March 18, Shopping Center North County. Shopping Center Washington & 77 McDonnell- - Monday thru Friday NORTHBOUND Effective: March 18, 2019 & Valley Industries 4:53A 4:59A 5:10A 5:18A 5:27A 5:39A 5:33A 5:39A 5:50A 5:58A 6:07A 6:19A 6:13A 6:19A 6:31A 6:39A 6:49A 7:02A 6:53A

More information

4 YORK REGION TRANSIT DON MILLS SUBWAY STATION ACCESS AGREEMENT

4 YORK REGION TRANSIT DON MILLS SUBWAY STATION ACCESS AGREEMENT 4 YORK REGION TRANSIT DON MILLS SUBWAY STATION ACCESS AGREEMENT The Transit Committee recommends the adoption of the recommendations contained in the following report, September 20, 2007, from the General

More information

Claremont Project Background and Update Community Meeting September 11, 2017

Claremont Project Background and Update Community Meeting September 11, 2017 Claremont Project Background and Update Community Meeting September 11, 2017 Topics Project Background Claremont Segment Information Project Timeline Upcoming Discussion Items Upcoming Meetings Questions

More information

TORONTO AND EAST YORK COMMUNITY COUNCIL AGENDA MEETING 5

TORONTO AND EAST YORK COMMUNITY COUNCIL AGENDA MEETING 5 TORONTO AND EAST YORK COMMUNITY COUNCIL AGENDA MEETING 5 1. Naming the Proposed Private Lane 466 and 466 Rear Brunswick Avenue Sibelius Lane (Trinity-Spadina, Ward 20) 2. Naming the Proposed Private Lane

More information

Request to Improve Transit along the Dufferin Street Corridor

Request to Improve Transit along the Dufferin Street Corridor For Action Request to Improve Transit along the Dufferin Street Corridor Date: July 10, 2018 To: TTC Board From: Chief Customer Officer Summary The 29 Dufferin bus route is one of the top five busiest

More information

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures

Metrolinx Projects: Temporary Delegation for Long- Term Road Closures PW29.1 REPORT FOR ACTION Metrolinx Projects: Temporary Delegation for Long- Term Road Closures Date: April 24th, 2018 To: Public Works and Infrastructure Committee From: General Manager, Transportation

More information

Capital Projects 2015 Ward 21

Capital Projects 2015 Ward 21 Capital Projects 2015 Ward 21 BIA Projects Forest Hill North Gateway: The City of Toronto Economic Development and the Forest Hill Village BIA are collaborating to create a dynamic northern gateway to

More information

Cell: (408) Release MA June 25, 2012

Cell: (408) Release MA June 25, 2012 VTA NEWS CONTACT: Bernice Alaniz FOR IMMEDIATE RELEASE Cell: (408) 888-9983 Release MA 12 06 08 Bernice.Alaniz@vta.org June 25, 2012 Construction Activities Underway For BART Silicon Valley The Santa Clara

More information

Regulations to deter cut-through traffic - Heath Street V\fest, between Spadina Road and Avenue Road. Toronto and East York Community Council

Regulations to deter cut-through traffic - Heath Street V\fest, between Spadina Road and Avenue Road. Toronto and East York Community Council TORONTO STAFF REPORT ACTION REQUIRED Regulations to deter cut-through traffic - Heath Street V\fest, between Spadina Road and Avenue Road Dnte: February 16,2009 To: From: Toronto and East York Community

More information

COMMITTEE OF THE WHOLE (WORKING SESSION) APRIL 19, 2011 YORK REGION RAPID TRANSIT HIGHWAY 7 BUS RAPID TRANSIT- VMC STATION WARD 4.

COMMITTEE OF THE WHOLE (WORKING SESSION) APRIL 19, 2011 YORK REGION RAPID TRANSIT HIGHWAY 7 BUS RAPID TRANSIT- VMC STATION WARD 4. COMMITTEE OF THE WHOLE (WORKING SESSION) APRIL 19, 2011 YORK REGION RAPID TRANSIT HIGHWAY 7 BUS RAPID TRANSIT- VMC STATION WARD 4 Recommendation The Commissioner of Engineering and Public Works and the

More information

Toronto Transit Commission Express bus services March 2009

Toronto Transit Commission Express bus services March 2009 The TTC operates express or limited-stop rocket services on 22 bus routes. All of the services operate during the peak periods from Monday to Friday, and some of the services also operate at off-peak times.

More information

Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street

Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street STAFF REPORT ACTION REQUIRED Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street Date: March 12, 2007 To: From: Toronto and East York Community Council Director, Transportation Infrastructure

More information

HALO Yonge St. at Grosvenor Street PUBLIC ART PLAN

HALO Yonge St. at Grosvenor Street PUBLIC ART PLAN HALO 480-494 Yonge St. at Grosvenor Street PUBLIC ART PLAN Submitted to the City of Toronto by Cresford Developments For Presentation to the Toronto Public Art Commission Prepared by: Irene Szylinger,

More information

Corktown Parks. Public Meeting. City of Toronto

Corktown Parks. Public Meeting. City of Toronto Corktown Parks Public Meeting City of Toronto 15-04-20 Agenda 1. Reasons for Study 2. Consultation to Date 3. Parks Evaluation 4. Community Context 5. Bright St. Playground 6. Orphans Green (Dog Off Leash)

More information

Application for Outdoor Encroachment Agreement 4906 Dundas Street West

Application for Outdoor Encroachment Agreement 4906 Dundas Street West STAFF REPORT ACTION REQUIRED Application for Outdoor Encroachment Agreement 4906 Dundas Street West Date: September 23, 2009 To: From: Wards: Reference Number: Etobicoke York Community Council Curtis Sealock,

More information

Design Meeting Presentation

Design Meeting Presentation Contract No. 17ECS-TI-05SP April November 2017 Design Meeting Presentation November 2015 Agenda Items: Introduction (5 min) Overview (10 min) Scope of work (60 min): Schedule and Traffic Staging / Closures

More information

Parking Amendments - Bay Street, between Harbour Street and Queens Quay West (York Street, Bay Street, and Yonge Street Ramp Removal)

Parking Amendments - Bay Street, between Harbour Street and Queens Quay West (York Street, Bay Street, and Yonge Street Ramp Removal) REPORT FOR ACTION between Harbour Street and Queens Quay West (York Street, Bay Street, and Yonge Street Ramp Removal) Date: October 26, 2017 To: Toronto and East York Community Council From: Acting Director,

More information

H1: BIRMINGHAM CURZON STREET STATION

H1: BIRMINGHAM CURZON STREET STATION HIGH SPEED TWO INFORMATION PAPER H1: BIRMINGHAM CURZON STREET STATION This paper outlines the proposals for Curzon Street Station. It will be of particular interest to those potentially affected by the

More information

Georgetown-Lewes Rail/Trail Study. Rail/Trail Study: Cool Spring to Cape Henlopen State Park New Road Extension (House Resolution No.

Georgetown-Lewes Rail/Trail Study. Rail/Trail Study: Cool Spring to Cape Henlopen State Park New Road Extension (House Resolution No. Georgetown-Lewes Rail/Trail Study Rail/Trail Study: Cool Spring to Cape Henlopen State Park New Road Extension (House Resolution No. 47) August 22, 2011 Presentation Outline Background Benefits Statewide

More information

FINCH HYDRO CORRIDOR TRAIL PROJECT

FINCH HYDRO CORRIDOR TRAIL PROJECT FINCH HYDRO CORRIDOR TRAIL PROJECT Pharmacy Avenue to Birchmount Road January 29 th, 2018 L Amoreaux Community Centre (2000 McNicoll Avenue) 1 Purpose of Drop In Event The purpose of today s drop-in event

More information

Frequently Asked Questions on the Route 29 Solutions Improvements Projects

Frequently Asked Questions on the Route 29 Solutions Improvements Projects Frequently Asked Questions on the Route 29 Solutions Improvements Projects Background What are the Route 29 Solutions improvement projects? These projects include the Route 29/250 Interchange ( Best Buy

More information

Review of Overnight Services. January 2005

Review of Overnight Services. January 2005 Review of Overnight Services January 2005 Review of Overnight Services - 3 - Table of contents Table of contents 1. Background...4 History of overnight service... 4 Changes since the mid-1990s... 5 Present

More information

415 YONGE STREET, TORONTO

415 YONGE STREET, TORONTO 415 YONGE STREET, TORONTO RETAIL FOR LEASE OVER 100 FT OF WRAPAROUND FRONTAGE ON YONGE STREET FOR MORE INFORMATION PLEASE CONTACT ASHLAR URBAN REALTY INC. Real Estate Brokerage 166 Pearl Street, Suite

More information

Pedestrian Safety Review Spadina Avenue

Pedestrian Safety Review Spadina Avenue STAFF REPORT ACTION REQUIRED Pedestrian Safety Review Spadina Avenue Date: October 13, 2015 To: Toronto and East York Community Council From: Director, Transportation Services, Toronto and East York District

More information

9 VIVA DIRECT UNDERGROUND CONNECTION TO THE TORONTO-YORK SPADINA SUBWAY EXTENSION AT THE VAUGHAN METROPOLITAN CENTRE

9 VIVA DIRECT UNDERGROUND CONNECTION TO THE TORONTO-YORK SPADINA SUBWAY EXTENSION AT THE VAUGHAN METROPOLITAN CENTRE 9 VIVA DIRECT UNDERGROUND CONNECTION TO THE TORONTO-YORK SPADINA SUBWAY EXTENSION AT THE VAUGHAN METROPOLITAN CENTRE The Finance and Administration Committee recommends the adoption of the recommendations

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017

Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017 Crenshaw/LAX Transit Project Construction Update Community Meeting September 27 th, 2017 1 Project Overview Mainline Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018

Crenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018 Crenshaw/LAX Transit Project Construction Update Community Meeting July 12 th, 2018 1 Project Overview Walsh Shea Corridor Constructors (WSCC) Main Line & Stations Contractor Hensel Phelps Herzog (HPH)

More information

Report for Action. Events of January 30, 2018 on Line 1. Summary. Date: February 15, 2018 To: TTC Board From: Chief Executive Officer

Report for Action. Events of January 30, 2018 on Line 1. Summary. Date: February 15, 2018 To: TTC Board From: Chief Executive Officer Report for Action Events of January 30, 2018 on Line 1 Date: February 15, 2018 To: TTC Board From: Chief Executive Officer Summary On a typical weekday, ridership on Line 1 is approximately 740,000 customer

More information

Palm Beach County Traffic Report July 13 through July 20, 2012

Palm Beach County Traffic Report July 13 through July 20, 2012 For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be

More information

Crenshaw/LAX Transit Project Construction Update Community Meeting March 22 nd, 2018

Crenshaw/LAX Transit Project Construction Update Community Meeting March 22 nd, 2018 Crenshaw/LAX Transit Project Construction Update Community Meeting March 22 nd, 2018 1 Project Overview Design-Build Contractor: Walsh Shea Corridor Constructors (WSCC) Southwestern Yard Maintenance Facility:

More information

3529 Souris River Flood Plan (Phase MI-1)

3529 Souris River Flood Plan (Phase MI-1) Date: September 28, 2018 To: Derek Hackett, Public Information Officer From: Grant Goldader, Civil Engineering Specialist Re: Traffic Control Report for the week of 10/01/2018 3529 Souris River Flood Plan

More information

I-70/I-71 Project Public Meeting Presented By

I-70/I-71 Project Public Meeting Presented By I-70/I-71 Project Public Meeting Presented By Ohio Department of Transportation ms consultants, inc. engineers, architects, planners MSI Design June 9, 2010 W e l c o m e Thom Slack Planning Administrator,

More information

STAFF REPORT FOR ACTION

STAFF REPORT FOR ACTION Insert TTC logo here STAFF REPORT FOR ACTION Hillcrest Complex Property Study Date: November 30, 2016 To: From: TTC Board Chief Executive Officer Summary This report outlines a plan for staff to proceed

More information

Committee. Presentation Outline

Committee. Presentation Outline CW-33-15 11/9/2015 Community and Corporate Services Committee November 10, 2015 1 Presentation Outline Background Vision and Objectives Study Process and Timeline Public and Stakeholder Engagement Organization

More information

Metrolinx Board of Directors. President, Union Pearson Express Date: September 22, 2015 UP Express Quarterly Board Report

Metrolinx Board of Directors. President, Union Pearson Express Date: September 22, 2015 UP Express Quarterly Board Report To: From: Metrolinx Board of Directors Kathy Haley President, Union Pearson Express Date: September 22, 2015 Re: UP Express Quarterly Board Report RECOMMENDATION That this report be received for information.

More information

Boston Redevelopment Authority 2/26/ Chestnut Hill Avenue Boston/Brookline, MA

Boston Redevelopment Authority 2/26/ Chestnut Hill Avenue Boston/Brookline, MA Boston Redevelopment Authority 2/26/2014 Cassidy Playground Waterworks Design revisions made since the DPIR submission March 2013 Massing - Reduced project 16,030 SF, for a total project area of 218,520

More information