1 Lorena Gold Project Malachite AGM 29 November 2017
2 Disclaimer and Competent Person Statement Disclaimer This presentation may contain forward looking statements that are subject to risk factors associated with exploration and mining. It is believed that the expectations reflected in these statements are reasonable but they may be affected by variables and changes in underlying assumptions which could cause actual results or trends to differ materially, including but not limited to price fluctuations, actual demand, currency fluctuations, drilling and production results, reserve estimations, loss of market, industry competition, environmental risks, physical risks, legislative, fiscal and regulatory changes, economic and financial market conditions in various countries and regions, political risks, project delay or advancement, approvals and cost estimates. All references to dollars, cents or $ in this presentation are to Australian currency unless otherwise stated. Such forward-looking statements only speak as to the date of this Presentation and MAR assumes no obligation to update such information. Competent Person Statement The information in this report that relates to the Lorena Gold Project resource is extracted from the report entitled Resource Update at Lorena created and released to the ASX on 27 January 2012 (which contained a separate Competent Person Statement by Geos Mining). The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement and, in the case of estimates of Mineral Resources, that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person s findings are presented have not been materially modified from the original market announcement. 2
3 Lorena Gold Project The Lorena Gold project, 15km east of Cloncurry and 135km east of Mt Isa, Qld Located on 6 Mining Leases covering 2.2km2 Initial development to produce 30,000 to 35,000 ozs of gold over eighteen months from an open cut operation. Fully permitted with development commenced July
4 Lorena Project Site Footprint 14km to Cloncurry 2km of dirt road to site ML90193 ML90196 ML90192 ML7147 Access Point ML90195 ML90194 Fisher Creek Flinders Highway to Townsville Mt Isa Townsville Railway Line 4
5 Lorena Gold Joint Venture Malachite finalised a joint venture agreement with Ore Processing Services (OPS) and Cloncurry Gold Recovery (CGR) in July CGR is a joint venture between Chinova Resources (70%) and BIM Gold (30%). Chinova Resources holds a number of projects in the Mt Isa Inlier including the Osborne and Merlin projects. BIM Gold is part of the BIM Metals group: a private mining and contracting company, operating a number of projects in the Cloncurry and Mt Isa region. Lorena Gold JV Open Cut Interest Stage 1 Resources on Lorena MLs not included in open cut Malachite 55% 70% Tenement holder CGR 30% 15% BIM Metals is mine operator OPS 15% 15% Processing contract 5
6 Project Funding CGR and OPS are funding project development to the commencement of commercial production; CGR is funding the preliminary project capital requirements of $2.5m. CGR is completing preliminary capital works including construction of the tailings dam, water structures and carrying out initial mining; CGR is providing a CIL plant on site (CGR retains ownership) to treat both the gold concentrate and tailings; OPS acquired the existing Lorena Concentrator Plant (OPS retains ownership); and CGR, OPS, and BIM Metals are funding the joint venture s ongoing working capital requirements in relation to the project in proportion to each joint venture party s interest on an interest bearing loan basis; 6
7 Lorena Gold Project - Resource High grade gold arsenopyrite zones in a shear hosted structure structurally controlled Good continuity Significant Drill Hole Results at less than 80m depth include: 18.8g/t Au 21.1g/t Au 20.0g/t Au Cutoff Measured Indicated Total Au g/t Tonnes Au g/t Au Oz Tonnes Au g/t Au Oz Tonnes Au g/t Au Oz , ,100 57, ,600 91, , , , , , , , , , , , , , , , , , , , , , , , , ,900 7
8 Lorena Gold Project Mining approximately 250,000t at 5.0g/t from an initial open cut operation (Stage 1). Around 30,000 to 35,000 ozs gold recovered from the open cut. Overall metallurgical recovery of around 75% for sulphides. Recovery of 90% to concentrate and 85% from concentrate to CIL. Ore is of medium hardness and non-refractory. Processing up to 15,000 tonnes per month. Operating costs forecast at around A$1,000/oz (including project plant charges). Commissioning of concentrator plant commenced in late Oct/early November CIL plant commissioning starting by end of this month. First gold production before year end with steady state operations expected by end of January
9 Lorena Project Site Layout Plant Site Pit Tailings Dam Waste Rock Dump 9
10 Lorena Project Mining 10
11 Lorena Project Tailings Dam and Processing Plant 11
12 Lorena Project Plant 12
13 Lorena Project Targeting Resources at Depth Potential to increase the mine life via an underground operation subject to delineating resources beneath the open cut. Drilling intersected 5.3m at 13g/t Au at a depth of 200m Survey highlighted 2 strong electromagnetic conductors that represent sulphide targets Each target is similar in size to the current resource Excellent potential for resource additions at depth Significant underground mining potential Malachite has 70% JV interest 14
14 Lorena Gold Project Underground (Stage 2) Portal designed to come off near bottom of pit in competent ground Conventional underground mining 5.3m at 13g/t Au at a depth of 200m is a mineable width for underground Lorena JV considering best approach for exploration via new review of data Forecast exploration in March 2018 Third party ore sources available prior to a potential underground operation. Initial Target Area 13g/t Au Lorena Long Section - Targeting resources at depth 15
For personal use only
5 September 2016 ABN 91 124 752 745 Drilling Underway At The Koala Gold Mine, Mt Coolon Gold Project, Qld Stage 1 drilling for 1,100 metres has commenced on schedule at the Koala Gold Mine. Drilling is
More informationMARCH 2018 QUARTERLY ACTIVITIES REPORT
X AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT 27 April 2018 MARCH 2018 QUARTERLY ACTIVITIES REPORT Syndicated prepares for new phase of drilling at Monument Gold Project drilling commences in early April
More informationDecember 2017 Quarterly Report
ASX Announcement 31 January 2018 ASX: CRB December 2017 Quarterly Report KEY POINTS Continuation of work including final design criteria and front end engineering following Demonstration Plant test work
More informationRamelius Resources Limited ASX:RMS
Ramelius Resources Limited ASX:RMS INVESTOR PRESENTATION March 2012 1 Forward Looking and Competent Persons Statements Forward looking statements This presentation contains certain forward looking statements
More informationFor personal use only
For the period ended 30 September 2014 HIGHLIGHTS STORMONT (TASMANIA) JOINT VENTURE GOLD PROJECT MINING AND PRODUCTION COMPLETED. LORENA GOLD PROJECT CONSTRUCTION CONTINUES TO ADVANCE. COMMISSIONING EXPECTED
More informationFor personal use only
ASX ANNOUNCEMENT 30 APRIL 2015 QUARTERLY ACTIVITIES REPORT HIGHLIGHTS PROJECTS Over 2,000m of RC drilling planned at SA Titan Gold & IOCG Project Drilling planned to test strong EM conductor for high grade
More informationFor personal use only
Southern Cross Goldfields Ltd ASX Announcement 5 September 2014 Wonawinta Silver Project to be acquired; Mount Boppy development cost and risk cut back Wonawinta Silver Project (60 M oz) to be acquired
More informationFor personal use only
ASX Release 24 April 2012 Westgold secures the High Grade Great Fingall Gold Mine Westgold Resources (ASX:WGR) is pleased to advise that it has acquired the 49% relevant interest in the Great Fingall Deeps
More informationHaoma Mining NL A.B.N
Haoma Mining NL A.B.N 12 008 676 177 Registered Office & Head Office: Level 1, 401 Collins Street, Melbourne, Vic., 3000, GPO Box 2282U, Melbourne, Vic., 3001. Telephone (03) 9629 6888, Facsimile (03)
More informationOn The Road To Silver Mining In Mexico
On The Road To Silver Mining In Mexico ASX: AZS @AzureMinerals www.azureminerals.com.au Tony Rovira Managing Director & CEO Corporate Overview ASX Code KEY STATISTICS AZS Share Price A$0.034 (@ 5/10/2016)
More informationGenius Properties / Cerro de Pasco Resources Merger Opportunity. June 2018
Genius Properties / Cerro de Pasco Resources Merger Opportunity June 2018 Forward-looking Statement This presentation contains forward-looking statements within the meaning of the United States Private
More informationFor personal use only
ABN 52 007 626 575 Date 23 rd May 2016 The Manager Market Announcements Office ASX Ltd 4th Floor, 20 Bridge Street Sydney NSW 2000 ASX Code: JRV JOINT VENTURE WITH AUSTRALIAN MINES LIMITED (ASX: AUZ) The
More informationOn The Road To Silver & Gold Mining In Mexico
On The Road To Silver & Gold Mining In Mexico ASX: AZS @AzureMinerals www.azureminerals.com.au Tony Rovira Managing Director & CEO Corporate Overview ASX Code KEY STATISTICS AZS Share Price A$0.032 (@
More informationKidman agrees to acquire 1Moz Mt Holland gold field in WA
December 18th, 2015 Kidman Resources Limited ABN 88 143 526 096 Corporate Details: ASX Code: KDR Issued capital: 142.3M ordinary shares Substantial Shareholders: Capri 22.7m (15.97%) Holdex Nominees 11.3m
More informationQuarterly Activities Report Period Ended 31 March 2018
23 April 2018 Quarterly Activities Report Period Ended 31 March 2018 ASX Code: EXG Key Points During the March 2018 Quarter, Kalgoorlie North Gold Project (KNGP) activities predominantly involved resource
More informationFor personal use only
HIGHLIGHTS Mount Bundy Gold Project Drill results from Rustlers Roost shows 117m at 1.5 g/t gold including 8m at 6.9 g/t gold with other broad intercepts - Drill program highlights potential to further
More informationKinross Production Continues on Plan
Kinross Production Continues on Plan 40 KING STREET WEST, 52 ND FLOOR TORONTO, ON M5H 3Y2 TEL: 416 365 5123 FAX: 416 363 6622 TOLL FREE: 866-561-3636 PRESS RELEASE July 28, 2005, Toronto, Ontario Kinross
More informationQuarterly Report for the Period Ending 30 September 2014
For Immediate Release 17 October 2014 Quarterly Report for the Period Ending 30 September 2014 17 October 2014 ISSUED CAPITAL Ordinary Shares: DIRECTORS 468M CHAIRMAN: Robert Kennedy NON-EXECUTIVE DIRECTORS:
More informationFor personal use only
QUARTERLY ACTIVITIES REPORT PERIOD ENDED 30 JUNE 2015 ASX Announcement ASX Code: VXR Released: 31 July 2015 Venturex Resources Limited (ASX: VXR) is pleased to report its activities for the June 2015 Quarter.
More informationFOUR EAGLES JV FORMALISED SEISMIC AND DRILLING PROGRAMME COMMENCES
ASX ANNOUNCEMENT 21 April 2015 FOUR EAGLES JV FORMALISED SEISMIC AND DRILLING PROGRAMME COMMENCES The new Four Eagles Gold Project Joint Venture with GEV and Providence has commenced after the renewal
More informationAustralian Mines increases Marymia ground holding
11 June 2015 Australian Mines increases Marymia ground holding Australian Mines Limited ( Australian Mines or the Company ) is pleased to advise shareholders that it has entered into a farm-in and joint
More informationMungana Signs Agreement with Newcrest to unlock Porphyry Gold-Copper Potential at Chillagoe
Market Announcements Office ASX Ltd 4 th Floor, 20 Bridge Street, Sydney NSW 25 May 2015 ASX code: MUX Mungana Signs Agreement with Newcrest to unlock Porphyry Gold-Copper Potential at Chillagoe Agreement
More informationASX Announcement 7 June 2011 Mt Isa Metals Ltd Drilling Recommences at Nabanga, Burkina Faso
ASX Announcement 7 June 2011 Mt Isa Metals Ltd Drilling Recommences at Nabanga, Burkina Faso The Directors of D Aguilar Gold Limited (ASX Code: DGR) are pleased to draw the attention of shareholders to
More informationQuarterly Activities Report for the period ended 30 September 2018
Maroon Gold s Black Jack Gold Processing Plant which will process Agate Creek Ore Level 9, Waterfront Place, 1 Eagle St, Brisbane QLD 4000 Directors GPO Box 1164, Brisbane QLD 4001 Mr Stephen Bizzell (Chairman)
More informationEL LIMON MINE: EMPLOYEES & CONTRACTORS 133
132 EL LIMON MINE: EMPLOYEES & CONTRACTORS 133 B2Gold Employees Direct 552 Nicaraguans 548 Expats 4 Unionized 494 Men 499 Women 53 Contractors Employees 570 Men 529 Women 41 EL LIMON MINE: NICARAGUA OPEN
More informationFor personal use only
INDOCHINE MINING LIMITED ACN 141 677 385 ASX: IDC 29 July 2011 Company Announcements Office Australian Securities Exchange 8 Pages Quarterly Activities Report For Quarter ended 30 June 2011 Highlights
More informationAUSIMM - Technical Meeting & AGM
The Construction, Commissioning and Ramp-Up of the Prominent Hill Mine John Nitschke Executive General Manager Projects and Technical Services AUSIMM - Technical Meeting & AGM Tuesday 10th November 2009
More informationKinross Gold Corporation Merrill Lynch Global Metals, Mining & Steel Conference May 13 15, 2008
DELIVERING DISCIPLINED GROWTH 1 Cautionary Statements All statements, other than statements of historical fact, contained or incorporated by reference in this presentation, including any information as
More informationQUARTERLY REPORT 1 JULY 2017 to 30 SEPTEMBER 2017
31 October, 2017 Australian Securities Exchange Level 5, 20 Bridge Street SYDNEY NSW 2000 QUARTERLY REPORT 1 JULY 2017 to 30 SEPTEMBER 2017 Stonewall Resources Limited (ASX: SWJ) Stonewall, Company or
More informationFor personal use only
Suite 4, Level 3 South Shore Centre 85 South Perth Esplanade South Perth WA 6151 TEL +61 8 6313 3800 FAX +61 8 6313 3888 ABN 38 108 779 782 ASX ANNOUNCEMENT 04 July 2012 Completion of Asset Sale Agreement
More informationASX ANNOUNCEMENT 25 JANUARY 2008 FURTHER HIGH GRADE INTERCEPTS FROM THE KOKA GOLD DEPOSIT, ERITREA
ASX ANNOUNCEMENT 25 JANUARY 2008 FURTHER HIGH GRADE INTERCEPTS FROM THE KOKA GOLD DEPOSIT, ERITREA Zara Joint Venture, Eritrea (Dragon Mining Limited - 20% interest) Koka Gold Deposit Dragon Mining Limited,
More informationNewcrest Mining Limited
Newcrest Mining Limited Colin Moorhead Newcrest a portfolio of opportunities Disclaimer Forward Looking Statement These materials include forward looking statements. Often, but not always, forward looking
More informationMarket Announcement ASX:NTL, NZX:NTL For Immediate Release
Market Announcement ASX:NTL, NZX:NTL For Immediate Release Commodity Exposure GOLD and SILVER Board and Management Charbel Nader Chairman/Independent Director Quarterly Activities Report to 30 September
More informationGruyere Project Development Update
ASX Announcement 21 June 2017 Gruyere Project Development Update Highlights Project Capital budget revised to A$532 1 million (3.5% increase) following engineering, procurement and construction review
More informationFocus Begins Accelerated Development of the Mount into New Stand Alone Mining Operation
Focus Begins Accelerated Development of the Mount into New Stand Alone Mining Operation Outstanding exploration and trial mining results from The Mount deposit pave way to create a 2 nd operational centre
More informationHARMONY GOLD AND NEWCREST FORM PAPUA NEW GUINEA GOLD JOINT VENTURE
HARMONY GOLD AND NEWCREST FORM PAPUA NEW GUINEA GOLD JOINT VENTURE The world s 5 th largest gold producer, Harmony Gold Mining Company Limited ( Harmony ) and Australasia s largest gold company, Newcrest
More informationKEY POINTS. Significant Resource increase at the Tier-1 mines:
NORTHERN STAR ESTABLISHES 10-YEAR MINE LIVES AFTER RESERVES TRIPLE TO 3.5MOZ AND RESOURCES HIT 10.2MOZ Outstanding result underpins increase in production to 600,000ozpa from next year; Reserves added
More informationORION METALS LIMITED (ASX: ORM) ACTIVITIES REPORT FOR QUARTER ENDING 31 st August 2014.
ORION METALS LIMITED (ASX: ORM) ACTIVITIES REPORT FOR QUARTER ENDING 31 st August 2014. EXPLORATION ACTIVITIES Orion s efforts towards project growth, evaluation, and rationalisation have been the focus
More informationQUARTERLY ACTIVITIES REPORT
QUARTERLY ACTIVITIES REPORT For the quarter ended 31 December 2010 ABN: 38 108 779 782 Silver Lake Resources Ltd ( Silver Lake or the Company ) is pleased to present this Quarterly Activities Report. Les
More informationFor personal use only
ASX ANNOUNCEMENT 31 Oct 2016 Focus Minerals Ltd Activities and Cashflow Report for September Quarter 2016 Exploration Highlights During the Quarter During the September Quarter, Focus Minerals Ltd ( Focus
More informationCadia Valley. Peter Smith Executive General Manager Australian Operations
Cadia Valley Peter Smith Executive General Manager Australian Operations Disclaimer Forward Looking Statement These materials include forward looking statements. Often, but not always, forward looking
More informationHaoma Mining NL A.B.N
A.B.N 12 008 676 177 Registered Office & Head Office: Level 1, 401 Collins Street, Melbourne, Vic., 3000, GPO Box 2282U, Melbourne, Vic., 3001. Telephone (03) 9629 6888, Facsimile (03) 9629 1250 Email:
More informationInvestor Presentation July 2013
ASX and Media Release: 1 ASX code: RXM Investor Presentation Rex Minerals Ltd (Rex) is pleased to release its latest investor presentation. This presentation will be used for International and domestic
More informationFor personal use only
ASX Announcement 15 May 2012 ARTEMIS ACQUIRES STRATEGIC WEST PILBARA GOLD AND BASE METALS ASSETS About Artemis Resources Artemis Resources is an ASX-listed mineral exploration company with a focus on gold:
More informationNEWCREST LOOKING TO THE FUTURE
NEWCREST LOOKING TO THE FUTURE Sandeep Biswas Managing Director and Chief Executive Officer Disclaimer Forward Looking Statements This presentation includes forward looking statements. Forward looking
More informationQuarterly Activities Report Period Ended 31 December 2017
24 January 2018 ASX Code: EXG Quarterly Activities Report Period Ended 31 December 2017 Key Points Successful completion of the Zoroastrian open pit ore treatment campaign. Cash balance peaks at $8.1M
More informationCATALYST SECURES $1.5 MILLION PLACEMENT WITH ST BARBARA LIMITED
ASX ANNOUNCEMENT 16 MARCH 2017 CATALYST SECURES $1.5 MILLION PLACEMENT WITH ST BARBARA LIMITED St Barbara Limited (SBM) commits $1.5 million placement at 50 cents per share for 5% stake Funding will allow
More informationRamelius Resources Limited ASX:RMS
Ramelius Resources Limited ASX:RMS Diggers & Dealers 3-5 August 2015 Ramelius Resources Limited Diggers and Dealers - August 2015 2 Forward Looking and Competent Persons Statements Forward Looking Statements
More informationFor personal use only
ASX / Media Announcement 10 November 2017 Artemis Resources Limited ARBN: 80 107 051 749 Level 3, IBM Building, 1060 Hay Street, West Perth, WA Australia, 6006 PO Box R933 Royal Exchange NSW Australia,
More informationKEMPFIELD DRILLING COMMENCES, TARGETING Ag, Au, Pb AND Zn
29 November 2016 KEMPFIELD DRILLING COMMENCES, TARGETING Ag, Au, Pb AND Zn Argent at a glance ASX-listed mineral resource company focused on the expansion, development, extraction and marketing of its
More informationFor personal use only OZ MINERALS AUSTRALIAN COPPER CONFERENCE. TERRY BURGESS - Managing Director & CEO March
OZ MINERALS AUSTRALIAN COPPER CONFERENCE TERRY BURGESS - Managing Director & CEO 23-24 March 2011 WWW.OZMINERALS.COM DISCLAIMER This presentation has been prepared by OZ Minerals Limited ( OZ Minerals
More informationMarket Release 11 March 2019
Market Release 11 March 2019 Newcrest to acquire potential Tier 1 orebody in Canada Newcrest Mining Limited (Newcrest) has entered into an agreement with TSX-listed Imperial Metals Corporation (Imperial)
More informationORO VERDE LIMITED (ASX: OVL)
ORO VERDE LIMITED (ASX: OVL) Nicaragua A golden past and future Proactive Investor Luncheons Sydney & Melbourne February 2017 Trevor Woolfe (Managing Director) Disclaimer Forward Looking Statements - This
More informationQUARTERLY OPERATIONS REPORT 30 JUNE Highlights: BOARD AND MANAGEMENT YAMARNA
QUARTERLY OPERATIONS REPORT 30 JUNE 2016 Highlights: YAMARNA Geochemical blade-refusal aircore programme confirms the extent of the Jatz basement gold anomaly at over 1.5 km in strike. Multiple RC drilling
More informationOn The Road To Silver Mining In Mexico
On The Road To Silver Mining In Mexico ASX: AZS @AzureMinerals www.azureminerals.com.au Tony Rovira Managing Director & CEO Corporate Overview ASX Code AZS KEYSTATISTICS Share Price A$0.028 (9 Sep 2016)
More informationFor personal use only
Artemis Resources Limited ARBN: 80 107 051 749 Level 3, IBM Building, 1060 Hay Street, West Perth, WA Australia, 6006 PO Box R933 Royal Exchange NSW Australia, 1225 Phone: +61 2 9078 7670 Facsimile: +61
More informationLihir Operations PNG Mining and Petroleum Conference 24 November Peter Aitsi Country Manager, PNG
Lihir Operations PNG Mining and Petroleum Conference 24 November 2015 Peter Aitsi Country Manager, PNG Disclaimer Forward Looking Statements These materials include forward looking statements. Often, but
More informationQuinto Resources Inc. (TSX-V: QIT)
Quinto Resources Inc. () Corporate Presentation November 2017 Disclaimer This presentation contains certain forward-looking statements, including, but not limited to, statements regarding the Company s
More informationOMNR. ^ååì~ä=déåéê~ä=jééíáåö. OT=klsbj_bo=OMNR=== ^puw=cjp===
OMNR ^ååì~ä=déåéê~ä=jééíáåö OT=klsbj_bo=OMNR=== ^puw=cjp=== 2 `çêéçê~íé=pìãã~êó Board & Management Capital Structure Robert Kennedy Non-Executive Chairman A Chartered Accountant and a Director since 14
More informationCandelaria and Ojos del Salado Chile
TSX : LUN OMX : LUMI 2016 Candelaria Key Facts Open Pit and Underground Mine Copper, gold, and silver 2016 estimate 130,000-132,000 tonnes copper Cash costs of $1.35 per lb copper after by-product credits
More informationFor personal use only
ABN: 57 126 634 606 Phone: +61 (7) 4032 3319 info@csdtin.com.au Snapshot: Current CSD Share Price: $0.10 Current LME Tin Price: $24,475 Key Points Snow Peak Mining Pty Ltd acquisition of Kagara s Central
More informationHighlights. Quarterly Activities Report: September Kurnalpi Project. Lindsays project
Quarterly Activities Report: September 2018 KalNorth Gold Mines Limited Date: 31 October 2018 ASX Code: KGM Issued Capital 894.24 million Ordinary shares Current Share Price $0.006 Market tfollo Capitalisation
More informationNorthern Territory. Ark wishes to extend the strike and further define the size of the Golden Honcho deposit, with the
Ark Secures Approval to Commencee Mining Activities at Project, Northern Territory Sydney, 19 August 2014: The Board of Ark Mines Ltd (ASX: AHK) is pleased to announce that it has obtained approval from
More informationArtemis Resources Limited
Artemis Resources Limited ASX: ARV Australian focused Mining Exploration and Development Gold, Nickel, Cobalt, Copper, Zinc, Platinum, Iron Ore Karratha West Pilbara -Western Australia Investor Update
More informationQuarterly Report Newcrest Mining Limited For the three months ending 30 June 2007 (These figures are unaudited)
Quarterly Report Newcrest Mining Limited For the three months ending 30 June 2007 (These figures are unaudited) Key Points Operations Record quarterly gold production of 463,170oz (390,096oz). Group cash
More informationFor personal use only
28 September 2018 GBM EXECUTES AGREEMENT WITH MINJAR TO ACQUIRE TWIN HILLS GOLD PROJECT IN DRUMMOND BASIN, QUEENSLAND HIGHLIGHTS Binding Sale and Purchase Agreement signed with Minjar Gold Pty Ltd 1 to
More informationFOR THE THREE MONTHS ENDED 31 MARCH 2012
FOR THE THREE MONTHS ENDED 31 MARCH 2012 PROMINENT HILL CONTAINED METAL PRODUCTION MARCH 2012 QUARTER TOTAL COPPER (TONNES) 27,182 TOTAL GOLD (OUNCES) 38,887 OZMINERALS.COM C1 CASH COSTS US96.9c/lb HIGHLIGHTS
More information2011 Annual General Meeting. Greg Robinson Managing Director & CEO
2011 Annual General Meeting Greg Robinson Managing Director & CEO Disclaimer Forward Looking Statements These materials include forward looking statements. Forward looking statements inherently involve
More informationDECEMBER 2017 QUARTERLY ACTIVITIES REPORT
DECEMBER 2017 QUARTERLY ACTIVITIES REPORT Completion of 1.3Moz WA gold merger and $5.33m capital raising allows Spitfire to hit the ground running in 2018 Scheme of arrangement between Aphrodite Gold and
More informationFor personal use only
ASX Release / 5 December 2016 Presentation to PNG Mining and Petroleum Investment Conference Attached is a presentation by Bob Vassie, Managing Director and CEO, to the 14th Papua New Guinea Mining and
More informationKinross Nevada tour highlights growth potential at Bald Mountain and Round Mountain
25 York Street, 17th Floor Toronto, ON Canada M5J 2V5 NEWS RELEASE Kinross Nevada tour highlights growth potential at Bald Mountain and Round Mountain Toronto, Ontario June 29, 2016 In advance of an analyst
More informationJUNE 2017 QUARTERLY ACTIVITIES REPORT
ASX RELEASE 25 JULY 2017 JUNE 2017 QUARTERLY ACTIVITIES REPORT Cash flow positive result for the quarter even after significant development activities and repayment of Nullagine deferred royalties to the
More informationExploration. General Manager Minerals Development
Exploration Fraser MacCorquodale General Manager Minerals Development Disclaimer Forward Looking Statement These materials include forward looking statements. Often, but not always, forward looking statements
More informationTHE NEW HIGH- GRADE AUSTRALIAN GOLD DISCOVERY
THE NEW HIGH- GRADE AUSTRALIAN GOLD DISCOVERY BELLEVUE GOLD PROJECT WESTERN AUSTRALIA Follow us @bellevuegold NORTH AMERICAN ROADSHOW SEPTEMBER 2018 WWW.BELLEVUEGOLD.COM.AU ASX: BGL DISCLAIMER CAUTIONARY
More informationBMO CAPITAL MARKETS GLOBAL METALS & MINING CONFERENCE PRESENTATION 25 FEB 2008
ASX ANNOUNCEMENT Manager Announcements Company Announcements Office ASX Limited 4th Floor, 20 Bridge Street Sydney NSW 2000 By E-Lodgement No. of pages: 25 25 February 2008 BMO CAPITAL MARKETS GLOBAL METALS
More informationAngas Zinc Mine From Prediction to Production
TERRAMIN AUSTRALIA LIMITED Angas Zinc Mine From Prediction to Production Bob Singer SA Explorers Conferenc ce 28 November 2008 Important information The information in this presentationn is designed as
More informationCAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION
December 11 2012 KINROSS GOLD CORPORATION 1 1 CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION All statements, other than statements of historical fact, contained or incorporated by reference in or
More informationAnnual Mineral Resources and Ore Reserves Statement - 31 December 2016
Market Release 13 February 2017 Annual Mineral Resources and Ore Reserves Statement - 31 December 2016 Newcrest Mining Limited has updated its Mineral Resource and Ore Reserve estimates for the twelve
More informationJellinbah Mine COAL SEAM GAS STATEMENT. For. Plains Extension MLAs. Jellinbah East Joint Venture. 31 March 2015
Jellinbah Mine COAL SEAM GAS STATEMENT For Plains Extension MLAs Jellinbah East Joint Venture 31 March 2015 1 J e l l i n b a h R e s o u r c e s P t y L t d A B N 6 0 0 1 0 8 2 5 2 1 5 L e v e l 7, 1
More informationFor personal use only
28 July 2016 ASX Release Kidman Resources Limited ABN 88 143 526 096 Corporate Details: ASX Code: KDR / KDRO Issued capital: 237.2 M ordinary shares 47.45 M Options Substantial Shareholders: Capri Holdings
More informationUNLOCKING THE POTENTIAL OF THE EAST MENZIES GOLDFIELD
NOVEMBER 2013 UNLOCKING THE POTENTIAL OF THE EAST MENZIES GOLDFIELD www.stratummetals.com.au ASX:SXT DISCLAIMER This presentation may contain certain forward looking statements and projections regarding:
More informationFor personal use only
24 January 2017 Quarterly Activities Report Period ended 31 December 2016 HIGHLIGHTS Sconi Scandium-Cobalt Project Executed a joint venture agreement to acquire up to 75% of Sconi Scandium-Cobalt Project
More informationActivities Report for the quarter ended 30 th June 2011
Activities Report for the quarter ended 30 th June 2011 Admiralty Resources NL (ASX: ADY) Issued capital 606,518,966 shares (as of 30 June 2011) 606,518,966 shares (current) Top 20 Shareholders : 50.50%
More informationAustralian Securities Exchange Notice
Australian Securities Exchange Notice 12 December 2017 ASX: ILU CATABY PROJECT APPROVED WITH OFFTAKE AGREEMENTS SECURED FOR 85 OF SYNTHETIC RUTILE PRODUCTION Cataby mineral sands project approved; with
More informationQuarterly Activities Report For The Period Ending 30 June 2018
Quarterly Activities Report For The Period Ending 30 June 2018 Highlights for the quarter ending 30 June 2018 Accent Resources completed one Diamond drill hole on the Magnetite Range Project E59/875 during
More informationSEPTEMBER 2018 QUARTERLY ACTIVITIES REPORT
26 October 2018 Suite 4, Level 3 South Shore Centre 85 South Perth Esplanade South Perth WA 6151 TEL +61 8 6313 3800 FAX +61 8 6313 3888 ABN 38 108 779 782 Board of Directors: David Quinlivan Luke Tonkin
More informationFor personal use only
For personal use only ASX:DRX Exploration Activities Report Quarter ended 30 June 2014 HIGHLIGHTS Cyclone Zircon (WA) de-risking activities continued under the Perpetual Mining Holding Limited Heads of
More informationAnnual Mineral Resources and Ore Reserves Statement - 31 December 2017
Market Release 15 February 2018 Annual Mineral Resources and Ore Reserves Statement - 31 December 2017 Newcrest Mining Limited has updated its Mineral Resource and Ore Reserve estimates for the twelve
More informationQuarterly Activities Report For The Period Ending 31 March 2018
Quarterly Activities Report For The Period Ending 31 March 2018 Highlights for the quarter ending 31 March 2018 Accent Resources have completed one Diamond drill hole (DD03) on the Magnetite Range Project
More informationFor personal use only
ASX Announcement 11 May 2017 ORO VERDE PRESENTATION IN SYDNEY Oro Verde Limited (ASX: OVL) ( Oro Verde or the Company ) is pleased to announce that Managing Director Trevor Woolfe is attending and presenting
More informationMATRIX METALS LIMITED
LEVERAGED TO COPPER MATRIX METALS LIMITED PDAC Presentation March 2004 A$ & US$ Copper Price Copper Price since 1 January 2003 in USD and AUD Cents per Pound 1.80 1.60 Australian Dollar Plot 1.40 1.20
More informationNovo Resources Corp. Suite West Georgia Street Vancouver, BC, V6E 3C9
Novo Resources Corp. Suite 1980 1075 West Georgia Street Vancouver, BC, V6E 3C9 NOVO TO CONSOLIDATE INTERESTS IN LARGE LAND POSITION IN KARRATHA REGION, WESTERN AUSTRALIA VANCOUVER, BC, June 26, 2017 Novo
More informationSouth America Copper Site Visit Non-ferrous overview
Spence, Chile South America Copper Site Visit Non-ferrous overview Andrew Mackenzie Chief Executive Non-ferrous 26 September 2010 Disclaimer Reliance on Third Party Information The views expressed here
More informationGENERAL CONCEPT. Contents
WHITEPAPER contained herein. 2017, 2018 Paraguay Mineral Mining SA Contents GENERAL CONCEPT... 2 EXECUTIVE SUMMARY... 3 THE PROBLEM... 3 SOLUTION... 4 THREE PROJECT VERSIONS.... 4 Project Versions 1-2
More informationSPITFIRE RESOURCES LIMITED SPITFIRE DIVERSIFIES WITH TASMANIAN COAL ACQUISITION
Regulatory Announcement Go to market news section Company TIDM Headline Released Number CHL Spitfire Resources Update 07:00 23-May-08 1434V07 RNS Number : 1434V 23 May 2008 Spitfire Resources Limited Update
More informationZinc. Proven Mineral Reserves Probable Mineral Reserves Total Proven & Probable. As at December 31, 2018 Mineral Reserves (Proven and Probable)
As at December 31, 2018 Mineral Reserves (Proven and Probable) Alumbrera (12.5%) 8,435 0.39 106 294 0.37 4 8,728 0.39 109 Canadian Malartic (50%) 23,029 0.89 658 55,799 1.18 2,122 78,829 1.10 2,780 Cerro
More informationGOLD RESOURCE CORPORATION REPORTS 2017 ALTA GRACIA EXPLORATION DRILL RESULTS, INCLUDING 1.29 METERS GRADING 4.33 G/T GOLD AND 1,710 G/T SILVER
FOR IMMEDIATE RELEASE October 24, 2017 NEWS NYSE American: GORO GOLD RESOURCE CORPORATION REPORTS 2017 ALTA GRACIA EXPLORATION DRILL RESULTS, INCLUDING 1.29 METERS GRADING 4.33 G/T GOLD AND 1,710 G/T SILVER
More informationAustralian Resource Reviews Gold 2016
Australian Resource Reviews Gold 2016 Anthony Senior, Geoscience Australia Resource figures are current as at 31 December 2015. The principal uses for gold (Au) are as an investment instrument for governments,
More informationAustralian Site Tour Mt Keith Operation. Jaco Harwig General Manager
Australian Site Tour Mt Keith Operation Jaco Harwig General Manager 28 October 2008 Important notices Reliance on third party information The views expressed here contain information that have been derived
More informationPROJECTS & TECHNICAL SERVICES
PROJECTS & TECHNICAL SERVICES 1.0 2.0 3.0 4.0 5.0 JOHN NITSCHKE EGM Projects & Technical Services 6.0 7.0 8.0 9.0 OZ MINERALS NOVEMBER 2009 PAGE 40 STRATEGY SUPERIOR TOTAL SHAREHOLDER RETURNS ZERO HARM