OZ MINERALS CONTINUED INVESTMENT IN SOUTH AUSTRALIA. TERRY BURGESS - Managing Director & CEO SAREIC - 02 May 2011

Size: px
Start display at page:

Download "OZ MINERALS CONTINUED INVESTMENT IN SOUTH AUSTRALIA. TERRY BURGESS - Managing Director & CEO SAREIC - 02 May 2011"

Transcription

1 OZ MINERALS CONTINUED INVESTMENT IN SOUTH AUSTRALIA TERRY BURGESS - Managing Director & CEO SAREIC - 02 May

2 DISCLAIMER This presentation has been prepared by OZ Minerals Limited ( OZ Minerals ) and consists of written materials/slides for a presentation concerning OZ Minerals. By reviewing/attending this presentation, you agree to be bound by the following conditions. No representation or warranty, express or implied, is made as to the fairness, accuracy, or completeness of the information, contained in the presentation or of the views, opinions and conclusions contained in this material. To the maximum extent permitted by law, OZ Minerals and its related bodies corporate and affiliates, and its respective directors, officers, employees, agents and advisers disclaim any liability (including, without limitation any liability arising from fault or negligence) for any loss or damage arising from any use of this material or its contents, including any error or omission there from, or otherwise arising in connection with it. Some statements in this presentation relate to the future and are forward looking statements. Such statements may include, but are not limited to, statements with regard to intention, capacity, future production and grades, projections for sales growth, estimated revenues and reserves, targets for cost savings, the construction cost of new projects, projected capital expenditures, the timing of new projects, future cash flow and debt levels, the outlook for minerals and metals prices, the outlook for economic recovery and trends in the trading environment and may be (but are not necessarily) identified by the use of phrases such as will, expect, anticipate, believe and envisage. By their nature, forward-looking statements involve risk and uncertainty because they relate to events and depend on circumstances that will occur in the future and may be outside OZ Mineral s control. Actual results and developments may differ materially from those expressed or implied in such statements because of a number of factors, including levels of demand and market prices, the ability to produce and transport products profitably, the impact of foreign currency exchange rates on market prices and operating costs, operational problems, political uncertainty and economic conditions in relevant areas of the world, the actions of competitors, activities by governmental authorities such as changes in taxation or regulation. Given these risks and uncertainties, undue reliance should not be placed on forward-looking statements and intentions which speak only as at the date of the presentation. Subject to any continuing obligations under applicable law or any relevant stock exchange listing rules, OZ Minerals does not undertake any obligation to publicly release any updates or revisions to any forward looking statements contained in this presentation, whether as a result of any change in OZ Minerals expectations in relation to them, or any change in events, conditions or circumstances on which any such statement is based. Certain statistical and other information included in this presentation is sourced from publicly available third party sources and has not been independently verified. OZ MINERALS PAGE 2

3 OZ MINERALS SNAPSHOT Market capitalisation: Prominent Hill: Exploration: ~A$5 billion Open-pit copper and gold operation. Underground development underway. Priority area Prominent Hill. Further global and regional opportunities. Business Development: Pursuing opportunities in copper. In process of acquiring 100% of Carrapateena copper project. A$1.3 billion: Cash at 31 December No debt. Equity investments: 42.5% of Toro Energy, 12.9% of IMX Resources, 18.9% of Sandfire Resources and others. OZ MINERALS PAGE 3

4 CONTINUED INVESTMENT IN SOUTH AUSTRALIA 1. Prominent Hill update including our underground development. 2. Carrapateena. 3. Making a difference in South Australia. OZ MINERALS PAGE 4

5 PROMINENT HILL The Prominent Hill copper/gold mine is located 650 km north-northwest of Adelaide, approximately 130 km southeast of Coober Pedy and 150 km northwest of Roxby Downs (Olympic Dam) in the Gawler Craton of South Australia. Convenient access to the Adelaide to Darwin railway shipments of concentrate take 48 hours to reach the Port of Darwin. We have approximately 6 trains/wk to Darwin (600-1,000t each). 2 weeks to major Asian ports. 1 truck/day to Olympic Dam. OZ MINERALS PAGE 5

6 PROMINENT HILL SITE VILLAGE ANKATA DEPOSIT AREA ROM PAD NORTHERN WASTE DUMP PROCESSING PLANT MALU PIT SOUTHERN WASTE DUMP TAILINGS DAM OZ MINERALS PAGE 6

7 PROMINENT HILL FACTS A workforce of approximately 800 this includes contractors. Plus 150 underground construction Plus 100 steady-state underground operations 2012 onward. We have a local workforce 80% of our people are from South Australia. Mining partner Thiess. Underground contractor Byrnecut Mining Village Services Sodexo Charter Flight services - 10 flights a week from Adelaide and six flights a week from Port Augusta. Daily bus service from Coober Pedy. Site Facilities 1200 rooms with en-suites, swimming pool, sports courts and gymnasium. Regular family days to bring family members to site to experience life at Prominent Hill. OZ MINERALS PAGE 7

8 PROMINENT HILL PRODUCTION Product: Production (2010): High grade (~50% Cu), high quality, copper concentrate. 112,171t contained copper, 196,400oz gold. Production Guidance: Contained copper 100,000t to 110,000t Contained gold 185,000oz plus -for 5+ years Mine and Plant: Open pit, mine, crush, grind, flotation. Cash costs: Competitive C1 cash costs US70.3c/lb for Q Estimated C1 costs 2011: <US70c/lb. Cu and Au Recovery TPH Milled Recovery (%) Cu Au TPH Milled (Dry) Q Q Q Q Q Q Q Q Q Q OZ MINERALS PAGE 8

9 OPEN-CUT MINE CROSS SECTION NORTH-SOUTH Complete August 2012 June 2014 October 2017 (Stock piles continue to be processed after mining of open-cut complete) OZ MINERALS PAGE 9

10 PROMINENT HILL ANKATA - UNDERGROUND Ankata underground will enable production of 100,000t to 110,000t copper to be maintained. The portal was accessed in November and advanced 626 meters by Q First ore to be produced from stoping by Q Full mining rates (1.2Mtpa) by Q VR4A April 2011 Interim Decline Ankata Decline Final Portal VR2A OZ MINERALS PAGE 10

11 PROMINENT HILL ANKATA - UNDERGROUND Interim Decline Permanent Decline OZ MINERALS PAGE 11

12 PROMINENT HILL FOCUS ON MUNDA/KALAYA CONTINUITY APPEARS GOOD PROMINENT HILL LONG SECTION 2011 OZ MINERALS PAGE 12

13 PROMINENT HILL FOCUS ON MUNDA/KALAYA CONTINUITY APPEARS GOOD PROMINENT HILL LONG SECTION 2011 MINING STUDY 2011/2012 OZ MINERALS PAGE 13

14 REGIONAL EXPLORATION NEW MINERAL PROVINCE Coober Pedy EL3445 Shadwell IMX tenements IP Surveys in Progress EL3830 EL3729 EL4429 EL3518 Airborne Magnetic Survey completed in Q4 Arapiles EL4283 EL3730 Rouse EL4132 EL4429 EL4429 Bluebird Taurus Blue Duck Cressida EL3795 Epsilon Near Mine EL4025 Prominent Hill EL3730 Neptune Metis Future OZ Minerals Prospects IMX JV target areas EL4390 OZ Minerals tenements EL3387 EL4446 Perseus Hallifax Danae Hill Approximately 7,000km 2 tenement area - 4,000km 2 OZ Minerals - 3,000km 2 IMX JV $50 million regional exploration budget. Detailed geophysics surveys undertaken five drill rigs dedicated to the OZ Minerals regional program and one drill rig for IMX JV exploration. 21 holes drilled in quarter one. Many holes intersected IOCG alteration. Some low-grade mineralisation. Program continues. Gravity 20km OZ MINERALS PAGE 14

15 ACQUISTION OF THE CARRAPATEENA COPPER GOLD DEPOSIT IN SOUTH AUSTRALIA Agreement to purchase Carrapateena IOCG copper project in March. US$250 million, plus US$50 million on production of copper and uranium, gold or silver. Benefits for OZ Minerals: Meets strategy: copper, appropriate production scale potential, favourable mining jurisdiction, long-life potential. Development could be funded from anticipated Prominent Hill cash flows. Offers development, operations, exploration, logistics and management synergies. OZ MINERALS PAGE 15

16 COMPETITIVE ACQUISTION Exploration / Development Construction / Production EVc/lb CuEq Advanced Projects / Producers OZ Minerals/ Carrapateena OZ MINERALS PAGE 16

17 CARRAPATEENA DEPOSIT - INITIAL INFERRED RESOURCE TO SOUTH Chalcopyrite shell in yellow Exploration & Inferred Resource status area Exploration area Historic drillhole collar Historic drillhole trace N Target range: 1% Cu, 0.4g/t Au, 140ppm U 3 O 8, 4g/t Ag Mineralisation not well understood, potential for extension to the east Main deposit Potential for extension at depth Mineralisation open to the east Exploration area Exploration & Inferred Resource status area Inferred resource: 0m 250m 1.31% Cu, 0.56g/t Au, 270ppm U 3 O 8, 6g/t Ag OZ MINERALS PAGE 17

18 MINING OPTIONS STUDY Options: Block caving. Inclined sublevel caving. Stoping at higher levels (then caving). Visual representation of the Carrapateena deposit Lower mining costs <$10/t $10 20/t $20 50/t Block caving Sublevel caving Sublevel open stoping Lower development costs OZ MINERALS PAGE 18

19 BLOCK CAVING INCREASINGLY COMMON Source: New Gold OZ MINERALS PAGE 19

20 CARRAPATEENA COMPARABLE WITH OTHER GLOBAL BLOCK CAVES Cu % Cu/Au grades and relative deposit size global block caves (Mt) Northparkes Lift Oyu-Tolgoi Hugo North Lift Northparkes Lift 2 Grasberg IOZ Northparkes E48 Carrapateena Grasberg DOZ Grasberg GBC 0.75 Bingham Canyon SE mine Bingham Canyon NE mine Wafi-Golpu Red Chris 0.50 Skouries 0.25 Cadia East Ridgeway Deeps Au g/t Operating mines Development project Size = Reserves Mt * NB: Carrapateena based on target range not Resource or Reserve Source: OZ Minerals research OZ MINERALS PAGE 20

21 CARRAPATEENA CONCEPTUAL PROJECT SCHEDULE Exploration drilling to complete initial Inferred Resource, 10,000m Option studies for mining Phase II exploration drilling to move to Indicated Resource Geotechnical drilling Pre-feasibility Exploration shaft Feasibility study Construction OZ MINERALS PAGE 21

22 GENERATION OF LOCAL ECONOMIC BENEFITS xxx We actively provide employment and business opportunities for people from communities close to Prominent Hill and preferentially purchase goods and services locally wherever feasible. Over 20 local businesses are currently employed at Prominent Hill. During 2010 $12 million was spent in the Coober Pedy region $7.5 million in the Upper Spencer gulf and $80 million within the state of South Australia. Our major contractor also have significant spend in the local area. We also spend about $30 million on salaries in South Australia - again this does not include the amounts that our major contractors spend. There over 500 people employed by contractors as part of our workforce at Prominent Hill. In 2010 we contributed 16 million in State Government royalties. OZ MINERALS PAGE 22

23 DEVELOPMENT OF LOCAL EMPLOYMENT OPPORTUNITIES AND SKILLS Employing locally and developing people from outside the industry - a key priority. Continued success with our locally targeted pre-employment training program. In 2010, eight indigenous trainees from the APY lands graduated from the program and as a result became full-time employees at Prominent Hill. 51 people have now graduated and been offered employment from this program. Nationally accredited TAFE qualifications. Guaranteed employment We have started a new program to train local and indigenous employees to work in a supervisory capacity this program commenced today. OZ MINERALS PAGE 23

24 GRADUATES AND APPRENTICES Our university graduate program is a two year program building on technical planning and people management skills. We currently have graduates from the areas of metallurgy, mining engineering, environmental engineering and geology. Apprenticeships are a great way to enter the workforce. Our apprenticeships are conducted on a full-time basis for a four year fixed term period in electrical and mechanical areas. New pilot program in conjunction with DECS teachers from four schools to visit Prominent Hill this month to better understand opportunities for careers in the mining industry. OZ MINERALS PAGE 24

25 RECRUITMENT CAMPAIGN Attraction of ready skilled people to South Australia is critical OZ MINERALS PAGE 25

26 Investor contact: Natalie Worley Head of Investor & External Relations THE INFORMATION IN THIS PRESENTATION WHICH REFERS TO MINERAL RESOURCES AND EXPLORATION RESULTS AT CARRAPATEENA IS BASED IN INFORMATION COMPILED BY STUART MASTERS WHO IS A MEMBER OF THE AUSTRALASIAN INSTITUTE OF MINING AND METALLURGY (AUSIMM) (108430). STUART MASTERS IS EMPLOYED BY CS-2 PTY LTD AND IS A CONSULTANT TO OZ MINERALS. HE HAS SUFFICIENT EXPERIENCE WHICH IS RELEVANT TO THE STYLE OF MINERALISATION AND TYPE OF DEPOSIT UNDER CONSIDERATION AND TO THE ACTIVITY WHICH HE IS UNDERTAKING TO QUALIFY AS A COMPETENT PERSON AS DEFINED IN THE 2004 EDITION OF THE AUSTRALIAN CODE FOR REPORTING OF EXPLORATION RESULTS, MINERAL RESOURCES AND ORE RESERVES. STUART MASTERS CONSENTS TO THE INCLUSION IN THE REPORT OF THE MATTERS BASED ON HIS INFORMATION IN THE FORM AND CONTEXT IN WHICH IT APPEARS. WITHIN THIS PRESENTATION REFERENCES TO EXPLORATION RESULTS RELATING TO PROMINENT HILL ARE BASED ON INFORMATION COMPILED BY MR MARCEL VAN ECK MSC WHO IS A FULL-TIME EMPLOYEE OF OZ MINERALS, IS A MEMBER OF THE AUSTRALIAN INSTITUTE OF GEOSCIENTISTS AND HAS SUFFICIENT EXPERIENCE RELEVANT TO THE STYLE OF MINERALISATION AND TYPE OF DEPOSIT UNDER CONSIDERATION AND TO THE ACTIVITIES UNDERTAKEN TO QUALIFY AS A COMPETENT PERSON AS DEFINED BY THE JORC CODE (2004). MR VAN ECK HAS CONSENTED TO THE INCLUSION OF THE MATERIAL IN THE FORM AND CONTEXT IN WHICH IT APPEARS. ALL OTHER REFERENCES TO EXPLORATION RESULTS WITHIN THIS PRESENTATION/STATEMENT ARE BASED ON INFORMATION COMPILED BY MR A HOUSTON BSC WHO IS A FULL-TIME EMPLOYEE OF OZ MINERALS, IS A MEMBER OF THE AUSTRALIAN INSTITUTE OF GEOSCIENTISTS AND HAS SUFFICIENT EXPERIENCE RELEVANT TO THE STYLE OF MINERALISATION AND TYPE OF DEPOSIT UNDER CONSIDERATION AND TO THE ACTIVITIES UNDERTAKEN TO QUALIFY AS A COMPETENT PERSON AS DEFINED BY THE JORC CODE (2004). MR HOUSTON HAS CONSENTED TO THE INCLUSION OF THE MATERIAL IN THE FORM AND CONTEXT IN WHICH IT APPEARS.

OZ MINERALS AUSTRALIA & EUROPE ROADSHOW. May 2011

OZ MINERALS AUSTRALIA & EUROPE ROADSHOW. May 2011 OZ MINERALS AUSTRALIA & EUROPE ROADSHOW May 2011 WWW.OZMINERALS.COM DISCLAIMER This presentation has been prepared by OZ Minerals Limited ( OZ Minerals ) and consists of written materials/slides for a

More information

For personal use only OZ MINERALS AUSTRALIAN COPPER CONFERENCE. TERRY BURGESS - Managing Director & CEO March

For personal use only OZ MINERALS AUSTRALIAN COPPER CONFERENCE. TERRY BURGESS - Managing Director & CEO March OZ MINERALS AUSTRALIAN COPPER CONFERENCE TERRY BURGESS - Managing Director & CEO 23-24 March 2011 WWW.OZMINERALS.COM DISCLAIMER This presentation has been prepared by OZ Minerals Limited ( OZ Minerals

More information

OZ MINERALS UK ROADSHOW OCTOBER

OZ MINERALS UK ROADSHOW OCTOBER OZ MINERALS UK ROADSHOW OCTOBER 2011 WWW.OZMINERALS.COM DISCLAIMER This presentation has been prepared by OZ Minerals Limited ( OZ Minerals ) and consists of written materials/slides for a presentation

More information

OZ MINERALS US ROADSHOW

OZ MINERALS US ROADSHOW OZ MINERALS US ROADSHOW SEPTEMBER 2012 WWW.OZMINERALS.COM DISCLAIMER This presentation has been prepared by OZ Minerals Limited ( OZ Minerals ) and consists of written materials/slides for a presentation

More information

OZ MINERALS CITI S 4 TH AUSTRALIAN INVESTMENT CONFERENCE OCTOBER

OZ MINERALS CITI S 4 TH AUSTRALIAN INVESTMENT CONFERENCE OCTOBER OZ MINERALS CITI S 4 TH AUSTRALIAN INVESTMENT CONFERENCE OCTOBER 2012 WWW.OZMINERALS.COM DISCLAIMER This presentation has been prepared by OZ Minerals Limited ( OZ Minerals ) and consists of written materials/slides

More information

AUSIMM - Technical Meeting & AGM

AUSIMM - Technical Meeting & AGM The Construction, Commissioning and Ramp-Up of the Prominent Hill Mine John Nitschke Executive General Manager Projects and Technical Services AUSIMM - Technical Meeting & AGM Tuesday 10th November 2009

More information

FOR THE THREE MONTHS ENDED 31 MARCH 2012

FOR THE THREE MONTHS ENDED 31 MARCH 2012 FOR THE THREE MONTHS ENDED 31 MARCH 2012 PROMINENT HILL CONTAINED METAL PRODUCTION MARCH 2012 QUARTER TOTAL COPPER (TONNES) 27,182 TOTAL GOLD (OUNCES) 38,887 OZMINERALS.COM C1 CASH COSTS US96.9c/lb HIGHLIGHTS

More information

ROADSHOW PRESENTATION

ROADSHOW PRESENTATION OZ MINERALS ROADSHOW PRESENTATION September 2013 WWW.OZMINERALS.COM DISCLAIMER This presentation has been prepared by OZ Minerals Limited ( OZ Minerals ) and consists of written materials/slides for a

More information

Newcrest Mining Limited

Newcrest Mining Limited Newcrest Mining Limited Colin Moorhead Newcrest a portfolio of opportunities Disclaimer Forward Looking Statement These materials include forward looking statements. Often, but not always, forward looking

More information

For personal use only

For personal use only ASX ANNOUNCEMENT 30 APRIL 2015 QUARTERLY ACTIVITIES REPORT HIGHLIGHTS PROJECTS Over 2,000m of RC drilling planned at SA Titan Gold & IOCG Project Drilling planned to test strong EM conductor for high grade

More information

Ramelius Resources Limited ASX:RMS

Ramelius Resources Limited ASX:RMS Ramelius Resources Limited ASX:RMS INVESTOR PRESENTATION March 2012 1 Forward Looking and Competent Persons Statements Forward looking statements This presentation contains certain forward looking statements

More information

2011 Annual General Meeting. Greg Robinson Managing Director & CEO

2011 Annual General Meeting. Greg Robinson Managing Director & CEO 2011 Annual General Meeting Greg Robinson Managing Director & CEO Disclaimer Forward Looking Statements These materials include forward looking statements. Forward looking statements inherently involve

More information

FOUR EAGLES JV FORMALISED SEISMIC AND DRILLING PROGRAMME COMMENCES

FOUR EAGLES JV FORMALISED SEISMIC AND DRILLING PROGRAMME COMMENCES ASX ANNOUNCEMENT 21 April 2015 FOUR EAGLES JV FORMALISED SEISMIC AND DRILLING PROGRAMME COMMENCES The new Four Eagles Gold Project Joint Venture with GEV and Providence has commenced after the renewal

More information

Quarterly Activities Report Period Ended 31 March 2018

Quarterly Activities Report Period Ended 31 March 2018 23 April 2018 Quarterly Activities Report Period Ended 31 March 2018 ASX Code: EXG Key Points During the March 2018 Quarter, Kalgoorlie North Gold Project (KNGP) activities predominantly involved resource

More information

For personal use only

For personal use only ABN 52 007 626 575 Date 23 rd May 2016 The Manager Market Announcements Office ASX Ltd 4th Floor, 20 Bridge Street Sydney NSW 2000 ASX Code: JRV JOINT VENTURE WITH AUSTRALIAN MINES LIMITED (ASX: AUZ) The

More information

FOR THE THREE MONTHS ENDING 30 JUNE 2011

FOR THE THREE MONTHS ENDING 30 JUNE 2011 FOR THE THREE MONTHS ENDING 30 JUNE 2011 PROMINENT HILL CONTAINED METAL PRODUCTION JUNE 2011 QUARTER YEAR TO DATE 2011 TOTAL COPPER 28,017t 53,725t TOTAL GOLD 44,219oz 86,129oz C1 CASH US56.1c/lb US62.9c/lb

More information

For personal use only

For personal use only 5 September 2016 ABN 91 124 752 745 Drilling Underway At The Koala Gold Mine, Mt Coolon Gold Project, Qld Stage 1 drilling for 1,100 metres has commenced on schedule at the Koala Gold Mine. Drilling is

More information

For personal use only

For personal use only ASX Release 24 April 2012 Westgold secures the High Grade Great Fingall Gold Mine Westgold Resources (ASX:WGR) is pleased to advise that it has acquired the 49% relevant interest in the Great Fingall Deeps

More information

For personal use only

For personal use only Suite 4, Level 3 South Shore Centre 85 South Perth Esplanade South Perth WA 6151 TEL +61 8 6313 3800 FAX +61 8 6313 3888 ABN 38 108 779 782 ASX ANNOUNCEMENT 04 July 2012 Completion of Asset Sale Agreement

More information

South America Copper Site Visit Non-ferrous overview

South America Copper Site Visit Non-ferrous overview Spence, Chile South America Copper Site Visit Non-ferrous overview Andrew Mackenzie Chief Executive Non-ferrous 26 September 2010 Disclaimer Reliance on Third Party Information The views expressed here

More information

Recent Exploration of the Olympic Dam

Recent Exploration of the Olympic Dam Recent Exploration of the Olympic Dam Southern Orebody DAVE THOMAS Olympic Dam Development Study SA Explorers Conference 2 December 2005 BHP Billiton profile (2005) The company BHP Billiton is the world

More information

CATALYST SECURES $1.5 MILLION PLACEMENT WITH ST BARBARA LIMITED

CATALYST SECURES $1.5 MILLION PLACEMENT WITH ST BARBARA LIMITED ASX ANNOUNCEMENT 16 MARCH 2017 CATALYST SECURES $1.5 MILLION PLACEMENT WITH ST BARBARA LIMITED St Barbara Limited (SBM) commits $1.5 million placement at 50 cents per share for 5% stake Funding will allow

More information

Mungana Signs Agreement with Newcrest to unlock Porphyry Gold-Copper Potential at Chillagoe

Mungana Signs Agreement with Newcrest to unlock Porphyry Gold-Copper Potential at Chillagoe Market Announcements Office ASX Ltd 4 th Floor, 20 Bridge Street, Sydney NSW 25 May 2015 ASX code: MUX Mungana Signs Agreement with Newcrest to unlock Porphyry Gold-Copper Potential at Chillagoe Agreement

More information

Market Announcement ASX:NTL, NZX:NTL For Immediate Release

Market Announcement ASX:NTL, NZX:NTL For Immediate Release Market Announcement ASX:NTL, NZX:NTL For Immediate Release Commodity Exposure GOLD and SILVER Board and Management Charbel Nader Chairman/Independent Director Quarterly Activities Report to 30 September

More information

Exploration. General Manager Minerals Development

Exploration. General Manager Minerals Development Exploration Fraser MacCorquodale General Manager Minerals Development Disclaimer Forward Looking Statement These materials include forward looking statements. Often, but not always, forward looking statements

More information

Australian Mines increases Marymia ground holding

Australian Mines increases Marymia ground holding 11 June 2015 Australian Mines increases Marymia ground holding Australian Mines Limited ( Australian Mines or the Company ) is pleased to advise shareholders that it has entered into a farm-in and joint

More information

NEWCREST Newcrest to acquire potential Tier 1 orebody in Canada Sandeep Biswas Managing Director and Chief Executive Officer

NEWCREST Newcrest to acquire potential Tier 1 orebody in Canada Sandeep Biswas Managing Director and Chief Executive Officer NEWCREST Newcrest to acquire potential Tier 1 orebody in Canada Sandeep Biswas Managing Director and Chief Executive Officer Disclaimer Forward Looking Statements This presentation includes forward looking

More information

MARCH 2018 QUARTERLY ACTIVITIES REPORT

MARCH 2018 QUARTERLY ACTIVITIES REPORT X AUSTRALIAN SECURITIES EXCHANGE ANNOUNCEMENT 27 April 2018 MARCH 2018 QUARTERLY ACTIVITIES REPORT Syndicated prepares for new phase of drilling at Monument Gold Project drilling commences in early April

More information

December 2017 Quarterly Report

December 2017 Quarterly Report ASX Announcement 31 January 2018 ASX: CRB December 2017 Quarterly Report KEY POINTS Continuation of work including final design criteria and front end engineering following Demonstration Plant test work

More information

NEWCREST LOOKING TO THE FUTURE

NEWCREST LOOKING TO THE FUTURE NEWCREST LOOKING TO THE FUTURE Sandeep Biswas Managing Director and Chief Executive Officer Disclaimer Forward Looking Statements This presentation includes forward looking statements. Forward looking

More information

For personal use only

For personal use only QUARTERLY ACTIVITIES REPORT PERIOD ENDED 30 JUNE 2015 ASX Announcement ASX Code: VXR Released: 31 July 2015 Venturex Resources Limited (ASX: VXR) is pleased to report its activities for the June 2015 Quarter.

More information

Lorena Gold Project Malachite AGM 29 November 2017

Lorena Gold Project Malachite AGM 29 November 2017 Lorena Gold Project Malachite AGM 29 November 2017 Disclaimer and Competent Person Statement Disclaimer This presentation may contain forward looking statements that are subject to risk factors associated

More information

BMO CAPITAL MARKETS GLOBAL METALS & MINING CONFERENCE PRESENTATION 25 FEB 2008

BMO CAPITAL MARKETS GLOBAL METALS & MINING CONFERENCE PRESENTATION 25 FEB 2008 ASX ANNOUNCEMENT Manager Announcements Company Announcements Office ASX Limited 4th Floor, 20 Bridge Street Sydney NSW 2000 By E-Lodgement No. of pages: 25 25 February 2008 BMO CAPITAL MARKETS GLOBAL METALS

More information

Annual Mineral Resources and Ore Reserves Statement - 31 December 2016

Annual Mineral Resources and Ore Reserves Statement - 31 December 2016 Market Release 13 February 2017 Annual Mineral Resources and Ore Reserves Statement - 31 December 2016 Newcrest Mining Limited has updated its Mineral Resource and Ore Reserve estimates for the twelve

More information

HARMONY GOLD AND NEWCREST FORM PAPUA NEW GUINEA GOLD JOINT VENTURE

HARMONY GOLD AND NEWCREST FORM PAPUA NEW GUINEA GOLD JOINT VENTURE HARMONY GOLD AND NEWCREST FORM PAPUA NEW GUINEA GOLD JOINT VENTURE The world s 5 th largest gold producer, Harmony Gold Mining Company Limited ( Harmony ) and Australasia s largest gold company, Newcrest

More information

For personal use only

For personal use only ASX / Media Announcement 10 November 2017 Artemis Resources Limited ARBN: 80 107 051 749 Level 3, IBM Building, 1060 Hay Street, West Perth, WA Australia, 6006 PO Box R933 Royal Exchange NSW Australia,

More information

For personal use only

For personal use only ASX Announcement 15 May 2012 ARTEMIS ACQUIRES STRATEGIC WEST PILBARA GOLD AND BASE METALS ASSETS About Artemis Resources Artemis Resources is an ASX-listed mineral exploration company with a focus on gold:

More information

Angas Zinc Mine From Prediction to Production

Angas Zinc Mine From Prediction to Production TERRAMIN AUSTRALIA LIMITED Angas Zinc Mine From Prediction to Production Bob Singer SA Explorers Conferenc ce 28 November 2008 Important information The information in this presentationn is designed as

More information

Market Release 11 March 2019

Market Release 11 March 2019 Market Release 11 March 2019 Newcrest to acquire potential Tier 1 orebody in Canada Newcrest Mining Limited (Newcrest) has entered into an agreement with TSX-listed Imperial Metals Corporation (Imperial)

More information

Quarterly Activities Report Period Ended 31 December 2017

Quarterly Activities Report Period Ended 31 December 2017 24 January 2018 ASX Code: EXG Quarterly Activities Report Period Ended 31 December 2017 Key Points Successful completion of the Zoroastrian open pit ore treatment campaign. Cash balance peaks at $8.1M

More information

Annual Mineral Resources and Ore Reserves Statement - 31 December 2017

Annual Mineral Resources and Ore Reserves Statement - 31 December 2017 Market Release 15 February 2018 Annual Mineral Resources and Ore Reserves Statement - 31 December 2017 Newcrest Mining Limited has updated its Mineral Resource and Ore Reserve estimates for the twelve

More information

For personal use only

For personal use only ABN: 57 126 634 606 Phone: +61 (7) 4032 3319 info@csdtin.com.au Snapshot: Current CSD Share Price: $0.10 Current LME Tin Price: $24,475 Key Points Snow Peak Mining Pty Ltd acquisition of Kagara s Central

More information

Focus Begins Accelerated Development of the Mount into New Stand Alone Mining Operation

Focus Begins Accelerated Development of the Mount into New Stand Alone Mining Operation Focus Begins Accelerated Development of the Mount into New Stand Alone Mining Operation Outstanding exploration and trial mining results from The Mount deposit pave way to create a 2 nd operational centre

More information

ASX Announcement 7 June 2011 Mt Isa Metals Ltd Drilling Recommences at Nabanga, Burkina Faso

ASX Announcement 7 June 2011 Mt Isa Metals Ltd Drilling Recommences at Nabanga, Burkina Faso ASX Announcement 7 June 2011 Mt Isa Metals Ltd Drilling Recommences at Nabanga, Burkina Faso The Directors of D Aguilar Gold Limited (ASX Code: DGR) are pleased to draw the attention of shareholders to

More information

For personal use only

For personal use only Iron Ore Holdings Ltd Investor Presentation July 2014 IOH - Company Status 2 Corporate Overview Background ASX listed in 2005 1.6 billion tonnes JORC Mineral Resources Iron Valley Project production in

More information

SA Exploration and Mining Conference. Monax Exploration Update. Targeting the next large copper deposit on the Gawler Craton.

SA Exploration and Mining Conference. Monax Exploration Update. Targeting the next large copper deposit on the Gawler Craton. SA Exploration and Mining Conference November 28, 2013 Monax Exploration Update Targeting the next large copper deposit on the Gawler Craton Gary Ferris Managing Director Monax Mining Project Overview

More information

For personal use only

For personal use only INDOCHINE MINING LIMITED ACN 141 677 385 ASX: IDC 29 July 2011 Company Announcements Office Australian Securities Exchange 8 Pages Quarterly Activities Report For Quarter ended 30 June 2011 Highlights

More information

ASX ANNOUNCEMENT 25 JANUARY 2008 FURTHER HIGH GRADE INTERCEPTS FROM THE KOKA GOLD DEPOSIT, ERITREA

ASX ANNOUNCEMENT 25 JANUARY 2008 FURTHER HIGH GRADE INTERCEPTS FROM THE KOKA GOLD DEPOSIT, ERITREA ASX ANNOUNCEMENT 25 JANUARY 2008 FURTHER HIGH GRADE INTERCEPTS FROM THE KOKA GOLD DEPOSIT, ERITREA Zara Joint Venture, Eritrea (Dragon Mining Limited - 20% interest) Koka Gold Deposit Dragon Mining Limited,

More information

LAS OPEÑAS DRILLING COMMENCED

LAS OPEÑAS DRILLING COMMENCED ASX Announcement 17 October 2012 LAS OPEÑAS DRILLING COMMENCED LAS OPEÑAS, ARGENTINA Diamond drilling program commenced Targeting both high-grade epithermal veins and breccia bodies CERRO VERDE, CHILE

More information

OMNR. ^ååì~ä=déåéê~ä=jééíáåö. OT=klsbj_bo=OMNR=== ^puw=cjp===

OMNR. ^ååì~ä=déåéê~ä=jééíáåö. OT=klsbj_bo=OMNR=== ^puw=cjp=== OMNR ^ååì~ä=déåéê~ä=jééíáåö OT=klsbj_bo=OMNR=== ^puw=cjp=== 2 `çêéçê~íé=pìãã~êó Board & Management Capital Structure Robert Kennedy Non-Executive Chairman A Chartered Accountant and a Director since 14

More information

For personal use only

For personal use only ASX ANNOUNCEMENT 31 Oct 2016 Focus Minerals Ltd Activities and Cashflow Report for September Quarter 2016 Exploration Highlights During the Quarter During the September Quarter, Focus Minerals Ltd ( Focus

More information

For personal use only

For personal use only RENAISSANCE URANIUM LIMITED AND SUBSIDIARIES A.B.N. 90 135 531 341 CONSOLIDATED FINANCIAL REPORT FOR THE HALF-YEAR ENDED 31 DECEMBER 2012 RENAISSANCE URANIUM LIMITED CORPORATE DIRECTORY DIRECTORS David

More information

For personal use only

For personal use only 22 November 2018 ASX : ARV FRANKFURT : ATY US OTCQB : ARTTF GOLD, COBALT AND COPPER IN THE WEST PILBARA ARTEMIS RESOURCES LIMITED IS AN AUSTRALIAN MINERAL DEVELOPER ADVANCING ITS WEST PILBARA BASE, BATTERY

More information

For personal use only

For personal use only Artemis Resources Limited ARBN: 80 107 051 749 Level 3, IBM Building, 1060 Hay Street, West Perth, WA Australia, 6006 PO Box R933 Royal Exchange NSW Australia, 1225 Phone: +61 2 9078 7670 Facsimile: +61

More information

Cadia Valley. Peter Smith Executive General Manager Australian Operations

Cadia Valley. Peter Smith Executive General Manager Australian Operations Cadia Valley Peter Smith Executive General Manager Australian Operations Disclaimer Forward Looking Statement These materials include forward looking statements. Often, but not always, forward looking

More information

For personal use only

For personal use only HIGHLIGHTS Mount Bundy Gold Project Drill results from Rustlers Roost shows 117m at 1.5 g/t gold including 8m at 6.9 g/t gold with other broad intercepts - Drill program highlights potential to further

More information

Kinross Gold Corporation Merrill Lynch Global Metals, Mining & Steel Conference May 13 15, 2008

Kinross Gold Corporation Merrill Lynch Global Metals, Mining & Steel Conference May 13 15, 2008 DELIVERING DISCIPLINED GROWTH 1 Cautionary Statements All statements, other than statements of historical fact, contained or incorporated by reference in this presentation, including any information as

More information

ON TIME AND ON BUDGET: PROCESSING PLANT OVER 90% COMPLETE AND FIRST PRODUCTION SET FOR MARCH

ON TIME AND ON BUDGET: PROCESSING PLANT OVER 90% COMPLETE AND FIRST PRODUCTION SET FOR MARCH MT MORGANS GOLD PROJECT UPDATE 11 JANUARY 2018 ON TIME AND ON BUDGET: PROCESSING PLANT OVER 90% COMPLETE AND FIRST PRODUCTION SET FOR MARCH Underground mining 873m ahead of schedule with ore intersected

More information

Lihir Operations PNG Mining and Petroleum Conference 24 November Peter Aitsi Country Manager, PNG

Lihir Operations PNG Mining and Petroleum Conference 24 November Peter Aitsi Country Manager, PNG Lihir Operations PNG Mining and Petroleum Conference 24 November 2015 Peter Aitsi Country Manager, PNG Disclaimer Forward Looking Statements These materials include forward looking statements. Often, but

More information

Quarterly Report Newcrest Mining Limited For the three months ending 30 June 2007 (These figures are unaudited)

Quarterly Report Newcrest Mining Limited For the three months ending 30 June 2007 (These figures are unaudited) Quarterly Report Newcrest Mining Limited For the three months ending 30 June 2007 (These figures are unaudited) Key Points Operations Record quarterly gold production of 463,170oz (390,096oz). Group cash

More information

Candelaria and Ojos del Salado Chile

Candelaria and Ojos del Salado Chile TSX : LUN OMX : LUMI 2016 Candelaria Key Facts Open Pit and Underground Mine Copper, gold, and silver 2016 estimate 130,000-132,000 tonnes copper Cash costs of $1.35 per lb copper after by-product credits

More information

For personal use only

For personal use only Market Release Newcrest Mining Limited 8 February 2013 December 2012 Resources and Reserves Statement Newcrest Mining Limited has updated its Mineral Resource and Ore Reserve estimates for the twelve month

More information

Quarterly Results. Greg Robinson CEO & Managing g Director

Quarterly Results. Greg Robinson CEO & Managing g Director December 2011 Quarterly Results Greg Robinson CEO & Managing g Director Disclaimer Forward Looking Statements These materials include forward looking statements. Forward looking statements inherently involve

More information

For personal use only

For personal use only 28 September 2018 GBM EXECUTES AGREEMENT WITH MINJAR TO ACQUIRE TWIN HILLS GOLD PROJECT IN DRUMMOND BASIN, QUEENSLAND HIGHLIGHTS Binding Sale and Purchase Agreement signed with Minjar Gold Pty Ltd 1 to

More information

Wafi Golpu. Craig Jones Executive General Manager Australian Operations and Projects. 7 October 2014

Wafi Golpu. Craig Jones Executive General Manager Australian Operations and Projects. 7 October 2014 Wafi Golpu Craig Jones Executive General Manager Australian Operations and Projects 7 October 2014 Disclaimer Forward Looking Statements These materials include forward looking statements. Often, but not

More information

Market Release Newcrest Mining Limited 10 February 2012

Market Release Newcrest Mining Limited 10 February 2012 Market Release Newcrest Mining Limited 10 February 2012 December 2011 Resources and Reserves Statement Newcrest Mining Limited has updated its Mineral Resource and Ore Reserve estimates for the six month

More information

Kidman agrees to acquire 1Moz Mt Holland gold field in WA

Kidman agrees to acquire 1Moz Mt Holland gold field in WA December 18th, 2015 Kidman Resources Limited ABN 88 143 526 096 Corporate Details: ASX Code: KDR Issued capital: 142.3M ordinary shares Substantial Shareholders: Capri 22.7m (15.97%) Holdex Nominees 11.3m

More information

Gruyere Project Development Update

Gruyere Project Development Update ASX Announcement 21 June 2017 Gruyere Project Development Update Highlights Project Capital budget revised to A$532 1 million (3.5% increase) following engineering, procurement and construction review

More information

QUARTERLY ACTIVITIES REPORT

QUARTERLY ACTIVITIES REPORT QUARTERLY ACTIVITIES REPORT For the quarter ended 31 December 2010 ABN: 38 108 779 782 Silver Lake Resources Ltd ( Silver Lake or the Company ) is pleased to present this Quarterly Activities Report. Les

More information

Australian Securities Exchange Notice

Australian Securities Exchange Notice Australian Securities Exchange Notice 30 January 2017 ILUKA BUSINESS REVIEW UPDATE AND THE IMPACT ON 2016 AND 2017 FINANCIAL RESULTS Iluka Resources Limited (Iluka) provides the following update relating

More information

ORO VERDE LIMITED (ASX: OVL)

ORO VERDE LIMITED (ASX: OVL) ORO VERDE LIMITED (ASX: OVL) Nicaragua A golden past and future Proactive Investor Luncheons Sydney & Melbourne February 2017 Trevor Woolfe (Managing Director) Disclaimer Forward Looking Statements - This

More information

BMO Capital Markets Global Metals & Mining Conference Feb 2012, Florida USA

BMO Capital Markets Global Metals & Mining Conference Feb 2012, Florida USA BMO Capital Markets Global Metals & Mining Conference 26-29 Feb 2012, Florida USA Greg Robinson Managing Director & CEO Disclaimer 2 Forward Looking Statements These materials include forward looking statements.

More information

Kinross Nevada tour highlights growth potential at Bald Mountain and Round Mountain

Kinross Nevada tour highlights growth potential at Bald Mountain and Round Mountain 25 York Street, 17th Floor Toronto, ON Canada M5J 2V5 NEWS RELEASE Kinross Nevada tour highlights growth potential at Bald Mountain and Round Mountain Toronto, Ontario June 29, 2016 In advance of an analyst

More information

Australian Site Tour Mt Keith Operation. Jaco Harwig General Manager

Australian Site Tour Mt Keith Operation. Jaco Harwig General Manager Australian Site Tour Mt Keith Operation Jaco Harwig General Manager 28 October 2008 Important notices Reliance on third party information The views expressed here contain information that have been derived

More information

HANNAN CONTINUES DRILL SUCCESS OUTSIDE RESOURCE AREA AT KILBRICKEN, IRELAND Drill Results Include 8.0% ZnEQ and 10.

HANNAN CONTINUES DRILL SUCCESS OUTSIDE RESOURCE AREA AT KILBRICKEN, IRELAND Drill Results Include 8.0% ZnEQ and 10. 1305 1090 West Georgia Street, Vancouver, BC, V6E 3V7 Phone: +1 604 685 9316 / Fax: +1 604 683 1585 NEWS RELEASE November 27, 2017 HANNAN CONTINUES DRILL SUCCESS OUTSIDE RESOURCE AREA AT KILBRICKEN, IRELAND

More information

An Emerging Coal Company. Investor Update October 2012

An Emerging Coal Company. Investor Update October 2012 An Emerging Coal Company Investor Update October 2012 Cautionary Statement The information contained in this document (Presentation) has been prepared by NuCoal Resources Ltd and Doyles Creek Mining Pty

More information

4th Quarter Report 2015

4th Quarter Report 2015 4th Quarter Report 2015 HIGHLIGHTS Successful visit of Algerian Delegation to China Increase and extension of Asipac debt facility Marketing Agreement for production from Bird-in-Hand Gold Project Placement

More information

Company Update. August 2015

Company Update. August 2015 Company Update August 2015 Disclaimer This presentation has been prepared by and issued by Bathurst Resources Limited ( Bathurst ) to assist it in informing interested parties about the Company and its

More information

Ramelius Resources Limited ASX:RMS

Ramelius Resources Limited ASX:RMS Ramelius Resources Limited ASX:RMS Diggers & Dealers 3-5 August 2015 Ramelius Resources Limited Diggers and Dealers - August 2015 2 Forward Looking and Competent Persons Statements Forward Looking Statements

More information

OZ minerals business review 2010 OZ MINERALS LIMITED ABN A clear direction

OZ minerals business review 2010 OZ MINERALS LIMITED ABN A clear direction OZ minerals business review 2010 OZ MINERALS LIMITED ABN 40 005 482 824 A clear direction now and for the future about us OZ Minerals is an Australian mining company focused on copper. The Prominent Hill

More information

Mining Address. Ian Smith MD & CEO Newcrest Mining Limited

Mining Address. Ian Smith MD & CEO Newcrest Mining Limited Mining Address Ian Smith MD & CEO Newcrest Mining Limited Disclaimer Competent Persons Statement The information in this presentation that relates to Exploration Results, Mineral Resources and Ore Reserves

More information

2 September The Manager Market Announcements Australian Securities Exchange 20 Bridge Street SYDNEY NSW 2000 AURORA TANK PROJECT

2 September The Manager Market Announcements Australian Securities Exchange 20 Bridge Street SYDNEY NSW 2000 AURORA TANK PROJECT 2 September 2014 The Manager Market Announcements Australian Securities Exchange 20 Bridge Street SYDNEY NSW 2000 AURORA TANK PROJECT Please find following for shareholders information, an announcement

More information

Morgan Stanley Asia Pacific Summit November Ian Smith MD & CEO

Morgan Stanley Asia Pacific Summit November Ian Smith MD & CEO Morgan Stanley Asia Pacific Summit November 2008 Ian Smith MD & CEO Disclaimer Forward Looking Statements These materials include forward looking statements. Forward looking statements inherently involve

More information

BHP Billiton: A Strategy of Diversification

BHP Billiton: A Strategy of Diversification Olympic Dam, Australia BHP Billiton: A Strategy of Diversification Andrew Mackenzie Chief Executive Non-Ferrous 9 June 2010 Disclaimer Reliance on Third Party Information The views expressed here contain

More information

QUARTERLY OPERATIONS REPORT 30 JUNE Highlights: BOARD AND MANAGEMENT YAMARNA

QUARTERLY OPERATIONS REPORT 30 JUNE Highlights: BOARD AND MANAGEMENT YAMARNA QUARTERLY OPERATIONS REPORT 30 JUNE 2016 Highlights: YAMARNA Geochemical blade-refusal aircore programme confirms the extent of the Jatz basement gold anomaly at over 1.5 km in strike. Multiple RC drilling

More information

Highlights. Quarterly Activities Report: September Kurnalpi Project. Lindsays project

Highlights. Quarterly Activities Report: September Kurnalpi Project. Lindsays project Quarterly Activities Report: September 2018 KalNorth Gold Mines Limited Date: 31 October 2018 ASX Code: KGM Issued Capital 894.24 million Ordinary shares Current Share Price $0.006 Market tfollo Capitalisation

More information

Altera Resources Ltd

Altera Resources Ltd 31 January 2011 QUARTERLY REPORT FOR THE 3 MONTHS ENDED 31 December 2010 HIGHLIGHTS Completed the acquisition of JDC and coal projects in Kalimantan, Indonesia New board and management of highly experienced

More information

Australian Site Tour Ravensthorpe Nickel Operation. Isak Buitendag General Manager

Australian Site Tour Ravensthorpe Nickel Operation. Isak Buitendag General Manager Australian Site Tour Ravensthorpe Nickel Operation Isak Buitendag General Manager 29 October 2008 Important notices Reliance on third party information The views expressed here contain information that

More information

Q3 FY18 Business Highlights

Q3 FY18 Business Highlights Q3 FY18 RESULTS Q3 FY18 Business Highlights 1 2 3 4 5 6 7 Record passengers 7.1m, record revenues 423m Investing in growth 24% passenger growth in Q3 Disciplined cost management flat ex-fuel CASK Largest

More information

PROJECTS & TECHNICAL SERVICES

PROJECTS & TECHNICAL SERVICES PROJECTS & TECHNICAL SERVICES 1.0 2.0 3.0 4.0 5.0 JOHN NITSCHKE EGM Projects & Technical Services 6.0 7.0 8.0 9.0 OZ MINERALS NOVEMBER 2009 PAGE 40 STRATEGY SUPERIOR TOTAL SHAREHOLDER RETURNS ZERO HARM

More information

For personal use only

For personal use only ASX Release / 5 December 2016 Presentation to PNG Mining and Petroleum Investment Conference Attached is a presentation by Bob Vassie, Managing Director and CEO, to the 14th Papua New Guinea Mining and

More information

For personal use only

For personal use only ASX Announcement 11 May 2017 ORO VERDE PRESENTATION IN SYDNEY Oro Verde Limited (ASX: OVL) ( Oro Verde or the Company ) is pleased to announce that Managing Director Trevor Woolfe is attending and presenting

More information

NEWS RELEASE Orca Gold Receives Ministerial Approval for the Acquisition of the Kinross Côte d Ivoire Property Portfolio

NEWS RELEASE Orca Gold Receives Ministerial Approval for the Acquisition of the Kinross Côte d Ivoire Property Portfolio Orca Gold Inc. 2000-885 West Georgia St. Vancouver, B.C., V6C 3E8, Canada Tel: +1 604 689 7842 Fax: +1 604 689 4250 NEWS RELEASE Orca Gold Receives Ministerial Approval for the Acquisition of the Kinross

More information

FOCUS MINERALS LIMITED

FOCUS MINERALS LIMITED FOCUS MINERALS LIMITED FFT:FZA ASX:FML Driving Sustainable Profitable Production Focus 1.2Mtpa Three Mile Hill processing plant in Coolgardie, WA Campbell Baird, CEO Denver Gold Forum: 9 th 12 th September

More information

December 2014 Quarterly Report

December 2014 Quarterly Report Corporate Structure Shares 35,970,000 Options 7,250,000 Perf. Rights 5,000,000 Cash $4.2m ASX Code - BBR Directors Patrick Ford Non-Executive Chairman Chris Cowan Executive Director Nelson Reynolds Non-Executive

More information

For personal use only

For personal use only 31 January 2012 DIRECTORS Michael Fry Chairman Ian Prentice Managing Director Darren Misquitta Executive Director Robert Kipp Non Executive Director Matthew Driscoll Non Executive Director Suzie Foreman

More information

Kinross acquires mining rights to land adjacent Fort Knox mine, adds more than 2 million ounces to mineral resource estimates

Kinross acquires mining rights to land adjacent Fort Knox mine, adds more than 2 million ounces to mineral resource estimates 25 York Street, 17th Floor Toronto, ON Canada M5J 2V5 NEWS RELEASE Kinross acquires mining rights to land adjacent Fort Knox mine, adds more than 2 million ounces to mineral resource estimates Toronto,

More information

EL LIMON MINE: EMPLOYEES & CONTRACTORS 133

EL LIMON MINE: EMPLOYEES & CONTRACTORS 133 132 EL LIMON MINE: EMPLOYEES & CONTRACTORS 133 B2Gold Employees Direct 552 Nicaraguans 548 Expats 4 Unionized 494 Men 499 Women 53 Contractors Employees 570 Men 529 Women 41 EL LIMON MINE: NICARAGUA OPEN

More information

ORION METALS LIMITED (ASX: ORM) ACTIVITIES REPORT FOR QUARTER ENDING 31 st August 2014.

ORION METALS LIMITED (ASX: ORM) ACTIVITIES REPORT FOR QUARTER ENDING 31 st August 2014. ORION METALS LIMITED (ASX: ORM) ACTIVITIES REPORT FOR QUARTER ENDING 31 st August 2014. EXPLORATION ACTIVITIES Orion s efforts towards project growth, evaluation, and rationalisation have been the focus

More information

Investor Presentation July 2013

Investor Presentation July 2013 ASX and Media Release: 1 ASX code: RXM Investor Presentation Rex Minerals Ltd (Rex) is pleased to release its latest investor presentation. This presentation will be used for International and domestic

More information