1 PURPOSE AND NEED 1.1 INTRODUCTION

Size: px
Start display at page:

Download "1 PURPOSE AND NEED 1.1 INTRODUCTION"

Transcription

1 1.1 INTRODUCTION 1 PURPOSE AND NEED This Environmental Assessment (EA) addresses projects at Juneau International Airport (JIA) that are the direct outcome of a Master Plan prepared for the airport and approved by the City and Borough of Juneau (CBJ) Assembly in The Master Plan provides projections of aviation demand, demand/capacity analysis, and determination of facility requirements for a 20-year planning horizon. Four projects within the 20-year Master Plan (Figure 1-1, Proposed Development) have been identified as requiring preparation of an EA (Federal Aviation Administration [FAA] Order A, paragraph 22). The need for these projects has been identified by the FAA and the Master Plan (demand/capacity analysis and determination of facility requirements). These four projects are: + Runway Safety Area (RSA) Improvements. The purpose of this project is to bring the airport into compliance with FAA regulations. The FAA action required for this project is funding and Airport Layout Plan (ALP) approval. Additional federal action required for this project is permitting. The time frame for this project is three years. + Snow Removal Equipment Building (SREB) and Sand Shed. The purpose of this project is to provide adequate shelter and storage for snow removal equipment, sand, pavement deicing and anti-icing compounds, and other materials and supplies. The FAA action required for this project is funding and ALP approval. Additional federal action required for this project is permitting. The time frame for this project is five years. + East Aviation and Helicopter Area. The purpose of this project is to provide area for fixed base operator facilities, hangars, helicopter operation facilities, and tiedowns. The FAA action required for this project is funding and ALP approval. Additional federal action required for this project is permitting. The development of this area will start at the time of environmental and permit approval and continue over the next 20 years. + Medium Intensity Approach Lighting System with RAIL (Runway Alignment Indicator Lights) (MALSR). The purpose of this project is to install a MALSR and access road at the east approach to the JIA runway to provide a visual guidance system that helps the pilot align with the runway. The FAA action required for this project is funding and ALP approval. Additional federal action required for this project is permitting. The time frame for this project is two years. The proposed projects listed above all have independent utility, although several projects address similar needs. For instance, the RSA Improvements and the MALSR both address safety issues. However, these two projects are not dependent on the existence of the other to fulfill their intended purpose either could work with or without the other. Similarly, the SREB complex would serve its 6/5/00 Page 1-1 Rev. 2

2 Insert Figure 1-1 6/5/00 Page 1-2 Rev. 2

3 purpose whether or not the East Aviation and Helicopter Area was constructed, and vice versa, although both projects address existing and future needs at the airport. Each of the four projects addresses different deficiencies, but because they are in proximity to one another, they are operationally interrelated and it is appropriate to consider them together in one environmental document. Five projects included in the Master Plan are categorically excluded from consideration under this EA and have independent utility from projects evaluated in this EA: Construction of acute-angled exit taxiways. Paving existing filled gravel tie-down areas. Construction of a new apron and ramp at the terminal expansion. Expansion of the terminal building to the east into the area currently occupied by rental cars. Conversion of Yandukin Drive to a two-way street by means of traffic islands and signage. Under FAA Order a, these types of projects are categorically excluded unless extraordinary circumstances exist. A review of the projects reveals that no extraordinary circumstances exist. These projects: 1) will not have effects on properties protected under the Historic Preservation Act; 2) are not expected to be highly controversial; 3) will not have significant impacts on natural, ecological, cultural, or scenic resources; 4) are not likely to disrupt or divide the community; 5) will not cause a significant increase in surface traffic congestion; 6) will not produce a significant impact on noise levels; 7) will not have significant impacts on air or water quality; and 8) will not be inconsistent with any federal, state, or local law. Therefore, these five projects will not be considered by this EA except as they contribute to cumulative impacts (see Chapter 4). Several other projects are ongoing at JIA including float pond improvements, west-end general aviation (GA) hangars, and east-end tie-down development. These projects have completed environmental documentation and will be included in the cumulative impact analysis in Chapter 4 of this EA. 1.2 DEVELOPMENT PROJECTS RSA Improvements The Federal Aviation Act charges the FAA with providing for a safe and efficient national airspace system. FAA accomplishes this in part by funding airport development that enhances aviation safety. RSAs are an example of airport development that help to accomplish this mission. Airports that provide scheduled air carrier service with passenger aircraft of 30 seats or more are required to hold an Airport Operating Certificate from FAA issued under Federal Aviation Regulation (FAR) Part 139. JIA is FAR Part 139 certified. This regulation requires, in part, that the airport provide for a standard RSA to the maximum extent practicable. This requirement must be met at the time that the airport implements an improvement project for the runway. JIA repaved its runway in the summer of Therefore, JIA is overdue in meeting this requirement and must make an effort to meet this requirement to maintain its certification. 6/5/00 Page 1-3 Rev. 2

4 The RSA is intended to provide a surface that will prevent damage to an airplane that lands short or long or that veers off the runway and enhance the ability of aircraft fire fighting and rescue equipment to access downed aircraft, minimizing the loss of life and injury. FAA standards require an RSA to be a cleared and graded area surrounding the runway. The RSA should also be properly drained; capable of supporting aircraft, snow removal equipment, and aircraft rescue/firefighting equipment; and free of objects, except those mounted on frangible supports such as runway lights. FAA design standards require that all runways have a sufficient RSA for the type of design aircraft. Safety area dimensions are based on aircraft performance and accident statistics. Based on these criteria for aircraft regularly using runway 8/26 at JIA, the RSA should be 500 feet wide and extend 1,000 feet beyond each end of the runway. The critical design aircraft for runway 8/26 is the Boeing which requires an 8,700-foot runway at maximum takeoff payload. The existing RSA extends about 250 feet past both runway ends. From the runway 26 end, the runway has an RSA width of 228 feet for the first 3,500 feet and a width of 480 feet for the rest of the 8,456-foot-long runway (Chapter 4, JIA Master Plan, 1999). In addition, the existing RSA has several deficiencies relating to potentially hazardous surface variations, including "... ruts, humps, depressions, and other surface variations" (FAA Letter of Correction, July 7, 1996). The provision of an RSA at the Juneau Airport that meets FAA design standards is considered very important because of the challenging terrain and weather conditions. The full RSA would provide an additional measure of safety, which when combined with other improvements at the airport such as the global positioning system (GPS) approach system, will substantially increase the safety margin for the traveling public. The JIA will request approval for funding of percent by the FAA for construction of the RSA upon approval of the environmental documentation. Construction of the RSA will begin immediately upon receipt of FAA funding and receipt of necessary permits and is expected to be completed within three years SREB and Sand Shed The Master Plan identifies the need for a new SREB as well as a new storage building for sand, pavement deicing and anti-icing compounds, and other materials and supplies. The airport currently has 18 pieces of snow removal and maintenance equipment valued at approximately $6.5 million. Funding for this equipment has come primarily from FAA. The existing maintenance facility, at 5,200 square feet, is inadequate to house this equipment, leaving the equipment outdoors exposed to the elements and subject to freeze-up and causing significant long-term damage. Both the existing maintenance facility and sand storage hangar are more than 37 years old and are not in compliance with all local building codes, employee accessibility laws, and worker safety per Occupational Safety and Health Administration (OSHA) codes. The sand storage hangar is also in a state of disrepair. FAA has emphasized the critical importance of a vehicle storage building to the longevity of the equipment they have funded to date and will fund in the future. Additionally equipment stored outside is not able to respond to snow removal operations efficiently due to the additional time involved in warming and clearing of snow. Prompt snow removal and deicing is 6/5/00 Page 1-4 Rev. 2

5 essential for safe airport operations. The equipment s sensitive electronic controls are subject to premature failure when continually exposed to inclement weather. The FAA has indicated that replacement of equipment that has failed because of weather damage prior to completion of its normal life-span will not be eligible for full funding. The airport maintenance crew uses about 5,000 cubic yards of sand each year to improve traction on icy aprons and taxiways during the winter. A sand storage building is needed to protect the sand from becoming saturated by rainfall and subsequently freezing when the weather cools. Deicing chemicals, such as urea, are also stored in the sand shed. In addition to the previous noted deficiencies, both the existing maintenance facility and the sand storage hangar are poorly sited with respect to operational safety. Since their construction, fixedwing and rotary-wing operations have grown around the facilities, requiring transit of heavy equipment through the aircraft operation areas en route to the runway. The Master Plan recommends that a new SREB and sand storage facility be constructed. The SREB should have a sufficient area to house most of the inventory of equipment, comply with current codes and laws, have long-term operational efficiencies, and allow convenient land-side access. Vehicle storage requires at least 23,000 square feet. Other maintenance and administrative requirements would bring the total square footage needed to 40,000 square feet. A sand storage facility with a capacity of 5,000 cubic yards of sand would need an area of 9,500 square feet, and should be colocated with the SREB East Aviation and Helicopter Area GA facilities at the airport include fixed-base operator (FBO) facilities, T- and conventional hangars, floatplane slips, and aircraft parking apron/tiedowns. The Master Plan demand/capacity and facility requirements analysis identified a need for 24,700 square yards of tie-downs, including taxi lanes, to accommodate 35 based and transient GA aircraft within the next five years. This total square yardage includes taxilanes. Facilities currently under construction as well as planned facilities west of Duck Creek and in the floatplane pond were taken into account in computing these needs. The Master Plan recommends development of the needed tie-down aprons in the area between the Wings of Alaska hangar and the TEMSCO helicopter facility. Tourism activities, area businesses and industries, and the availability of maintenance and fuel services attract transient aircraft to an airport. Transient ramp areas are used for loading and unloading passengers, for short-term parking by aircraft using the airport's facilities, or for those visiting the area. A planning factor of approximately 700 square yards per tie-down reflects the diverse mix of transient aircraft, including large corporate and military aircraft using the airport on a regular basis. In addition to the transient aircraft requirements, FAA planning guidelines recommend that tie-down spaces be provided for all based aircraft not stored in hangars. Approximately 40 percent of the aircraft based at the airport are currently tied down. Tie-down requirements also include a provision for the tie-down of 70 percent of the based floatplane fleet, which are stored in slips during the summer, but require a tie-down apron area during the winter. 6/5/00 Page 1-5 Rev. 2

6 Helicopter operations at the airport are currently located in three areas: near the east end of the airport, just east of the terminal building, and west of the terminal building. Location of helicopter operations both east and west of the terminal building results in mingling of rotary-wing and fixedwing operations which is undesirable from a safety standpoint. In addition, the helicopter operations in those areas increase noise in adjacent residential areas. The Master Plan forecasts increases in helicopter operations that will lead to increased conflicts between the fixed- and rotary-wing operations. There are currently 31 helicopters based at the airport. As the helicopter fleet increases, so will the need for associated storage and operations areas. Several helicopter operators have no room to expand at their present locations. The Master Plan recommends locating all helicopter operations near the east end of the airport. This location will provide room for forecast increases in helicopter operations as well as consolidating rotary-wing operations and decreasing noise in residential areas MALSR The FAA has identified the need for a MALSR at the east approach to the JIA runway (FAA, Anchorage National Airspace System Implementation Center, March 11, 1999). The MALSR would be directly funded by the FAA and constructed within five years of environmental approval. The MALSR provides a visual guidance system for aircraft approaching an airport by helping the pilot align properly with the runway. This navigational aid (navaid) would increase safety for aircraft landing on runway 26. A MALSR currently exists off the west end of the runway to guide aircraft landing on runway 8. The MALSR is a series of lights on standards that align with the runway centerline. The system would consist of a total of 12 light towers. The towers would be at 200-foot intervals, beginning at the east end of the runway, at the runway threshold. If the full RSA is constructed, the first five lights would be flush with the surface of the RSA, and would not require towers or additional fill. The lighting system extends a total of 2,400 feet from the runway threshold. The system provides both steady burning and flashing lights. The lights for the flasher system sequence toward the runway threshold and appear as an arrow or pointer from the aviator's perspective during the approach phase of the flight. The system is activated by the Air Traffic Control Tower (ATCT) and is not intended for constant use. The system is especially important for instrument approaches that are now available using the GPS. The MALSR allows a more secure transition from instrument navigation to visual navigation on approach. A 12-foot-wide at-grade road along the lighting system is proposed to properly repair, maintain, and test the system. The road would allow maintenance crews vehicular access to the light towers at low tide cycles. This minimal footprint road system would provide access for a ¾-ton utility vehicle. The vehicle is needed to carry replacement equipment, tools, and maintenance personnel. For example, the equipment needed to repair a light would consist of a replacement flasher unit weighing approximately 75 pounds, tools, and a ladder. The last light bar is close to one-half mile from the threshold. Due to the importance of the approach lighting system in establishing approach minima and 6/5/00 Page 1-6 Rev. 2

7 its role in safe visual acquisition of the runway environment during reduced visibility approaches, a maintenance road for the lighting system is considered an essential component of the development. 6/5/00 Page 1-7 Rev. 2

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved TABLE OF CONTENTS Description Page Number LIST OF ACRONYMS... a CHAPTER ONE INTRODUCTION General... 1-1 Study Objectives... 1-1 Public Involvement... 1-2 Issues to Be Resolved... 1-2 CHAPTER TWO EXISTING

More information

STUDY WORK GROUP MEETING No. 3. November 29, 2016

STUDY WORK GROUP MEETING No. 3. November 29, 2016 STUDY WORK GROUP MEETING No. 3 November 29, 2016 Agenda Welcome and introductions Update project schedule Brief overview of previous SWG meeting Update on aviation forecasts Introduction to airfield demand/capacity

More information

CHAPTER 3 ALTERNATIVES CONSIDERED

CHAPTER 3 ALTERNATIVES CONSIDERED CHAPTER 3 ALTERNATIVES CONSIDERED 3.0 ALTERNATIVES The 2010 Stevensville Airport Master Plan contained five (5) airside development options designed to meet projected demands. Each of the options from

More information

CHAPTER 1 EXECUTIVE SUMMARY

CHAPTER 1 EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY 1 1 EXECUTIVE SUMMARY INTRODUCTION William R. Fairchild International Airport (CLM) is located approximately three miles west of the city of Port Angeles, Washington. The airport

More information

Chapter 2 FINDINGS & CONCLUSIONS

Chapter 2 FINDINGS & CONCLUSIONS Chapter 2 FINDINGS & CONCLUSIONS 2.01 GENERAL Dutchess County acquired the airport facility in 1947 by deed from the War Assets Administration. Following the acquisition, several individuals who pursued

More information

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton.

Milton. PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton. Milton GeneralAviationAirport PeterPrinceAirportislocatedinSantaRosaCounty, approximatelythreemileseastofmilton. Existing Facilities Peter Prince Airport is served by one runway, Runway 18/36, 3,700 feet

More information

II. Purpose and Need. 2.1 Background

II. Purpose and Need. 2.1 Background II. 2.1 Background The Metropolitan Washington Airports Authority is preparing an Environmental Assessment of potential environmental impacts associated with proposed enhancements to the Runway 4-22 and

More information

CHAPTER FOUR AIRPORT ALTERNATIVES

CHAPTER FOUR AIRPORT ALTERNATIVES 4.0 INTRODUCTION CHAPTER FOUR The goal of the master planning process is to provide the City of New Smyrna Beach with an assessment of the adequacy and capabilities of the Airport as well as to identify

More information

B GEORGIA INFRASTRUCTURE REPORT CARD AVIATION RECOMMENDATIONS DEFINITION OF THE ISSUE. Plan and Fund for the Future:

B GEORGIA INFRASTRUCTURE REPORT CARD AVIATION RECOMMENDATIONS DEFINITION OF THE ISSUE. Plan and Fund for the Future: 2014 GEORGIA INFRASTRUCTURE REPORT CARD B + RECOMMENDATIONS Plan and Fund for the Future: While the system continues to enjoy excess capacity and increased accessibility it still needs continued focus

More information

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Agenda > Introductions > Public Meetings Overview > Working Paper 3 - Facility Requirements > Working Paper 4 - Environmental Baseline

More information

FORECASTING FUTURE ACTIVITY

FORECASTING FUTURE ACTIVITY EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver

More information

Chapter The All-new, World-class Denver International Airport Identify Describe Know Describe Describe

Chapter The All-new, World-class Denver International Airport Identify Describe Know Describe Describe Chapter 10 The aerospace subject is very large and diverse. As seen in previous chapters, there are many subject areas. So far you have learned about history, weather, space and aerodynamics. Now you will

More information

Chapter 8.0 Implementation Plan

Chapter 8.0 Implementation Plan Chapter 8.0 Implementation Plan 8.1 Introduction This chapter is the culmination of the analytical work accomplished in the previous chapters. The result is a prioritized list of the essential projects.

More information

Alternatives. Introduction. Range of Alternatives

Alternatives. Introduction. Range of Alternatives Alternatives Introduction Federal environmental regulations concerning the environmental review process require that all reasonable alternatives, which might accomplish the objectives of a proposed project,

More information

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development plans

More information

Appendix 6.1: Hazard Worksheet

Appendix 6.1: Hazard Worksheet Appendix 6.1: Appendix 6.1: Ref. Condition, real or potential; that can cause injury, illness, etc. This is a prerequisite for an Airfield Hazards 1. Taxiway Geometry Direct access to runway from ramp

More information

Tallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016

Tallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016 Tallahassee International Airport Master Plan Technical Advisory Committee Meeting #2 October 19, 2016 Agenda Welcome / Introductions Master Plan Process and Project Status Forecast of Aviation Demand

More information

CatExes vs. EAs When and How to Prepare

CatExes vs. EAs When and How to Prepare CatExes vs. EAs When and How to Prepare Panel: Steve Culberson, Ricondo & Associates Frank Smigelski, FAA Mary Vigilante, Synergy Tuesday December 10, 2013 Washington, DC 1 So you have a project Do I have

More information

Table of Contents. Overview Objectives Key Issues Process...1-3

Table of Contents. Overview Objectives Key Issues Process...1-3 Table of Contents Chapter One Introduction Overview...1-1 Objectives...1-1 Key Issues...1-2 Process...1-3 Chapter Two Inventory of Existing Conditions Airport Setting...2-1 Locale...2-1 Airport Surroundings...2-5

More information

The purpose of this Demand/Capacity. The airfield configuration for SPG. Methods for determining airport AIRPORT DEMAND CAPACITY. Runway Configuration

The purpose of this Demand/Capacity. The airfield configuration for SPG. Methods for determining airport AIRPORT DEMAND CAPACITY. Runway Configuration Chapter 4 Page 65 AIRPORT DEMAND CAPACITY The purpose of this Demand/Capacity Analysis is to examine the capability of the Albert Whitted Airport (SPG) to meet the needs of its users. In doing so, this

More information

October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION

October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION The Master Plan Process Inventory Of Existing Conditions Complete. Forecasts Of Aviation Demand Complete. Facility Requirements Complete.

More information

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include:

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include: 4.1 INTRODUCTION The previous chapters have described the existing facilities and provided planning guidelines as well as a forecast of demand for aviation activity at North Perry Airport. The demand/capacity

More information

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 10 Preferred Inaugural Airport Concept 10.0 Introduction The Preferred Inaugural Airport Concept for SSA was developed by adding the preferred support/ancillary facilities selected in Section 9

More information

Lake Tahoe Airport Master Plan

Lake Tahoe Airport Master Plan Lake Tahoe Airport Master Plan City Council Briefing October 20, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development

More information

Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES

Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES Chapter Four Airport Development Alternatives Prior to formulating a development program for Ryan Airfield, it is important to consider development potential

More information

DRAFT MASTER PLAN UPDATE

DRAFT MASTER PLAN UPDATE DRAFT MASTER PLAN UPDATE CHAPTER VI: AIRPORT LAYOUT PLAN NARRATIVE DRAFT REPORT APRIL 2017 PREPARED BY: Table of Contents WESTCHESTER COUNTY AIRPORT 6 AIRPORT LAYOUT PLAN NARRATIVE REPORT... 6-1 6.1 AGIS

More information

Addendum - Airport Development Alternatives (Chapter 6)

Addendum - Airport Development Alternatives (Chapter 6) Bowers Field Addendum - Airport Development Alternatives (Chapter 6) This addendum to the Airport Development Alternatives chapter includes the preferred airside development alternative and the preliminary

More information

Merritt Island Airport

Merritt Island Airport TABLE OF CONTENTS CHAPTER 1 INTRODUCTION... 1-1 INTRODUCTION AND PROJECT OVERVIEW... 1-1 General Guidelines... 1-1 Prior Planning Documentation... 1-2 Key Issues... 1-2 Goals and Objectives... 1-2 Regulatory

More information

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35 Runway 17-35 Airport Master Plan Runway 12-30 Brookings Regional Airport Table of Contents Table of Contents Chapter 1: Master Plan Goals... 1-1 1.1. Introduction... 1 1.2. Objective 1 Identify improvements

More information

1. Background and Proposed Action

1. Background and Proposed Action 1. Background and Proposed Action This chapter describes Hillsboro Airport and the planning background for the proposed project. The Port of Portland (the Port) is the sponsor for the Hillsboro Airport

More information

Punta Gorda Airport Master Plan Update

Punta Gorda Airport Master Plan Update Punta Gorda Airport Master Plan Update Draft Executive Summary Prepared for: The Charlotte County Airport Authority January 2018 Charlotte County Airport Authority James Herston, Chair Robert D. Hancik,

More information

CHAPTER 1 BACKGROUND AND PROPOSED ACTION

CHAPTER 1 BACKGROUND AND PROPOSED ACTION CHAPTER 1 BACKGROUND AND PROPOSED ACTION 1.0 INTRODUCTION An Environmental Assessment (EA) evaluates the effects of a proposed Federal action on the surrounding environment and is prepared in compliance

More information

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal Airport Master Plan Rapid City Regional Airport October 2015 FAA Submittal Rapid City Regional Airport Master Plan Update Table of Contents Executive Summary... i Scope & Timeline... i Forecasts... i Preferred

More information

CHAPTER 5: Landside Facility Requirements and Development Concepts

CHAPTER 5: Landside Facility Requirements and Development Concepts CHAPTER 5: Landside Facility Requirements and Development Concepts Overview Implementation of the preferred intermediate-term (10-year) and long-term (20-year) airside alternatives will have a significant

More information

Technical Memorandum. Synopsis. Steve Carrillo, PE. Bryan Oscarson/Carmen Au Lindgren, PE. April 3, 2018 (Revised)

Technical Memorandum. Synopsis. Steve Carrillo, PE. Bryan Oscarson/Carmen Au Lindgren, PE. April 3, 2018 (Revised) Appendix D Orange County/John Wayne Airport (JWA) General Aviation Improvement Program (GAIP) Based Aircraft Parking Capacity Analysis and General Aviation Constrained Forecasts Technical Memorandum To:

More information

JUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM JANUARY 25, 2017

JUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM JANUARY 25, 2017 JUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM JANUARY 25, 2017 1 Agenda Program Description Runway Incursions Design and Geometry Deficiencies Runway 8/26 Operations Potential Mitigation Next Steps

More information

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL This chapter delineates the recommended 2005 2024 Sussex County Airport Capital Improvement Program (CIP). It further identifies probable construction

More information

Appendix C AIRPORT LAYOUT PLANS

Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Airport Master Plan Santa Barbara Airport As part of this Airport Master Plan, the Federal Aviation Administration (FAA) requires the development

More information

Source: Chippewa Valley Regional Airport ASOS, Period of Record

Source: Chippewa Valley Regional Airport ASOS, Period of Record Chapter 1 Inventory Runway wind coverage is the percentage of time a runway can be used without exceeding allowable crosswind velocities. Allowable crosswind velocities vary depending on aircraft size

More information

Consideration will be given to other methods of compliance which may be presented to the Authority.

Consideration will be given to other methods of compliance which may be presented to the Authority. Advisory Circular AC 139-10 Revision 1 Control of Obstacles 27 April 2007 General Civil Aviation Authority advisory circulars (AC) contain information about standards, practices and procedures that the

More information

FACILITY REQUIREMENTS SUMMARY OF KEY ISSUES OVERVIEW

FACILITY REQUIREMENTS SUMMARY OF KEY ISSUES OVERVIEW FACILITY REQUIREMENTS SUMMARY OF KEY ISSUES OVERVIEW This summary is intended to provide a brief overview of the key issues associated with conformance to FAA standards at Methow Valley State Airport.

More information

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis Appendix B ULTIMATE AIRPORT CAPACITY & DELAY SIMULATION MODELING ANALYSIS B TABLE OF CONTENTS EXHIBITS TABLES B.1 Introduction... 1 B.2 Simulation Modeling Assumption and Methodology... 4 B.2.1 Runway

More information

BUSINESS OF THE CITY COUNCIL CITY OF MERCER ISLAND, WA

BUSINESS OF THE CITY COUNCIL CITY OF MERCER ISLAND, WA BUSINESS OF THE CITY COUNCIL CITY OF MERCER ISLAND, WA AB 4564 September 7, 2010 Regular Business RENTON AIRPORT STATUS UPDATE Proposed Council Action: Receive update. No action required. DEPARTMENT OF

More information

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014 DRAFT FINAL REPORT AIRPORT MASTER PLAN Rifle Garfield County Airport Revised May 15, 2014 As required by Paragraph 425.B(4) of FAA Order 5100.38C, Airport Improvement Program (AIP) Handbook: The preparation

More information

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013 New York State Department of Transportation Safety, Infrastructure, and Tenant Improvement Project Public Hearing Informational Brochure February 26, 2013 This DEIS/Draft EA evaluates the potential impacts

More information

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN LAST UPDATE JULY 2013 Acknowledgements The preparation of this document was financed in part by a grant from the Federal Aviation Administration (Project No: 3-27-0000-07-10), with the financial support

More information

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017 Lopez Island Airport Master Plan Update Public Meeting June 15, 2017 Master Plan Update Team Reid Middleton/Everett, WA Shannon Kinsella, Project Manager Melania Haagsma, Project Engineer Mead & Hunt/Tulsa,

More information

CHAPTER 5 - FACILITY REQUIREMENTS

CHAPTER 5 - FACILITY REQUIREMENTS CHAPTER 5 - FACILITY REQUIREMENTS This chapter identifies the requirements for airfield and landside facilities to accommodate the forecast demand level. Facility requirements have been developed for the

More information

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906 Master Plan The preparation of this document was financed in part through a planning grant from the Federal Aviation Administration (FAA) as provided under Section 505 of the Airport and Airway Improvement

More information

Table of Contents. Master Plan March 2014 TOC i Spokane International Airport

Table of Contents. Master Plan March 2014 TOC i Spokane International Airport Table of Contents Page Chapter 1 Inventory 1. Introduction... 1 1 1.1 Community Profile... 1 2 1.1.1 Location and Setting... 1 1 1.1.2 Climate... 1 2 1.1.3 Socioeconomic Conditions... 1 5 1.1.4 Area Land

More information

1.1.3 Taxiways. Figure 1-15: Taxiway Data. DRAFT Inventory TYPICAL PAVEMENT CROSS-SECTION LIGHTING TYPE LENGTH (FEET) WIDTH (FEET) LIGHTING CONDITION

1.1.3 Taxiways. Figure 1-15: Taxiway Data. DRAFT Inventory TYPICAL PAVEMENT CROSS-SECTION LIGHTING TYPE LENGTH (FEET) WIDTH (FEET) LIGHTING CONDITION 1.1.3 Taxiways EWN has an extensive network of taxiways and taxilanes connecting the terminal, air cargo, and general aviation areas with the runways as listed in Figure 1-15. A 50-foot wide parallel taxiway

More information

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport Executive Summary MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport As a general aviation and commercial service airport, Fort Collins- Loveland Municipal Airport serves as an important niche

More information

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3 Airport Master Plan for Brown Field Municipal Airport PAC Meeting #3 Public Meeting #1 > 8/24/17 from 5:30 to 8:00 pm > 41 attendees signed-in > Comments: > EAA area > Environmental constraints > Focus

More information

Agenda: SASP SAC Meeting 3

Agenda: SASP SAC Meeting 3 Agenda: SASP SAC Meeting 3 Date: 04/12/18 Public Involvement Plan Update Defining the System Recommended Classifications Discussion Break Review current system Outreach what we heard Proposed changes Classification

More information

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project GENERAL AIRPORT INFORMATION AIRPORT USERS Airport ownership: Public, owned by the Pullman-Moscow Regional Airport Board Year opened: February

More information

Chapter 4.0 Alternatives Analysis

Chapter 4.0 Alternatives Analysis Chapter 4.0 Alternatives Analysis Chapter 1 accumulated the baseline of existing airport data, Chapter 2 presented the outlook for the future in terms of operational activity, Chapter 3 defined the facilities

More information

Yolo County Airport. ALP Narrative Report. April Prepared by Mead & Hunt, Inc. for the County of Yolo, California

Yolo County Airport. ALP Narrative Report. April Prepared by Mead & Hunt, Inc. for the County of Yolo, California Yolo County Airport ALP Narrative Report April 2016 Prepared by Mead & Hunt, Inc. for the County of Yolo, California Yolo County Airport ALP Narrative Report Prepared for the County of Yolo Mindi Nunes,

More information

Meeting Notes Public Open House

Meeting Notes Public Open House Meeting Notes Public Open House, 5:30-8:00 pm Fairbanks Pipeline Training Center, 3605 Cartwright Court, Fairbanks, Alaska= Agenda: Open House: 30 minutes Presentation: 45 minutes Question and Answers:

More information

Chapter Three AIRPORT FACILITY REQUIREMENTS/ALTERNATIVES

Chapter Three AIRPORT FACILITY REQUIREMENTS/ALTERNATIVES Chapter Three AIRPORT FACILITY REQUIREMENTS/ALTERNATIVES Airport Layout Plan Report In this chapter, existing components of the Airport are evaluated so that the capacities of the overall system are identified.

More information

Norfolk International Airport

Norfolk International Airport Norfolk International Airport Master Plan Update Technical Advisory Committee Meeting #1 Community Advisory Committee Meeting #1 January 24, 2018 Agenda Project Background Introductions Overview of Airport

More information

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016

Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016 Kittitas County Airport Bowers Field Airport Master Plan Planning Advisory Committee Meeting #1 April 6, 2016 Project Team Kittitas County, WA Airport Owner (Sponsor) and Operator, Land Use Century West

More information

6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP)

6.0 Capital Improvement Program. 6.1 Capital Improvement Plan (CIP) 6.0 The addresses the phased scheduling of projects identified in this Master Plan and their financial implications on the resources of the Airport and the City of Prescott. The phased Capital Improvement

More information

Master Plan Update Community Advisory Committee Kick-off Meeting

Master Plan Update Community Advisory Committee Kick-off Meeting Nashville International Airport Master Plan Update Community Advisory Committee Kick-off Meeting September 13, 2018 Agenda Welcome and Introductions Master Plan Objectives Master Plan Process BNA Vision

More information

Chapter 4 Airport Facility Requirements

Chapter 4 Airport Facility Requirements Chapter 4 Airport Facility Requirements Introduction CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-1 Organization of Materials CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-2 RPZ - ROAD RPZ - NON-AIRPORT

More information

RULES OF TENNESSEE DEPARTMENT OF TRANSPORTATION AERONAUTICS DIVISION CHAPTER LICENSING AND REGISTRATION OF AIRPORTS TABLE OF CONTENTS

RULES OF TENNESSEE DEPARTMENT OF TRANSPORTATION AERONAUTICS DIVISION CHAPTER LICENSING AND REGISTRATION OF AIRPORTS TABLE OF CONTENTS RULES OF TENNESSEE DEPARTMENT OF TRANSPORTATION AERONAUTICS DIVISION CHAPTER 1680-1-2 LICENSING AND REGISTRATION OF AIRPORTS TABLE OF CONTENTS 1680-1-2-.01 Purpose 1680-1-2-.06 Repealed 1680-1-2-.02 Definitions

More information

3.9 AIRPORT SUPPORT FACILITIES

3.9 AIRPORT SUPPORT FACILITIES 3.9 AIRPORT SUPPORT FACILITIES This section details additional airfield facilities that may be required over the next 20 years. 3.9.1 Airport Rescue and Fire Fighting (ARFF) Station GEG is certified under

More information

CATCODE ] CATCODE

CATCODE ] CATCODE Runways. FAC: 1111 CATCODE: 111111 OPR: AFCEC/COS OCR: AF/A3O-A 1.1. Description. The runway is the paved surface provided for normal aircraft landings and take offs. Runways are classified as either Class

More information

3 INTRODUCTION. Chapter Three Facility Requirements. Facility Requirements PEAKING CHARACTERISTICS

3 INTRODUCTION. Chapter Three Facility Requirements. Facility Requirements PEAKING CHARACTERISTICS Chapter Three Facility Requirements 3 INTRODUCTION This chapter identifies the long-range airfield and terminal area facilities needed to satisfy the 20-year forecast of aviation demand at Monett Municipal

More information

Grants Pass Airport Master Plan & Airport Layout Plan Update

Grants Pass Airport Master Plan & Airport Layout Plan Update Attendees: Grants Pass Airport Master Plan & Airport Layout Plan Update Meeting #3 January 26, 2010 Merlin Community Center 100 Acorn Street, Merlin 5:45 7:15 p.m. Josephine County Department of Airports:

More information

Chapter 9 - AIRPORT SYSTEM DESIGN

Chapter 9 - AIRPORT SYSTEM DESIGN Chapter 9 - AIRPORT SYSTEM DESIGN 9.01 GENERAL This chapter discusses the development program for Dutchess County Airport to the year 2020. This airport system design is based upon the airport's existing

More information

Appendix A - Definitions

Appendix A - Definitions Appendix A - Definitions Aeronautical Activity Any activity conducted at airports which involves, makes possible, or is required for the operation of aircraft, or which contributes to or is required for

More information

Current and Forecast Demand

Current and Forecast Demand Existing Facilities Jacksonville International Airport (JIA) is served by a number of airside and landside facilities. There are two runways that serve the airport in an open V configuration. The Annual

More information

Chapter Six ALP Drawings. Tacoma Narrows Airport. Master Plan Update

Chapter Six ALP Drawings. Tacoma Narrows Airport. Master Plan Update Chapter Six ALP Drawings Master Plan Update The master planning process for the (Airport) has evolved through efforts in the previous chapters to analyze future aviation demand, establish airside and landside

More information

CHAPTER 3 FACILITY REQUIREMENTS

CHAPTER 3 FACILITY REQUIREMENTS CHAPTER 3 FACILITY REQUIREMENTS 3.1 INTRODUCTION To properly plan for the future requirements of Newport News/Williamsburg International Airport, it is necessary to translate the forecasts of aviation

More information

Hartford-Brainard Airport Potential Runway Closure White Paper

Hartford-Brainard Airport Potential Runway Closure White Paper Hartford-Brainard Airport Potential Runway 11-29 Closure White Paper June 2012 In recent years there has been discussion regarding the necessity of Runway 11-29 to the Hartford- Brainard Airport (HFD)

More information

General Aviation Master Plan Update

General Aviation Master Plan Update Peter O. Knight Airport Public Meeting #2 Peter O. Knight Airport Agenda Welcome and Introductions HCAA System of Airports Purpose of Public Meetings Master Plan Status Update Next Steps Q & A 2 Our System

More information

B.C. MINISTRY OF TRANSPORTATION. SA17 Local Area Specification #2 SMALL AIRPORT WINTER MAINTENANCE

B.C. MINISTRY OF TRANSPORTATION. SA17 Local Area Specification #2 SMALL AIRPORT WINTER MAINTENANCE 1. OBJECTIVE B.C. MINISTRY OF TRANSPORTATION SA17 SMALL AIRPORT WINTER MAINTENANCE To ensure the Anahim Lake airport is kept open and safe for small airport users. 2. GENERAL PERFORMANCE SPECIFICATIONS

More information

2018 Airport Master Plan Overview of Development Concepts. Greg Ballentine (WSP)

2018 Airport Master Plan Overview of Development Concepts. Greg Ballentine (WSP) 2018 Airport Master Plan Overview of Development Concepts Greg Ballentine (WSP) Thank You Stakeholder and community consultation has included discussions with over 40 stakeholder groups including airport

More information

Regular Board Meeting August 4, 2015

Regular Board Meeting August 4, 2015 Regular Board Meeting August 4, 2015 1616 Airport Circle Hailey, ID 83333 208.788.4956 PUBLIC COMMENT FY 16 Rates & Charges FY 16 Budget Approval Rates & Charges will provide the Board the ability to operate

More information

Exhibit A. Excerpt from the New Jersey Forest Fire Service s Andover- Aeroflex Airport Facility Operations Manual January 2009

Exhibit A. Excerpt from the New Jersey Forest Fire Service s Andover- Aeroflex Airport Facility Operations Manual January 2009 Exhibit A Excerpt from the New Jersey Forest Fire Service s Andover- Aeroflex Airport Facility Operations Manual January 2009 Minimum Standards for Aeronautical Activities AEROFLEX ANDOVER AIRPORT FACILITY

More information

Technical Advisory Committee Meeting February 29, 2016

Technical Advisory Committee Meeting February 29, 2016 Technical Advisory Committee Meeting February 29, 2016 Meeting Agenda Introduction Recap of Planning Process Project Status Goals and Objectives Forecasts of Aviation Demand Overview of Facility Requirements

More information

Burke Lakefront Airport (BKL) Master Plan Update

Burke Lakefront Airport (BKL) Master Plan Update Burke Lakefront Airport () Master Plan Update Public Workshop August 2, 2007 City of Cleveland Department of Port Control (DPC) City of Cleveland DPC Studies Currently In Progress Market Assessment & Feasibility

More information

Preferred Alternative Summary

Preferred Alternative Summary Tacoma Narrows Airport Master Plan Update Preferred Alternative Summary The Preferred Alternative represents Pierce County s vision for the long-term development of the Tacoma Narrows Airport. This Alternative

More information

Bremerton National Airport Airport Master Plan Project Update February 12, 2013

Bremerton National Airport Airport Master Plan Project Update February 12, 2013 Bremerton National Airport Airport Master Plan Project Update February 12, 2013 Project Team Century West Engineering Northwest firm founded in 1969 500+ airport projects completed throughout the Pacific

More information

Chapter 5. Facility Requirements

Chapter 5. Facility Requirements Chapter 5 Facility Requirements Chapter 5 Facility Requirements INTRODUCTION The Baseline Forecast was used to determine facility requirements. Chapter 4 produced a forecast of traffic volumes expected

More information

Airport Master Plan Open House Front Range Airport February 23, 2017

Airport Master Plan Open House Front Range Airport February 23, 2017 Airport Master Plan Open House Front Range Airport February 23, 2017 MASTER PLAN PROCESS AND OVERVIEW MASTER PLAN ELEMENTS The Master Plan is a 20-year plan to understand the needs of current and future

More information

Apron. FAC: 1131 CATCODE: OPR: AFCEC/COS OCR: AF/A3O-A 1.1. Description. Aprons are paved areas provided for aircraft parking, servicing, and

Apron. FAC: 1131 CATCODE: OPR: AFCEC/COS OCR: AF/A3O-A 1.1. Description. Aprons are paved areas provided for aircraft parking, servicing, and Apron. FAC: 1131 CATCODE: 113321 OPR: AFCEC/COS OCR: AF/A3O-A 1.1. Description. Aprons are paved areas provided for aircraft parking, servicing, and loading. Apron space is necessary for operational aircraft;

More information

Chapter III - Demand/Capacity and Facility Requirements

Chapter III - Demand/Capacity and Facility Requirements Chapter III - Demand/Capacity and Facility Requirements The facility requirements identified in this chapter are summarized on Exhibit III.1. The future requirements serve to determine which airport facilities

More information

4.0 Context for the Crossing Project

4.0 Context for the Crossing Project 4.0 Context for the Crossing Project This section provides background information about key features of the North Douglas Crossing project area, and opportunities and constraints. This information is important

More information

National Transportation Safety Board Washington, D.C

National Transportation Safety Board Washington, D.C E PLURIBUS UNUM NATIONAL TRA SAFE T Y N S PORTATION B OAR D National Transportation Safety Board Washington, D.C. 20594 Safety Recommendation Date: June 25, 2004 In reply refer to: A-04-48 through -50

More information

Runway Length Analysis Prescott Municipal Airport

Runway Length Analysis Prescott Municipal Airport APPENDIX 2 Runway Length Analysis Prescott Municipal Airport May 11, 2009 Version 2 (draft) Table of Contents Introduction... 1-1 Section 1 Purpose & Need... 1-2 Section 2 Design Standards...1-3 Section

More information

Chapter 4.0 Facility Requirements

Chapter 4.0 Facility Requirements Chapter 4.0 Facility Requirements Having inventoried the existing infrastructure and forecasted demand, determining airport facility requirements is the next essential step in the airport master planning

More information

AIRPORT MASTER PLAN UPDATE

AIRPORT MASTER PLAN UPDATE AIRPORT MASTER PLAN UPDATE PENSACOLA INTERNATIONAL AIRPORT Technical Advisory Committee Meeting #2 June 20, 2017 Agenda» Introduction» Facility Requirements Airside Terminal Landside General Aviation Cargo

More information

Andres Lainoja Eesti Lennuakadeemia

Andres Lainoja Eesti Lennuakadeemia Andres Lainoja Eesti Lennuakadeemia In the beginning was the Word... Convention on International Civil Aviation (Doc 7300) was signed on 7 December 1944 International Civil Aviation Organization began

More information

Alternatives Analysis EXECUTIVE SUMMARY

Alternatives Analysis EXECUTIVE SUMMARY Alternatives Analysis EXECUTIVE SUMMARY Alternative development plans were created as part of the Master Plan for Harrisburg International Airport. The aim is to provide sufficient capacity for projected

More information

City of Redding Airports

City of Redding Airports City of Redding Airports Benton Airpark Redding Municipal Airport DEVELOPMENT AND USE GUIDELINES FOR GENERAL AVIATION HANGARS April 7, 2009 PREFACE The City of Redding, as owner of federally obligated

More information

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER PETE FLAHERTY COMMISSIONER TOM FOERSTER CHAIRMAN DEPARTMENT OF AVIATION BARBARA HAFER COMMISSIONER STEPHEN A. GEORGE DIRECTOR ROOM M 134, TERMINAL BUILDING GREATER PITTSBURGH INTERNATIONAL AIRPORT PITTSBURGH,

More information

Table of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update

Table of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update Table of Contents 7.1. Airport Layout Plan (Existing Conditions)... 2 7.2. Airport Layout Plan (Future Conditions)... 3 7.3. Technical Data Sheet... 5 7.4. Commercial Terminal Area Drawing... 5 7.5. East

More information

Chapter One INVENTORY

Chapter One INVENTORY Chapter One INVENTORY Airport Layout Plan Report The initial step in the preparation of the Airport Layout Plan Report for is the collection of information pertaining to the Airport and the area it serves.

More information