1 Re: Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport Los Angeles World Airports (LAWA) intends to submit a Passenger Facility Charge (PFC) application at Los Angeles International Airport (Airport or LAX) to the Federal Aviation Administration (FAA). LAWA is posting this public notice as part of the PFC Application process under 14 CFR LAWA will be accepting public comments on the proposed new PFC Application through May 15, As part of this process, the following information is being provided: (1) project descriptions and brief project justifications, (2) PFC collection level, estimated PFC revenue, proposed charge effective date, and estimated PFC expiration date, and (3) LAWA point of contact. PROJECT DESCRIPTIONS AND JUSTIFICATIONS A. Terminal 6 Improvement Project Project Amount: $290,415,721 PFC PAYGO: $0 PFC Bond Capital: $129,790,000 PFC Bond Financing & Interest $80,341,523 Federal Grants (TSA): $18,502,216 Local Funds: $61,781,982 PFC Collection Level: $4.50 Start Date: April 2011 End Date: December 2013 Description. On April 4, 2010, the Board of Airport Commissioners of the City of Los Angeles (Board) approved a Settlement Agreement with Alaska that settled all outstanding litigation. One condition of the Settlement Agreement was execution of a new lease for space in Terminal 6 that required Alaska to make certain renovations to Terminal 6. On April 4, 2011, the Board approved the Terminal Facilities Lease and License Agreement with Alaska for space in Terminal 6 at the Airport (Lease), which was executed on June 24, The Lease required Alaska to make renovations in Terminal 6 and LAX to acquire such completed improvements, including but not limited to: Design and implement a new in-line checked baggage inspection system (CBIS) and baggage sorting system for use by all Terminal 6 airlines (Terminal 6 is used
2 Page 2 of 6 by Alaska, Delta, United, Allegiant Air (split operations between Terminals 5 and 6), Frontier, and Copa for domestic and international operations). Upgrade holdrooms and provide Federal Inspection Station (FIS) capability to at least two additional gates that currently only have domestic capabilities. Install Common Use Systems to allow any airline to use Alaska s gates for processing passengers. Expand the Terminal 6 west ticket counter lobby. Enlarge the passenger security screening checkpoint. Refurbish the arrival/baggage claim area. Create consolidated operations space Build a new premium passenger lounge and other improvements branded and unique to Alaska s operational needs (fully funded by Alaska). In summary, the Terminal 6 Improvement Project consists of improvements made as part of the modernization of Terminal 6, including a new in-line baggage screening system, renovated ticketing/check-in lobby with kiosks for check-in and bag-check, new boarding areas, a new passenger lounge, new gate information displays, and renovated FIS facilities to accommodate international passengers. Project Need/Justification. Much of Terminal 6 has not seen re-investment for over 50 years, and the last time any significant work was done to Terminal 6 was 30 years ago. Major renovations to the infrastructure and improvements/upgrades to the interior are long overdue, which was the result of a number of factors including, but not limited to, past 40-year leases with airlines that became barriers to LAWA s planned improvements. B. Elevators/Escalators/Moving Walkways Replacement Program Project Amount: $178,750,601 PFC PAYGO: $110,000,000 PFC Bond Capital: $0 PFC Bond Financing & Interest: $0 Federal Grants: $0 Local Funds: $68,750,601 PFC Collection Level: $3.00 Start Date: April 2009 End Date: October 2016 Description. The Elevators/Escalators/Moving Walkways Replacement Program includes the replacement and modernization of approximately 200 elevators, escalators, and moving walkways in the terminals. These units to be replaced were installed at different times ranging from the 1950 s through the early 1980 s. The replacement of units is based on units with the greatest maintenance demands and
3 Page 3 of 6 highest failure risk being done first. Following this schedule there are a planned four (4) construction phases to complete all units in During replacement all airline service areas are to remain operational. The replacement units are all heavy duty, Transit-Rated type units designed to provide higher levels of service and safety in the high traffic airport environment. The new Transit-Rated units have a 40 year life cycle, while operating with lower maintenance and power requirements. Advanced features, such as motion sensors that enable units to reduce speed and power when no traffic is present are included as part of the Transit-Rated design as well. LAX is one of the first airports in the United States and the first facility in California to use sleep mode on the new escalators. If the escalator is not used for a set period of time, this feature will automatically reduce escalator speed to 20 percent of normal speed. The benefits are significant savings in power usage and maintenance and repairs. In addition, all elevators have improved safety features such as 3D infrared light curtains that operate during door movements. The detectors emit green light as doors open and flash and turn red as doors close. The Elevators/Escalators Program will replace and upgrade many of the units that have exceeded their 25 year operational life span which should increase passenger safety and convenience. Project Need/Justification. Last year LAX had a total of 67 million passengers compared to 56 million approximately six years ago during the recession. Therefore, it is imperative that passengers can move quickly and safely through the terminals which will occur with the newer and faster elevators plus there will be a major reduction in units that are placed out of service due to the more frequent repairs with the older elevator/escalator/moving walkway equipment. The completion of this program will expedite the movement of passengers and their baggage within the Airport s Central Terminal Area (CTA). C. Central Utility Plant (CUP) Replacement Project Project Amount: $426,495,242 PFC PAYGO: $190,000,000 PFC Bond Capital: $0 PFC Bond Financing & Interest: $0 Federal Grants: $0 Local Funds: $236,495,242 PFC Collection Level: $3.00 Start Date: March 2009 End Date: March 2015 Description. This project provides for the replacement of the existing CUP at the Airport, which currently provides heating and cooling to the Airport s Central Terminal Area (CTA). When completed, the $426 million, four-story, 64,000 square foot facility will enhance passenger comfort, reliability of utility service and safety by providing additional capacity for air conditioning and heating of the airline terminals, Administration East Building and the Theme Building.
4 Page 4 of 6 The existing CUP also has a cogeneration function that generates electricity that provides power to the CUP, with excess power sold to the Los Angeles Department of Water and Power. The CUP Replacement Project includes the following components: Replacement of the existing CUP and maintenance shop building, including replacement of the boilers and electrical cogeneration equipment. Replacement of the existing cooling tower system. Construction of an underground thermal energy storage tank the site of the existing CUP. Electrical upgrades to include a new electrical substation and a retro-fit of the existing substation. Replacement of the direct buried chilled and hot water service lines in the CTA. Demolition of the existing CUP and associated ancillary facilities. Project Need/Justification. The existing CUP was constructed in 1961 and, although considered technologically advanced at the time it was installed, is now considered to be obsolete. More specifically, it no longer meets energy and safety codes. As the equipment ages, the associated costs to repair and maintain the existing CUP, control air pollution emissions, and comply with environmental rules and regulations increase. Furthermore, the facility is facing capacity shortfalls, and replacement of the existing CUP is needed to accommodate both existing and anticipated demand for heating and cooling within the CTA. The new CUP is necessary to maintain system efficiency and accommodate recently expanded building capacity at LAX. D. Midfield Satellite Concourse North Project (EIR and Advanced Planning) Project Amount: $5,960,000 PFC PAYGO: $5,960,000 PFC Bond Capital: $0 PFC Bonding Financing & Interest: $0 Federal Grants: $0 Local Funds: $0 PFC Collection Level: $4.50 Start Date: June 2012 End Date: April 2014 Description. LAWA has commenced a multi-billion dollar modernization program at the Airport designed to provide improved, state-of-the-art facilities for travelers. The Midfield Satellite Concourse (MSC) Program is part of these improvements.
5 Page 5 of 6 The MSC Program includes a new passenger concourse facility, as shown on the approved ACIP. The MSC facility will be located in the central area of the airfield, west of Tom Bradley International Terminal. The MSC Program also includes a Central Terminal Processor, conveyance systems for passengers and baggage, and new taxiways/taxilanes and airport aprons. The MSC Program will (1) permit greater flexibility in scheduling improvements at other facilities without disrupting day-to-day airline operations, (2) reduce reliance on remote gates, and (3) ensure a high level of service for Airport passengers during modernization upgrades, which may at times require the temporary closure of existing gates. Due to the size and scale of the MSC Program, LAWA proposes to develop the MSC Program in demand-driven phases. Phase 1 (MSC North Project) of the MSC Program is the construction of the northern portion of the multi-story MSC facility and associated improvements. The MSC North Project is intended to improve the terminal operations, concessions facilities, and overall passenger experience at the Airport. The facility will be designed to serve both domestic and international traffic. For this PFC application, the project being funded with PFC revenue on a PAYGO basis will include the development of a project level Environmental Impact Report (EIR) to comply with California law for the MSC North Project, as well as program definition work for this facility. Program definition for the MSC North Project will refine key areas that are important to the efficient operation of the facility and passenger experience. Examples of key areas include detailed analysis of the positioning of passenger loading bridges to optimize flexibility of aircraft parking positions; identifying alternative interfaces to landside connectors and circulation systems (particularly the separation of sterile international arrivals from secure domestic passengers); busport and passenger loading areas; baggage systems and rooms; back of house service corridors; and baggage rooms. Project Need/Justification. Modernization is a continuing process at the Airport as the needs of the travelers and airlines change and as improved safety measures are implemented. The MSC North Project will provide LAWA with the flexibility to accommodate demand for aircraft gates at LAX. PFC LEVEL, PROPOSED CHARGE EFFECTIVE DATE, ESTIMATED CHARGE EXPIRATION DATE, AND ESTIMATED TOTAL PFC REVENUE PFC collection level: $4.50 per eligible enplaned passenger. Estimated charge effective date for the PFC Application: December 1, 2019 (which reflects the estimated charge expiration date for PFC Application No C-00-LAX that is currently being reviewed by the FAA). Estimated charge expiration date for the PFC Application: Based on five years of PFC Quarterly Reports, the Airport collected approximately $650,400,000 in PFC revenues at a $4.50 collection level for the 60 months ending December 31, 2013 (including interest earned), or approximately $10,840,000 per month. As a result, it is expected that the additional $516,091,523 in PFC revenue (see below) would be collected within approximately 48 months (or until collected PFC revenue plus interest
6 Page 6 of 6 thereon equals the allowable costs of the approved projects, as permitted by regulation). Therefore, the charge expiration date for this PFC Application No C-00-LAX is estimated to be December 1, Estimated total PFC revenue to be collected under this PFC Application: $516,091,523. LAWA POINT OF CONTACT Any comments regarding this public notice should be sent to Doug Schmidt of LAWA at the following address: Los Angeles World Airports Los Angeles International Airport 1 World Way Los Angeles, CA If there are any questions regarding this proposed new PFC Application, Mr. Schmidt can also be reached at (424) or at dschmidt@lawa.org.
14 C.F.R. Part 158. Passenger Facility Charge Program Logan International Airport. Public Notice
14 C.F.R. Part 158 Passenger Facility Charge Program Logan International Airport Public Notice Summary of Proposed 2018 PFC Application PFC Project Descriptions and Justifications PFC Financial Plan Class
More informationNOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019
NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019 The City of Atlanta is providing an opportunity for public comment until April 25, 2019 related to the
More informationCOUNTY OF ORANGE, CALIFORNIA AIRPORT REVENUE BONDS, SERIES 2009 A & B ANNUAL REPORT FOR FISCAL YEAR ENDED JUNE 30, 2013
COUNTY OF ORANGE, CALIFORNIA AIRPORT REVENUE BONDS, SERIES 2009 A & B ANNUAL REPORT FOR FISCAL YEAR ENDED JUNE 30, 2013 Dated: January 28, 2014 COUNTY OF ORANGE, CALIFORNIA AIRPORT REVENUE BONDS, SERIES
More informationTRACK: B TERMINAL/LANDSIDE
Salt Palace Convention Center TRACK: B TERMINAL/LANDSIDE WORKSHOP: 3 Title: Airlines and Airports Consolidation and Changing Faces Who is building the Terminals, Technology, and Flexibility? Moderator:
More informationGSP TERMINAL IMPROVEMENT PROGRAM PRESS KIT
About GSP MISSION STATEMENT At Greenville-Spartanburg International Airport (GSP), we begin each day fully committed to finding new ways to achieve our mission to provide the citizens of Upstate South
More informationBOARD ITO Aide REPORT TO THE AIRPORT COMMISSIONERS
1 [1 11 BOARD ITO Aide 001:4 Los Angeles World Airports REPORT TO THE Approved by: Justin rbacci - hief Innovation and Commercial St tegy Officer (--(AtSotA_ /1//r/'(10 PV Reviewed by: Samson Mengistu
More informationTampa International Airport Master Plan Update. December 12, 2012
Tampa International Airport Master Plan Update December 12, 2012 1 Prior Presentation Consolidated rental car and people mover Decongest curbsides and roadways Enable rental car growth Gain long term parking
More informationPUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017
PUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017 Agenda Overview of PFC Program at Spokane Airport (GEG) Proposed New PFC 11 Application Project
More informationLos Angeles International Airport (LAX) Airside $907M
Los Angeles International Airport (LAX) $3,948M Airside $907M Airfield Electrical Systems Rehabilitation Bradley West Core Renovation, East Ramp and Concourse Demolition Imperial Terminal Aircraft Parking
More informationSAN JOSÉ INTERNATIONAL AIRPORT
SAN JOSÉ INTERNATIONAL AIRPORT NEAR-TERM TERMINAL CAPACITY ANALYSIS AIRPORT COMMISSION AUGUST 14, 2017 August 14, 2017 AGENDA 1. Forecast Review (with 14 MAP High Case) 2. Gate Requirements and Aircraft
More informationNOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018
NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018 LAWTON-FORT SILL REGIONAL AIRPORT LAWTON, OKLAHOMA PASSENGER FACILITY CHARGE PROPOSED
More informationGREATER ORLANDO AVIATION AUTHORITY
GREATER ORLANDO AVIATION AUTHORITY Amendment to PFC Applications #7, 8, and 16 and New PFC Application #18 PUBLIC NOTICE June 7, 2016 1 P age Table of Contents PUBLIC NOTICE... 3 PROPOSED ACTIONS... 3
More informationNotice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport
Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport Pursuant to 14 CFR Part 158.24(a) (1) (III), the Broward County
More informationCity of Tallahassee, FL Department of Aviation
City of Tallahassee, FL Department of Aviation Proposed Application to Federal Aviation Administration For Authority to Impose a Passenger Facility Charge (PFC) at Tallahassee International Airport and
More informationLAX Specific Plan Amendment Study (SPAS) Update. December 3, 2012
LAX Specific Plan Amendment Study (SPAS) Update December 3, 2012 Response to the Draft Environmental Impact Report Draft EIR Release and Public Comment Official Comment Period was July 27, 2012 through
More informationPITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM
PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM FREQUENTLY ASKED QUESTIONS September 2017 Master Plan Update: 1. What is a Master Plan Update? The objective of a Master Plan Update (MPU)
More informationNew PFC Application #13
PUBLIC CONSULTATION New PFC Application #13 Buffalo, NY December 16, 2015 Agenda PFC Program at Notice to Carriers and Consultation Meeting Class of Carrier Not Required to Collect PFC Air Carrier Requirements
More informationDEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER
PETE FLAHERTY COMMISSIONER TOM FOERSTER CHAIRMAN DEPARTMENT OF AVIATION BARBARA HAFER COMMISSIONER STEPHEN A. GEORGE DIRECTOR ROOM M 134, TERMINAL BUILDING GREATER PITTSBURGH INTERNATIONAL AIRPORT PITTSBURGH,
More informationPUBLIC NOTICE OF PASSENGER FACILITY CHARGE FOR DENVER INTERNATIONAL AIRPORT
PUBLIC NOTICE OF PASSENGER FACILITY CHARGE FOR DENVER INTERNATIONAL AIRPORT Pursuant to CFR 158.24, the City and County of Denver Department of Aviation ( City ), owner and operator of the Denver International
More informationAppendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis
Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis ITB MAIN TERMINAL DEPARTURES LEVEL & BOARDING AREAS A & G ALTERNATIVES ANALYSIS
More information? 0-? WA", ilp. Y ON 1Z Cond 1 0 AIRPORT COMMISSIONERS BOARD REPORT TO THE Los Angeles World Airports 0*1-
I 1 RW MT BOARD 0*1-.04 11 Los Angeles World Airports REPORT TO THE 0 AIRPORT COMMISSIONERS Meeting Date: Approved /by: Dave Jone - Airline Prop nd Concession Services ) 7/13/2017 Reviewed by:.',...ek
More informationNotice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application
July 3, 2018 Notice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application The City of Kansas City (City), Missouri through its Aviation Department ( the Department
More informationJANUARY MODERNIZATION UPDATE: MAJOR PROJECTS ON TAP AT LAX AS NEW YEAR BEGINS
For Immediate Release January 2, 2018 Contact: Charles H. Pannunzio (424) 646-5260 JANUARY MODERNIZATION UPDATE: MAJOR PROJECTS ON TAP AT LAX AS NEW YEAR BEGINS Access to Parking Structure 4 from the Upper/Departure
More informationP U B L I C N O T I C E. MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application C-00-MBS
P U B L I C N O T I C E MBS International Airport Freeland, Michigan Passenger Facility Charge (PFC) Application 10-07-C-00-MBS INTRODUCTION: This Public Notice is issued as part of a Federal Aviation
More informationJuly 21, Mayor & City Council Business Session KCI Development Program Process Update
July 21, 2015 Mayor & City Council Business Session KCI Development Program Process Update History of KCI 2 Airport Funding KCI Improvements are Funded by Airlines & Travelers City tax revenues do not,
More informationGreater Orlando Aviation Authority
Greater Orlando Aviation Authority Orlando International Airport & Orlando Executive Airport Budgets Fiscal Year 2017-2018 Greater Orlando Aviation Authority Orlando, Florida Greater Orlando Aviation Authority
More informationLos Angeles Business Travel Association
Los Angeles Business Travel Association Jenny Wedge Manager, Public Relations Public Information Officer June 3, 2010 John Wayne Airport Owned and operated by the County of Orange 503 acres surrounded
More informationAIRLINE CONSULTATION MEETING
AIRLINE CONSULTATION MEETING Passenger Facility Charges Proposed Projects Bangor International Airport Bangor, Maine June 2011 Bangor International Airport intends to file an application with the Federal
More informationLove Field Modernization Program Update: Master Planning Recommendations
Love Field Modernization Program Update: Master Planning Recommendations Briefing to the Council Transportation and Environment Committee April 28, 2008 1 1 Briefing Objective Discuss the background and
More informationFORECASTING FUTURE ACTIVITY
EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver
More informationSection (a)(1). Description of Projects Impose and Use
November 21, 2017 Mrs. Kelly Lane SkyWest Airlines 444 South River Road St. George, UT 84790 RE: Notice of Intent to Impose and Use a New Passenger Facility Charge Bert Mooney Airport Butte, Montana Dear
More informationLAX Specific Plan Amendment Study (SPAS) Final EIR and Related Actions. Board of Airport Commissioners February 5, 2013
LAX Specific Plan Amendment Study (SPAS) Final EIR and Related Actions Board of Airport Commissioners February 5, 2013 1 Background The LAX Master Plan Program serves as the airport s long range development
More informationBrief Recap of Project to Date
CITY AND BOROUGH OF SITKA Rocky Gutierrez Airport (SIT) Terminal Improvements Project Brief Recap of Project to Date Schematic Design: Design Development Meetings June 26 & 27, 2018 Project Description
More informationPFC Quarterly Status Report September 30, 2016
PFC Quarterly Status Report September 0, 06 Public Agency: Greater Orlando Aviation Authority Use Airport: Orlando International Airport (MCO) Charge Expiration Date: $4.50 8//08 Total Collection Authority
More informationBirmingham Airport 2033
Over the next 15 years, we will expand and improve the Airport to maximise our potential as a single runway airport by investing 500 million in new development. Our plans take account of our forecasted
More informationMidfield Satellite Concourse (MSC)
ock Los Angeles TM. r Midfield Satellite Concourse (MSC) ` JRPORîS elos Angeles DEVELOPMENT GROUP Agenda Topics Ongoing TBIT and MSC Baggage Screening /Processing Challenges Recommended Integrated Comprehensive
More informationCity of Kansas City AIRPORT COMMITTEE BRIEFING. Major Renovation Evaluation for Kansas City International Airport.
City of Kansas City AIRPORT COMMITTEE BRIEFING Major Renovation Evaluation for Kansas City International Airport February 2, 2016 1 Agenda Briefly review Exhibit K Process to establish Program Requirements
More informationAirports of the Future Taking the Terminal to the Traveler
Passenger Terminal World Expo 2011 Copenhagen, Denmark Airports of the Future Taking the Terminal to the Traveler Steven B. Cornell Assoc. Vice President Summary Aviation Timeline First Controlled Airplane
More informationKansas City Aviation Department. August 25, 2015
Kansas City Aviation Department August 25, 2015 KCI History Prior to the 1972 Charles B Wheeler Downtown Airport (MKC) was Kansas City s commercial airport Trans World Airlines (TWA) influenced the planning
More information. /lj(b~)v~ Los Angeles World Airports ~~~5J. February 14, 2013
Los Angeles World Airports February 14, 2013 LAX V;llI Nuy:> City af t,,~alig("5. Ahl!.mKi H~\/m~lr~-~il_~i:ic:;~1 l'a
More informationCharles H. Ada II Executive Manager A.B. Won Pat International Airport Guam
Charles H. Ada II Executive Manager A.B. Won Pat International Airport Guam ABOUT THE GUAM AIRPORT Autonomous instrumentality of the Government of Guam; created in 1975 by P.L. 13-57; only commercial
More informationState of Hawaii, Department of Transportation, Airports Division. PATA Hawai i. September 13, 2018
State of Hawaii, Department of Transportation, Airports Division PATA Hawai i September 13, 2018 Department of Transportation DOTA Continues Major Initiatives in 2018 Airports Division Enhance financial
More informationScoping Meeting LAX Landside Access Modernization Program
Welcome Scoping Meeting LAX Landside Access Modernization Program Thursday, February 19, 2015 5:00 p.m. to 8:00 p.m. Proud Bird Restaurant 11022 Aviation Boulevard Los Angeles, CA 90045 Welcome Scoping
More informationFort Lauderdale Hollywood International Airport
ATLANTA, GEORGIA 1 2 ATLANTA, GEORGIA Fort Lauderdale Hollywood International Airport Master Plan to Master Plan Implementation Jamie McCluskie Director of Aviation Planning & Environmental Broward County
More informationEXHIBIT E to Signatory Airline Agreement for Palm Beach International Airport RATE AND FEE SCHEDULE
EXHIBIT E to Signatory Airline Agreement for Palm Beach International Airport RATE AND FEE SCHEDULE SECTION I - DEFINITIONS The following words, terms and phrases used in this Exhibit E shall have the
More informationFinancial Feasibility Analysis Terminal Programming Study Des Moines Airport Authority
Financial Feasibility Analysis Terminal Programming Study Des Moines Airport Authority September 12, 2017 Contents 1. Funding Sources for Airport Projects 2. Financial Metrics 3. CIP Summary and Funding
More informationLOS ANGELES WORLD AIRPORTS LAX AIRPORT OPERATIONS
LOS ANGELES WORLD AIRPORTS LAX AIRPORT OPERATIONS TBIT TICKET COUNTER ASSIGNMENT POLICY Effective October 2015 REVISION 1 EFFECTIVE NOVEMBER 2016 Jacqueline Yaft Executive Deputy Director, LAWA - Airport
More informationAmendments to PFC Applications C 03 LAX and C 00 LAX
Noise Mitigation: Residential Soundproofing and Other Local Jurisdictions Los Angeles World Airports Los Angeles International Airport Overview Los Angeles World Airports (LAWA) intends to submit to the
More informationPublic Notice Passenger Facility Charge PFC Application No. 2 Amendment No. 2 Charlotte Douglas International Airport. Effective: February 22, 2019
Public Notice Passenger Facility Charge PFC Application No. 2 Amendment No. 2 Charlotte Douglas International Airport Effective: February 22, 2019 Pursuant to 49 CFR Part 158.24, the city of Charlotte
More informationImplications of Construction Cost Escalation
Implications of Construction Cost Escalation 2007 ACI-NA Economics and Finance Conference James Gill, CPA Deputy Airport Director Finance, Business & Administration Raleigh-Durham Airport Authority Presentation
More informationTERMINAL 3. tour guide booklet. April 2012
TERMINAL 3 tour guide booklet April 2012 T3 PRE-TOUR PARKING / RESTROOMS All attendees should park on the north side of the Department of Aviation s Administration Building, located at 1845 E. Russell
More informationKansas City Aviation Department. Update to Airport Committee Customer Service
Kansas City Aviation Department Update to Airport Committee Customer Service 1 Perspective An estimated 800,000 people participated in the Royals Word Series Parade On average 883,000 airline passengers
More information2017 Appropriation Budget Table of Contents Board Approved August 19, 2016
INDIANAPOLIS AIRPORT AUTHORITY 2017 APPROPRIATION BUDGET ORDINANCE NO. 2-2016 BOARD APPROVED AUGUST 19, 2016 2017 Appropriation Budget Table of Contents Board Approved August 19, 2016 1 Appropriation Summary
More informationLOS ANGELES INTERNATIONAL AIRPORT
LOS ANGELES INTERNATIONAL AIRPORT INVESTOR PRESENTATION May 15, 2018 Disclaimer GENERAL This presentation you are about to view is provided as of May 15, 2018. If you are viewing this presentation after
More informationKansas City Aviation Department. Airport Committee July 19, 2018
Kansas City Aviation Department Airport Committee July 19, 2018 AGENDA Labor Update Design Process General Updates Community Outreach LABOR UPDATE Overarching Goals: Labor Harmony on the project Ensure
More informationDestination Lindbergh
Technical Appendix 16 Destination Lindbergh Appendix Contents Destination Lindbergh... TA 16-2 2050 Regional Transportation Plan Destination Lindbergh Destination Lindbergh is a comprehensive planning
More informationPassenger Facility Charge: No. 7 Application. Public Notice Materials. Luis Muñoz Marín International Airport San Juan Puerto Rico.
Passenger Facility Charge: No. 7 Application December 2013 Public Notice Materials Luis Muñoz Marín International Airport San Juan Puerto Rico INTRODUCTION Aerostar Airport Holdings has initiated the process
More informationKansas City Aviation Department. Community Listening Session
Kansas City Aviation Department Community Listening Session Listening Session Purpose The Kansas City Aviation Department is moderating these community listening sessions in order to gather feedback from
More informationAIRPORT MASTER PLAN UPDATE
AIRPORT MASTER PLAN UPDATE PENSACOLA INTERNATIONAL AIRPORT Technical Advisory Committee Meeting #2 June 20, 2017 Agenda» Introduction» Facility Requirements Airside Terminal Landside General Aviation Cargo
More informationRAPID CITY REGIONAL AIRPORT
RAPID CITY REGIONAL AIRPORT Budget: $16,232,274 Full time Employees: 24 Mission Statement It is the mission of the Rapid City Regional Airport Board to provide safe, efficient, environmentally sensitive,
More informationPreliminary Draft Budget FY Airline Rates and Charges. Sea-Tac International Airport
Draft Budget FY 2015 Airline Rates and Charges Sea-Tac International Airport Aviation Finance & Budget 2015 Budget Airline Rates and Charges TABLE OF CONTENTS Exhibit Contents 1 Aeronautical Revenue Summary
More informationCurrent and Forecast Demand
Existing Facilities Jacksonville International Airport (JIA) is served by a number of airside and landside facilities. There are two runways that serve the airport in an open V configuration. The Annual
More informationSouthwestFloridaInternational Airport
SouthwestFloridaInternational Airport SouthwestFloridaInternationalAirportislocatedinLee CountyalongtheGulfCoastofSouthFlorida,tenmiles southeastofthefortmyerscentralbusinessdistrict. Theprimaryhighwayaccesstotheairportfrom
More information2018 Accomplishments
CY2018 ANNUAL REPORT Vision The Chippewa Valley Regional Airport will provide our users with a safe, efficient and welcoming operation while striving to meet the current and future needs of the community
More informationCHAPTER 4: ALTERNATIVES
MSP Long Term Comprehensive Plan Update Metropolitan Airports Commission 4.1 INTRODUCTION CHAPTER 4: ALTERNATIVES Several alternatives were developed and evaluated based on their capability to meet the
More informationAIRPORT DEVELOPMENT PLAN. Design-Build Institute of America September 8, 2015
AIRPORT DEVELOPMENT PLAN Design-Build Institute of America September 8, 2015 Lindbergh Field - 1935 3 Page 2 Lindbergh Field - 1944 3 Page 3 Lindbergh Field - 1955 3 Page 4 San Diego International Airport
More informationTABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary.
TABLE OF CONTENTS Section Page Section Page 1.0 INTRODUCTION... 1 1.1 Purpose of an... 1 1.2 Goals and Objectives... 1 1.3 Mission Statement... 2 1.4 Stakeholder/Public Involvement... 2 1.5 Major Deliverables...
More informationSTUDY WORK GROUP MEETING No. 4. July 12, 2017
STUDY WORK GROUP MEETING No. 4 July 12, 2017 Agenda Welcome and introductions Update of project schedule Brief overview of previous SWG meeting Introduction to airport development alternatives Comments,
More informationTERMINAL DEVELOPMENT PLAN
5.0 TERMINAL DEVELOPMENT PLAN 5.0 TERMINAL DEVELOPMENT PLAN Key points The development plan in the Master Plan includes the expansion of terminal infrastructure, creating integrated terminals for international,
More informationCVG Overview Connect with CVG March 29, 2017
CVG Overview Connect with CVG March 29, 2017 Launching Point Strategic Plan CVG Launching Point Strategies for 2016 and Beyond Vision: Make travel through CVG and unforgettably positive experience Mission:
More informationGreater Orlando Aviation Authority Orlando International Airport One Jeff Fuqua Boulevard Orlando, Florida Memorandum TO: FROM:
Greater Orlando Aviation Authority One Jeff Fuqua Boulevard Orlando, Florida 32827-4399 Memorandum TO: FROM: Participating Airlines Phil Brown, Executive Director DATE: SUBJECT: Rate Methodology for FY
More informationIAH Terminal Redevelopment Project. Memorandum of Agreement with United Airlines
IAH Terminal Redevelopment Project Memorandum of Agreement with United Airlines May 29, 2014 On April 24, HAS presented plans for a new Mickey Leland International Terminal (MLIT) Sufficient capacity for
More informationRNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan
RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan Project Schedule Today Slide 40 Project Vision To provide an achievable, flexible, fiscally, and environmentally
More informationAIRPORT RATES AND CHARGES October 1, 2016 to September 30, 2017 SIGNATORY AIRLINE CHARGES
AIRPORT RATES AND CHARGES October 1, 2016 to September 30, 2017 SIGNATORY AIRLINE CHARGES Landing Fees - per 1,000 lbs. of Maximum Gross Landed Weight Terminal Rental Rate - includes ATO, BSO, ticket counters,
More informationOpening A New Airport Terminal
Opening A New Airport Terminal A Systematic Approach to Activation & Lessons Learned Leo Fermin Deputy Airport Director San Francisco International Airport Clearly Define Objectives Clearly define the
More informationLAWA Breaks Ground on Midfield Satellite Concourse
LAX CAPITAL IMPROVEMENTS PROGRAM E-NEWSLETTER LAWA Breaks Ground on Midfield Satellite Concourse Taso Papadakis DIGGING IN Airport and city officials take part in the Feb. 27 groundbreaking. Pictured from
More information2006 ANNUAL GENERAL MEETING
2006 ANNUAL GENERAL MEETING Address by Garth F. Atkinson President and Chief Executive Officer April 19, 2006 Thank you Peter and good morning ladies and gentlemen and invited guests. Before proceeding
More informationCOUNTY OF MUSKEGON MUSKEGON COUNTY AIRPORT Rates, Charges and Fee for FY18 October 1, 2017 through September 30, 2018
COUNTY OF MUSKEGON MUSKEGON COUNTY AIRPORT Rates, Charges and Fee for FY18 October 1, 2017 through September 30, 2018 GROUND & FACILITY LEASE RATES Ground Lease Rate Bare ground for development Per Individual
More informationPFC Application #2 Niagara Falls International Airport
Public Notice Application #2 Falls International April 12, 2018 Agenda Program at the Falls International Notice to air carriers and consultation meeting Class of air carriers not required to collect Air
More informationBURLINGTON INTERNATIONAL AIRPORT
BURLINGTON INTERNATIONAL AIRPORT VISION 2030 AIRPORT MASTER PLAN UPDATE Summary Presentation AIRPORT STAFF AND STUDY TEAM Robert McEwing, Director of Planning & Development Brad Worthen, Community Facilitator
More information::f BOA OF AIRPORT COMMISSIONERS REPORT TO THE. -A. A_ A.4k fig
3/3/208 2/26/208 Approval NY a NY Y RW JH BOA /...-_ 0...0 00:4.4 Los Angeles World Airports REPORT TO THE OF AIRPORT COMMISSIONERS -A. A_ A.4k._ra. At, Approved y: Dave Jones - Air.n:TPro:-.,. oncession
More informationLogan International Airport Right Sizing and Good Terminal Planning
Logan International Airport Right Sizing and Good Terminal Planning Two Case Studies: Terminal E Expansion Terminal C Checkpoint Presented by: Sam Sleiman, PE, CCM Director Of Capital Programs and Environmental
More informationPassenger Facility Charge Public Notice. February 14, 2018
Passenger Facility Charge Public Notice February 14, 2018 Overview The Memphis-Shelby County Airport Authority intends to submit a new Passenger Facility Charge (PFC) application for a project at Memphis
More informationFeasibility Study Federal Inspection Service Facility at Long Beach Airport
Feasibility Study Federal Inspection Service Facility at Long Beach Airport 13 December 2016 Long Beach City Council PLEASE NOTE: The information, analysis, assessments and opinions contained in this presentation
More informationCOUNTY OF MUSKEGON MUSKEGON COUNTY AIRPORT Rates, Charges and Fees for Fiscal Year 2019 October 1, 2018 through September 30, 2019
COUNTY OF MUSKEGON MUSKEGON COUNTY AIRPORT Rates, Charges and Fees for Fiscal Year 2019 October 1, 2018 through September 30, 2019 GROUND & FACILITY LEASE RATES Ground Lease Rate Bare ground for development
More informationCLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257
Form PDES 8 THE CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257 Summary of Duties: A Senior Airport Engineer performs the more difficult and
More informationTHE CASE OF A SUCCESSFUL PFC APPLICATION
THE CASE OF A SUCCESSFUL PFC APPLICATION 1 Chapter One: Scene of the case study 2 Chapter One: The Scene Spokane, WA Home of the RED TURF at Eastern WA University (and Gonzaga) 3 Chapter One: The Scene
More informationFinance and Implementation
5 Finance and Implementation IMPLEMENTATION The previous chapters have presented discussions and plans for development of the airfield, terminal, and building areas at Sonoma County Airport. This chapter
More informationPORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting August 23, 2016
PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting August 23, 2016 DATE: TO: FROM: Michael Ehl, Director, Airport Operations Wayne Grotheer, Director, Aviation Project
More informationEXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES
EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES Over the term of the Master Amendment to the Airline Use and Lease Agreement, the Kansas City Aviation Department
More informationMaster Plan Phase 2 Workshop
Master Plan Phase 2 Workshop Tampa Airport: A Legacy of Innovation and Convenience Tampa Airport: A legacy of Innovation and Convenience The world s first airport people mover Tampa Airport: A legacy of
More informationPUBLIC NOTICE. Table 1 Projects Proposed by Amendment
PUBLIC NOTICE The Dallas Department of Aviation (the Department) intends to file an amendment application to increase the PFC amount of one previously approved project at Dallas Love Field Airport (the
More informationThe challenges of growth, the growth of challenges Airports Canada 2013 April 11, JAMES C. CHERRY CEO Aéroports de Montréal
The challenges of growth, the growth of challenges Airports Canada 2013 April 11, 2013 JAMES C. CHERRY CEO Aéroports de Montréal AGENDA THE CHALLENGES OF GROWTH, THE GROWTH OF CHALLENGES Trafic growth
More informationLos Angeles World Airports
Los Angeles World Airports June 3, 2014 The Honorable City Council of the City of Los Angeles City Hall, Room 395 Los Angeles, CA 90012 LA" LA/Ontario Van Nuys City of los Angeles Eric Garcetti Mayor Board
More informationSECTION NO. PAGE NO. Amendment NO.
INDEX TO AIRLINE RATES, FEES AND CHARGES AMENDED ORDINANCE 201601 GREATER ASHEVILLE REGIONAL AIRPORT AUTHORITY DESCRIPTION ORDINANCE NO. SECTION NO. PAGE NO. Amendment 201601 12 10 Effective Date 201601
More informationChapter 4 Terminal Facility Requirements and Alternatives
Chapter 4 Terminal Facility Requirements and Alternatives I. Terminal Facility Requirements Introduction This chapter of the master plan converts the forecasted passenger demand levels that were identified
More informationThe Big 4 Airline Era, New Ultra Low Cost Carriers, and Implications for Airports
The Big 4 Airline Era, New Ultra Low Cost Carriers, and Implications for Airports Linda Perry, Director AAAE Rates and Charges Workshop November 4, 2016 Outline The Big 4 American Delta Southwest United
More informationPublic Notice July 14, 2017
Public Notice July 14, 2017 PROPOSED IMPLEMENTATION OF PFC 13 NOTICE TO AIR CARRIERS AND CONSULTATION MEETING Implementation of PFC On June 14, 2017 the Omaha Airport Authority provided written notice
More information1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan
TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201
More informationPlanning, Development and Environment Committee
Page 1 of 7 MEMORANDUM TO: Planning, Development and Environment Committee FROM: Neil Ralston, Airport Planner Airport Development (726-8129) SUBJECT: 2035 MSP LONG TERM COMPREHENSIVE PLAN FORECAST, FACILITY