1 MASTER PLAN UPDATE Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT Meeting #4 December 14, 2017
2 Today s Agenda o Welcome o Introductions o Progress update o Alternatives analysis Airfield Terminal area General aviation ATCT ARFF o Next steps
3 Airport Master Plan Process Aerial Survey & Mapping We are Here Implementation Plan Pre-Planning, Study Design, Secure Grants Inventory Existing Conditions Activity & Demand Forecasting Capacity Analysis & Facility Requirements Alternative Concepts Financial Plan Final Documents & Plan Adoption PAC #1 PAC #2 PAC #3 PAC #4 ALP Plan Set PAC #5 Stakeholder Engagement & Planning Advisory Committee Public Workshop #1 Public Workshop #2 Public Workshop #3 Complete Current Work Future Effort
4 Alternatives Analysis CON PRO Image sources: Wikimedia Commons, 9/11/17
5 Airfield
6 Areas of Concern Terminal Apron, High-speed Exits and Taxiway A Capability Provide Group-III Access Middle third of runway Areas of concern
7 Terminal Apron and Taxilane A Existing Configuration & Concerns Objective adhere to FAA criteria and simplify configuration Confusing multi-node taxiway intersection, wide expanse of pavement Direct apron-runway access B7 Taxiway B (Grp-IV) Taxilane A (Grp-III) B5 Conflict between Taxilane A and gates 16, 17, 14B B3 Taxiway A (Grp-II) Non-movement Area Confusing intersection, non-standard angles, expanse of pavement, and mix of aircraft types 14B 16 17
8 Terminal Apron and Taxilane A Basic Solution remove B6 B6 Movement Area Boundary Extended Alternative remove Taxilane A and expand non-movement area B6 Apron expands 150 Advantages o Maintain familiar procedures o ATC maintains more control of circulation Disadvantages o Does not de-conflict pushback o Less flexibility for ramp agents Middle third of runway Pavement to be removed Taxiway island Advantages o Increases apron space o De-conflicts pushbacks o Reduces ATC workload Disadvantages o Increases ramp agent responsibility o Reduces ATC routing flexibility loss of 1 apron connector
9 Terminal Apron and Taxilane A Refined Alternative reconfigure B6, remove Taxilane A, expand commercial apron and non-movement area B6 B3 B7 Movement Area Non-movement Area (aka. Commercial ramp limits) Middle third of runway New pavement Pavement to be removed Taxiway island
10 High-speed Exits Northbound high-speed exit Southbound 90-degree exits Advantages o Good capture rate for Runway 29R Disadvantages o Doesn t support current ground traffic needs o Higher pavement cost Advantages o Better capture rates for both 11R-29L o Reduces taxi time o Maintains operational flexibility o Lower pavement cost Disadvantages o Lower capture rate from 11L-29R These are not mutually exclusive. Prioritize 90-degree exits and reserve potential north high-speed for future if needed.
11 High-speed Exits Connection with terminal apron and Taxiway A Minimum spacing from B5 and B7 Align w/b7 add apron connector Advantages o Less pavement cost Disadvantages o Less circulation options 2 terminal apron connectors Advantages o Spacing allows for 3 Group-IV terminal apron connectors Disadvantages o Higher pavement cost
12 Blended Terminal Apron and Exit Taxiway Alternatives Potential Future High-speed Exit Middle third of runway New pavement Pavement to be removed Taxiway island Movement area/commercial ramp limits
13 Upgrade Taxiway A to Group-III Objective: improve access and circulation for large corporate and charter aircraft Maintain Taxiway Centerline Features o Relocate service road on to GA apron Advantages o Lower construction cost Disadvantages o Reduces apron depth by ±20 (220 remaining) Shift Taxiway Centerline Features o TW centerline shifts ±26 Advantages o Maintains service road and GA apron space Disadvantages o o Relocate airfield electrical vault Higher construction cost Group-II OFA: 131 Group-III OFA: 186 New pavement Pavement to be removed
14 Terminal Area
15 Enplanement Forecast 1,800,000 1,600,000 PAL 3 (1.65M) Planning Activity Levels (PALs) Used for planning of terminal and parking facilities. 1,400,000 1,200,000 1,000,000 PAL 2 (1.24M) PAL 1 (1.0M) 800, , , , Historic Baseline Preliminary FAA TAF High Growth
16 Terminal Requirements Functional Area Existing Facilities PAL 1 Requirement PAL 2 Requirement PAL 3 Requirement Enplanements 773,000 (2016) 1.0 M 1.24 M 1.65M Total Additional Needed International Arrivals Facility (FIS) 10,500 sf 16,000 16,000 16,000 5,500 Peak Aircraft Parking Positions (i.e. contact gates) * International Arrival Positions * Remote Aircraft Parking Positions Passenger Hold Room 19,900 sf 14,600 17,400 22,900 3,000 Concessions (pre and post security) 9,400 sf 8,500 9,000 14,850 5,450 Security Screening Checkpoint 4,300 sf 3,300 5,300 8,800 4,500 Baggage Makeup 2,900 sf 6,800 8,400 9,900 7,000 Public Parking 2,050 spaces 2,460 3,050 4,050 2,000 Rental Car Ready Return 570 spaces Rental Car Storage 580 spaces 1,220 1,520 2,020 1,440 * One program objective is to provide Passenger Boarding Bridges at all gates.
17 Incremental PAL 1 Requirements Spare peak hour positions PAL 1 REQUIREMENTS New auto parking FIS expansion (process 2 simultaneous aircraft) Post security concession expansion Additional baggage makeup Additional passenger boarding bridges 9 peak hour positions 2 international arrival positions 11 remain overnight positions Tugged to departure positions BAGGAGE MAKEUP EXPANSION FIS EXPANSION Aircraft Parking Positions PAL 1 PARKING GARAGE 500 SPACES Domestic mainline International mainline Domestic regional Remote/RON position
18 Incremental PAL 2 Requirements Spare peak hour positions PAL 2 REQUIREMENTS Expanded FIS Concession expansion Additional baggage makeup Security checkpoint expansion Baggage makeup expansion New passenger hold room New circulation space Additional passenger boarding bridges Parking garage expansion 10 peak hour positions 2 international positions 14 remain overnight positions PAL 1 PARKING GARAGE 500 SPACES PAL 2 PARKING GARAGE 500 SPACES
19 Incremental PAL 3 Requirements Spare remote positions if needed PAL 3 REQUIREMENTS Parking garage expansion Rental car ready/return expansion or relocation Additional baggage makeup 12 peak hour positions 2 international positions 15 remain overnight positions Spare peak hour position PAL 1 PARKING GARAGE 500 SPACES PAL 2 PARKING GARAGE 500 SPACES PAL 3 PARKING GARAGE 1,000 SPACES
20 Logical Phase 1 Program PHASE ONE IMPROVEMENT HIGHLIGHTS New auto parking (could be incremental) East concourse Apron expansion Expanded FIS Concession expansion Baggage makeup expansion Security checkpoint expansion Additional R.O.N. parking Spare peak hour positions PARKING GARAGE 500 SPACES GARAGE EXPANSION 500 SPACES Satisfies all PAL 2 and some PAL 3 requirements
21 Logical Phase 2 Program Spare remote positions if needed PHASE TWO IMPROVEMENT HIGHLIGHTS Existing concourse spine upgrades and expansion Concession expansion Parking garage expansion Additional R.O.N. parking Spare peak hour position PARKING GARAGE 500 SPACES GARAGE EXPANSION 500 SPACES GARAGE EXPANSION 1,000 SPACES Satisfies all PAL 3 requirements and upgrades spine concourse
22 Future Expansion Options DEVELOPMENT OPTIONS East concourse expansion New west concourse Rental car relocation New head house Parking garage expansion PARKING GARAGE PARKING GARAGE PARKING GARAGE
23 General Aviation
24 Aircraft Storage Requirements 1,000, ,000 Combined Based & Transient Aircraft 910,100 sf available 800, , , , , , surplus = 534,000 sf 2036 deficit = 137,000 sf 200, , ,800 sf available Apron/Tie-Down T-Hangar Shared Hangar ,500 sf available Unmet hangar demand currently accommodated on apron
25 Aircraft Storage Alternatives New western hangar area New western area + redevelopment Advantages o Undeveloped site, flexible configuration o Consistent with previous planning o Segregation aircraft/operator types Disadvantages o Not centrally located Advantages o Replaces aging T-hangars o Central community hangar location Disadvantages o Tenant disruptions o Potential impact to T-hangar revenues
26 Aircraft Storage Alternatives Extension of Anderson w/ in-fill Expand GA Apron & Shift Taxiway A Advantages o Additional developable space o Consistent with previous planning o Improves adjacent land use o Improves traffic safety along Anderson, Winery and Shields Avenues Disadvantages o Residential property acquisition/relocation o Complex road realignments Advantages o Potential to increase FBO apron space o Replaces aging T-hangars o Central location Disadvantages o Relocate electrical vault o Difficult phasing o Tenant disruptions o Complicates apron parking o Precludes upgrading Taxiway A to Grp-III
27 Aircraft Storage Alternatives New hangar area south of Anderson Group-III Taxilane Advantages o Segregation aircraft/operator types o Centrally located Expandability with relocation of maintenance warehouse Disadvantages o Reduced commercial development property o Impacts road circulation o Limits rental car expansion o Eliminates tie-downs and likely requires hangar relocations
28 Airport Traffic Control Tower Outdated building (56 years old) Difficult/expensive to update Limited expandability, constrained site ATCT Sources: PictometryOnline, Wikimedia Commons, accessed 12/4/17
29 ATCT Potential Relocation Sites Preliminary FAA Tower Siting Study (2010) 4 leading sites PRIMARY SITING ISSUES Airfield and approach line of sight Tower height Access and security Development cost
30 ARFF
31 ARFF Facilities Existing Configuration & Concerns Undersized facility (±7,500 sf - need ±15,000 sf) and constrained site AIRPORT TRAFFIC CONTROL TOWER
32 ARFF Location Alternatives Existing location w/ maintenance Existing location move maintenance Maintenance Maint. Expansion ARFF ARFF Potential ATCT Site Advantages o Proximity to terminal apron o Ease of co-locating safety services o Can provide for maintenance expansion Disadvantages o Limits ATCT expandability o Limits terminal apron use o Construction phasing and operational impacts o Limits optimum ARFF design Advantages o Proximity to terminal area o Ease of co-locating safety services o Pull through bays o Additional parking Disadvantages o Limits ATCT expansion o Limits terminal apron use o Relocate maintenance building o Construction phasing and operational impacts o Limits optimum ARFF design
33 ARFF Location Alternatives Northside of airfield Relocate hangars Available for Redevelopment ARFF ARFF Maint. Potential ATCT Site Advantages o Ease of development o Flexible site design o ATCT flexibility and security o ±0.8 ac. available for redevelopment (ATC, maintenance building, terminal apron) Disadvantages o Distance from terminal apron o Does not support co-located public safety Advantages o Proximity to terminal area o ATCT flexibility and security o ±1 ac. available for redevelopment (ATC, terminal apron) Disadvantages o Tenant disruption o Hangar redevelopment cost o Reduced general aviation area
34 ARFF Location Alternatives East of RTR Future Apron Expansion Future RTR Relocation A M Future Terminal Support Facilities Advantages o Proximity to terminal o Ability to co-locate safety services o Ease of development o Flexible site design o ATCT flexibility and security o ±1 ac. available for redevelopment (ATC, terminal apron) o Consistent with previous planning o Supports potential CANG ARFF management Disadvantages o ±500 further from terminal apron
35 Next Steps o Public Open House tonight o Awaiting FAA approval of forecasts o Finalize Working Paper #4 Facility Requirements o Draft Working Paper #5 Alternatives
36 Thank You Please contact the following with comments, questions or concerns regarding the Master Plan Study Mark Davis Airports Planning Manager City of Fresno (559) Pam Keidel-Adams Kimley-Horn Kevin Clarke Kimley-Horn
MASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #3
MASTER PLAN UPDATE Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT Meeting #3 September 20, 2017 Today s Agenda o Progress update o Summary of forecasts o Preliminary facility requirements
More informationBNA Master Plan Update Community Advisory Committee Meeting No. 5
A Six Sigma Organization BNA Master Plan Update Community Advisory Committee Meeting No. 5 September 19, 2012 Introductions MNAA Staff RW Armstrong Team Albersman & Armstrong, Ltd. Atkins North America,
More informationSTUDY WORK GROUP MEETING No. 4. July 12, 2017
STUDY WORK GROUP MEETING No. 4 July 12, 2017 Agenda Welcome and introductions Update of project schedule Brief overview of previous SWG meeting Introduction to airport development alternatives Comments,
More informationBNA Master Plan Update Public Meeting No. 2
A Six Sigma Organization BNA Master Plan Update Public Meeting No. 2 September 18, 2012 Agenda BNA Master Plan Update Consultants Status of the BNA Master Plan Update Workstation Boards Forecasts of Aviation
More informationAIRPORT MASTER PLAN UPDATE
AIRPORT MASTER PLAN UPDATE PENSACOLA INTERNATIONAL AIRPORT Technical Advisory Committee Meeting #2 June 20, 2017 Agenda» Introduction» Facility Requirements Airside Terminal Landside General Aviation Cargo
More informationLake Tahoe Airport Master Plan
Lake Tahoe Airport Master Plan City Council Briefing October 20, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development
More informationTABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved
TABLE OF CONTENTS Description Page Number LIST OF ACRONYMS... a CHAPTER ONE INTRODUCTION General... 1-1 Study Objectives... 1-1 Public Involvement... 1-2 Issues to Be Resolved... 1-2 CHAPTER TWO EXISTING
More informationOctober 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION
October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION The Master Plan Process Inventory Of Existing Conditions Complete. Forecasts Of Aviation Demand Complete. Facility Requirements Complete.
More informationAddendum - Airport Development Alternatives (Chapter 6)
Bowers Field Addendum - Airport Development Alternatives (Chapter 6) This addendum to the Airport Development Alternatives chapter includes the preferred airside development alternative and the preliminary
More informationMASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #2
MASTER PLAN UPDATE Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT Meeting #2 May 4, 2017 Today s Agenda o Progress update o Summary of existing facilities o Preliminary forecasts
More informationCHAPTER 4: ALTERNATIVES
MSP Long Term Comprehensive Plan Update Metropolitan Airports Commission 4.1 INTRODUCTION CHAPTER 4: ALTERNATIVES Several alternatives were developed and evaluated based on their capability to meet the
More informationThe CLE Master Plan Includes:
The CLE Master Plan Includes: An inventory of existing conditions Forecasting future demand and analyzing future needs Evaluating alternative development scenarios Preparing the Airport Layout Plan Preparing
More informationGerald R. Ford International Airport Authority Master Plan Update A World Class Gateway
Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway Master Plan Advisory Committee (MPAC) Alternatives September 28, 2017 AGENDA Review of Previous Work Ultimate Land
More informationSECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES
SECTION 5 ALTERNATIVE DEVELOPMENT CONCEPT ANALYSES 5.1 INTRODUCTION This section investigates Airfield Development Alternatives, generalized Land Use Alternatives, and more detailed General Aviation Alternatives.
More informationWestover Metropolitan Airport Master Plan Update
Westover Metropolitan Airport Master Plan Update June 2008 INTRODUCTION Westover Metropolitan Airport (CEF) comprises the civilian portion of a joint-use facility located in Chicopee, Massachusetts. The
More informationCHAPTER 5: Landside Facility Requirements and Development Concepts
CHAPTER 5: Landside Facility Requirements and Development Concepts Overview Implementation of the preferred intermediate-term (10-year) and long-term (20-year) airside alternatives will have a significant
More informationFORECASTING FUTURE ACTIVITY
EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver
More informationLake Tahoe Airport Master Plan Public Meeting March 16, 2015
Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development plans
More informationAppendix 6.1: Hazard Worksheet
Appendix 6.1: Appendix 6.1: Ref. Condition, real or potential; that can cause injury, illness, etc. This is a prerequisite for an Airfield Hazards 1. Taxiway Geometry Direct access to runway from ramp
More informationPunta Gorda Airport Master Plan Update
Punta Gorda Airport Master Plan Update Draft Executive Summary Prepared for: The Charlotte County Airport Authority January 2018 Charlotte County Airport Authority James Herston, Chair Robert D. Hancik,
More informationMaster Plan Update Community Advisory Committee Kick-off Meeting
Nashville International Airport Master Plan Update Community Advisory Committee Kick-off Meeting September 13, 2018 Agenda Welcome and Introductions Master Plan Objectives Master Plan Process BNA Vision
More informationCurrent and Forecast Demand
Existing Facilities Jacksonville International Airport (JIA) is served by a number of airside and landside facilities. There are two runways that serve the airport in an open V configuration. The Annual
More informationGeneral Aviation Master Plan Update
Peter O. Knight Airport Public Meeting #2 Peter O. Knight Airport Agenda Welcome and Introductions HCAA System of Airports Purpose of Public Meetings Master Plan Status Update Next Steps Q & A 2 Our System
More informationAirport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal
Airport Master Plan Rapid City Regional Airport October 2015 FAA Submittal Rapid City Regional Airport Master Plan Update Table of Contents Executive Summary... i Scope & Timeline... i Forecasts... i Preferred
More informationSTUDY WORK GROUP MEETING No. 3. November 29, 2016
STUDY WORK GROUP MEETING No. 3 November 29, 2016 Agenda Welcome and introductions Update project schedule Brief overview of previous SWG meeting Update on aviation forecasts Introduction to airfield demand/capacity
More informationCasper/Natrona County International Airport Master Plan Update Technical Advisory Committee Meeting Two - October 14th, :30 PM
Casper/Natrona County International Airport Master Plan Update Technical Advisory Committee Meeting Two - October 14th, 2014 1:30 PM Casper/Natrona County International Airport Master Plan Update Policy
More informationFort Lauderdale Hollywood International Airport
ATLANTA, GEORGIA 1 2 ATLANTA, GEORGIA Fort Lauderdale Hollywood International Airport Master Plan to Master Plan Implementation Jamie McCluskie Director of Aviation Planning & Environmental Broward County
More informationMeeting Summary ABE Master Plan Project Advisory Group (PAG) Meeting #3 August 15, Shannon Eibert, C&S Companies
Meeting Summary ABE Master Plan Project Advisory Group (PAG) Meeting #3 August 15, 2017 Prepared by: File: Attendees: Shannon Eibert, C&S Companies N93.012.001 See Sign-In List A third meeting was held
More informationInput Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot
Input Efforts Online survey of tenants and users Focus group meetings with Tenants and users Agencies and stakeholders General Aviation Pilot community Airport Advisory Board meetings Elected Officials
More informationTechnical Advisory Committee Briefing #3
(PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY Technical Advisory Committee Briefing #3 June 22, 2018 Master Plan Schedule Overview Coordination Review Recommended Remote 5-Gate Facility
More informationTABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary.
TABLE OF CONTENTS Section Page Section Page 1.0 INTRODUCTION... 1 1.1 Purpose of an... 1 1.2 Goals and Objectives... 1 1.3 Mission Statement... 2 1.4 Stakeholder/Public Involvement... 2 1.5 Major Deliverables...
More informationAppendix D Airfield Ongoing Projects Alternatives
Appendix D Appendix D D.1 Introduction The set of alternatives for each of the airfield facilities was compared with respect to each other and the existing condition. 1 The screening and evaluation process
More informationSouthwestFloridaInternational Airport
SouthwestFloridaInternational Airport SouthwestFloridaInternationalAirportislocatedinLee CountyalongtheGulfCoastofSouthFlorida,tenmiles southeastofthefortmyerscentralbusinessdistrict. Theprimaryhighwayaccesstotheairportfrom
More informationTO: Planning Advisory Committee (PAC) Members RE: Pangborn Airport Master Plan PAC Meeting #4 Presentation Material DATE: July 18, 2017
TO: Planning Advisory Committee (PAC) Members RE: Pangborn Airport Master Plan PAC Meeting #4 Presentation Material DATE: July 18, 2017 Please find attached for your review prior to the PAC Meeting #4,
More informationMASTER PLAN UPDATE GRANT NUMBER
T MASTER PLAN UPDATE D R AF GRANT NUMBER 3-48-0062-42 MAY 2015 1. Introduction... 1-1 1.1 History of Dallas Love Field... 1-1 1.2 Airport Setting... 1-2 1.2.1 DALLAS-FORT WORTH-ARLINGTON METROPOLITAN STATISTICAL
More informationAlternatives Analysis EXECUTIVE SUMMARY
Alternatives Analysis EXECUTIVE SUMMARY Alternative development plans were created as part of the Master Plan for Harrisburg International Airport. The aim is to provide sufficient capacity for projected
More informationNotice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application
July 3, 2018 Notice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application The City of Kansas City (City), Missouri through its Aviation Department ( the Department
More information1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan
TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201
More informationPlanning Advisory Committee November 20, 2014
Planning Advisory Committee November 20, 2014 Master Plan website up & running: www.flydurango.com Planning Advisory Committee (PAC) established & meeting Briefings provided to City Council, County Commissioners
More informationPrepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906
Master Plan The preparation of this document was financed in part through a planning grant from the Federal Aviation Administration (FAA) as provided under Section 505 of the Airport and Airway Improvement
More informationCHAPTER 1 EXECUTIVE SUMMARY
CHAPTER 1 EXECUTIVE SUMMARY 1 1 EXECUTIVE SUMMARY INTRODUCTION William R. Fairchild International Airport (CLM) is located approximately three miles west of the city of Port Angeles, Washington. The airport
More informationSavannah / Hilton Head International Airport Master Plan Update
EXECUTIVE SUMMARY Savannah / Hilton Head International Airport Master Plan Update Prepared for: The Savannah Airport Commission Prepared by: URS Corporation In Association With: RS&H and Ruth and Associates,
More informationNorfolk International Airport
Norfolk International Airport Master Plan Update Technical Advisory Committee Meeting #1 Community Advisory Committee Meeting #1 January 24, 2018 Agenda Project Background Introductions Overview of Airport
More informationTed Stevens Anchorage International Airport
Ted Stevens Anchorage International Airport 2014 MASTER PLAN UPDATE Executive Summary IN ASSOCIATION WITH: HDR DOWL HKM RIM Architects ATAC Ted Stevens Anchorage International Airport is planning for the
More informationFLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING
(PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY FLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING May 15, 2018 Master Plan Schedule Overview Progress Since Last Master Plan
More informationAirlake Airport 2035 Long Term Comprehensive Plan (LTCP)
Airlake Airport 2035 Long Term Comprehensive Plan (LTCP) Public Informational Meetings August 9 & 10, 2017 Draft LTCP Overview Briefing Agenda Airport Role & Context Existing Conditions & Previous Plan
More informationEugene Airport Master Plan Update Executive Summary
- ~o Eugene Airport Master Plan Update Executive Summary Prepared for City of Eugene, Oregon Prepared by May 2010 The Federal Aviation Administration (FAA) developed the airport master planning process
More informationTed Stevens Anchorage International Airport
Ted Stevens Anchorage International Airport 2014 MASTER PLAN UPDATE Executive Summary IN ASSOCIATION WITH: HDR DOWL HKM RIM Architects ATAC Ted Stevens Anchorage International Airport is planning for the
More informationWhat is an Airport Master Plan?
What is an Airport Master Plan? The goal of a master plan is to provide the framework needed to guide future airport development that will cost-effectively satisfy aviation demand, while considering potential
More informationAppendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis
Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis ITB MAIN TERMINAL DEPARTURES LEVEL & BOARDING AREAS A & G ALTERNATIVES ANALYSIS
More information2012 AIRPORT MASTER PLAN 2016 ADDENDUM VOLUME 1 SUBMITTED ON: SEPTEMBER 22, 2017
VOLUME 1 2012 AIRPORT MASTER PLAN 2016 ADDENDUM SUBMITTED ON: SEPTEMBER 22, 2017 VOLUME 1 CONTENTS SECTION 1 - INTRO AND AIRPORT CONTEXT SECTION 2 - FORECAST SECTION 3 - AIRFIELD FACILITIES AND DEMAND/CAPACITY
More informationDEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER
PETE FLAHERTY COMMISSIONER TOM FOERSTER CHAIRMAN DEPARTMENT OF AVIATION BARBARA HAFER COMMISSIONER STEPHEN A. GEORGE DIRECTOR ROOM M 134, TERMINAL BUILDING GREATER PITTSBURGH INTERNATIONAL AIRPORT PITTSBURGH,
More informationFLL Master Plan Update Policy Advisory Committee (PAC) Briefing #2 July 10, 2017
FLL Master Plan Update Policy Advisory Committee (PAC) Briefing #2 July 10, 2017 (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY PAC Committee (PRELIMINARY DRAFT) WORK IN PROGRESS -
More informationAirport Preliminary Master Plan Workshop Board of County Commissioners April 18, 2017
Airport Preliminary Master Plan Workshop Board of County Commissioners April 18, 2017 (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY Agenda (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR
More informationAirport Master Plan Open House Front Range Airport February 23, 2017
Airport Master Plan Open House Front Range Airport February 23, 2017 MASTER PLAN PROCESS AND OVERVIEW MASTER PLAN ELEMENTS The Master Plan is a 20-year plan to understand the needs of current and future
More informationChapter 4 AIRPORT DEVELOPMENT ALTERNATIVES
Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES Chapter Four Airport Development Alternatives Prior to formulating a development program for Ryan Airfield, it is important to consider development potential
More informationTERMINAL DEVELOPMENT PLAN
5.0 TERMINAL DEVELOPMENT PLAN 5.0 TERMINAL DEVELOPMENT PLAN Key points The development plan in the Master Plan includes the expansion of terminal infrastructure, creating integrated terminals for international,
More informationNOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019
NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019 The City of Atlanta is providing an opportunity for public comment until April 25, 2019 related to the
More informationMONTROSE REGIONAL AIRPORT
MONTROSE REGIONAL AIRPORT FEBRUARY 25, 2016 DRAFT AGENDA READY FOR TAKE OFF WHAT ARE WE GOING TO DO TODAY? Introductions Why conduct an airport master plan? Master Plan Process Deliverables Schedule Identify
More informationAirport Master Plan. Brookings Regional Airport. Runway Runway 17-35
Runway 17-35 Airport Master Plan Runway 12-30 Brookings Regional Airport Table of Contents Table of Contents Chapter 1: Master Plan Goals... 1-1 1.1. Introduction... 1 1.2. Objective 1 Identify improvements
More informationDRAFT MASTER PLAN UPDATE
DRAFT MASTER PLAN UPDATE CHAPTER VI: AIRPORT LAYOUT PLAN NARRATIVE DRAFT REPORT APRIL 2017 PREPARED BY: Table of Contents WESTCHESTER COUNTY AIRPORT 6 AIRPORT LAYOUT PLAN NARRATIVE REPORT... 6-1 6.1 AGIS
More informationPLU Airport Master Plan. Master Plan Advisory Committee (MPAC) Meeting #2 October 16, 2016
PLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #2 October 16, 2016 Meeting Agenda 1. Introductions and Contacts [10 Minutes] 2. Plan Overview and MPAC Role [20 Minutes] 3. MPAC Visioning
More informationChapter 5 Airport Development Alternatives
Chapter 5 Airport Development Alternatives Introduction CHAPTER 5 AIRPORT DEVELOPMENT ALTERNATIVES JUNE 2013-1 Evaluation Process No-Action Alternative CHAPTER 5 AIRPORT DEVELOPMENT ALTERNATIVES JUNE 2013-2
More informationBlue Grass Airport (LEX) serves the needs of a multi-county area that
SUMMARY BACKGROUND This Master Plan Update balances needed airport improvements with the goals of the community and arrived at a consensus on how to best meet future demand without sacrificing those natural
More informationBirmingham Airport 2033
Over the next 15 years, we will expand and improve the Airport to maximise our potential as a single runway airport by investing 500 million in new development. Our plans take account of our forecasted
More informationIDENTIFICATION AND EVALUATION OF ALTERNATIVES ST. PETERSBURG-CLEARWATER INTERNATIONAL AIRPORT
IDENTIFICATION AND EVALUATION OF ALTERNATIVES ST. PETERSBURG-CLEARWATER INTERNATIONAL AIRPORT 7 7.1 GENERAL The primary objective of this chapter is to evaluate potential development alternatives and identify
More informationAirport Master Plan for. Brown Field Municipal Airport PAC Meeting #3
Airport Master Plan for Brown Field Municipal Airport PAC Meeting #3 Public Meeting #1 > 8/24/17 from 5:30 to 8:00 pm > 41 attendees signed-in > Comments: > EAA area > Environmental constraints > Focus
More informationTampa International Airport Master Plan Update. December 12, 2012
Tampa International Airport Master Plan Update December 12, 2012 1 Prior Presentation Consolidated rental car and people mover Decongest curbsides and roadways Enable rental car growth Gain long term parking
More informationPUBLIC NOTICE OF PASSENGER FACILITY CHARGE FOR DENVER INTERNATIONAL AIRPORT
PUBLIC NOTICE OF PASSENGER FACILITY CHARGE FOR DENVER INTERNATIONAL AIRPORT Pursuant to CFR 158.24, the City and County of Denver Department of Aviation ( City ), owner and operator of the Denver International
More informationCHAPTER 3 ALTERNATIVES CONSIDERED
CHAPTER 3 ALTERNATIVES CONSIDERED 3.0 ALTERNATIVES The 2010 Stevensville Airport Master Plan contained five (5) airside development options designed to meet projected demands. Each of the options from
More informationTable of Contents. Overview Objectives Key Issues Process...1-3
Table of Contents Chapter One Introduction Overview...1-1 Objectives...1-1 Key Issues...1-2 Process...1-3 Chapter Two Inventory of Existing Conditions Airport Setting...2-1 Locale...2-1 Airport Surroundings...2-5
More informationPORT OF PORTLAND. Chapter Six AIRPORT PLANS
PORT OF PORTLAND Chapter Six AIRPORT PLANS CHAPTER SIX PORT OF PORTLAND AIRPORT PLANS The planning process for the Hillsboro Airport Master Plan has included several technical efforts as outlined in the
More informationAirport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3
Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Agenda > Introductions > Public Meetings Overview > Working Paper 3 - Facility Requirements > Working Paper 4 - Environmental Baseline
More informationMONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES
MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES Recurring topics emerged in some of the comments and questions raised by members of the
More informationDraft Concept Alternatives Analysis for the Inaugural Airport Program September 2005
Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 3 - Refinement of the Ultimate Airfield Concept Using the Base Concept identified in Section 2, IDOT re-examined
More informationNew PFC Application #13
PUBLIC CONSULTATION New PFC Application #13 Buffalo, NY December 16, 2015 Agenda PFC Program at Notice to Carriers and Consultation Meeting Class of Carrier Not Required to Collect PFC Air Carrier Requirements
More informationTable E-3 Phased Capital Improvement Program...E - 11
Ni ag ar af r ont i e rt r ans por t at i onaut hor i t y Buffa l oni a ga r ai nt e r na t i ona l Ai r por t Execut i vesummar y AI P#33600097010 NF T APr oj ec t#30bg0916 NYS DOTPI N#5913 11 Ma y2013
More informationJUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM JANUARY 25, 2017
JUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM JANUARY 25, 2017 1 Agenda Program Description Runway Incursions Design and Geometry Deficiencies Runway 8/26 Operations Potential Mitigation Next Steps
More informationTallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016
Tallahassee International Airport Master Plan Technical Advisory Committee Meeting #2 October 19, 2016 Agenda Welcome / Introductions Master Plan Process and Project Status Forecast of Aviation Demand
More informationSTUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES
INTRODUCTION An Airport Master Plan provides an evalua on of the airport s avia on demand and an overview of the systema c airport development that will best meet those demands. The Master Plan establishes
More informationGrants Pass Airport Master Plan & Airport Layout Plan Update
Attendees: Grants Pass Airport Master Plan & Airport Layout Plan Update Meeting #3 January 26, 2010 Merlin Community Center 100 Acorn Street, Merlin 5:45 7:15 p.m. Josephine County Department of Airports:
More informationNOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018
NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018 LAWTON-FORT SILL REGIONAL AIRPORT LAWTON, OKLAHOMA PASSENGER FACILITY CHARGE PROPOSED
More informationCHAPTER 1: INTRODUCTION
CHAPTER 1: INTRODUCTION Purpose and Scope The information presented in this report represents the study findings for the 2016 Ronan Airport Master Plan prepared for the City of Ronan and Lake County, the
More informationPULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project
PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project GENERAL AIRPORT INFORMATION AIRPORT USERS Airport ownership: Public, owned by the Pullman-Moscow Regional Airport Board Year opened: February
More informationSAN JOSÉ INTERNATIONAL AIRPORT
SAN JOSÉ INTERNATIONAL AIRPORT NEAR-TERM TERMINAL CAPACITY ANALYSIS AIRPORT COMMISSION AUGUST 14, 2017 August 14, 2017 AGENDA 1. Forecast Review (with 14 MAP High Case) 2. Gate Requirements and Aircraft
More informationAppendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update
Appendix D Project Newsletters Tacoma Narrows Airport Master Plan Update This appendix contains the newsletters distributed throughout the project. These newsletters provided updates and information on
More informationGrove Field Airport Environmental Assessment
Grove Field Airport Environmental Assessment Advisory Committee Meeting #2 December 9, 2008 Port of Camas-Washougal Conference Room 6:00 7:30 PM Agenda: Welcome and Overview Dave Ripp, Director, Port of
More informationChapter 8.0 Implementation Plan
Chapter 8.0 Implementation Plan 8.1 Introduction This chapter is the culmination of the analytical work accomplished in the previous chapters. The result is a prioritized list of the essential projects.
More informationINDEPENDENCE STATE AIRPORT (7S5)
INDEPENDENCE STATE AIRPORT (7S5) Airport Master Plan Update 2018 Planning Advisory Committee PAC Meeting #3 April 11, 2018 1994-2016 AGENDA The second PAC workshop will cover the following topics: Recap
More informationMeeting Notes Public Open House
Meeting Notes Public Open House, 5:30-8:00 pm Fairbanks Pipeline Training Center, 3605 Cartwright Court, Fairbanks, Alaska= Agenda: Open House: 30 minutes Presentation: 45 minutes Question and Answers:
More informationAIRPORT DEVELOPMENT PLAN. Design-Build Institute of America September 8, 2015
AIRPORT DEVELOPMENT PLAN Design-Build Institute of America September 8, 2015 Lindbergh Field - 1935 3 Page 2 Lindbergh Field - 1944 3 Page 3 Lindbergh Field - 1955 3 Page 4 San Diego International Airport
More informationCity of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan. Public Workshop #2 April 19, 2018
City of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan Public Workshop #2 April 19, 2018 DISCUSSION TOPICS Introduction About the Master Plan Public Workshop #1 Recap
More informationTable of Contents. Master Plan March 2014 TOC i Spokane International Airport
Table of Contents Page Chapter 1 Inventory 1. Introduction... 1 1 1.1 Community Profile... 1 2 1.1.1 Location and Setting... 1 1 1.1.2 Climate... 1 2 1.1.3 Socioeconomic Conditions... 1 5 1.1.4 Area Land
More informationHILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Meeting 1
HILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Meeting 1 Feb. 27, 2017 HILLSBORO AIRPORT MASTER PLAN UPDATE Planning Advisory Committee Welcome Curtis Robinhold, Port of Portland 1 HILLSBORO
More informationJUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM. April 10 th 2017
JUNEAU RUNWAY INCURSION MITIGATION (RIM) PROGRAM April 10 th 2017 1 Agenda Recap Potential Mitigation Response to Stakeholder Questions Next Steps 2 Recap 3 Background Master Plan considered the runway
More informationChapter Seven COST ESTIMATES AND FUNDING A. GENERAL
Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL This chapter delineates the recommended 2005 2024 Sussex County Airport Capital Improvement Program (CIP). It further identifies probable construction
More informationINFORMATION PAPER TO THE STRATEGIC DEVELOPMENT COMMITTEE
INFORMATION PAPER TO THE STRATEGIC DEVELOPMENT COMMITTEE BRIEFING ON RONALD REAGAN WASHINGTON NATIONAL AND WASHINGTON DULLES INTERNATIONAL AIRPORTS CAPITAL CONSTRUCTION PROGRAM APRIL 2015 2015 Use & Lease
More informationMEETING SUMMARY. Project: Ted Stevens Anchorage International Airport (ANC) Master Plan Update. Location: Anchorage North Terminal Room NA165
MEETING SUMMARY Project: Ted Stevens Anchorage International Airport (ANC) Master Plan Update RS&H Project #: 226-2566-000 Subject: Technical Advisory Committee Meeting #3 Location: Anchorage North Terminal
More informationRegular Board Meeting August 4, 2015
Regular Board Meeting August 4, 2015 1616 Airport Circle Hailey, ID 83333 208.788.4956 PUBLIC COMMENT FY 16 Rates & Charges FY 16 Budget Approval Rates & Charges will provide the Board the ability to operate
More informationCHAPTER FOUR AIRPORT ALTERNATIVES
4.0 INTRODUCTION CHAPTER FOUR The goal of the master planning process is to provide the City of New Smyrna Beach with an assessment of the adequacy and capabilities of the Airport as well as to identify
More information