1 GARFIELD BRIDGE Building A Bridge to No-Where

2 OCEANA COUNTY

3 LOCATION Garfield Road leads to Stony Lake Outlet, a Benona Township park and popular Lake Michigan access

4

5 GARFIELD BRIDGE OVER STONY CREEK STONY CREEK OUTLET PARK (THE OVAL) STONY LAKE PARK

6 LOCATION Garfield Road leads to Stony Lake Outlet, a Benona Township park and popular Lake Michigan access The Bridge over Stony Creek is the only access to the township park

7 LAKE MICHIGAN AT STONY CREEK OUTLET

8 LAKE MICHIGAN AT STONY CREEK OUTLET

9 LOCATION Garfield Road leads to Stony Lake Outlet, a Benona Township park and popular Lake Michigan access The Bridge over Stony Creek is the only access to the township park The park contains one of Oceana County s 2 boat access points to Lake Michigan

10

11

12 HISTORY A Road Commission truck went through a wooden structure in the early 30 s

13

14

15 HISTORY A Road Commission truck went through a wooden structure in the early 30 s In the?early 1950 s? a 9 10 by 14 2 by 20 long Steel culvert was installed. This provided a wide 1 lane access to the park. A letter from MDNR in 1980 states that the culvert is undersized, but assumes that it was properly sized at installation years before.

16

17 SHOWING RESTRICTION (Hydraulic Jump Upstream end of Culvert)

18 SHOWING RESTRICTION (Hydraulic Jump Upstream end of Culvert)

19 HISTORY In the 1970 s, 80 s and through out the 90 s, minor cave-ins have been experienced on both approaches. A storm in 1998 caused severe erosion on the site. At this time a through inspection of the structure was done. Findings were not good. Severe under mining was present on both ends of the culvert

20 HISTORY Brechting Bridge & Engineering, Inc. was hired to scope the site for possible solutions. Recommendations were replacement with a Conspan (3 sided frame culvert), or a timber bridge. The 3 sided culvert was settled upon due to the flexibility of adjusting the road grade

21

22

23

24 HISTORY Road Commission, Benona Township, WMSRDC representatives met in early 1999 to address the culvert. All supported culvert replacement and park enhancement, and began applying for grants to fund the construction of these as a combined project.

25 Funding Applied For Numerous grants & funding sources were applied for & denied, including: Critical Bridge not a bridge because of 14 span of existing culvert WMSRDC, MDNR, CMI, GLFT,- Not Applicable Township Primary Road, and they were upgrading park, they couldn t handle both

26 HISTORY Meanwhile nature continued to tear apart the road

27

28

29 HISTORY Meanwhile nature continued to tear apart the road Different storms further eroded the site In 2000 alone, $22,133 was spent on restoration after a storm event

30 HISTORY At the end of 2002, the culvert replacement appeared to be a dead project. Everybody still wanted it, but nobody could afford it. The project had grown to an estimated $434,000 ($320,000 was for the structure replacement) Benona Township stated they were committed to park improvements regardless if the culvert was replaced or not. They began to secure their own funding.

31 HISTORY In 2004, various agencies & individuals pressed the Road Commission to improve the culvert. Most of this was because the township was improving the park. (They built a boardwalk in late 2003 & were working on the parking lot) The Road Commission made one last look for economical alternatives for replacement County work crews had done several timber decks in the previous years with little difficulty, so the timber bridge option was seriously looked into

32 HISTORY Krenn Bridge Companies, Inc. was contacted to review the site & rough quote timber bridge materials. Using the County s workforce, the project seemed feasible.

33 ESTIMATED Costs Wood Structure $ 84,500 Pile Driver $ 27,000 Misc. Materials $ 5,500 Labor & Equipment $ 83,800 Asphalt $ 6,000 TOTAL $206,800 Precast Concrete $320,000

34 HISTORY Krenn Bridge Companies, Inc. was contacted to review the site & rough quote timber bridge materials. Using the County s workforce, the project seemed feasible. Also Benona Township and MDEQ was in favor of the timber bridge

35 HISTORY In 2005, the Road Commission contracted with Krenn Bridge companies to deliver materials for a timber structure.

36

37

38 HISTORY In 2005, the Road Commission contracted with Krenn Bridge companies to deliver materials for a timber structure. Work began in October 2005.

39 JUST STARTING WORK

40 WEST SIDE REMOVALS

41 VIEW OF CHANNEL UPSTREAM

42 PILING SET ON THE W. SIDE PIER AND HEADWALL

43 VIEW OF OLD CULVERT

44 FALL OF 05

45 MARCH 16, 2006

46 TOOL CRIB AND MATERIAL HANDLER

47 BUNDLE OF MATERIAL 1 OF 5

48 LOOKING CREEK FROM E. DAY 1

49 DAY 1 DEADMEN AND PILING

50 PILING BEING CABLED OFF AND CUT

51 PILING OF E. HEADWALL

52 DAY 2 SHOWING PILING CAP IN PLACE

53 HEADWALL STARTED DAY 3

54 NEARING COMPLETION OF E. HEADWALL

55 FABRIC BEING INSTALLED

56 FABRIC IN PLACE AND TIE-BACK RINGS INSTALLED, DAY 5

57 THIS WOULD BE CALLED JOB PERKS

58 LOOKING E. SHOWING HEADWALL

59 TUG AND PULL, PULL AND TUG!!!!

60 THE WRENCH IS FOR THE BOLTS, NOT A FISH CLUB!!!

61 EAST PIER SHOWING HEAVY CROSS BRACING

62 OH $#!?, I HAD THE PLANS UPSIDE DOWN

63 SETTING THE FIRST PANEL

64 CHECK OUT THAT STEELHEAD

65 WORK ON LAND

66 COMPLETED FIRST SPAN, SPREADER BEAM, HEADWALL, AND DECK

67 DETAILS, DETAILS, DETAILS!!!!

68 SHOT LOOKING W. SHOWING W. PIER AND HEADWALL

69 FIRST CENTER SPAN PANEL SET DAY 10

70 INSTALLING LOAD TRANSFER (SPREADER) BEAM

71 ANCHORING CENTER SPAN TO CAPS AND PIER

72 SKID SHOWING SOME OF THE HARDWARE

73 TOOLS USED

74 SHOT OF CENTER SPAN WITH SPREADER BEAM INSTALLED

75 ANOTHER VIEW OF SPREADER BEAM IN PLACE

76 SETTING ANOTHER PANNEL

77 MOST IMPORTANT TOOLS HAMMER DRILL & SLEDGE

78 HIT IT MIKE

79 CENTER DECK SPAN ALMOST COMPLETED

80 MORE DRILLING AND POUNDING

81

82 LOOKING W. FROM THE CENTER SPAN

83 SQUARING THINGS UP AS WE GO

84 LOOKING DOWNSTREAM NEAR THE END OF DAY 13

85 INSTALLING W. WING WALL PLANKS

86 WORK PROGRESSING ON THE W. HEADWALL

87 GOT TO GO DEEPER

88 EXCAVATION MOVIE

89 NOW THE LAST BOARD WILL FIT

90 COMPLETED W. HEADWALL

91 MAKING GOOD PROGRESS

92 GETTING LAST DECK PANEL READY FOR INSTALLATION

93 AT LAST WE HAVE A BRIDGE AGAIN

94 SHOT SHOWING FULL SPAN W/SCUPPERS AND REINFORCING RINGS

95 CLOSE-UP SHOWING SCUPPERS AND RINGS

96 GETTING CURBING STARTED

97 STARTING TO LOOK LIKE A BRIDGE

98 LOOKING E. SHOWING GUARDRAIL POSTS AND WINGWALL

99 AGAIN LOOKING W. TOWARDS LAKE MICHIGAN

100 EROSION CONTROL IN PLACE

101 AGAIN LOOKING E.

102 LOOKING W. TOWARDS LAKE MICHIGAN LAST DAY

103 N. VIEW OF STRUCTURE

104 S. VIEW OF STRUCTURE

105 NEW IMPROVED FLOW LINE OF CREEK

106 PRECONSTRUCTION (Hydraulic Jump Upstream end of Culvert)

107 GOOD JOB GUYS

108 LAST DAY SHOWING FINAL PRODUCT

109 Actual Costs Wood Structure $ 84, Pile Driver $ 27, Misc. Materials $ 8, Labor Equipment $ 65, Asphalt $ 8, TOTAL $193, Precast Concrete Estimate $320,000

110

111 QUESTIONS?

The Holes Creek Bridge Replacement By Bradley McClelland

The Holes Creek Bridge Replacement By Bradley McClelland The Holes Creek Bridge Replacement By Bradley McClelland Each time there is a heavy rainstorm, the folks along Sheffield Road in the Dayton, Ohio suburb of West Carrollton have cause to be concerned. Holes

More information

Mason Street Bike/Pedestrian Trail Project

Mason Street Bike/Pedestrian Trail Project Construction of the much-anticipated Mason Trail is underway! Mountain Constructors was awarded the contract in September but had to go through a 2- month process to obtain construction clearance permits

More information

Installation Instructions

Installation Instructions Installation Instructions Hex Sierra TopTec Products, LLC 7061 Highway 221 Moore, SC 29369 Phone: (800) 845-2830 Fax: (800) 921-7750 e-mail: sales@toptecproducts.com www.toptecproducts.com 2004 TopTec

More information

Hospital Link Project Project Update September 2015

Hospital Link Project Project Update September 2015 Hospital Link Project Project Update September 2015 General The project provides a link between Riverside Drive and the Transitway to the Hospital Ring Road. This link is needed to improve transit service

More information

TENDER NO. T WESTDALE ROAD SANITARY SEWER UPGRADE ADDENDUM NO. 1

TENDER NO. T WESTDALE ROAD SANITARY SEWER UPGRADE ADDENDUM NO. 1 TENDER NO. T-2170-2018 ADDENDUM NO. 1 SCHEDULE OF QUANTITIES AND PRICES REPLACE A revised copy of the Schedule of Quantities and Prices with changes bolded in red has been posted online (pdf attached).

More information

Stories from Maritime America

Stories from Maritime America Sam Casarez Sam Casarez describes his experiences as a junior engineer aboard a Liberty ship during World War II. Engine room training I trained for the engine room. You could train for the engine room

More information

INSTRUCTION MANUAL ALEKO RETRACTABLE AWNING

INSTRUCTION MANUAL ALEKO RETRACTABLE AWNING INSTRUCTION MANUAL for ALEKO RETRACTABLE AWNING www.alekoproducts.com FAILURE TO FOLLOW THESE INSTRUCTIONS MAY RESULT IN PERSONAL INJURY! 1 Important Safety Precautions WARNING NOTE: FOR PERSONAL SAFETY,

More information

2015 COVER COLLECTION

2015 COVER COLLECTION 2015 COVER COLLECTION 25 years The Cover Company has been manufacturing the highest quality covers available for 25 years. We are a family run business that prides itself on quality manufacturing, products,

More information

Photographic Log Client: Project Number: Site Location: Site Name: Photograph ID: Date: Location: Direction: Comments: Photograph ID:

Photographic Log Client: Project Number: Site Location: Site Name: Photograph ID: Date: Location: Direction: Comments: Photograph ID: Photograph ID: 1 west View of one of the monitoring well and the large parking lot on the south side of Center Street. Photograph ID: 2 Monitoring well located in the middle of the parking lot located

More information

DRAFT. Dorabelle Campground Rehabilitation

DRAFT. Dorabelle Campground Rehabilitation DRAFT Dorabelle Campground Rehabilitation September 2012 1.1 REGIONAL SETTING AND PROJECT LOCATION The Dorabelle Campground is located on the western shore of Shaver Lake in Fresno County, California (Section

More information

Hydraulic Report. Trail 5 Snowmobile Trail Over Mulligan Creek. Prepared By: COLEMAN ENGINEERING COMPANY Karisa V. Falls, P.E.

Hydraulic Report. Trail 5 Snowmobile Trail Over Mulligan Creek. Prepared By: COLEMAN ENGINEERING COMPANY Karisa V. Falls, P.E. Prepared for: Prepared by: Marquette County Road Commission Coleman Engineering Company Marquette, Michigan Iron Mountain, MI December 2011 Hydraulic Report Trail 5 Snowmobile Trail Over Mulligan Creek

More information

Crew Chief: Start Date: Completion Date: T & A Code:

Crew Chief: Start Date: Completion Date: T & A Code: Completed Work Data Work order # Crew Chief: Start Date: Completion Date: T & A Code: Work Complete Comments: Personnel Service: Equipment: Item ID# Hours/Miles Rental Cost Supplies & Materials: Item Invoice#

More information

Recommendation: THAT the Council of the Township of Centre Wellington award the following two tenders:

Recommendation: THAT the Council of the Township of Centre Wellington award the following two tenders: Report to Council To: Mayor Linton and Members of Council Prepared By: Wes Snarr, Managing Director of Corporate Services Report: COR-45 Date: 12 Jul RE: Recomendation for Award of Request for Tenders

More information

Tenders. Manitoba Infrastructure

Tenders. Manitoba Infrastructure Tenders Manitoba Heavy Construction Association Unit 3-1680 Ellice Ave. Winnipeg, MB R3H 0Z2 Tel: (204) 947-1379 Fax: (204) 943-2279 www.mhca.mb.ca Email: jocelyn@mhca.mb.ca Manitoba Infrastructure Reference

More information

Ohio Department of Transportation Construction Update

Ohio Department of Transportation Construction Update Ohio Department of Transportation Construction Update DISTRICT 5 DAVE RAY, P.E., P.S., DISTRICT DEPUTY DIRECTOR 9600 Jacksontown Road Jacksontown, OH 43030 www.transportation.ohio.gov/dist5 ODOT District

More information

Boardman River Dams Implementation Team. DRAFT Meeting Minutes

Boardman River Dams Implementation Team. DRAFT Meeting Minutes Location: Traverse City Governmental Center, Commission Chambers 400 Boardman Avenue Traverse City, MI 49684 Boardman River Dams Implementation Team Grand Traverse County Traverse City Light and Power

More information

DISTRICT PARISH STATE OF LOUISIANA DEPARTMENT OF TRASNPORTATION AND DEVELOPMENT BRIDGE INSPECTION REPORT ROUTE STRUCTURE NUMBER Form 3097_PO 09/2012 Page 1 of RECALL NUMBER CROSSING DESCRIPTION LENGTH

More information

Alien Flier Zip Line Products Installation/Owner s Manual

Alien Flier Zip Line Products Installation/Owner s Manual Alien Flier Zip Line Products Installation/Owner s Manual 1 Table of Contents SAFETY PLEASE READ CAREFULLY... 4 Constructing your Zip Line Xtreme Models... 6 Installing your Alien Flier Trolley on an Existing

More information

TITAN Fuel Tanks. INSTALLATION INSTRUCTIONS G e n e r a t i o n V

TITAN Fuel Tanks. INSTALLATION INSTRUCTIONS G e n e r a t i o n V TITAN pt. no.: 02 0000 0128 Important: Please read these instructions carefully and completely before starting the installation. TITAN Fuel Tanks INSTALLATION INSTRUCTIONS G e n e r a t i o n V Extended

More information

TECHNICAL INSTRUCTION MANUAL: TRADITIONAL PARTY CANOPIES

TECHNICAL INSTRUCTION MANUAL: TRADITIONAL PARTY CANOPIES 1. Inspect the site and make sure the area is level, free of underground utilities and any overhead obstructions. Unload poles and tent bundles. Assembly (20'x20' Shown) 2. Lay the canopy out, on a ground

More information

Community Park Capital Project. February 6, 2017

Community Park Capital Project. February 6, 2017 Community Park Capital Project February 6, 2017 Construction Budget Estimate Bid Recommended $10,318,690 $7,725,000 Staff Recommended +$1.1M $8,850,000 +$2.6M -$1.47M Pre-Bid Estimate 11/22/2016

More information

IMPORTANT OWNER-OPERATOR INSTALLATION INSTRUCTIONS C2213 / C2220

IMPORTANT OWNER-OPERATOR INSTALLATION INSTRUCTIONS C2213 / C2220 IMPORTANT OWNER-OPERATOR INSTALLATION INSTRUCTIONS C2213 / C2220 Minor movement (or settling) can occur in some incidental harsh driving conditions (On or off road). A rubber bed mat is not a requirement

More information

CONVEX Awning Instructions

CONVEX Awning Instructions CONVEX Awning Instructions IMPORTANT NOTE: Please take a few minutes to become familiar with this entire document BEFORE beginning your installation. The time you spend doing this is well spent and will

More information

Design and Construction of the Lake St. Martin Emergency Outlet

Design and Construction of the Lake St. Martin Emergency Outlet Design and Construction of the Lake St. Martin Emergency Outlet Background 2011 was the largest flood event experienced in the last 200 years Flood Fighting required some difficult decisions by the Manitoba

More information

BUILD. Update CONSTRUCTION. In this issue: FEATURED PROJECT: KENT AVENUE ARCH CONSTRUCTION AT THE SJ RIVER VIADUCT FEBRUARY 2019

BUILD. Update CONSTRUCTION. In this issue: FEATURED PROJECT: KENT AVENUE ARCH CONSTRUCTION AT THE SJ RIVER VIADUCT FEBRUARY 2019 BUILD CONSTRUCTION Update FEBRUARY 2019 In this issue: ARCH CONSTRUCTION AT THE SJ RIVER VIADUCT FEATURED PROJECT: KENT AVENUE * Featured Project KENT AVENUE CP 2-3 CONSTRUCTION UPDATE February 2019 At

More information

Project A: Revetment Scale: 1 = 10. 3/7 Revision: Benchmarks. Eroding Parking Area. View from Above. Locklies Creek. Ebb.

Project A: Revetment Scale: 1 = 10. 3/7 Revision: Benchmarks. Eroding Parking Area. View from Above. Locklies Creek. Ebb. Project A: Revetment Scale: 1 = 10 View from Above Floating Dock 3/7 Revision: Benchmarks 34 Locklies Creek Ebb Flood E. 18x8 Floating Dock Channelward of Vegetation 30 Class A1A Rip Rap MLW MHW 57 1 4

More information

Standard Awning Installation Instructions

Standard Awning Installation Instructions Standard Awning Installation Instructions Important Note: Please become familiar with this entire document BEFORE beginning your installation. The time you spend doing this is well spent and will make

More information

COATING AND STRUCTURAL CONCRETE COATING (ANTI-GRAFFITI) 1'-3" FINISHED GRADE 1'-3" 3" VENEER ALLOWANCE LEDGER W/ MECHANICAL ANCHOR BOLT

COATING AND STRUCTURAL CONCRETE COATING (ANTI-GRAFFITI) 1'-3 FINISHED GRADE 1'-3 3 VENEER ALLOWANCE LEDGER W/ MECHANICAL ANCHOR BOLT R "W" PAY LIMITS OF ITEM 601 PAY LIMITS OF ITEM 601 STRUCTURAL CONCRETE STRUCTURAL CONCRETE 1'3" PCBC END SEGMENT B C 1'3" COATING AND STRUCTURAL CONCRETE COATING (ANTIGRAFFITI) 1'3" CURB FINISHED GRADE

More information

July 5, Re: Contract ID Plan, & Proposal July 11, 2017 Letting. The Contractor is hereby advised of modifications to the bid documents.

July 5, Re: Contract ID Plan, & Proposal July 11, 2017 Letting. The Contractor is hereby advised of modifications to the bid documents. July 5, 2017 Dear Prospective Bidders: Re: Contract ID 2688050 Plan, & Proposal July 11, 2017 Letting The Contractor is hereby advised of modifications to the bid documents. The Proposal has been modified:

More information

WAIMAKARIRI DISTRICT COUNCIL REPORT. Craig Sargison, Manager Community and Recreation

WAIMAKARIRI DISTRICT COUNCIL REPORT. Craig Sargison, Manager Community and Recreation WAIMAKARIRI DISTRICT COUNCIL REPORT FILE NO: GOV-26-01-07, CPR-04-04-01 / 150609090834 REPORT TO: Kaiapoi Community Board DATE OF MEETING: 15 June 2015 FROM: SUBJECT: Craig Sargison, Manager Community

More information

Agenda Report. Spruce Street Outlet Drainage Improvements Tower Road Relief Sewer

Agenda Report. Spruce Street Outlet Drainage Improvements Tower Road Relief Sewer Agenda Report Subject: Prepared By: Spruce Street Outlet Drainage Improvements Tower Road Relief Sewer Steven M. Saunders, Director of Public Works/Village Engineer Date: August 12, 2012 On March 8, 2012

More information

The combined Planning and Zoning and Council Meeting was called to order at 7:00 p.m.

The combined Planning and Zoning and Council Meeting was called to order at 7:00 p.m. Lake Remediation Master Plan The combined Planning and Zoning and Council Meeting was called to order at 7:00 p.m. Roll Call: Councilman Joe Curl, Councilwoman Tiffany Hughes, Councilwoman Lori Howard,

More information

Sample Estimate Reports Estimate Reports were created in XL-Pro Software

Sample Estimate Reports Estimate Reports were created in XL-Pro Software Sample Estimate Reports Estimating Pro Software Estimate Reports were created in XL-Pro Software / TIME EQUIP.. COST* AMOUNT - 1 GENERAL REQUIREMENTS 1.00 LSUM - INSURANCE - general liability 1.00 lsum

More information

The Covered Bridge of Pepperell

The Covered Bridge of Pepperell The Covered Bridge of Pepperell 1742 - An uncovered wooden bridge historically referred to as the cart bridge at Joseph Blood s Fordway, links Groton West Parish and Groton. Cost Unknown 1753 - As Pepperell

More information

Astoria Boulevard ADA Upgrade and Station Renewal. January 7, 2019

Astoria Boulevard ADA Upgrade and Station Renewal. January 7, 2019 Astoria Boulevard ADA Upgrade and Station Renewal January 7, 2019 Major Scope of Work Replace Street and Platform Stairs Work Description Install Two Street-to-Mezzanine Elevators Install Two Mezzanine-to-Platform

More information

Datum on benchmarks All benchmarks with a Township name and number are on 1929 datum:. All benchmarks with a four-digit number are on 1988 datum:

Datum on benchmarks All benchmarks with a Township name and number are on 1929 datum:. All benchmarks with a four-digit number are on 1988 datum: Datum on benchmarks All benchmarks with a Township name and number are on 1929 datum:. All benchmarks with a four-digit number are on 1988 datum: LAWRENCE 2 Destroyed 8/29/05 TG General coordinates: 10800E

More information

SS SERIES STAINLESS STEEL SLIDE GATE

SS SERIES STAINLESS STEEL SLIDE GATE SS-250-1 SERIES STAINLESS STEEL SLIDE GATE THE BEST OF TECHNOLOGY FOR STRENGTH AND LONGEVITY IN CORROSIVE ATMOSPHERES 304 OR 316 STAINLESS STEEL WITH UHMW PLASTIC SLIDING AND SEATING SURFACES MEETS LEAKAGE

More information

BUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018

BUILD. In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4. August 2018 BUILD C O N ST R U C T I O N Update August 2018 In this issue: NEW AERIALS OF CONSTRUCTION NEW PROJECT IN CONSTRUCTION PAC K AG E 4 AVENUE 12 CEDAR VIADUCT A VIEW FROM ROAD 27 ABOVE HSR CONSTRUCTION FRESNO

More information

IS A BUDGET ONLY DESCRIPTION QUANTITY UNIT

IS A BUDGET ONLY DESCRIPTION QUANTITY UNIT Miller Creek Consultants LLC CONCRETE RECAP 1/29/2009 ESTIMATE DATE: 1-Jan-09 Project: 4000 psi 95.00 Location: 3000 psi 88.00 PROJECT DATA PROJECT NAME: Concrete Estimate THIS IS A BUDGET ONLY DESCRIPTION

More information

Side Posts. Galaxy. Orion. Polaris. Astral-TC Brooks Drive Baldwin Park, CA p f

Side Posts. Galaxy. Orion. Polaris. Astral-TC Brooks Drive Baldwin Park, CA p f OTHER SHADEMAKER STYLES AVAILABLE Side Posts Polaris Orion Center Posts Corona Galaxy Beam Mount Astral-TC Nova 13401 Brooks Drive Baldwin Park, CA 91706 p 626.338.8810 f 626.338.8816 info@shademakerusa.com

More information

4 Corner Section. 4x8. 4x12. 4x16. 5x8. 5x12. 5x16. The Dock-Lock. Standard Dock Sizes

4 Corner Section. 4x8. 4x12. 4x16. 5x8. 5x12. 5x16. The Dock-Lock. Standard Dock Sizes Aqua Lounge OUR COMMITMENT TO QUALITY Aqua Lounge Producing superior products at competitive prices is our goal here at Aqua Lounge. We are not content with duplicating products already available on today

More information

Hancock. Hancock. Hancock County Population 54,558. Land Area (sq mi) 1,587 Bridges 120 Highway Corridor Priority Miles HCP 1 81 HCP 2 34

Hancock. Hancock. Hancock County Population 54,558. Land Area (sq mi) 1,587 Bridges 120 Highway Corridor Priority Miles HCP 1 81 HCP 2 34 Hancock Hancock County Population 54,558 T3 ND Oqiton Twp Land Area (sq mi) 1,587 Bridges 120 Highway Corridor Priority Miles T41 MD 81 HCP 2 34 T39 MD T40 MD 141 HCP 4 62 215 Total -5 533 T32 MD Great

More information

User s Manual Trampoline 8

User s Manual Trampoline 8 User s Manual Trampoline 8 Model! WARNING Read all precautions and instructions in this manual before using this equipment. Save this manual for future reference. Maximum user weight 17 lbs. ASSEMBLY IMPORTANT

More information

County of Fairfax, Virginia. Silver Line Update. Committee for Dulles March 2, Mark Canale Fairfax County Department of Transportation

County of Fairfax, Virginia. Silver Line Update. Committee for Dulles March 2, Mark Canale Fairfax County Department of Transportation Silver Line Update Committee for Dulles March 2, 2017 Mark Canale Fairfax County Department of Transportation Phase 1 Summary Old Meadow Road Realignment design work proceeding, construction to be completed

More information

13401 Brooks Drive Baldwin Park, CA p f shademakerusa.com

13401 Brooks Drive Baldwin Park, CA p f shademakerusa.com 13401 Brooks Drive Baldwin Park, CA 91706 p 626.338.8810 f 626.338.8816 info@shademakerusa.com shademakerusa.com 2018 Shademaker. All rights reserved. SMOM-POLARIS-1018 W A R R A N T Y : Upon receipt of

More information

13401 Brooks Drive Baldwin Park, CA p f shademakerusa.com

13401 Brooks Drive Baldwin Park, CA p f shademakerusa.com 13401 Brooks Drive Baldwin Park, CA 91706 p 626.338.8810 f 626.338.8816 info@shademakerusa.com shademakerusa.com 2018 Shademaker. All rights reserved. SMOM-LIBRA-0718 W A R R A N T Y : Upon receipt of

More information

Barnsley, Dearne & Dove Canals Trust HS2 Mitigation Options

Barnsley, Dearne & Dove Canals Trust HS2 Mitigation Options Page 1 of 13 Barnsley, Dearne & Dove Canals HS2 Mitigation Options December 2013 Elsecar Branch, Top Pound Prepared by Ulrich Signer, Director, BDDCT Mike Silk, Engineer, BDDCT The Barnsley, Dearne and

More information

Assembly Instructions: Square Tile Fire Pit With Embossed Side Panels

Assembly Instructions: Square Tile Fire Pit With Embossed Side Panels Assembly Instructions: Square Tile Fire Pit With Embossed Side Panels FT501PTESMLID Part List Part List Description Qty. Drawings Part # A Mantle Frame 1 8-07-00158-01-055 B Side Panel 4 8-20-00059-01-077

More information

Striving for resilience in the face of climate change

Striving for resilience in the face of climate change Striving for resilience in the face of climate change Three years and eight months have elapsed since the country suffered one of its worst flooding events, affecting a couple of districts mainly in east-south

More information

YORKSHIRE 48 OR 52 CARTON 1 CARTON 2 CARTON 3. Description Part No BLUE LAGOON WALL 12 BLUE LAGOON WALL

YORKSHIRE 48 OR 52 CARTON 1 CARTON 2 CARTON 3. Description Part No BLUE LAGOON WALL 12 BLUE LAGOON WALL CARTON 1 CARTON 2 CARTON 3 YORKSHIRE Part # 420860 ROUND PACKING LIST Description Part No. 8 21 24 27 30 33 8 BLUE LAGOON WALL 48 1492 52 1327 1 - - - - - - - - BLUE LAGOON WALL 48 1493 52 1328-1 - - -

More information

BID FORM. Bid by: Name of Bidder. Address: Address: To the Texas Department of Transportation hereinafter called the Agent.

BID FORM. Bid by: Name of Bidder. Address:  Address: To the Texas Department of Transportation hereinafter called the Agent. BID FORM TxDOT CSJ No. Project Description: This project includes reconstruction of a hangar access taxiway with trench drain and pipe drainage system; local reconstruction of failing pavement on Taxiway

More information

Poly Shelters. Instruction Manual. Sunblocker Shade House 10' Wide x 30' Long SKU #1030SPC. Note: Photo may be of a different but similar model

Poly Shelters. Instruction Manual. Sunblocker Shade House 10' Wide x 30' Long SKU #1030SPC. Note: Photo may be of a different but similar model Poly Shelters Note: Photo may be of a different but similar model Instruction Manual Sunblocker Shade House 10' Wide x 30' Long SKU #1030SPC 2004 ClearSpan TM All rights reserved. Reproduction prohibited

More information

ASTM E 1886 and ASTM E 1996 TEST REPORT. Report No.: A Rendered to: CORAL ARCHITECTURAL PRODUCTS Tuscaloosa, Alabama

ASTM E 1886 and ASTM E 1996 TEST REPORT. Report No.: A Rendered to: CORAL ARCHITECTURAL PRODUCTS Tuscaloosa, Alabama Architectural Testing ASTM E 1886 and ASTM E 1996 TEST REPORT Report No.: A2651.02 401 44 Rendered to: CORAL ARCHITECTURAL PRODUCTS Tuscaloosa, Alabama PRODUCT TYPE: 90 Corner Curtain Wall SERIES/MODEL:

More information

Model 698/ and Model in 1 Hose Reel Owner s Manual

Model 698/ and Model in 1 Hose Reel Owner s Manual Model 698/694 200 and Model 706 100 4 in 1 Hose Reel Owner s Manual 698/694 706 VISIT OUR WEBSITE: WWW.LIBERTYGARDENPRODUCTS.COM OR CALL US TOLL FREE AT 1-866-820-5805 LIBERTY GARDEN PRODUCTS, INC. 500

More information

Indiana Department of Natural Resources / Division of Water

Indiana Department of Natural Resources / Division of Water The Department of Natural Resources is providing this report to satisfy the requirements of the "Procedures Concerning Certain Licenses Act", IC 14-11-4, and its associated administrative rule, 312 IAC

More information

ALEKO Victoria Series Retractable Awning Instructions for Installation and Operation

ALEKO Victoria Series Retractable Awning Instructions for Installation and Operation www.alekoproducts.com ALEKO Victoria Series Retractable Awning Instructions for Installation and Operation PLEASE DO NOT RETURN THIS PRODUCT TO THE STORE! The owner s manual includes assembly and operating

More information

Community Services Associates, Inc. (CSA) Maintenance, Enhancements and Major Projects Committee March 1 st, 2018

Community Services Associates, Inc. (CSA) Maintenance, Enhancements and Major Projects Committee March 1 st, 2018 Community Services Associates, Inc. (CSA) Maintenance, Enhancements and Major Projects Committee March 1 st, 2018 On Thursday, March 1 st 2018, a regular meeting of the Maintenance, Enhancements and Major

More information

The Covered Bridges of Preble County. Past, Present and Future By: R. Kyle Cross, P.E., P.S.

The Covered Bridges of Preble County. Past, Present and Future By: R. Kyle Cross, P.E., P.S. The Covered Bridges of Preble County Past, Present and Future By: R. Kyle Cross, P.E., P.S. The History of the 8 Covered Bridges There are 8 covered bridges in Preble County. Only 2 of them are moved for

More information

Oil By-Pass Filter Installation. By: Woodnthings8

Oil By-Pass Filter Installation. By: Woodnthings8 Oil By-Pass Filter Installation By: Woodnthings8 Keeping clean oil in a 7.3L Powerstroke is probably the most important thing you can do to increase longevity and decrease wear. The oil filter installed

More information

The Two-Row Cultivator Converted into a Weed Control Machine

The Two-Row Cultivator Converted into a Weed Control Machine South Dakota State University Open PRAIRIE: Open Public Research Access Institutional Repository and Information Exchange Bulletins South Dakota State University Agricultural Experiment Station 8-1-1936

More information

LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE. CALABASAS CITY COUNCIL April 26, 2017

LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE. CALABASAS CITY COUNCIL April 26, 2017 LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE CALABASAS CITY COUNCIL LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Construction of CIDH piles for the soundwall foundation commenced on March 20

More information

Del Cobre Playground Replacement Cost Proposals

Del Cobre Playground Replacement Cost Proposals Del Cobre Playground Replacement Cost Proposals Proposal 1 (Exact duplicate replacement of Timberform structure): Demolition/Removal by City: $1,949.66 Material (Structure): $44,267.00 Installation (Including

More information

GET YOUR RENTAL BUSINESS UP TO SPEED

GET YOUR RENTAL BUSINESS UP TO SPEED GET YOUR RENTAL BUSINESS UP TO SPEED RENTAL SOLUTIONS the Wenger rental line other rental lines WENGER INNOVATION MAKES INVENTORY RENTAL SOLUTIONS STRATA TENT FLOOR SYSTEM The any tent, anywhere, anytime

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg)

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg) RELEASE: IMMEDIATE March 1, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 3 March 9, 2019 All work is scheduled weather permitting. Real-time information

More information

Dinoot Trailer Building Overview Revision /30/16

Dinoot Trailer Building Overview Revision /30/16 Dinoot Trailer Building Overview Revision 1.3 01/30/16 Dinoot trailers are a straightforward DIY project which can be completed with basic tools; although a few optional tools make things easier and faster.

More information

Door Bushing Replacement & Latch Adjustment Monaco Group Coaches

Door Bushing Replacement & Latch Adjustment Monaco Group Coaches Door Bushing Replacement & Latch Adjustment Monaco Group Coaches Contents Door Latch Adjustment & Repair... 1 Symptoms:... 1 Replacing the bushing VS. Adjusting the latch rods.... 1 How the bushing works....

More information

Head Pond Connector Trail Final Report Project Area: From Head Pond in Berlin to Rt. 110B in Milan

Head Pond Connector Trail Final Report Project Area: From Head Pond in Berlin to Rt. 110B in Milan Milan Trail Huggers ATV Club P.O. Box 42 Milan, NH 03588 Maintaining Trails in Milan, Stark and Dummer Head Pond Connector Trail Final Report Project Area: From Head Pond in Berlin to Rt. 110B in Milan

More information

Elite Party Canopy: Stylish backyard canopies with a distinctive peaked roof and optional color band.

Elite Party Canopy: Stylish backyard canopies with a distinctive peaked roof and optional color band. Elite Party Canopy: Stylish backyard canopies with a distinctive peaked roof and optional color band. Elite Party Canopy Construction Features: 13-14 oz.vinyl laminate tent fabric Anodized sectional aluminum

More information

Welcome KROSNO CREEK DIVERSION PROJECT CLASS ENVIRONMENTAL ASSESSMENT

Welcome KROSNO CREEK DIVERSION PROJECT CLASS ENVIRONMENTAL ASSESSMENT Welcome KROSNO CREEK DIVERSION PROJECT PUBLIC INFORMATION CENTRE # 1 Tonight s Presentation Study Overview Background Existing Conditions Alternative Solutions Preliminary Preferred Solution Next Steps

More information

Universal 10 x 27 Canopy

Universal 10 x 27 Canopy Universal 10 x 27 Canopy C81027PC Size: 10 8 x 27 x 6 8 (side) x 9 9 (center) With 10 Legs, Frame, and Cover Powell & Powell Supply Company Distributed by: 1730 Five Points Lane Fuquay-Varina, North Carolina

More information

IMPORTANT OWNER-OPERATOR INSTALLATION INSTRUCTIONS. Part # A7006

IMPORTANT OWNER-OPERATOR INSTALLATION INSTRUCTIONS. Part # A7006 IMPORTANT OWNER-OPERATOR INSTALLATION INSTRUCTIONS Part # A7006 Parts List Wobble Stopper Body Wobble Stopper Shaft Camper Bracket Lower Bracket Assembly Upper Bracket Upper Bracket Clamp 3/8 SAE Flat

More information

Greetings! We ll see you out on the line, Alan, Chris, and Richard.

Greetings! We ll see you out on the line, Alan, Chris, and Richard. Greetings! This is your Maintenance of Way Team update for March 2, 2014. It s hard to believe that it s March already. The opening of the 2014 train season is just four weeks off. So, let s get this update

More information

Core Systems Installation Instructions

Core Systems Installation Instructions 185-3017 185-3018 185-3517 607-0149 WLH 09/17/18 TABLE OF CONTENTS ***Assembly*** Roller Tube Assembly Roller Tube Assembly... Standard Application Attaching Tarp to Roller Tube - Standard... Installing

More information

Wilts and Berks Canal Trust

Wilts and Berks Canal Trust Wilts and Berks Canal Trust Melksham Link Waterway, Pedestrian and Off-road Cycle Routes Engineering Design Contents Background 4 Technical Design Part 1 Semington to Berryfield 5 Part 2 Berryfield to

More information

Axiom Surface Mounted Headwalls

Axiom Surface Mounted Headwalls www.hsiheadwalls.com Axiom Surface Mounted Headwalls Installation Instructions Tel: 925.427.7800 Fax: 925.427.0800 support@hsiheadwalls.com Hospital Systems Inc. 750 Garcia Avenue Pittsburg CA 94565 USA

More information

Improvements to the Railroad Infrastructure Airport Drive/RFD Airport Davis Jct. Flag Center

Improvements to the Railroad Infrastructure Airport Drive/RFD Airport Davis Jct. Flag Center Winnebago County Rail Authority Rail Engineering and Planning Study Improvements to the Railroad Infrastructure Airport Drive/RFD Airport Davis Jct. Flag Center Table of Contents 1.0 Introduction and Study

More information

4-foot Economy Sign Post. 4-foot post is rated at 2 pounds per foot. 7-foot Economy Sign Post

4-foot Economy Sign Post. 4-foot post is rated at 2 pounds per foot. 7-foot Economy Sign Post Introduction: ComplianceSigns.com offers a variety of sign posts, sign mounting hardware, sign bases, mounting tape and more to mount your safety signs indoors or out. We offer three styles of sign posts,

More information

DATA BOOK IV : COST ESTIMATE

DATA BOOK IV : COST ESTIMATE The Study on Comprehensive Disaster Prevention around Mayon Volcano DATA BOOK IV : COST ESTIMATE DT IV List of (1/5) Clearing and Grubbing ha 59,192.92 Excavation (Road way & Drainage) Mech. cu.m 80.55

More information

Bird-Shots PAP Kit Assembly Instructions August 15, 2008

Bird-Shots PAP Kit Assembly Instructions August 15, 2008 Bird-Shots PAP Kit Assembly Instructions August 15, 2008 (Please Read Carefully BEFORE Starting) Why a kit? Over the past several years I have tried several platforms to obtain commercial low-level aerial

More information

Oxford Round. Carton # 1. Carton # 2. Carton # 3 ITEM DESCRIPTION PART #

Oxford Round. Carton # 1. Carton # 2. Carton # 3 ITEM DESCRIPTION PART # Oxford Round Part # 420833-11 Round Packing List ITEM DESCRIPTION PART # 8 21 24 27 30 33 Carton # 1 Carton # 2 Carton # 3 8 x52 Gray Pearl 130309 1 - - - - - - - - x52 Gray Pearl 130310-1 - - - - - -

More information

TREASURE ISLAND FERRY SHELTER & BUS SHELTERS. Arts Commission Civic Design Review APRIL 18, 2016

TREASURE ISLAND FERRY SHELTER & BUS SHELTERS. Arts Commission Civic Design Review APRIL 18, 2016 TREASURE ISLAND FERRY SHELTER & BUS SHELTERS PHASE 3 - CD Arts Commission Civic Design Review APRIL 18, 2016 PHASE 2 COMMENTS/INFORMAL SESSION FOLLOW UP 1. Lighten up the concrete base of the Ferry Shelter

More information

APPENDIX D: SUSTAINABLE TRAIL DESIGN. APPENDICES Town of Chili Parks and Recreation Master Plan Update

APPENDIX D: SUSTAINABLE TRAIL DESIGN. APPENDICES Town of Chili Parks and Recreation Master Plan Update APPENDIX D: SUSTAINABLE TRAIL DESIGN APPENDICES Town of Chili Parks and Recreation Master Plan Update Sustainable Trail Construction Sustainable trails are defined by the US Forest Service as trails having

More information

Attenda Floor Mount Bed

Attenda Floor Mount Bed Attenda Floor Mount Bed ATN101 Bed Deck Width 80" Bed Deck Depth 36" Height 15.5" Overall Width 84" Overall Depth 40" Weight 110-115 lbs solution. Premium Tru material is fully compounded for superior

More information

Big Sable Point Lighthouse Les & Arlene Meverden Ludington, MI 49431

Big Sable Point Lighthouse Les & Arlene Meverden Ludington, MI 49431 Les & Arlene Meverden Ludington, MI 49431 My Interview with Les and Arlene Meverden and their daughter Janet was held on June 5, 2004. I first learned about the Meverden family through an article published

More information

Alien Flier Zip Line Products Installation/Owner s Manual

Alien Flier Zip Line Products Installation/Owner s Manual Alien Flier Zip Line Products Installation/Owner s Manual 1 Table of Contents SAFETY PLEASE READ CAREFULLY... 4 Explorer Zip Line EZ Up Cable Kit Installation... 5 Xtreme Zip Line EZ Up Cable Kit Installation...

More information

OCCUPATIONAL TOOL AND EQUIPMENT LIST

OCCUPATIONAL TOOL AND EQUIPMENT LIST OCCUPATIONAL TOOL AND EQUIPMENT LIST Ironworker (Generalist) Government of Newfoundland Labrador Department of Advanced Education and Skills March 2012 Preface This document is intended as a companion

More information

READ AND SAVE THESE INSTRUCTIONS! EasyAwn Standard Awning Installation

READ AND SAVE THESE INSTRUCTIONS! EasyAwn Standard Awning Installation EasyAwn Installation, Care and Maintenance Manual EasyAwn Quality, Since 1946 EasyAwn, LLC Toll Free: 877-EasyAwn http://www.easyawn.com READ AND SAVE THESE INSTRUCTIONS! EasyAwn Standard Awning Installation

More information

/ Tool and Equipment Safety Tether System (T.E.S.T.S)

/ Tool and Equipment Safety Tether System (T.E.S.T.S) 20 INSTRUCTIONS FOR USE AND PRODUCT GUIDE 799953 / 799955 Tool and Equipment Safety Tether System (T.E.S.T.S) Part # T353012 Rev 2 Reliance Industries LLC 2802 East X Street Deer Park, Texas 77536 281-930-800

More information

300 Model 870 Four Wheel Hose Cart Owner s Manual

300 Model 870 Four Wheel Hose Cart Owner s Manual 300 Model 870 Four Wheel Hose Cart Owner s Manual IMPORTANT: READ THE OWNER S MANUAL BEFORE ASSEMBLING TOOLS REQUIRED: TWO ADJUSTABLE WRENCHES; HAND PUMP Estimated assembly time: 30 minutes PARTS LIST

More information

LITE Spear Awning Instructions

LITE Spear Awning Instructions LITE Spear Awning Instructions IMPORTANT NOTE: Please take a few minutes to become familiar with this entire document BEFORE beginning your installation. The time you spend doing this is well spent and

More information

1. The scour elevation can normally be found on the bridge hydraulics sheet and in the Pile Data Table. True False

1. The scour elevation can normally be found on the bridge hydraulics sheet and in the Pile Data Table. True False Homework 1 1. The scour elevation can normally be found on the bridge hydraulics sheet and in the Pile Data Table. True False 2. The Required Nominal Bearing Resistance Resistance will normally be shown

More information

Wooden Koi/Octagonal Pond Instruction Manual

Wooden Koi/Octagonal Pond Instruction Manual www.gardenparadise.net Wooden Koi/Octagonal Pond Instruction Manual Introduction Please take time to read these instructions prior to installing your pond. This will help you understand the product and

More information

Vinyl French Door Assembly Instructions

Vinyl French Door Assembly Instructions Vinyl French Door Assembly Instructions SERIES FD 5455/5555 Para instrucciones en español, visite: http://bit.ly/pgtassemblyinstructions FD 5455 / 5555 Parts List ITEM 1 FD 5455/5555 PARTS LIST FRAME HEAD

More information

1946 READ AND SAVE THESE INSTRUCTIONS!

1946 READ AND SAVE THESE INSTRUCTIONS! EasyAwn Installation, Care and Maintenance Manual EasyAwn Quality, Since 1946 EasyAwn, LLC Toll Free: 877-EasyAwn http://www.easyawn.com READ AND SAVE THESE INSTRUCTIONS! EasyAwn Quarter Round Awning Installation

More information

Continued Operational Safety Risk Assessment of Textron Aviation s Commercial Fleet. July 5, 2018

Continued Operational Safety Risk Assessment of Textron Aviation s Commercial Fleet. July 5, 2018 Continued Operational Safety Risk Assessment of Textron Aviation s Commercial Fleet July 5, 2018 Textron Aviation s Commercial Fleet Several Textron Aviation piston and turboprop models are used in scheduled

More information

Color Light Streams Lighted Bubbler Spillway Pot (CLSDLP) Installation Manual

Color Light Streams Lighted Bubbler Spillway Pot (CLSDLP) Installation Manual Color Light Streams Lighted Bubbler Spillway Pot (CLSDLP) Installation Manual 27.75 23.75 25.50 20.75 Specifications: 8-13 GPM 12-14 VAC only (Class 2 transformer required) 3W max. 100 ft. cord, conduit

More information

State Route 8 Corridor. Northern Summit County s Path to Success

State Route 8 Corridor. Northern Summit County s Path to Success State Route 8 Corridor Northern Summit County s Path to Success Construction Guide: 2008-2009 State Route 8 corridor work description State Route 8 Corridor 10 projects $262 million With its close proximity

More information

ONONDAGA CREEKWALK PHASE II. Public Information Meeting Series 1

ONONDAGA CREEKWALK PHASE II. Public Information Meeting Series 1 ONONDAGA CREEKWALK PHASE II Public Information Meeting Series 1 Andrew Maxwell Director, Syracuse-Onondaga County Planning Agency Owen Kerney Assistant Director for City Planning Russell Houck, PE City

More information

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane

More information

Welcome to Webinar on Accelerated Bridge Construction Colorado Flyover Ramp Showcases Precast Pier Caps and Curved Spliced Precast U-Girders

Welcome to Webinar on Accelerated Bridge Construction Colorado Flyover Ramp Showcases Precast Pier Caps and Curved Spliced Precast U-Girders Welcome to Webinar on Accelerated Bridge Construction Colorado Flyover Ramp Showcases Precast Pier Caps and Curved Spliced Precast U-Girders Sponsored by Accelerated Bridge Construction University Transportation

More information