Public Workshop Preliminary Plans Review. Projects PW 1605, 1701, & 1702
|
|
- Dylan Little
- 6 years ago
- Views:
Transcription
1 Queens Mirror Circle Pedestrian Safety Improvements Quail Pond Circle Complete Street/Pedestrian Connectivity Improvements Southcot Drive Bicycle/Pedestrian Improvements Public Workshop Preliminary Plans Review Projects PW 1605, 1701, & 1702 June 20, 2017
2 Project Background All three projects included in the Connecting Casselberry: The Casselberry Multimodal Transportation Master Plan (MTMP) adopted in 2016 Increased focus on pedestrian and bicycle improvements and complete streets Queens Mirror Circle included in current FDOT Work Program Quail Pond Circle & Southcot Dr included in current Metroplan Orlando Prioritized Project List
3 Queens Mirror Circle Pedestrian Safety Improvements
4 Queens Mirror Project Location: Queens Mirror Circle (north side of Queens Mirror Lake)
5 Project Area Queens Mirror Project Limits
6 Enhance pedestrian safety and connectivity/safe route to school Install Button activated RRFB s (rectangular rapid flashing beacon) for pedestrian S Lost Lake Lane Install permanent speed feedback devices for traffic calming Improve accessibility and visibility of crossing at Rotary Park Queens Mirror: Project Objectives
7 Queens Mirror Draft Plan
8 Queens Mirror Draft Plan Remove old crossing signage
9 Queens Mirror Draft Plan Add button activated RRFB (flashing beacon operates only when pressed)
10 Queens Mirror Draft Plan Install permanent speed feedback devices
11 Queens Mirror Draft Plan
12 Reorient and restripe crossing with ADA compliant curb ramps Queens Mirror Draft Plan
13 Install new crossing signage Queens Mirror Draft Plan
14 Queens Mirror Preliminary Add wayfinding Additional Staff Recommendations Can be completed as separate in-house City staff project Confirm whether existing advance warning signage should remain (except New ) Confirm School crossing designation(s) Coordinate with Seminole County Public Schools and Sheriff
15 City Commission presentation/discussion July 24, 2017 Complete design by approx. September 30, 2017 Construction funded (by FDOT) for Fiscal Year 2020 (mid ) Queens Mirror Anticipated Schedule
16 Quail Pond Circle Complete Street/Pedestrian Connectivity Improvements
17 Quail Pond Project Location: Quail Pond Circle (from Triplet Lake Dr to Sunset Dr)
18 Quail Pond Project Context
19 Quail Pond Project Context
20 Quail Pond Project Context
21 Project Area Quail Pond Project Limits
22 Quail Pond Project Objectives Enhance bike/ped safety and connectivity Add sidewalks to Quail Pond Circle Create ped connection(s) from Quail Pond Circle to Lake Concord Park (north phase) Create shared use path connection from Quail Pond Cir to Sunset Dr Install ped crossing at Sunset Dr
23 Quail Pond Draft Plan
24 Quail Pond Draft Plan
25 Quail Pond Draft Plan
26 Quail Pond Draft Plan
27 Construct 6 ft sidewalk starting at new parking lot driveway Quail Pond Draft Plan
28 Quail Pond Draft Plan
29 Quail Pond Draft Plan
30 Quail Pond Draft Plan Construct 8 ft sidewalk starting at Art House driveway Construct connection to Art House Add raised curb and pave Quail Pond Circle Construct roadside swales
31 Quail Pond Draft Plan
32 Quail Pond Draft Plan
33 Quail Pond Draft Plan
34 Quail Pond Draft Plan Construct cul-desac Construct 10 ft shared use path to Sunset Dr Add crossing at Sunset Dr
35 Quail Pond Preliminary Additional Staff Recommendations Add accessible ped connection (if feasible) from Triplet Lake/ Quail Pond to Public Works sidewalk Relocate oak tree a few feet to suit
36 Quail Pond Preliminary Additional Staff Recommendations Reorient sidewalk to shorten driveway Make it a brick crossing
37 Quail Pond Preliminary Additional Staff Recommendations Add wider (8 ft) and more direct sidewalk connection to Art House/Lake Concord Park Mimic brick pattern in Lake Concord Park for connection to Art House
38 Quail Pond Preliminary Additional Staff Recommendations Shift sidewalk onto City properties and within right of way as needed to minimize conflicts
39 Quail Pond Preliminary Additional Staff Recommendations LED acorn lights Art House to cul-de-sac LED path lights for shared use path
40 Quail Pond Preliminary Additional Staff Recommendations Add sharrows Landscape swales with cordgrass
41 Quail Pond Preliminary Additional Staff Recommendations Remove invasive trees and plants and failing magnolias Plant new trees
42 Quail Pond Preliminary Additional Staff Recommendations No Parking from eastern edge of City property to culde-sac Remove unnecessary driveway aprons Add fence along Sunset lot line for screening from adjacent residence
43 Quail Pond Anticipated Schedule City Commission presentation/ discussion July 24, 2017 Complete design by approx. September 30, 2017 Construction funded (by sales tax) for Fiscal Year 2020 (late )
44 Southcot Drive Bicycle/Pedestrian Improvements
45 Southcot Project Location: Southcot Drive from Sunset Dr to S Triplet Lake Dr
46 Southcot Project Context
47 Southcot Project Context
48 Southcot Project Context
49 Southcot Project Context
50 Project Area Southcot Project Limits
51 Southcot Project Objectives Enhance bike/ped safety and connectivity Widen sidewalk Add midblock crossing Conduct 4-way stop analysis at Sunset Dr Integrate traffic calming
52 Southcot Draft Plan
53 Southcot Draft Plan
54 Southcot Draft Plan
55 Southcot Draft Plan Conduct 4-way stop warrant analysis for Southcot & Sunset Waiting for N Oxford to conclude and school to resume
56 Southcot Draft Plan
57 Install curb ramps & stripe crossing Southcot Draft Plan
58 Southcot Draft Plan Install curb ramps & stripe crossing Widen sidewalks to 8 feet Relocate electric poles
59 Southcot Draft Plan Add raised curb and gutter with 2-3 ft sod strip
60 Southcot Draft Plan
61 Southcot Draft Plan
62 Southcot Draft Plan
63 Southcot Draft Plan End south side sidewalk at existing location Add midblock crossing
64 Southcot Draft Plan
65 Southcot Draft Plan
66 Southcot Draft Plan
67 Widen sidewalk to 8 feet Southcot Draft Plan
68 Southcot Draft Plan Install raised curb on north side with 2 ft sod strip only
69 Southcot Preliminary Additional Staff Recommendations Evaluate installing crossing across Sunset Southcot Consider safety concerns if 4- way stop determined to be unwarranted Make Southcot curb ramp more direct rather than angled
70 Southcot Preliminary Additional Staff Recommendations Only widen north side sidewalk Keep south side as-is/avoid pole relocates and landscape disruption
71 Southcot Preliminary Additional Staff Recommendations Install raised midblock crosswalk instead of at-grade
72 Southcot Preliminary Additional Staff Recommendations Integrate golf cart path better and address tie-in grading concerns adjacent to golf course
73 City Commission presentation/ discussion July 24, 2017 Complete design by approx. September 30, 2017 Construction funded (by sales tax) for Fiscal Year 2020 (late ) Southcot Anticipated Schedule
74 Please provide comments by June 30 th 2017 to: Kelly Brock (407) ext 1235 Project updates (and this presentation):
Longmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT
Longmont to Boulder Regional Trail Jay Road Connection DRAFT FINAL REPORT December 2018 Project Summary Boulder County, Colorado, in partnership with the City of Boulder, is evaluating options for multi-use
More informationAuburn Trail / Ontario Pathways Trail Connector Feasibility Study Public Information Meeting Wednesday, August 22, 2012
Auburn Trail / Ontario Pathways Trail Connector Feasibility Study Public Information Meeting Wednesday, August 22, 2012 Purpose of Feasibility Study Purpose Evaluate the feasibility of constructing a multiuse
More information4. Safety Concerns Potential Short and Medium-Term Improvements
NH Route 104 Access Management Study Page 19 4. Safety Concerns Potential Short and Medium-Term Improvements Potential safety improvement strategies are listed by priority based on field observations by
More informationMemo. Orange City Trail Plan Becky Mendez, AICP Jamie Krzeminski, PE, PTOE Matt Wiesenfeld, PE, AICP. Development of the Existing and Proposed Network
Memo Date: Friday, December 22, 2017 Project: To: From: Subject: Trail Plan Becky Mendez, AICP Jamie Krzeminski, PE, PTOE Matt Wiesenfeld, PE, AICP Development of the Existing and Proposed Network HDR
More informationADVANCED WARNING SYSTEM FOR SHARED USE CROSSING ON HOWARD STREET EAST OF NORDICA AVENUE
ADVANCED WARNING SYSTEM FOR SHARED USE CROSSING ON EAST RDICA AVENUE FOR THE LOCATION MAP STANDARD SYMBOLS FEATURE EISTING PROPOSED BENCHMARK BM/TBM SHEET INDE. BM/TBM TITLE SHEET CONCRETE R.O.W. MONUMENT
More informationFINAL. Bicycle/Pedestrian Feasibility Study City of DeBary Dirksen Drive Trail. Prepared For: Volusia County MPO
City of DeBary Dirksen Drive Trail FINAL Prepared By: Reynolds, Smith and Hills, Inc. Prepared For: Volusia County MPO September 2007 Table of Contents INTRODUCTION...1 PROJECT PURPOSE AND SCOPE...2 PHYSICAL
More informationSeptember 30, 2016 PUBLIC HEARING RESULTS
The Sustainable Streets Division of the San Francisco Municipal Transportation Agency held a public hearing on Friday,, at 10:00 AM, in Room 416 (Hearing Room 4), City Hall, 1 Dr. Carlton B. Goodlett Place,
More informationAttachment No. 20 RRLRT No. 1. Committee. Busway Grade Crossings STATUS/DATE OF ACTION
Attachment No. 20 RRLRT No. 1 TECHNICAL COMMITTEE: Railroad / Light Rail Transit Technical Committee TOPIC: Busway Grade Crossings STATUS/DATE OF ACTION RRLRT TC Draft: 06/23/2011 RRLRT TC Approval: 06/27/2014
More informationPalm Beach County Traffic Report July 13 through July 20, 2012
For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be
More informationGeorgetown-Lewes Rail/Trail Study. Rail/Trail Study: Cool Spring to Cape Henlopen State Park New Road Extension (House Resolution No.
Georgetown-Lewes Rail/Trail Study Rail/Trail Study: Cool Spring to Cape Henlopen State Park New Road Extension (House Resolution No. 47) August 22, 2011 Presentation Outline Background Benefits Statewide
More informationDATE: April 19, 2016 REPORT NO. PW Chair and Members Committee of the Whole Operations and Administration
PUBLIC WORKS COMMISSION DATE: April 19, 2016 REPORT NO. PW2016-034 TO: FROM: Chair and Members Committee of the Whole Operations and Administration E. (Beth) Goodger General Manager, Public Works Commission
More informationCrystal City Station Improvements. Project Overview. Table 2: North Entrance. Table 1: South Entrance. 20th St. S 18th St. S.
Table 1: South Entrance Table 2: North Entrance 20th St. S 18th St. S Proposed Second Entrance Crystal Drive Existing Station Location Platform Future 4 th Track Future New Airport Connection (by others)
More informationSite Location and Setting
Memorandum Date: To: From: Subject: Kristy Le, Gary Black Steve Orem Santa Teresa County Park Historic Area Traffic and Parking Study Hexagon Transportation Consultants, Inc. has completed a traffic and
More informationMain Street Station Upgrades
Main Street Station Upgrades Public Meeting Hope United Church 1 Main Street Station Upgrades Bus diversions Planned improvements Construction staging Pedestrian flows 2 Main Street Station Aerial Bar
More informationTransportation TRANSPORTATION PROJECTS
Transportation TRANSPORTATION PROJECTS Balls Ford Road Interchange Total Project Cost $142.9M This project includes the construction of a new diverging diamond interchange at Route 234 Bypass (Prince William
More informationEAKINS OVAL / 25 TH & PENNSYLVANIA AREA PROJECT SUMMARY 1
EAKINS OVAL / 25 TH & PENNSYLVANIA AREA PROJECT SUMMARY The Parkway Council Foundation is studying potential road and sidewalk reconfigurations of two areas at the western edge of the Benjamin Franklin
More information10.1 INTRODUCTION NORTH PERRY AIRPORT MASTER PLAN UPDATE SECTION 10: CAPITAL IMPROVEMENT PROGRAM
10.1 INTRODUCTION Based on the findings from the Facility Requirements and the combined plan recommended in the Alternative Analysis, a capital improvement program for North Perry Airport has been developed
More informationTRAFFIC COMMISSION, VILLAGE OF LINCOLNWOOD 6900 N. Lincoln Avenue, Lincolnwood, IL 60712
TRAFFIC COMMISSION, VILLAGE OF LINCOLNWOOD 6900 N. Lincoln Avenue, Lincolnwood, IL 60712 Meeting Agenda Thursday, May 25, 2017 7:00 p.m. Village Hall Council Chambers 6900 N. Lincoln Ave. Lincolnwood,
More informationAdditional Economic Development Strategy submissions- Klickitat County
Klickitat County Transportation Improvement Projects 1 White Salmon to Hood River Bridge Final EIS, design, bridge replacement 2 Klickitat County Rural Arterials Reconstruct to all-weather roads Part of
More informationWHY MOVE YOUR BUSINESS TO HOLLYWOOD?
WHY MOVE YOUR BUSINESS TO HOLLYWOOD? Close to international airport and seaport Centrally located in 3.5 million population No personal income tax Diverse labor force and talent pool Waterfront executive
More informationCommunity Development Department Council Chambers, 7:30 PM, December 20, 2012
STAFF REPORT 2012-56P: Alley Vacation Community Development Department Council Chambers, 7:30 PM, December 20, 2012 To: From: Re: Paul Luke, Chairman, Skokie Plan Commission Mike Voitik, Planning Technician
More informationPalm Beach County Traffic Report August 24 through August 31, 2012
For Immediate Release August 24, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report August 24 through August 31, 2012 Palm Beach County Palm Beach County traffic will
More informationMONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION
MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION MCPB Item No. Date: 6/23/2016 Lucy V. Barnsley Elementary School Addition, Mandatory Referral MR2016027
More informationCity of Madison, Buckeye Road Monona Drive to Stoughton Road County AB Dane County Public Involvement Meeting
City of Madison, Buckeye Road Monona Drive to Stoughton Road County AB Dane County Public Involvement Meeting Wednesday, May 31, 2017 6:30 to 8 P.M. Frank Allis Elementary School 4201 Buckeye Road Madison,
More informationB10. Agate Beach State Recreation Site
B10. Agate Beach State Recreation Site Location Within the City of Newport, just south of the Yaquina Head Outstanding Natural Area. The park is located along the west side of Highway 101 at the mouth
More informationRAILROAD QUIET ZONE PROJECT
RAILROAD QUIET ZONE PROJECT VILLAGE OF ROSELLE Village of Roselle 31 S. Prospect Street Roselle, IL 60172 9575 WEST HIGGINS ROAD, SUITE 600 ROSEMONT, IL 60018 TEL. (847) 823-0500 FAX (847) 823-0520 Table
More informationArea Surrounding Maplewood Manor
BAY CITY, MICHIGAN HOUSING COMMISSION Neighborhood Revitalization Plan Area Surrounding Maplewood Manor January 13, 2014 CITY COMMISSION DRAFT PLAN PRESENTATION BAY CITY, MICHIGAN 1 Planners Phil McKenna,
More informationSR 934 Project Development And Environment (PD&E) Study
SR 934 Project Development And Environment (PD&E) Study Project Advisory Group Meeting March 1, 2018 State Road 934/NE/NW 79th Street from west of I-95 (NW 13th CT) to N. Bayshore Drive PD&E STUDY SR 934/NE/NW
More informationCorktown Parks. Public Meeting. City of Toronto
Corktown Parks Public Meeting City of Toronto 15-04-20 Agenda 1. Reasons for Study 2. Consultation to Date 3. Parks Evaluation 4. Community Context 5. Bright St. Playground 6. Orphans Green (Dog Off Leash)
More information3. COLTA / HUGA CONNECTIONS - PRELIMINARY
9 3. COLTA / HUGA CONNECTIONS - PRELIMINARY 3.1 COLTA The Chain of Lakes Trail Association (COLTA) trail, formerly identified as the Chester Spur Line, was completed and opened for use in June 2011. The
More informationProposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street
STAFF REPORT ACTION REQUIRED Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street Date: March 12, 2007 To: From: Toronto and East York Community Council Director, Transportation Infrastructure
More informationSecond Street Improvements Project Project Update Archive
Second Street Improvements Project Project Update Archive 12/03/18: In observance of the Holiday Moratorium, crews have paused a majority of construction activity on 2nd Street until January 2, 2019. A
More informationBoston Redevelopment Authority 2/26/ Chestnut Hill Avenue Boston/Brookline, MA
Boston Redevelopment Authority 2/26/2014 Cassidy Playground Waterworks Design revisions made since the DPIR submission March 2013 Massing - Reduced project 16,030 SF, for a total project area of 218,520
More informationRoute 29 Solutions Projects
Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement
More informationMeeting Notes Public Open House
Meeting Notes Public Open House, 5:30-8:00 pm Fairbanks Pipeline Training Center, 3605 Cartwright Court, Fairbanks, Alaska= Agenda: Open House: 30 minutes Presentation: 45 minutes Question and Answers:
More informationThe Baker/Carver Regional Trail is intended to
Section V Design Guidance The Baker/Carver Regional Trail is intended to safely accommodate 183,000 annual visits, an array of non-motorized uses, a variety of skill levels, and persons with special needs.
More informationLake Tahoe Airport Master Plan
Lake Tahoe Airport Master Plan City Council Briefing October 20, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development
More informationLower Salford Township Planning Commission Meeting September 26, 2012
Lower Salford Township Planning Commission Meeting September 26, 2012 Chairman Manus McHugh called to order the Lower Salford Township Planning Commission meeting at 7:27 p.m. Other Planning Commission
More informationCitrus Heights Creek Corridor Trail Project Trail Advisory Group Field Trip #2 September 11, :00 11:00 am Trellis Hall, Citrus Heights
September 11, 2013 9:00 11:00 am Trellis Hall, Citrus Heights Project Overview The City of Citrus Heights is studying the feasibility of establishing a multi use trail system within the City s 26 miles
More informationAGENDA ITEM 5 D WAKULLA ENVIRONMENTAL INSTITUTE (WEI) TRAIL FEASIBILITY STUDY
March 19, 2018 AGENDA ITEM 5 D WAKULLA ENVIRONMENTAL INSTITUTE (WEI) TRAIL FEASIBILITY STUDY TYPE OF ITEM: Action STATEMENT OF ISSUE The Wakulla Environmental Institute (WEI) Trail is one of several trails
More informationFLORIDA S HOLLYWOOD BEACH AND DOWNTOWN BUSINESS AND REDEVELOPMENT OPPORTUNITIES CAPITAL IMPROVEMENT PLAN
FLORIDA S HOLLYWOOD BEACH AND DOWNTOWN BUSINESS AND REDEVELOPMENT OPPORTUNITIES CAPITAL IMPROVEMENT PLAN 2015-2019 WHY MOVE YOUR BUSINESS TO HOLLYWOOD? Close to international airport and seaport Centrally
More informationSt. Dennis Drive Conversion of Traffic Lanes to On- Street Parking and Bicycle Lanes
STAFF REPORT ACTION REQUIRED St. Dennis Drive Conversion of Traffic s to On- Street Parking and Bicycle s Date: April 22, 2014 To: From: Wards: Reference Number: Public Works and Infrastructure Committee
More informationHudson Highlands Fjord Trail Draft Master Plan. April 29, 2015
Hudson Highlands Fjord Trail Draft Master Plan April 29, 2015 Agenda Route Overview Proposed Segment Results of Community Survey on that Segment Next Steps Municipal Endorsement Environmental Review Implementation
More informationNovember 21, 2012 Barbara Kelleher, (954)
November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related
More informationArvidson, Adam R. Adam,
Arvidson, Adam R. From: Andrew Hestness Sent: Wednesday, May 18, 2016 5:39 PM To: Arvidson, Adam R. Cc: Renee Spillum; Schroeder, Michael Subject: RE: Park Dedication Attachments: FranklinPlan - Bystrom
More informationLake Erie Commerce Center Traffic Analysis
LOCATION: East of NYS Route 5 at Bayview Road Town of Hamburg Erie County, New York PREPARED BY: Wendel Companies 140 John James Audubon Parkway Suite 200 Amherst, New York 14228 January 2012 i ii Table
More informationMEMORANDUM. Honorable Mayor and City Councilmembers William S. Joynes, Sr., City Administrator
AGENDA ITEM 1A MEMORANDUM DATE: January 17, 2017 TO: FROM: SUBJECT: Honorable Mayor and City Councilmembers William S. Joynes, Sr., City Administrator Sue Polka, Interim Asst. Public Works Director/City
More informationCity of Madera Engineering Division. Citizen s Oversight Committee February 13, 2019
City of Madera Engineering Division Citizen s Oversight Committee February 13, 2019 INTRODUCTION The City of Madera uses Measure T funds to support various programs as outlined in the Annual Expenditure
More informationCITY OF BEVERLY HILLS TRAFFIC & PARKING COMMISSION TO: FROM: SUBJECT: ATTACHMENTS: June 1,2017. Aaron Kunz, Deputy Director
CITY OF BEVERLY HILLS TRAFFIC & PARKING COMMISSION June 1,2017 TO: FROM: SUBJECT: ATTACHMENTS: Traffic & Parking Commission Aaron Kunz, Deputy Director North Santa Monica Boulevard Reconstruction Project
More informationONONDAGA CREEKWALK PHASE II. Public Information Meeting Series 1
ONONDAGA CREEKWALK PHASE II Public Information Meeting Series 1 Andrew Maxwell Director, Syracuse-Onondaga County Planning Agency Owen Kerney Assistant Director for City Planning Russell Houck, PE City
More informationHIGHWAY RAIL GRADE CROSSING CONSOLIDATION PROGRAM
HIGHWAY RAIL GRADE CROSSING CONSOLIDATION PROGRAM To decrease unnecessary train traffic exposure to life and property, promote public safety, and improve traffic conditions, the Texas Department of Transportation
More informationGulf Coast MPO Obligated Projects
Gulf Projects */ 104866/801000 STPD-9370-00(004) Dedeaux Rd. From Three Rivers Rd. to SR 605. MS $3,259,353 106448/701000 STP-8971-00(005) City of City of - widen to include three lanes on Hospital Road
More informationHospital Link Project Project Update Winter 2018
Hospital Link Project Project Update Winter 2018 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction of the Hospital Link facility is open
More informationSeek the Board s approval for the Donald Place kerb and channel renewal to progress to final design, tender and construction; and
3. DONALD PLACE - KERB AND CHANNEL RENEWAL General Manager responsible: General Manager City Environment Officer responsible: Transport and City Streets Manager Author: Michelle Flanagan, Streets Capital
More informationPURPOSE AND NEED (CONCURRENCE POINT 1) NEW CANADA ROAD PROJECT FROM STATE ROUTE 1 (U.S. HIGHWAY 70) TO U.S. INTERSTATE 40
PURPOSE AND NEED (CONCURRENCE POINT 1) NEW CANADA ROAD PROJECT FROM STATE ROUTE 1 (U.S. HIGHWAY 70) TO U.S. INTERSTATE 40 Project Description The primary purpose of this project is to improve the major
More informationTown of Frisco. Trails Master Plan. Legend. Planning Area 1. i l. 9 Campground. Lake Hill Development. Giberson Property. Frisco Transit Center
SO-UV I-70 UPPER SALT LICK TOO-PWECH SUNRISE 1 Town of Frisco Planning Area 1 NAH-OON-KARA I-70 Lake Hill Development Legend Existing Trails Existing USFS System Trails 2 A Existing Non-System Trails Bike
More informationConstruction Update. Local Officials Briefing March 2016
Construction Update Local Officials Briefing March 2016 1 History: Chicago-St. Louis Corridor Since 1980 s IDOT has been looking at this corridor for high-speed service 1992 Designated a HSR Corridor EIS
More informationCapital Prioritization
14 Capital Prioritization 279 279 280 Park & Recreation CAPITAL PRIORITIZATION As described in Chapter 8, the recommendations presented in Chapter 9 are prioritized to provide a guide for future capital
More informationCommunity Development Committee
C Community Development Committee For the Metropolitan Council meeting of October 31, 2012 Committee Report Item:2012-316 ADVISORY INFORMATION October 16, 2012 Date Prepared: Subject: Intercity Regional
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 11 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Approving various parking and traffic modifications on Van Ness Avenue
More informationCommittee Report. Community Development Committee For the Metropolitan Council meeting of April 13, Business Item No.
Committee Report Business Item No. 2016-48 Community Development Committee For the Metropolitan Council meeting of April 13, 2016 Subject: Harriet Island-South St. Paul Regional Trail Master Plan, Saint
More informationTrail # NW Tuesday, June DESIGN. Provide an Review the Provide an. Project Goals: System system. wayfinding
I. Welcome / Introductions Bethany Creek Trail #2 Segment 3 Neighborhood Meeting #1 Bethany Presbyterian Church 15505 NW Springville Road, Portland, OR 97229 Tuesday, June 26, 2018 @ 6:00PM Meeting Minutes
More informationSR 429/WEKIVA PARKWAY FTBA CONFERENCE March 20-21, Presented By Suzanne Phillips, P.E., FDOT District 5
SR 429/WEKIVA PARKWAY FTBA CONFERENCE March 20-21, 2012 Presented By Suzanne Phillips, P.E., FDOT District 5 Project Description The Wekiva Parkway project constructs 25 centerline miles of new toll expressway.
More informationSECTION 4(f) DE MINIMIS FINDING
Lake Merritt Improvement Project Bellevue Ave., Children s Fairyland and Garden Center Pedestrian and Bicycle Access Improvement Project SECTION 4(f) DE MINIMIS FINDING Oakland, California Ref: HP2IL 5012
More informationAVAILABLE FOR SALE ENTITLED 53,228 SF BUILDING FOR SALE Washington Dr., Fontana. Property Features:
Property Features: Free - Standing; Entitled 53,8 SF;,311 SF Office (3) Dock High Loading Rare, New Planned Wholesale Warehouse Corner Location (Live Oak Ave. & Washington Dr.) 1 Block South Of Valley
More informationFrequently Asked Questions on the Route 29 Solutions Improvements Projects
Frequently Asked Questions on the Route 29 Solutions Improvements Projects Background What are the Route 29 Solutions improvement projects? These projects include the Route 29/250 Interchange ( Best Buy
More informationAGENCY NAME TRANSPORTATION
TRANSPORTATION TRANSPORTATION AGENCY NAME Prince William County FY 2015 BUDGET CIP-TRANSPORTATION 561 Fuller Road/Fuller Heights Road Improvements Total Project Cost - $4.4 M This project will widen Fuller
More informationWelcome to the Cross County Trail Public Input Session!
Welcome to the Cross County Trail Public Input Session! Please sign in on the table below! What are we doing here? Camden County has proposed a bicycle and pedestrian trail spanning across the entire county.
More informationCity of Durango 5.8 FUNDING TRAILS DEVELOPMENT
5.8 FUNDING TRAILS DEVELOPMENT The City has been successful in establishing dedicated local funding sources as well as applying for grants to develop the City s trail system, having received nearly $2.4
More informationBusiness Item No XXX. Proposed Action That the Metropolitan Council approve the Coon Creek Regional Trail Master Plan.
Business Item No. 2015-XXX Metropolitan Parks and Open Space Commission Meeting date: July 7, 2015 For the Community Development Committee meeting of July 20, 2015 For the Metropolitan Council meeting
More informationThe Light Rail System Safety & Grade Crossing Equipment
The Light Rail System Safety & Grade Crossing Equipment A Peer Review Provided by the American Public Transportation Association (APTA) Presented by: Mark Benedict, Director, Light Rail Operations and
More informationCHASKA PLANNNING COMMISSION MINUTES September 13, 2017
CHASKA PLANNNING COMMISSION MINUTES 1. Call to Order Chairperson Huang called the meeting to order at 7:00 pm. 2. Roll Call Roll call was taken. Members present: Commissioners Cross, Keyport, Personius,
More informationuser s guide to Transportation Improvements in Astoria Planning Efforts outside Astoria for more information, contact:
The Miles Crossing/ Jeffers Garden transportation plan (underway), will identify needed improvements to the Warrenton Astoria Highway and local street improvements to serve expected growth in the Miles
More informationBecker County Trail Routing Feasibility Study
2016 Becker County Trail Routing Feasibility Study CONNECTING DETROIT MOUNTAIN AND MOUNTAIN VIEW RECREATIONAL AREA TO THE HEARTLAND TRAIL BECKER COUNTY ULTEIG ENGINEERS Contents Acknowledgements...2 INTRODUCTION...3
More informationFDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016
March 25, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 TREASURE COAST Construction and maintenance-related
More informationAnnual Listing of Federally Obligated Projects in Santa Barbara County Federal Fiscal Year (October 1, 2014 to September 30, 2015)
Annual Listing of Federally Obligated Projects in County Federal Fiscal Year 2015 (October 1, 2014 to September 30, 2015) Annual List of Projects with Federal Funding for Federal Fiscal Year 2015 Federal
More informationSpadina Avenue Built Form Study Preliminary Report
STAFF REPORT ACTION REQUIRED Spadina Avenue Built Form Study Preliminary Report Date: July 9, 2014 To: From: Wards: Reference Number: Toronto and East York Community Council Director, Community Planning,
More informationLaxon Terrace - Sarawia. Click to add title. Street Rail Level Crossing. Public Forum. December
Laxon Terrace - Sarawia Click to add title Street Rail Level Crossing Public Forum December 2012 www.aucklandtransport.govt.nz Overview of Presentation Objectives and Reasons for Separation Project Background
More informationATTACHMENT B. Reference No.
ATTACHMENT B Projects in the Five-Year Capital Improvement Program for Fiscal Years Ending 2014-2018 GOVERNMENT CODE SECTION 65402 GENERAL PLAN CONFORMITY ANALYSIS 1 4 Orcutt GS Station 21 (Orcutt) Rebuild
More informationMadison Metro Transit System
Madison Metro Transit System 1101 East Washington Avenue Madison, Wisconsin, 53703 Administrative Office: 608 266 4904 Fax: 608 267 8778 TO: FROM: SUBJECT: Plan Commission Timothy Sobota, Transit Planner,
More informationClaremont Project Background and Update Community Meeting September 11, 2017
Claremont Project Background and Update Community Meeting September 11, 2017 Topics Project Background Claremont Segment Information Project Timeline Upcoming Discussion Items Upcoming Meetings Questions
More informationRiverside County Transportation Department Summary of Bids
COUNTY'S ESTIMATE HARDY & HARPER, INC. Schedule 1: Project No. B6-0472 Santa Ana, CA 92705 ITEM NO. ITEM CODE CONTRACT ITEM UNITS QUANTITY UNIT PRICE ENG ESTIMATE BID AMOUNT 1 731521 MINOR CONCRETE (SIDEWALK)
More informationAGENCY SCOPING MEETING
AGENCY SCOPING MEETING Environmental Impact Statement (EIS) Conducted for the Friedman Memorial Replacement Airport in the Wood River Region of South Central Idaho December 4, 2007 1:00 p.m. 4:00 p.m.
More informationNon-Motorized Transportation
Non-Motorized Transportation Non-motorized facilities are important components to the transportation system. They provide an environmentally-friendly, low-cost mode of travel. Some of the facilities can
More informationATTACHMENT C CITY OF FEDERAL WAY 2018 ASPHALT OVERLAY PROJECT BID SCHEDULE
ATTACHMENT C CITY OF FEDERAL WAY ASPHALT OVERLAY PROJECT SCHEDULE NOTE: Unit Prices for all items, all extensions, and the total amount of the bid must be shown. Show unit prices in legible figures. Where
More informationMONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION
MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION Three Sisters Road: Abandonment No. AB740 MCPB Item No. 11 Date: 5-1-14 Katherine Holt, Senior Planner,
More informationLOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE. CALABASAS CITY COUNCIL April 26, 2017
LOST HILLS ROAD INTERCHANGE PROJECT CONSTRUCTION UPDATE CALABASAS CITY COUNCIL LOST HILLS ROAD INTERCHANGE PROJECT UPDATES Construction of CIDH piles for the soundwall foundation commenced on March 20
More information1.0 Purpose and Organization of the Community Impact Assessment Addendum
Memorandum To: From: cc: Laura Prickett, Horizon Water and Environment Carie Montero, Senior Project Manager/Environmental Lead, Parsons Transportation Group Parag Mehta, Kimley Horn Date: September 24,
More informationBlue River Trail Master Plan JSA to Town Hall June 2004
Blue River Trail Master Plan JSA to Town Hall June 2004 Prepared for: Silverthorne Town Council Silverthorne SPORT Committee Department of Recreation and Culture Silverthorne Public Works Silverthorne
More informationFDOT Treasure Coast Traffic Impact Report
July 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 7 through July 14, 2017 TREASURE COAST Construction and maintenance related lane
More informationA. CONCLUSIONS OF THE FGEIS
Chapter 11: Traffic and Parking A. CONCLUSIONS OF THE FGEIS The FGEIS found that the Approved Plan will generate a substantial volume of vehicular and pedestrian activity, including an estimated 1,300
More informationLake Tahoe Airport Master Plan Public Meeting March 16, 2015
Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development plans
More informationSANTA MONICA AIRPORT VISIONING PROCESS: PHASE III FINDINGS AND NEXT STEP RECOMMENDATIONS APRIL 30, 2013
SANTA MONICA AIRPORT VISIONING PROCESS: PHASE III FINDINGS AND NEXT STEP RECOMMENDATIONS APRIL 30, 2013 Visioning Process: Overview SMO in 1917 (Cloverfield) Grass Landing Strip WWI Pilot Training Visioning
More informationNorthaven Trail Phase 2 Initial Project Overview
Northaven Trail Phase 2 Initial Project Overview Partnership Project to extend existing Northaven Trail Improve Bike/Ped Connectivity On Dallas Trail Network Plan City and County Funding Oncor Texas Trails
More informationAppendix 4.1 L. No-Build Project Descriptions
Appendix 4.1 L No-Build Project Descriptions No-Build Projects New Bedford A new traffic signal system was installed and activated in early 2009 at the intersection of King s Highway and Mount Pleasant
More informationCitrus Heights Creek Corridor Trail Project. Trail Advisory Group Meeting #3 July 8, 2013
Citrus Heights Creek Corridor Trail Project Trail Advisory Group Meeting #3 July 8, 2013 Agenda Introductions Recap: Community Workshop, Survey Findings, and TAG Field Trip Community Concern Discussion:
More informationFDOT Treasure Coast Traffic Report through
FDOT Treasure Coast Traffic Report 02 26 16 through 03 04 16 Kathleen Dempsey Fri 2/26/2016 2:56 PM To:Kathleen Dempsey ; 1 attachment 355 KB CR 714_Median Access Modifications.pdf;
More informationUnion Station Queens Quay Transit Link Study
Welcome Union Station in 1899. Image: City of Toronto Archives Union Station today. Image: Camil Rosiak Activity along Queens Quay. Image: Waterfront Toronto For more information or to comment, visit toronto.ca/waterfronttransit
More informationTRANSPORTATION ELEMENT
Transportation TRANSPORTATION ELEMENT Data, Inventory, and Analysis Prepared by Contents 1.0 INTRODUCTION... 1 2.0 EXISTING CONDITIONS... 1 2.1 Roadways... 1 2.1.1 Jurisdiction... 1 2.1.2 Functional Classification...
More informationGrade Crossing Regulations
Grade Crossing Regulations An Overview of Municipal Roles and Responsibilities at Federally Legislated Grade Crossings March 21, 2017 presentation to Alberta Municipal Supervisor Association, Edmonton,
More information