Springettsbury Township. Road Improvement Projects

Size: px
Start display at page:

Download "Springettsbury Township. Road Improvement Projects"

Transcription

1 Springettsbury Township Road Improvement Projects

2 Township Road Improvement Projects Springettsbury Township is divided into the following 4 Sectors: Northwest Sector Sherman Street Route 30 North to Mundis Mill Road Pleasant Valley Road/Mount Zion Road Intersection Eden Road Widening: Rear of Harley Davidson Entrance to the National Guard Druck Valley Road Overly: Mount Zion Road to Sherman Street Safe Routes to School Central York High School COMPLETED 2009 Northeast Sector Mount Zion Road: Market Street to Sherman Street COMPLETED 2009 Lower Glades Road Resurfacing COMPLETED 2009 Druck Valley Road: Resurfacing Mount Zion to Range Road Southwest Sector Northern Way & Market Street Intersection Improvement I 83 Overpass Project Eberts Lane and Sherman Street Mount Rose Avenue at Plymouth Road Route 124 Widening Camp Betty Washington/Haines Road west to Chambers Road Industrial Highway/Mount Zion Road Interstate 83: Exit 18 Improvements Memory Lane Median Project COMPLETED 2010 Safe Routes to School York Suburban Elementary School COMPLETED 2010 Southeast Sector Market Street/Mount Zion Road Intersection Improvement Market Street Widening Mount Zion Road to Locust Grove Road Stonewood Road Bridge Project Old Orchard Road/Witmer Road Intersection Route 24/Route 124 Intersection Improvements: Carol Road to Windsor Road Page 2

3 Northwest Sector Projects Sherman Street: PennDOT project Resurfacing from Route 30, North to Mundis Mill Road. Road resurfacing scheduled for construction in 2011 Utility work started in 2010 Page 3

4 Northwest Sector Projects Pleasant Valley Road/Mount Zion Road Intersection Addition of right turn lane Estimated start Summer 2011 Page 4

5 Northwest Sector Projects Eden Road Widening Reconstruction to super elevate and widen the rear of Harley Davidson Entrance to the National Guard Armory 2000 foot of roadway affected Estimated to begin during the 2011 construction season Page 5

6 Northwest Sector Projects Druck Valley Road Overlay: Mount Zion Road to Sherman Street Estimated to begin in the 2011 construction season Page 6

7 Northeast Sector Projects Druck Valley Road Resurfacing: Mount Zion Road to Range Road Estimated to begin in the 2011 construction season Page 7

8 Southwest Sector Projects Northern Way and Market Street Intersection Improvements Stream enclosure required Total Township costs, including construction and engineering are estimated at $1,163, Township is applying for grants and funding Page 9

9 Southwest Sector Projects I 83 Overpass Project: Eberts Lane and Sherman Street PennDOT bridge projects Resurfacing of Sherman from Market Street to Route 30 Scheduled completion is Fall 2011 Eberts Lane Bridge North Sherman Street Bridge Page 10

10 Southwest Sector Projects Mount Rose Avenue at Plymouth Road Installation of Traffic light Estimated project start date of 2011 View looking East Mount Rose Avenue Page 11

11 Southwest Sector Projects Route 124 Widening Project Camp Betty Washington/Haines Road West to Chambers Road PennDOT project Estimated construction start date of 2014 Page 12

12 Southwest Sector Projects Industrial Highway/Mount Zion Road Intersection Installation of a turning lane from Mount Zion Road to Industrial Highway at the York Container site Improvements to the traffic signal Sidewalk installation on the West side of Mount Zion Road from Industrial Highway to the railroad overpass Estimated completion date is Fall 2011 Page 13

13 Southwest Sector Projects Interstate 83: Exit 18 Improvements Estimated construction start date in 2016 PennDot Project Page 14

14 Township Road Improvements Southeast Sector Projects Market Street/Mount Zion Road Intersection Improvement PennDOT and Springettsbury Township cooperative project New right turn lane from Eastbound Market Street onto Southbound Mount Zion Road New right turn lane from Westbound Market Street onto Southbound Mount Zion Road Additional left turn lane from Southbound Mount Zion Road onto Market Street Optimize signal timings Township has committed $500,000 to PennDOT Estimated to begin in March 2011 Page 15

15 Southeast Sector Projects Market Street Widening: Mount Zion Road to Locust Grove Road Widening road to 5 lanes Includes addition of median from Route 24 to Bloomingdale Avenue Federal and State Highway funded Estimated to begin in March 2011 *Traffic Study for Eastern Boulevard to Pleasant Valley Road, upon completion of the above project. This will be, in part, for optimization of re timing of the traffic lights. Proposed Median to Bloomingdale Avenue Page 16

16 Southeast Sector Projects Stonewood Road Bridge Project PennDOT design and build project Widen two bridges between Market Street and Old Orchard Road; replace existing bridge over Kreutz Creek Awarded to Kinsley Construction Estimated to begin during the 2011 construction season Page 17

17 Southeast Sector Projects Old Orchard Road/Witmer Road Intersection PennDOT and Springettsbury Township cooperative effort Currently in Feasibility Study phase The project proposes to realign the intersection Page 18

18 Southeast Sector Projects Route 24/Route 124 Improvements: Carol Road to Windsor Road Estimated start date in 2014 Page 19

19 NORTHWEST NORTHEAST SOUTHWEST SOUTHEAST PLEASE DIRECT ALL QUESTIONS AND COMMENTS TO: SPRINGETTSBURY TOWNSHIP 1501 MOUNT ZION ROAD YORK, PA PHONE: (717) FAX: (717)

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 22, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 22 through July 29, 2016 TREASURE COAST Construction and maintenance-related lane

More information

FY Regional Transportation Improvement Program Basic Project List (All Values in Thousands of Dollars) All costs in current dollars

FY Regional Transportation Improvement Program Basic Project List (All Values in Thousands of Dollars) All costs in current dollars FY2016-2020 Regional Transportation Improvement Program Basic Project List () All costs in current dollars Project Name Key # Year Project Cost 10th Avenue Bridge, Caldwell 13055 2018 $1,367 10th Avenue

More information

November 21, 2012 Barbara Kelleher, (954)

November 21, 2012 Barbara Kelleher, (954) November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 7 through July 14, 2017 TREASURE COAST Construction and maintenance related lane

More information

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane

More information

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015 May 1, 2015 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 1 through May 8, 2015 Palm Beach County Palm Beach County traffic will be affected this week by ongoing

More information

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015 From: Kathleen Dempsey To: Kathleen Dempsey Subject: FDOT Treasure Coast Traffic Report 10 09 15 through 10 16 15 Date: Friday, October 09, 2015 2:10:36 PM Attachments: image003.png CR 714_Median Construction

More information

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 April 4, 2014 Chuck McGinness, 954-777-4090 Chuck.McGinness@dot.state.fl.us FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 TREASURE COAST Construction and maintenance-related lane closures

More information

PROGRESS PARK CONNECTOR

PROGRESS PARK CONNECTOR PROGRESS PARK CONNECTOR Project No. 9999 098 R65, P102 ALTERNATIVES ANALYSIS 6 April 2015 Revised for updated dates PROGRESS PARK CONNECTOR ROAD ALTERNATIVES ALTERNATIVE # 1 West from the intersection

More information

PRIORITIES COMMITTEE MEETING

PRIORITIES COMMITTEE MEETING PRIORITIES COMMITTEE MEETING Meeting Date: 05/13/14 Agenda Item #: 13.1 Northeast Anthony Henday Drive Update Report Purpose To update the Priorities Committee on the progress of the Northeast Anthony

More information

Guide to. Road Construction Projects

Guide to. Road Construction Projects Guide to Road Construction Projects 2018 Spring is here and so is road construction season. This year PennDOT District 11-0 will invest an estimated $208 million on 68 projects to improve, preserve or

More information

A. From I-68 in Monongalia County, West Virginia to SR 6119 in Fayette County, Pennsylvania 1

A. From I-68 in Monongalia County, West Virginia to SR 6119 in Fayette County, Pennsylvania 1 Mon-Fayette Transportation Project A. From I-68 in Monongalia County, West Virginia to SR 6119 in Fayette County, Pennsylvania 1 The Mon/Fayette Transportation Project (MFTP) from I-68 in West Virginia

More information

PennDOT Interstate Work next week March 30-April 3:

PennDOT Interstate Work next week March 30-April 3: PennDOT Interstate Work next week March 30-April 3: Interstate 80 Interstate 81 DELAYS THIS WEEK: Exit 256 to the Schuylkill County line. Eastbound & Westbound. Bridge cleaning Monday (3/30), Tuesday (3/31)

More information

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY TRAFFIC ADVISORY FOR IMMEDIATE RELEASE Fiorella Teodista 954-934-1130 January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY FORT LAUDERDALE Florida s Turnpike announces

More information

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg)

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg) RELEASE: IMMEDIATE Feb. 22, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Feb. 24 March 2, 2019 All work is scheduled weather permitting. Real-time information

More information

Northeast Anthony Henday Drive Edmonton Ring Road Update. Strathcona Chamber of Commerce March 18, 2015

Northeast Anthony Henday Drive Edmonton Ring Road Update. Strathcona Chamber of Commerce March 18, 2015 Northeast Anthony Henday Drive Edmonton Ring Road Update Strathcona Chamber of Commerce March 18, 2015 Project Background 2 Edmonton Ring Road Northwest opened Nov 2011 Northeast to open Oct 2016 Southwest

More information

Appendix 4.1 L. No-Build Project Descriptions

Appendix 4.1 L. No-Build Project Descriptions Appendix 4.1 L No-Build Project Descriptions No-Build Projects New Bedford A new traffic signal system was installed and activated in early 2009 at the intersection of King s Highway and Mount Pleasant

More information

State Route 8 Corridor. Northern Summit County s Path to Success

State Route 8 Corridor. Northern Summit County s Path to Success State Route 8 Corridor Northern Summit County s Path to Success Construction Guide: 2008-2009 State Route 8 corridor work description State Route 8 Corridor 10 projects $262 million With its close proximity

More information

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 35EXPRESS PROJECT OVERVIEW 2 SEGMENT 1 3 SOUTH OF I-635 May Shift northbound mainlane traffic east in the southeast quadrant Miscellaneous frontage

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg)

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg) RELEASE: IMMEDIATE March 1, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 3 March 9, 2019 All work is scheduled weather permitting. Real-time information

More information

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS TRAFFIC ADVISORY For Immediate Release Christine Girardin 407-264-3069 January 19, 2018 Central and West Central Florida Weekly Lane Closures and Work Zone Advisory OCOEE Florida s Turnpike announces lane

More information

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk

STAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk STAGE 1 Viaduct removal, deck replacement on the River Bridge, and approach of the Chicago River Bridge north to Roscoe) Maintain local access roadways - 1 lane in each direction A signed alternate route

More information

TRAFALGAR PARK. 78: p.140 W 99th St FLAT ROCK CREEK PARK. W 103rd St OVERLAND PARK. Quivira Rd. College Blvd. Shared use path. Mountain bike trail

TRAFALGAR PARK. 78: p.140 W 99th St FLAT ROCK CREEK PARK. W 103rd St OVERLAND PARK. Quivira Rd. College Blvd. Shared use path. Mountain bike trail Lenexa: overview TRAFALGAR PARK 78: p.140 As the Westport Route crosses over Lenexa's boundaries with Olathe and Overland Park several times, approximately 2.75 or 3 miles of the historic route of the

More information

FY Transportation Improvement Program Basic Project List (in Thousands)

FY Transportation Improvement Program Basic Project List (in Thousands) FY2010-2014 Transportation Improvement Program Basic Project List (in Thousands) Project Name Key # Year Project Cost 16th Avenue North, 7th Street North to Garrity Boulevard GU09308 2011 $592 21st Avenue

More information

TRAFFIC ALERT FOR FEBRUARY 4-8, 2019 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR FEBRUARY 4-8, 2019 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE February 1, 2019 CONTACT: Sandy Myers 540-332-9201 (office) STA19 020 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

KDOT announces approved November bids

KDOT announces approved November bids IMMEDIATE RELEASE Nov. 27, 2018 For more information: Kim Stich 785.296.3585 KDOT announces approved November bids The Kansas Department of Transportation announces approved bids for state highway construction

More information

Project Location MP A44.5 MP A38 PRELIMINARY. A A57 (Future Project) A42 - A44.5 (Fall Fall 2019) A38 - A42. A31 - A38 - In Design

Project Location MP A44.5 MP A38 PRELIMINARY. A A57 (Future Project) A42 - A44.5 (Fall Fall 2019) A38 - A42. A31 - A38 - In Design RECONSTRUCTION AND WIDENING PROJECT Project Location A44.5 - A57 (Future Project) MP A44.5 Steinsburg Road (Fall 2015 - Fall 2016) John Fries Highway (Fall 2017 - Fall 2019) A42 - A44.5 (Fall 2017 - Fall

More information

FDOT Treasure Coast Traffic Report through

FDOT Treasure Coast Traffic Report through FDOT Treasure Coast Traffic Report 02 26 16 through 03 04 16 Kathleen Dempsey Fri 2/26/2016 2:56 PM To:Kathleen Dempsey ; 1 attachment 355 KB CR 714_Median Access Modifications.pdf;

More information

DULLES AREA HIGHLIGHTS. Gary Garczynski Commonwealth Transportation Board Northern Virginia District. Committee for Dulles August 4, 2016

DULLES AREA HIGHLIGHTS. Gary Garczynski Commonwealth Transportation Board Northern Virginia District. Committee for Dulles August 4, 2016 DULLES AREA HIGHLIGHTS Gary Garczynski Commonwealth Transportation Board Northern Virginia District Committee for Dulles August 4, 2016 Smart Scale (formerly HB2) Overview Round 1 completed with the adoption

More information

FREDERICKSBURG DISTRICT. District Engineer Marcie Parker, P.E. May 8, 2018

FREDERICKSBURG DISTRICT. District Engineer Marcie Parker, P.E. May 8, 2018 FREDERICKSBURG DISTRICT District Engineer Marcie Parker, P.E. May 8, 2018 3 Interstate 95 Projects Fredericksburg Area Fredericksburg region will see greatest degree of I-95 construction since widening

More information

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 March 25, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 TREASURE COAST Construction and maintenance-related

More information

Transportation TRANSPORTATION PROJECTS

Transportation TRANSPORTATION PROJECTS Transportation TRANSPORTATION PROJECTS Balls Ford Road Interchange Total Project Cost $142.9M This project includes the construction of a new diverging diamond interchange at Route 234 Bypass (Prince William

More information

TRAFFIC ALERT FOR MARCH 26-30, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR MARCH 26-30, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE March 23, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 057 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Falmouth)

Exit 148 (Quantico) to Exit 133 (Route 17/Falmouth) RELEASE: IMMEDIATE March 8, 2019 CONTACT: Tina.Bundy 540-907-8325 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 10 March 16, 2019 All work is scheduled weather permitting. Real-time information

More information

Palm Beach County Traffic Report July 13 through July 20, 2012

Palm Beach County Traffic Report July 13 through July 20, 2012 For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be

More information

U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County

U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County U.S. ROUTE 202 SECTION 300 IMPROVEMENT PROJECT East Whiteland Township Tredyffrin Township Chester County TMACC Information Session January 24, 2011 U.S. Route 202 Section 300 Project Limits U.S. ROUTE

More information

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018 FOR IMMEDIATE RELEASE Wednesday March 28, 2018 CONTACT: Nichole Lawrence CELL: 731-225-6041 West Tennessee Construction March 28-April 4, 2018 Per TDOT Specifications, there will be no temporary lane closures

More information

PennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects

PennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects PennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects Pittsburgh - PennDOT is pleased to announce the 2016 Allegheny County transportation improvement project list for state-owned

More information

ROUTE 630 DIVERGING DIAMOND INTERCHANGE

ROUTE 630 DIVERGING DIAMOND INTERCHANGE ROUTE 630 DIVERGING DIAMOND INTERCHANGE Virginia Department of Transportation Contract Value and Dates Contract Value: $99,949,969.50 Start of Construction: Summer 2017 Final Completion Date: July 31,

More information

FY Transportation Improvement Program Basic Project List (in Thousands) - Application Not Funded

FY Transportation Improvement Program Basic Project List (in Thousands) - Application Not Funded FY2011-2015 Transportation Improvement Program Basic Project List (in Thousands) - Application Not Funded Requesting Agency: ACHD Project Name Key # Year Project Cost ACHD Thin Lift Overlay Projects 11922

More information

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell)

RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers (office) STA (cell) RELEASE: IMMEDIATE September 14, 2012 CONTACT: Sandy Myers 540-332-9201 (office) STA12-130 540-292-2500 (cell) Sandy.Myers@VDOT.Virginia.gov Marshall Barnhill 540-332-9264 (office) 540-414-5670 (cell)

More information

5.1 Traffic and Transportation

5.1 Traffic and Transportation 5.1 When it opens in 2009, the Bellevue Nickel Improvement Project will increase the number of vehicles able to travel through the study area, improve travel speeds, and improve safety by reducing the

More information

Introduction. Project Overview

Introduction. Project Overview Washington Blvd./Andora Widening Project Community Open House & Public Scoping Meeting Summary Wednesday, September 21, 2016 6:00 7:30 p.m. Vencil Brown Elementary School, Roseville Introduction On Wednesday,

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT June 12 June 18, 2016

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT June 12 June 18, 2016 RELEASE: IMMEDIATE June 10, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov

More information

TRAFFIC ALERT FOR MARCH 5-9, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR MARCH 5-9, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE March 2, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-042 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

October 31, 2014 Chuck McGinness, (954)

October 31, 2014 Chuck McGinness, (954) From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 10 31 14 through 11 07 14 Date: Friday, October 31, 2014 2:59:04 PM Attachments: image002.png October

More information

Site Location and Setting

Site Location and Setting Memorandum Date: To: From: Subject: Kristy Le, Gary Black Steve Orem Santa Teresa County Park Historic Area Traffic and Parking Study Hexagon Transportation Consultants, Inc. has completed a traffic and

More information

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule Report for Monday, September 10, 2018 through Monday, September 17, 2018 S. Perry Park Rd. (DC105) and Red Rocks Dr. Intersection Improvements Safety improvements on the S. Perry Park Road (DC 105) and

More information

Lake Erie Commerce Center Traffic Analysis

Lake Erie Commerce Center Traffic Analysis LOCATION: East of NYS Route 5 at Bayview Road Town of Hamburg Erie County, New York PREPARED BY: Wendel Companies 140 John James Audubon Parkway Suite 200 Amherst, New York 14228 January 2012 i ii Table

More information

Whittier Bridge Project

Whittier Bridge Project Amesbury / Newburyport / Salisbury Whittier Bridge / I-95 Improvement Project Original Whittier Bridge Proposed Whittier Bridges 10/21/2016 Whittier Bridge Project 1 Project Description The project limits

More information

May 16, 2014 Chuck McGinness, (954) BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014

May 16, 2014 Chuck McGinness, (954) BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014 May 16, 2014 Chuck McGinness, (954) 777-4090 chuck.mcginness@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT May 16 through May 23, 2014 FORT LAUDERDALE -- Construction and maintenance-related lane

More information

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR JANUARY 15-19, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE January 11, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18-007 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness,

BROWARD COUNTY TRAFFIC IMPACT REPORT March 13 through March 20, March 13, 2015 Chuck McGinness, From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 03 13 15 through 03 20 15 Date: Friday, March 13, 2015 2:43:29 PM Attachments: image001.png BROWARD COUNTY

More information

FEASIBILITY STUDY REFINED CONCEPT 1 PROJECT A

FEASIBILITY STUDY REFINED CONCEPT 1 PROJECT A VIRGINIA DEPARTMENT OF TRANSPORTATION I-85 / I-95 INTERCHANGE FEASIBILITY STUDY REFINED CONCEPT 1 PROJECT A Columbia Rd REFINED CONCEPT 1 PROJECT A Bellevue Rd COST: $3.3M Siege Rd Eliminate the loop ramp

More information

Section 106 Update Memo #1 Attachment D. Traffic Diversion & APE Expansion Methodology & Maps

Section 106 Update Memo #1 Attachment D. Traffic Diversion & APE Expansion Methodology & Maps Section 106 Update Memo #1 Attachment D Traffic Diversion & APE Expansion Methodology & Maps I-65/I-70 North Split Interchange Reconstruction Project (Des. Nos. 1592385 & 1600808) Traffic Diversion and

More information

APPENDIX K RURAL ENVIRONMENTAL CLEARANCE PROJECTS

APPENDIX K RURAL ENVIRONMENTAL CLEARANCE PROJECTS APPENDIX K RURAL ENVIRONMENTAL CLEARANCE PROJECTS Appendix K contains a list of projects that are not planned for construction within the four-year time frame of the Rural TIP, but are referenced in the

More information

BY-LAW NO TO DIVIDE THE TOWN S TERRITORY INTO SIX ELECTORAL DISTRICTS

BY-LAW NO TO DIVIDE THE TOWN S TERRITORY INTO SIX ELECTORAL DISTRICTS BY-LAW NO. TO DIVIDE THE TOWN S TERRITORY INTO SIX ELECTORAL DISTRICTS ADOPTION PROCEDURE SUMMARY NOTICE OF MOTION: MARCH 21, 2016 ADOPTION OF BY-LAW: MAY 16, 2016 COMING INTO EFFECT: OCTOBER 31, 2016

More information

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley

More information

Culpeper District. Albemarle County Monthly Report December 2011

Culpeper District. Albemarle County Monthly Report December 2011 Culpeper District Albemarle County Monthly Report Special Issues Construction Significant Accomplishments (as of 11/15/11) Georgetown Road completed on November 8. I-64 Eastbound Shadwell Exit completed

More information

Route 29 Solutions Projects

Route 29 Solutions Projects Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement

More information

* Short term resurfacing projects are not included in this listing. 4T39.07 Project: Annual Rural County Sign Improvements, Genesee/Orleans Counties

* Short term resurfacing projects are not included in this listing. 4T39.07 Project: Annual Rural County Sign Improvements, Genesee/Orleans Counties New York State Department of Transportation 2008 Highway/Bridge Construction Projects * Short term resurfacing projects are not included in this listing. Genesee 4T39.07 Project: Annual Rural County Sign

More information

4. Safety Concerns Potential Short and Medium-Term Improvements

4. Safety Concerns Potential Short and Medium-Term Improvements NH Route 104 Access Management Study Page 19 4. Safety Concerns Potential Short and Medium-Term Improvements Potential safety improvement strategies are listed by priority based on field observations by

More information

Work in 2015 and Annual Mobility- Management Plan

Work in 2015 and Annual Mobility- Management Plan Work in 2015 and Annual Mobility- Management Plan KPH-Turcot July 14, 2015 2 Presentation Outline Division into sectors Work in 2015 without disruptions West sector Center sector East sector South sector

More information

user s guide to Transportation Improvements in Astoria Planning Efforts outside Astoria for more information, contact:

user s guide to Transportation Improvements in Astoria Planning Efforts outside Astoria for more information, contact: The Miles Crossing/ Jeffers Garden transportation plan (underway), will identify needed improvements to the Warrenton Astoria Highway and local street improvements to serve expected growth in the Miles

More information

Construction underway. STATUS: 229 5,190 5,419 5,305 STIP REFERENCE #FR /01/2013

Construction underway. STATUS: 229 5,190 5,419 5,305 STIP REFERENCE #FR /01/2013 FREDERICK COUNTY STATE HIGHWAY ADMINISTRATION -- Frederick County -- Line 1 PROJECT: I-7, Baltimore National Pike INTERSTATE CONSTRUCTION PROGRAM DESCRIPTION: Widen I-7 east of MD 355 to east of MD 144

More information

Need County Priority Needs Identification Major Projects/Emerging Taking Care of the System (TCOS) 1=High 2=Medium 3=Low

Need County Priority Needs Identification Major Projects/Emerging Taking Care of the System (TCOS) 1=High 2=Medium 3=Low PIONEER TRAILS REGIONAL PLANNING COMMISSION TRANSPORTATION NEEDS -- 2015 TRANSPORTATION PLANNING GOALS BY MODOT CATEGORIES Pioneer Trails transportation needs are listed according to MoDOT s two major

More information

Cell: (408) Release MA June 25, 2012

Cell: (408) Release MA June 25, 2012 VTA NEWS CONTACT: Bernice Alaniz FOR IMMEDIATE RELEASE Cell: (408) 888-9983 Release MA 12 06 08 Bernice.Alaniz@vta.org June 25, 2012 Construction Activities Underway For BART Silicon Valley The Santa Clara

More information

MONTANA CONSTRUCTION REPORT 06 / 14 / 2016

MONTANA CONSTRUCTION REPORT 06 / 14 / 2016 MONTANA CONSTRUCTION REPORT 06 / 14 / 2016 ROAD INCIDENTS DUE TO FIRES AND FLOODING PLEASE CHECK OUR WEBSITE FOR MORE UP TO DATE CLOSURES AND INFORMATION http://www.mdt.mt.gov/travinfo/scripts/alerts.pl

More information

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place.

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place. EASTER 2019 VDOT will lift most lane closures for holiday travel from noon Friday, April 19 until noon Tuesday, April 23. However, motorists may encounter semi-permanent work zones or travel delays in

More information

All closures this week happen at night, including full closures of Mesa and I-10

All closures this week happen at night, including full closures of Mesa and I-10 NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov May 25, 2018 North Mesa Tuesday, May 29 through Thursday, May 31 9 p.m. each

More information

El Dorado County / Tahoe Roadwork Schedule Sunday through Saturday September 9 September 15, 2012

El Dorado County / Tahoe Roadwork Schedule Sunday through Saturday September 9 September 15, 2012 Today s Date: Friday, September 7, 2012, #12-255 District: District 3 - Marysville, http://www.dot.ca.gov/dist3 Jody Jones, District Director Contact: Deanna Shoopman deanna_shoopman@dot.ca.gov 530. 741.4566

More information

Viaduct Demolition at Girard Interchange

Viaduct Demolition at Girard Interchange i-95news summer/fall 2015 2015 Stay current with construction at the Cottman Avenue, Betsy Ross Bridge/Aramingo Avenue and Girard Avenue interchanges at. PennDOT is enhancing communications with its I-95

More information

Changes in TIP projects Draft vs. Final Draft

Changes in TIP projects Draft vs. Final Draft Attachment 2 Dollars in $1,000 Key 08698 Franklin Road and Cloverdale Road Intersection Changes in TIP projects Draft vs. Final Draft RW - $1,314 UT - $1,000 CE - $341 CN - $3,675 CN - $499 09438 Caldwell

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016 RELEASE: IMMEDIATE Aug. 12, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Stafford County Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov

More information

Road Construction Ahead January-April 2015 NORTHWEST REGION

Road Construction Ahead January-April 2015 NORTHWEST REGION NORTHWEST REGION 1 Interstate 64 Augusta, Nelson, Albemarle counties: Installing communications conduit in median for active traffic management system on Afton Mountain. Periodic left-shoulder closures,

More information

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR DECEMBER 25, 2017 to JANUARY 5, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE December 21, 2017 CONTACT: Sandy Myers 540-332-9201 (office) STA17-204 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

2012 Boundary Counts October 5, 2011 Skyward Data Populations Within Boundaries October 5, 2011

2012 Boundary Counts October 5, 2011 Skyward Data Populations Within Boundaries October 5, 2011 STUDENT ACHIEVEMENT ATTENDANCE BOUNDARY CHANGE BACKGROUND INFORMATION: As a result of closing Dakota Middle School at the end of the current school year and opening East Middle School, it is necessary

More information

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND

CONSTRUCTION PROJECTS IN CUYAHOGA COUNTY CLEVELAND EUCLID 3/9/18 RICHMOND MAYFIELD HIGHLAND HEIGHTS HEIGHTS SOUTH EAST MAYFIELD EUCLID CLEVELAND BAY VILLAGE WESTLAKE OLMSTED NORTH TOWNSHIP OLMSTED FALLS OLMSTED BEREA STRONGSVILLE ROYALTON NORTH BROOK PARK PARMA PARMA BROADVIEW BRECKSVILLE HILLS SEVEN INDEPENDENCE BROOKLYN RIVER ROCKY LAKEWOOD PARK

More information

Northeast Corridor Transportation Update

Northeast Corridor Transportation Update Northeast Corridor Transportation Update Presented by: Stuart Basham Division 10 Planning Engineer North Carolina Department of Transportation October 2, 2014 Today s presentation includes: I-485 Outer

More information

PARK AND RIDE FROM THE GOLDEN TRIANGLE (DOWNTOWN) GARAGES WITH CONVENIENT SHUTTLE BUSES

PARK AND RIDE FROM THE GOLDEN TRIANGLE (DOWNTOWN) GARAGES WITH CONVENIENT SHUTTLE BUSES The current development taking place on the North Shore will be affecting a lot of things during the 2009 season at Heinz Field especially the parking situation. Unless you have pre-sold parking, the best

More information

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015

May 1, 2015 Chuck McGinness, BROWARD COUNTY TRAFFIC IMPACT REPORT May 1 through May 8, 2015 From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 05 01 15 through 05 08 15 Date: Friday, May 01, 2015 3:10:15 PM Attachments: image001.png May 1, 2015

More information

Important Lane Closures, April 3 9, 2011

Important Lane Closures, April 3 9, 2011 March 31, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 marcia.mcallister@dullesmetro.com Important Lane Closures, April 3 9, 2011 RESCHEDULED: Lane Shifts of Westbound Route 7 at Route

More information

US 19 Sunset Point Rd to Countryside Blvd.

US 19 Sunset Point Rd to Countryside Blvd. Frontage Lanes Alternative Six-Lane Roadway Two-Lane, One-Way Frontage Lanes Close All Median Openings w/ Concrete Median Barrier Construct Within Existing Right-of-Way Status Update Construction started

More information

ARMSTRONG COUNTY. Roadway realignment of PA 28 from State Route 1027 to State Route 1016 (Calhoun School Road) in Boggs Township 1 $ 7,850,

ARMSTRONG COUNTY. Roadway realignment of PA 28 from State Route 1027 to State Route 1016 (Calhoun School Road) in Boggs Township 1 $ 7,850, BRIDGE SD MILES IMPROVED BASE Bridge Replacement Lower Pine Run Bridge Replacement Bridge Replacement on Township Road 748 over Pine Run in Redbank Township 1 $ 1,600,000 1 1 0 BASE Bridge Replacement

More information

Ohio Department of Transportation Traffic Advisory. District 4 Allen C. Biehl, P.E., Deputy Director S. Arlington Road.

Ohio Department of Transportation Traffic Advisory. District 4 Allen C. Biehl, P.E., Deputy Director S. Arlington Road. Ohio Department of Transportation Traffic Advisory District 4 Allen C. Biehl, P.E., Deputy Director 2088 S. Arlington Road. Akron, Ohio 44306 www.transportation.ohio.gov/dist4 Friday, September 18, 2015

More information

Fuller/Fuller Heights Road Improvements

Fuller/Fuller Heights Road Improvements Fuller/Fuller Heights Road Improvements Total Project Cost - $4.4M Project Description This project will construct a mini-roundabout at the intersection of Fuller Heights Road and Old Triangle Road to

More information

Welcome to the Business Owners Task Force. Perry Leonard Blagg Tire and Service President/COO

Welcome to the Business Owners Task Force. Perry Leonard Blagg Tire and Service President/COO Welcome to the Business Owners Task Force Perry Leonard Blagg Tire and Service President/COO Safety: West Nile Virus Alyssa Tenorio NorthGate Constructors Public Information Manager West Nile Virus Carried

More information

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov Major Operation: 36 massive beams will be placed at Sunland & I 10. Operation

More information

AGENCY NAME TRANSPORTATION

AGENCY NAME TRANSPORTATION TRANSPORTATION TRANSPORTATION AGENCY NAME Prince William County FY 2015 BUDGET CIP-TRANSPORTATION 561 Fuller Road/Fuller Heights Road Improvements Total Project Cost - $4.4 M This project will widen Fuller

More information

Palm Beach County Traffic Report August 24 through August 31, 2012

Palm Beach County Traffic Report August 24 through August 31, 2012 For Immediate Release August 24, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report August 24 through August 31, 2012 Palm Beach County Palm Beach County traffic will

More information

2008 DEKALB COUNTY TRANSPORTATION PLAN (UPDATE)

2008 DEKALB COUNTY TRANSPORTATION PLAN (UPDATE) 2008 DEKALB COUNTY TRANSPORTATION PLAN (UPDATE) TABLE OF CONTENTS Introduction 1 Transportation Planning Activities 2 Identification of Problem Areas and Recommended Solutions 7 DeKalb County Projects

More information

TRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE February 8, 2019 CONTACT: Sandy Myers 540-332-9201 (office) STA19 027 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell)

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell) RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye 540-899-4019 (office) 540-907-8409 (cell) Darragh.Frye@VDOT.Virginia.Gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT October 8 October 14,

More information

GILLESPIE STREET SITE SITE DATA SHEET

GILLESPIE STREET SITE SITE DATA SHEET 1 of 7 PHYSICAL CHARACTERISTICS SIZE: 40.34 Acres LOCATION: This site is located on this southern edge of the Fayetteville Metro Area. It offers excellent accessibility to many areas of the city, including

More information

Pedestrian Safety Review Spadina Avenue

Pedestrian Safety Review Spadina Avenue STAFF REPORT ACTION REQUIRED Pedestrian Safety Review Spadina Avenue Date: October 13, 2015 To: Toronto and East York Community Council From: Director, Transportation Services, Toronto and East York District

More information

CONFIRMED BENCHMARKS UPDATED JUNE 26, 1991

CONFIRMED BENCHMARKS UPDATED JUNE 26, 1991 CONFIRMED BENCHMARKS UPDATED JUNE 26, 1991 1. Chiseled square on southwest side of street light base, in median of Gus Thomasson Rd., 40' northeast of centerline of Jamaica Way. Elevation: 536.49 2. Chiseled

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE Sept. 28, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Sept. 30 Oct. 6, 2018 All

More information

BICYCLE AND PEDESTRIAN COUNT PROGRAM 2016 Annual Report

BICYCLE AND PEDESTRIAN COUNT PROGRAM 2016 Annual Report BICYCLE AND PEDESTRIAN COUNT PROGRAM 2016 Annual Report TABLE OF CONTENTS A Message from the Mayor... 4 Data Count Reports... 5 Count Locations... 6 Count Locations Map... 7 Trail Data... 8 International

More information

Construction Staging Adelaide Street West

Construction Staging Adelaide Street West REPORT FOR ACTION Construction Staging Adelaide Street West Date: October 6, 2016 To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto and East York District

More information

Weekly construction update

Weekly construction update November 4, 2011 For more information, contact: Kim A. Rudat, Regional Communications Manager Kim.Rudat@dot.wi.gov, (920) 492-5743 For US 41 Expansion Project information, contact: Kris Schuller, US 41

More information