2 EXPANSION PROGRAM COMPONENTS Third Set of Locks The project consists of the design and build of new Post-Panamax locks in the Pacific and Atlantic sides of the Panama Canal. Each complex will feature three chambers, nine water-saving basins, a lateral filling and emptying system and 16 rolling gates. Pacific Access Channel This project undertakes the creation of a new access channel north of the Third Set of Locks on the Pacific side. It was divided into four phases (PAC 1-4) and entails the excavation of approximately 5 million cubic meters of earth or various geologic materials along 6.1 kilometers. Improvement of the navigation channels This component includes dredging of both entrances to the Canal and the course of the Culebra Cut and Gatun Lake. Improvement of the water supply These works will allow a 45 centimeter rise of the maximum operating level of Gatun Lake which will increase the Canal s water supply and reliability of its draft Atlantic entrance dredging 2. New Atlantic locks 3. Gatun Lake
3 PROJECTS The Panama Canal Expansion Program registers 81.6 % overall progress, as stated in the October 31, 2014 Report to the Nation. PACIFIC ACESS CHANNEL 43.8 M m³ excavated of 49 M m³ Progress as of October 31, 2014: 81% The 2.3 kilometers-long Borinquen 1E Dam is built west of the Pedro Miguel Locks. The dry excavation of a new channel to connect the Third Set of Locks with the Culebra Cut started on September 2007, when the expansion works were officially inaugurated. This project was divided into four phases: the first three have concluded successfully. The fourth and last is performed by the ICA-FCC-MECO consortium and it was awarded on January 7, A vital part of this project is the construction of a 2.3 kilometer-long dam to make up for the 9 meters difference in levels between Miraflores Lake and the new channel. Made of rock and an impermeable clay core it will separate the two fairways. Borinquen 1E its given name will be located west of the Pedro Miguel Locks. The dry excavation has required the clearing of 400 hectares of land contaminated with unexploded ordnance (UXO) left behind by the US military during its deployment in the Panama Canal Zone. 4. Culebra Cut entrance/exit 5. Pacific Access Channel 6. Miraflores Lake 7. New Pacific Locks 8. Pacific entrance dredging 3
4 DREDGING To guarantee the safe navigation of Neo-Panamax ships along the Canal s route, the Expansion Program included dredging projects on both oceanic entrances, Culebra Cut and Gatun Lake. The deepening and widening activities on the Atlantic and Pacific entrance have already concluded. Trailing suction hopper dredger De Boungainville removed material on the Atlantic entrance of the Panama Canal. Pacific Entrance 8.6 M m³ dredged Contract award: April 7, 2008 End of contract: July 31, 2013 This contract was awarded to the Belgian company Dredging International Panama, S. A. (DI). The project consisted of deepening the Canal s Pacific entrance to 15.5 meters below mean low water level and widening it to 225 meters. It also entailed the partial construction of the south access of the new locks. For this project DI deployed the powerful dredgers D Artagnan, Vlanderen XI and Lange Wapper. Atlantic Entrance 17.6 M m³ dredged Contract award: September 25, 2009 End of contract: October 4, 2013 Jan De Nul n.v. (Belgium) won the tender for this contract. It dredged 13.8 kilometers and widened the current navigation channel on the Atlantic entrance to a minimum of 225 meters and the access channel to the new locks to a minimum of 218 meters. An option to increase the depth from the established 15.5 meters to 16.1 meters was exercised in this contract, meaning an additional volume of 2.3 million cubic meters was dredged. A great variety of equipment was deployed simultaneously, among them the trailing suction hopper dredger Fillipo Bruneleschi and cutter suction Marco Polo. The operation concluded on January 30, 2013 when the Neo-Panamax dredger Charles Darwin removed the last high points of the expanded access. 4
5 CULEBRA CUT AND GATUN LAKE 24.3 M m³ dredged of 26 M m³ Progress as of October 31, 2014: 88% This project calls for the removal of subacuatic material to deepen and widen the navigation channel in the Gatun Lake and the Culebra Cut. Works for the latter were concluded by the end of Activities on the lake are mostly carried out by personnel and equipment of the Panama Canal Dredging Division, however they count with additional support from dredgers Il Principe y Cornelius, both rented from Boskalis Panama S.A. Remaining works were awarded to contractors Jan De Nul n.v. (North access to the new locks on the Pacific, finished on November 2012) and Dredging International (reaches at the north of Gatun Lake, finished on March 2012). The Dredging Division continues dredging on the lake using the hydraulic dredger Mindi, mechanical Rialto M. Christensen, cutter suction Quibian I and backhoe Alberto Aleman Zubieta. Thirty-three new sailing range towers have been installed along 38 kilometers of Gatun Lake, from Gamboa to the Atlantic locks. RAISING GATUN LAKE S MAXIMUM OPERATING LEVEL The Lake s level will increase 45 centimeters. Progress as of October 31, 2014: 93% This component of the Program consists of raising Gatun Lake s maximum operating level from 26.7 meters to 27.1 meters to improve the Canal s water supply. This improvement will increase the reservoir capacity by 200 million cubic meters of water, thus adjustments and modifications will be required to the structures of the existing locks. The 14 gates of the Gatun spillway have been extended to contain the new level and two additional gates were built at the Canal s industrial dry dock. In 2014, 32 hydraulic cylinders for the gates-opening mechanism were replaced on the Gatun and Pedro Miguel Locks to install new waterproof units. 5
6 6
7 7
8 DESIGN AND CONSTRUCTION OF THE THRID SET OF LOCKS Conceptual design of the Thrid Set of Locks M m³ excavated of 48.7 M m³ Progress as of October 31, 2014: 78% The design and construction of the Third Set of Locks is the largest and most complex project under the Expansion Program. With a cost of B/.3.2 billion, the contract is carried out by the consortium Grupo Unidos por el Canal, S.A. (GUPCSA), formed by Sacyr Vallehermoso, S.A. from Spain; Impregilo SpA, from Italy; Jan De Nul n.v., from Belgium, and Constructora Urbana, S.A. from Panama. The project involves the design and construction of two lock complexes, one on the Pacific and the other on the Atlantic side. Each will have three chambers, nine watersaving basins, a lateral filling and emptying system and a redundant system of rolling gates. The design of the Third Set of Locks, like the fabrication of some of its components, are developed in several parts of the world. In Italy, Cimolai S.p.A. fabricated the 16 gates that have already been delivered to Panama. South Korea, Hyundai Samho Heavy Industries fabricated 158 valves, 84 bulkheads and 328 trashracks. Their last delivery was on January 15, To build the new locks, the contractor erected industrial parks on each site for the concrete and aggregate production. The rock extracted from the Pacific side excavations basalt is used as aggregate and sand for the concrete mixes on both sites. EXISTING LOCKS Maximum capacity of transiting vessels 4,400 TEU m 33.5 m NEW LOCKS Maximum capacity of transiting vessels 13,000-14,000 TEU 49 m 366 m 55 m Vessel draft Lock wall height 30 m 427 m m Operating water depth 18.3 m Vessel draft 12.8 m min. Operating water depth The new rolling gates are easier to service. 8
9 ARRIVAL OF THE ROLLING GATES Six different types of gates were fabricated; their characteristics will depend on their location. The 16 rolling gates to be installed in the Third Set of Locks are in Panama already. Four shipments of four gates each sailed from the port of Trieste, in northern Italy, to Colon, on the Canal s Atlantic side. The first arrival happened on August 20th, 2013; the second on June 10th, 2014; the third on September 7th, 2014, and the last one on November 12th, The rolling gates system is one of the most significant element of the design and construction of the locks. Its cost of B/ million includes fabrication, transport and installation. Each one will open and close in five minutes. There will be six different types of gates and their characteristics vary according to where they will be installed. For example, the tallest ones 33.4 meters will be installed at the Pacific entrance of the Canal to resist the significant tidal oscillation. Even though the heaviest gates are 4,242 tons, they were designed with flotation chambers to be able to slide on rails with only 15% of its weight. The unloading and installation of the gates is done with transport vehicles with hundreds of wheels and remotely operated. The gates will be moved inside the recesses before the flooding, allowing installation time of mechanical parts to be reduced once the concrete walls are finished. In the second semester of 2014, the gates were moved to begin their installation. In July, five of them were mobilized to the chambers in the Atlantic locks, and between October and November, other six transited the Canal and arrived at a dock specially designed in the area of Cocoli, in the Pacific. The gates are mobilized with special transport vehicles that are remotely operated. 9
10 ENVIRONMENT Environmental activities on the Expansion Program continue with the coordination between contractors and Panamanian institutions, such as the National Environment Authority (ANAM) and the National Authority of Aquatic Resources (ARAP). LOCATION OF REFORESTATION PROJECTS 1. Volcan Baru National Park - 30 ha 2. Chiriqui Viejo River Mangrove - 50 ha 3. Forest Research Center ha 4. El Montuoso Forest Reserve - 50 ha 5. Omar Torrijos National Park ha 6. Altos de Campana National Park - 30 ha 7. Camino de Cruces National Park ha 8. Chagres National Park - 40 ha 9. Tapagra Hydro-Protected Zone, Chepo - 61 ha 10. Bahía de Chame Multiple Use Zone - 59 ha 11. Soberania National Park - Camping Resort - 65 ha 12. Soberania National Park - Aguas Claras - 62 ha PALEONTOLOGICAL AND ARCHAEOLOGICAL RESEARCH To date, more than 5,600 mammals, birds, reptiles and amphibians have been rescued and relocated. As part of the ecological compensation, reforestation with native species continues in 813 hectares two for each hectare affected by the Expansion Program. The ACP has paid B/.3,893, to ANAM and ARAP for the ecological indemnification of the Expansion Program. The Expansion Program also preserves the cultural heritage. Objects of great value have been rescued from the job sites like a 16th century Spanish dagger, pre- Columbian arrowheads, and bottles dating back to the beginning of the 20th century. In paleontological matters, a contract between ACP and the Smithsonian Tropical Research Institute (STRI) ended in The result: 8,862 samples of which 5,377 are rocks and sediment and 3,485 are fossils. Fossil finding during the excavation works. ACCOUNTABILITY To fulfill its responsibility of keeping the public informed about the Expansion Program, and in compliance with Law 28 of July 17, 2006, the Canal publishes quarterly progress reports. These contract reports are sent to the Executive Branch, the National Assembly, the Office of the Controller General, and the Ad-hoc Committee (formed by members of civil society). The contents of these reports are available for public review in the Canal Internet page at The Expansion Program has also established a hotline ( ) and an address (ampliacion@pancanal.com) to provide general information about the program. 10
11 LABOR The Expansion Program has been an important source of new jobs and training for professional in various fields. Since its inauguration, it has directly generated 36,000 jobs. Direct employment in the Expansion Program (until September 2014) contractors and SUB CONTRAcTors panama canal TOTAL FINANCING Accumulated jobs 34,818 1,182 36,000 active jobs 9, ,494 The Panama Canal Authority signed agreements with five bilateral and multilateral financing institutions to procure financing of up to B/.2.3 billion required to complete the Expansion of the waterway. All of these funds have already been paid out. 11
12
panama canal expansion program
panama canal expansion program september 2013 EXPANSION PROGRAM COMPONENTS Post-Panamax Locks Construction of the new locks complexes on the Pacific and Atlantic sides. Each one of the locks complexes
More informationJhan Schmitz. Executive Sponsor Panama Canal Expansion Program
Jhan Schmitz Executive Sponsor Panama Canal Expansion Program Capacity constraints need to double the capacity of the existing canal Accommodate post-panamax vessels Enhance Panama s strategic position
More informationThe Panama Canal Expansion Program. Alberto Alemán Zubieta Administrator Panama Canal Authority April 16, 2009
The Panama Canal Expansion Program Alberto Alemán Zubieta Administrator Panama Canal Authority April 16, 2009 Dredging Investment Program Accumulated Investment (in millions of US Dollars) 1,877 Locomotives
More informationThe Panama Canal: A Challenge to Efficiency in the 21st Century
The Panama Canal: A Challenge to Efficiency in the 21st Century Intertanko Chemical Conference April 8, 2008 Silvia de Marucci Leader, Liquid Bulk Segment smarucci@pancanal.com Physical Profile of the
More informationNEW TECHNOLOGIES AND THEIR IMPACT ON PORT DEVELOPMENT IN JAMAICA. Christopher Hamilton May
Organization Of American States Second Hemispheric Conference On Inland Ports, Waterways & Dredging NEW TECHNOLOGIES AND THEIR IMPACT ON PORT DEVELOPMENT IN JAMAICA Christopher Hamilton May 18 2017 2.83
More informationThe Panama Canal An Engineering Wonder
The Panama Canal An Engineering Wonder By Priyanka Ann Saini, Sea News - November 28, 2017 The Panama Canal is a modern day engineering wonder. It is approximately 80 kilometers long between the Atlantic
More informationPanama Jazz Festival
Panama Jazz Festival January 12-20, 2019 Day 1 Jan. 12 D On arrival at Tocumen International Airport in Panama City, transfer to the group hotel to rest before meeting your local guide and group for welcome
More informationSERVICE PROPOSAL FOR GROUPS
Company: American Immigration Lawyers Association Group size: to confirm Date: January 24-27 Hotel: InterContinental Playa Bonita Contact: Kathryn Chong Today`s date: December 11, 2012 Dear Ms. Chong,
More informationPANAMA HIGHLIGHTS PANAMA CITY PANAMA CANAL INDIGENOUS ENCOUNTER & THE COLONIAL TIMES
PANAMA HIGHLIGHTS PANAMA CITY PANAMA CANAL INDIGENOUS ENCOUNTER & THE COLONIAL TIMES Enjoy the most popular places in the Republic of Panama, you will be able to experience a fantastic mix of ecology,
More informationINTRODUCTION ITINERARY CENTRAL AMERICA MULTI COUNTRY - HIGHLIGHTS OF PANAMA TRIP CODE PNTSHOP DEPARTURE. Daily DURATION. 8 Days LOCATIONS.
INTRODUCTION This tour is a suggested itinerary designed by our specialist team! Choose this itinerary or alter it to design your own Journey. Discover some of the highlights of on this 8 day tour that
More informationPanama Canal: Expansion Status and Future Impact
Panama Canal: Expansion Status and Future Impact NUTC Business Advisory Council Meeting Evanston, IL - October 2015 Oscar Bazán Execu/ve Vice-President Planning and Business Development Panama Canal Authority
More informationPanama Adventure - 8 Days & 7 Nights
One amazing quality that makes Panama so unique is that from one location in Panama City travelers can enjoy so much of this beautiful country and its culture and nature without having to change hotels.
More informationAmerican Association of Port Authorities. Alberto Alemán Zubieta Administrator Panama Canal Authority January 26, 2010
American Association of Port Authorities Alberto Alemán Zubieta Administrator Panama Canal Authority January 26, 2010 The Panama Canal 1914 The Panama Canal Today The Panama Canal 2014 1915 1917 1919 1921
More informationThe New Locks of the Panama Canal. The Panama Canal Expansion Program
The New Locks of the Panama Canal PIANC Workshop Innovation in Navigation Lock Design Juan Wong H. Project Manager Third Set of Locks Pacific Panama Canal Authority 16 October, 2009 The Panama Canal Expansion
More informationIntroduction: Sample file. Instructions:
Introduction: Panama is the crossroads between North America and South America. From the days of early European explorers, people have looked for ways across the Isthmus of Panama. The French attempted
More informationPort of Durban. Entrance Channel Widening & Deepening Project Completion Function. 31 March 2010
Port of Durban Entrance Channel Widening & Deepening Project Completion Function 31 March 2010 Presented by: Theunis Steenkamp Project Director Natcor 1 The saying goes.. THE JOB IS NOT OVER UNTILL THE
More informationPIANC-World Congress Panamá City, Panamá, 2018
Contractual Model for Dredging Projects to Avoid Disputes: Case Studies of the application of Performance Based Contracts in dredging projects around the world. ABSTRACT Prieto-Portar, L. 1, Prins, J.
More informationPortMiami Director and CEO Juan M. Kuryla PUBLIC-PRIVATE PARTNERSHIPS (P3)
PortMiami Director and CEO Juan M. Kuryla PUBLIC-PRIVATE PARTNERSHIPS (P3) PORTMIAMI QUICK FACTS PortMiami is located in Miami-Dade County, one of the most diverse, multilingual populations in the U.S.
More information1/18/07 Day 4 This was one of the highlight days of the cruise when we will pass through the Panama Canal. Our route will take us from the Caribbean
1/18/07 Day 4 This was one of the highlight days of the cruise when we will pass through the Panama Canal. Our route will take us from the Caribbean Sea south to the Pacific Ocean through the locks, Gatun
More informationAmerican Institute of Marine Underwriters
American Institute of Marine Underwriters Mr. Scott Bergeron Chief Executive Officer, Liberian Registry Commissioner, Virginia Port Authority May 8, 2013 1 Existing Lock Dimensions vs. Expanded Lock Dimensions
More informationMIAMI INTERNATIONAL REAL ESTATE CONGRESS ERIC OLAFSON MANAGER TRADE DEVELOPMENT
MIAMI INTERNATIONAL REAL ESTATE CONGRESS ERIC OLAFSON MANAGER TRADE DEVELOPMENT Economic Impact One of Miami-Dade County s Principal Economic Engines 207,000 jobs $27 Billion annually 2 Cruise Capital
More informationDredging 101. Why, Who, How and So What! 2015 WAMSI Research Conference. 30 March 2015
Dredging 101 Why, Who, How and So What! 2015 WAMSI Research Conference 30 March 2015 Presentation Contents Quick Oversight on Why we need to Dredge and Who Carries it out Global Context of some of our
More informationDevelopment of New Markets for the Maritime Cluster
Development of New Markets for the Maritime Cluster 18 September, 2015 Palazzo San Giorgio Genoa, Italy Current Developments and Future Prespectives of the New Panama Canal: How the New Project will Affect
More informationOhio Freight Conference Great Lakes Commercial Navigation
Ohio Freight Conference Great Lakes Commercial Navigation Roger E. Haberly Regional Economist Buffalo New York 13 September 2013 US Army Corps of Engineers Presentation Overview 1. GL Physical System Description
More informationPanama THE AWAKENING DESTINATION
Panama THE AWAKENING DESTINATION Panama s leading corporate, meeting, and incentive groups DMC With more than 10 years in the industry, Gamboa Tours has developed luxurious programs for clients all over
More informationPort Everglades Overview
Port Everglades Overview Broward County Charter Review Infrastructure Subcommittee June 7, 2017 Steven M. Cernak, P.E., PPM Chief Executive & Port Director Jurisdictional Area Located in the cities of:
More informationCOMMONWEALTH OF THE BAHAMAS MINISTRY OF PUBLIC WORKS & TRANSPORT NASSAU HARBOUR PORT IMPROVEMENT PROJECT. Nassau Harbour Port Improvement Project
COMMONWEALTH OF THE BAHAMAS MINISTRY OF PUBLIC WORKS & TRANSPORT NASSAU HARBOUR PORT IMPROVEMENT PROJECT AUGUST 2009 OVERALL VIEW OF NASSAU HARBOUR AERIAL VIEW OF NASSAU HARBOUR PROJECT HISTORY 1960 s
More informationPanama Canal Expansion Antecedents
Panama Canal Expansion Antecedents May 1879: Baron Godin de Lepinay Canal Lock proposal at the International Congress for Study of an Interoceanic Canal ignored. January 1906: Report of the Consulting
More informationThe Panama Canal Expansion: Myths and Realities for the North American Economy
2015 Center for Transportation Studies Research Conference, University of Minnesota The Panama Canal Expansion: Myths and Realities for the North American Economy Jean-Paul Rodrigue Professor, Dept. of
More informationAdventuring Panama. The Journey
Adventuring Panama The Journey Day 1: Arrive in Panama City: Unfasten, unpack, unwind Upon arrival at the airport in Panama City, you will be greeted by our local crew and escorted to your hotel in the
More informationThe River Plate Experience; Maintenance Dredging by Means of Privatisation
The River Plate Experience Alan Lievens The River Plate Experience; Maintenance Dredging by Means of Privatisation Abstract At the beginning of the 1990s the Latin American continent needed to implement
More informationOperating and modernization of the Locks on the navigable canals Constanta - Romania
DANUBE INFORMATION SERVICES CONFERENCE DISC 2015 Budapest / Hungary, 08 th 09 th December, 2015 Operating and modernization of the Locks on the navigable canals Constanta - Romania General information
More informationRotary Humanitarian Mission
Rotary Humanitarian Mission Embera Indigenous Village 8:00 a.m. - 12:00 pm NET PRICE PER PERSON: $135.00 US. Minimum 6 Maximum 40 We will pick you up at the hotel and transfer you in a deluxe air conditioned
More informationNC Dredge Studies. Sterling Baker, P.E. NCDOT James Gregson NCDEQ April 5, 2018
NC Dredge Studies Study of the Use and Efficiency of the Dredge Manteo Study of Acquisition of Dedicated Dredging Capacity Study of Dredging Services Cost-Benefit Analysis Sterling Baker, P.E. NCDOT James
More informationAnnual Port Review. June 22, 2016
Annual Port Review June 22, 2016 2 Port Everglades by the Numbers (FY2015 unless indicated) #1 Seaport in Florida by Revenue - $153 million #1 Container Port in Florida - (#10 in U.S.) by volume 1,060,507
More informationPanama is the land bridge between two continents and divides two oceans, making it a crossroads of the world.
TOURISM IN PANAMA Panama is the land bridge between two continents and divides two oceans, making it a crossroads of the world. Each year hundreds of cruise ships transit a modern wonder of the world,
More informationNAFTA Next Chicago, Illinois April 23 rd, 2014
NAFTA Next Chicago, Illinois April 23 rd, 2014 IMPORTANCE OF THE PORT OF MIAMI TO FLORIDA/U.S. One of the top container seaports in Florida Second largest economic engine of Miami-Dade County Number 11
More informationDredging in Figures 2008 This review of the global dredging market focuses on the situation in 2008 and was published in October 2009.
Dredging in Figures 28 This review of the global dredging market focuses on the situation in 28 and was published in October 29. Maritime Solutions for a Changing World Dredging changes the world. Yet,
More informationNC Dredge Studies NCBIWA Spring Conference April 23, 2018
NC Dredge Studies Study of the Use and Efficiency of the Dredge Manteo Study of Acquisition of Dedicated Dredging Capacity Study of Dredging Services Cost-Benefit Analysis 2018 NCBIWA Spring Conference
More informationPanama2018. Always ready to serve! Bulletin 2
Bulletin 2 VI Interamerican Scout Forum Panama2018 XXVII Interamerican Scout Conference In a very short time we will be reunited again, holding the 6th Interamerican Scout Youth Forum and the 27th Interamerican
More informationMaximising Beneficial Reuse through the use of a Novel Dredging Contract
Maximising Beneficial Reuse through the use of a Novel Dredging Contract Nicola Clay & Katherine Harris Port of London Authority Nick Bray Dredging Research Paul Hesk Van Oord UK CEDA Dredging Days 2007
More informationCORPS OF ENGINEERS ALASKA DISTRICT Dredging Projects. Michael Tencza, PE Operations Project Manager November 4, 2015
CORPS OF ENGINEERS ALASKA DISTRICT 2016 Dredging Projects Michael Tencza, PE Operations Project Manager November 4, 2015 US Army Corps of Engineers Building and Preserving Alaska s Future AWARDED CONTRACTS
More informationport of brisbane Information Guide
port of brisbane Information Guide A B O U T U S The Port of Brisbane, managed by the Port of Brisbane Pty Ltd, is Queensland s largest general cargo and container port, and a driver of economic growth
More informationPORT DEVELOPMENT STRATEGIES & SUCCESS STORIES. PORTMIAMI AN EVOLVING GATEWAY Juan M. Kuryla, PPM PortMiami Director and CEO
PORT DEVELOPMENT STRATEGIES & SUCCESS STORIES PORTMIAMI AN EVOLVING GATEWAY Juan M. Kuryla, PPM PortMiami Director and CEO PORTMIAMI: AN EVOLVING GLOBAL GATEWAY PORT MISSION PortMiami s goal is to operate
More informationASL Marine Holdings Ltd.
ASL Marine Holdings Ltd. SHIPBUILDING SHIPREPAIR SHIPCHARTERING Pulse of Asia 2008 - Presentation 8 th July 2008 1 Presentation Outline Company Profile 9M FY2008 Financial Review Business Review - Shipbuilding
More informationCoral Reef Conservation. Panama
Coral Reef Conservation Panama Low nutrient levels Bocas del Toro Caribbean Sea Tides up to 0.5 m Temperatures 26-28 o C Guna Yala Narrow continental shelf Gulf of Chiriqui Without upwelling Temperatures
More informationU.S. Army Corps of Engineers Wilmington District
U.S. Army Corps of Engineers Wilmington District 2012 East Coast - WEDA October 9-11, 2012 Ongoing & Upcoming Contracts US Army Corps of Engineers Wilmington District Ongoing Contracts Project Quantity
More informationTurnover global dredging market 2009 per driver in mln
Dredging in Figures 2009 This review of the global dredging market focuses on the situation in 2009 and was published in October 2010. IADC is always very thorough and precise in estimating the dredging
More informationMOSE PROJECT: STATE-OF-THE-ART AND FUTURE DEVELOPMENT
AIPCN-France Third Mediterranean Days of Coastal and Harbour Engineering Troisièmes journées méditerranéennes de génie côtier et portuaire 23/05/2013 Marseille MOSE PROJECT: STATE-OF-THE-ART AND FUTURE
More informationTHE COMMERCIAL ROUTE OF PIRATES, CONQUERORS & PEOPLE CASCO ANTIGUO, PANAMA LA VIEJA, AGUA CLARA LOCK GATES, SAN LORENZO FORT, PORTOBELO 3D/2N
THE COMMERCIAL ROUTE OF PIRATES, CONQUERORS & PEOPLE CASCO ANTIGUO, PANAMA LA VIEJA, AGUA CLARA LOCK GATES, SAN LORENZO FORT, PORTOBELO 3D/2N Suggested age: 6 years and up The Experience The commercial
More informationPanama POST-CRUISE PACKAGES
Panama POST-CRUISE PACKAGES Welcome to Panama City! Located on the Pacific side of the American Continent, Panama City the capital of the Republic of Panama, is a beautiful, vibrant, cosmopolitan city.
More informationPort of Long Beach 2012 Capital Program Update. G.J. Cardamone, PE, FCMAA Director of Construction Management
Port of Long Beach 2012 Capital Program Update G.J. Cardamone, PE, FCMAA Director of Construction Management Who We Are 3,500 acres of land 4,600 acres of water 6 container terminals 66 Ship-to-Shore cranes
More informationDay 6 Panama Canal Transit 3/7/2012
Day 6 Panama Canal Transit 3/7/2012 The Panama Canal joins the Atlantic and Pacific oceans and is a key route for international maritime trade. One of the largest and most difficult engineering projects
More informationPanama Canal Outlook. Jorge L. Quijano Administrator/CEO Panama Canal Authority
Panama Canal Outlook Jorge L. Quijano Administrator/CEO Panama Canal Authority Japan November 21, 2014 Yesterday PANAMA AT A GLANCE GDP growth rate last 10 years 7.5% GDP (P) 2013 (billion of dollars)
More informationMAPUTO PORT DEVELOPMENT COMPANY
MAPUTO PORT DEVELOPMENT COMPANY PORT OF MAPUTO MAY 2015 Concession Information MPDC has the concession rights to operate the Port of Maputo and the approved concession period ends in 2033 with an option
More informationAmended Maintenance Dredge Spoil Management Plan. Shute Harbour Marina Resort
Amended Maintenance Dredge Spoil Management Plan Shute Harbour Marina Resort Amended Maintenance Dredge Spoil Management Plan Quality Information Document Ref Amended Maintenance Dredge and Spoil Maintenance
More informationExpanding Capacity of the Panama Canal
Expanding Capacity of the Panama Canal TRB 2006 Summer Conference La Jolla, California July 9-11, 2006 Rodolfo Sabonge Director, Corporate Planning and Marketing We are all part of the Global Transportation
More informationBigger, Deeper, Wider
Bigger, Deeper, Wider About Port Freeport Government entity created by voters in 1925 Local sponsor for the Freeport Harbor Channel and engages with the U.S. Army Corps of Engineers Significant responsibilities
More informationPort Everglades: Making The Last Mile Count. AAPA Annual Convention November 3, 2015
Port Everglades: Making The Last Mile Count AAPA Annual Convention November 3, 2015 Port Everglades Overview Enterprise Fund of Broward County Government Operations are supported 100% by user fees; no
More informationPanama Canal Stakeholder Working Group Meeting
Panama Canal Stakeholder Working Group Meeting POHA, Bayport Container Terminal, Houston, Texas August 27, 2012 TOTAL ECONOMIC IMPACT 9,749 Texas jobs are in some way related to the Port Of the 9,749
More informationPort Everglades 2014 Master/Vision Plan Update
1 Port Everglades 2014 Master/Vision Plan Update Environmental Stakeholders Meeting May 27, 2014 2 Agenda 2014 Master/Vision Plan Update Process Status of 2009 5-Year Master Plan Projects Summary of Market
More informationTSAKOS INDUSTRIAS NAVALES S.A.
2017 TSAKOS INDUSTRIAS NAVALES S.A. OUR COMPANY TSAKOS INDUSTRIAS NAVALES S.A. shipyard is located in the heart of the beautiful natural harbor of Montevideo, safe city of European appearance, Uruguay
More informationProject Data Sheet BASIC PROJECT DATA
BASIC PROJECT DATA Full project title: Short project title: (acronym) Improvement of navigation in the joint Bulgarian-Romanian section of the Danube river from km 530 to km 520 Batin and from km 576 and
More informationThe Lesser Antilles. Dominican Republic), and Puerto Rico
The Caribbean Islands are archipelagoes or groups of islands. The major archipelagoes are: The Greater Antilles - Cuba, Jamaica, Hispaniola (Composed of Haiti and the Dominican Republic), and Puerto Rico
More informationUnlocking Panama? Some thoughts on the impact of the Canal expansion on liner and bulk sea trade
Unlocking Panama? Some thoughts on the impact of the Canal expansion on liner and bulk sea trade Presentation to the Maritime Law Association annual conference 2 September 2017 Trevor Jones Director Unit
More informationFile of the company PEDRO ESTÉVEZ, S.L.
File of the company PEDRO ESTÉVEZ, S.L. www.pestevez.com/english C/ Lomo la Plana, 41, bajo Izq. 35019 Las Palmas. SPAIN Phone number: +34 928415771 Fax: +34 928415092 Who whe are? The company was founded
More informationPort Everglades Master/Vision Plan Update
Port Everglades Master/Vision Plan Update Public Meeting June 24, 2013 Agenda Port Everglades Overview Project Background Infrastructure Needs Identified in 2009 Plan Review of Priority Projects Review
More informationThe Americas. Port of the Americas. Rhonda M. Castillo Gammill, Esq., P.E. Executive Director, Port of the Americas Authority
Port of the Americas Rhonda M. Castillo Gammill, Esq., P.E. Executive Director, Port of the Americas Authority Public Corporation created by Law 171 of August 11, 2002 Objective: promote, develop, improve,
More informationSALLE miró, unesco paris, france
SALLE miró, unesco paris, france 8-19 October, 2018 panama: connecting cultures for sustanaible development Autoridad de Turismo de Panamá Autoridad del Canal de Panamá Conjunto Monumental Patronato Panamá
More informationThe Potential Impacts of the Panama Canal Expansion on Texas Ports Final report PRC 17-78
The Potential Impacts of the Panama Canal Expansion on Texas Ports Final report PRC 17-78 The Potential Impacts of the Panama Canal Expansion on Texas Ports Texas A&M Transportation Institute PRC 17-78
More informationLATIN AMERICA / CARIBBEAN COIBA NATIONAL PARK PANAMA
LATIN AMERICA / CARIBBEAN COIBA NATIONAL PARK PANAMA WORLD HERITAGE NOMINATION IUCN TECHNICAL EVALUATION COIBA NATIONAL PARK (PANAMA) ID Nº 1138 Bis Background note: Coiba National Park was nominated for
More informationPort Everglades 2014 Master/Vision Plan Update
1 Port Everglades 2014 Master/Vision Plan Update Public Meeting May 28, 2014 2 Agenda Port Everglades Mission Project Background 2014 Master/Vision Plan Update Process Status of 2009 5-Year Master Plan
More informationDiscontiguous Features Southern Adirondack Feeder Reservoirs
Section number 7 Page 191 Mile 17.32 Buoy R134 marking head of Cayuga-Seneca Canal at outlet of Seneca Lake limit of historic district boundary Discontiguous Features Southern Adirondack Feeder Reservoirs
More informationPanama Business Day- Hamburg. BAUER Fundaciones Panamá S.A.
Panama Business Day- Hamburg BAUER Fundaciones Panamá S.A. Opportunities in Infrastructure Development and Public Projects in Panama and beyond Hans Schwarzweller October 2016 BAUER Spezialtiefbau GmbH,
More informationInnovation based development of Klaipeda Port technologies
Discover a proven way! Innovation based development of Klaipeda Port technologies Mr. Artūras Drungilas Marketing and Corporate Affairs Director Klaipeda State Seaport Authority PortofKlaipeda.lt 1 Management
More informationOFFICE OF THE SECRETARY OF ECONOMIC DEVELOPMENT
OFFICE OF THE SECRETARY OF ECONOMIC DEVELOPMENT Colima, Mexico Tel: +52 (312) 316-2028 Fax: +52 (312) 316-2034 E-mail: sefome@col.gob.mx Infrastructure Colima's modern and well-developed infrastructure
More informationTHE ICs INTERNATIONAL BRISBANE AREA AQUA PARK PROPOSAL
Contacts: Mr Evan Pryor, Ph 38702756, evanpryor2002@yahoo.com.au Mr Bob Beatty, Ph 32883101, BobBeatty@BOSMIN.com Web Address: http://www.bosmin.com/ics/icharter.htm Postal Address: GPO Box 2927, Brisbane,
More informationBaltimore Harbor & Channels, Maryland and Virginia
FACT SHEET January 2006 Type of Project: Navigation Project Phase: Operation & Maintenance Authorization: Section 101 of the River and Harbor Act of 1958 (42-Foot Project), Section 101 of the River and
More informationTNPA 2 nd Strategic Customer Forum Update on Infrastructure Projects. 13 August
TNPA 2 nd Strategic Customer Forum Update on Infrastructure Projects 13 August 2014 1 THE TNPA WORLD OF PORT INFRASTRUCTURE Complete Pixman Images 2010 Dredging International - Pallieter Overview of Presentation
More informationSOLUZIONA S.A. Servicios Profesionales de UNIÓN FENOSA. Recognition of current status on the Access Roads to El Tesoro Project Report.
SOLUZIONA S.A. Servicios Profesionales de UNIÓN FENOSA Recognition of current status on the Access Roads to El Tesoro Project Report. July 22nd, 2002 Part 1 Meeting with Luis Verdugo Repetto, S.A. Beginning
More informationPort of Los Angeles CIP Shaun Shahrestani Chief Harbor Engineer Director of Construction September 27, 2018
Port of Los Angeles CIP Shaun Shahrestani Chief Harbor Engineer Director of Construction September 27, 2018 Port of Los Angeles at a Glance Founded in 1907 Non-taxpayer supported Business port model 4,300
More informationMEXICO CITY S NEW INTERNATIONAL AIRPORT 2017 ACI-LAC Conference. November 2017
MEXICO CITY S NEW INTERNATIONAL AIRPORT 2017 ACI-LAC Conference November 2017 Millions of Passengers The need for a new airport» New Airport opening in 2020 Passenger Projections Growth: 140 120 100 80
More informationPRESENTATION ON CAIRNS SHIPPING DEVELOPMENT PROJECT
PRESENTATION ON CAIRNS SHIPPING DEVELOPMENT PROJECT CAIRNS A STRATEGIC PORT NORTH EAST NAVY BASE MAIN MARITIME ACTIVITY AND EMPLOYMENT : NORTHERN AUSTRALIA CARGO SHIPPING SERVICING LARGEST POPULATION :
More informationPOP-UP INFLATABLE BESPOKE STRUCTURES
POP-UP INFLATABLE BESPOKE STRUCTURES BESPOKE AIR INFLATABLES Where inflation counts... Cintec International, an award-winning structural engineering company, is well known in the industrial market place
More informationSTRABAG SE Successful in Eastern Europe
STRABAG SE Successful in Eastern Europe STRABAG at a glance Building Construction & Civil Engineering Commercial and industrial Facilities Public Buildings Civil Engineering Power Plants Housing Environmental
More information30 November Randall G. Hintz Chief, Operations Support Branch Operations Division. US Army Corps of Engineers BUILDING STRONG
30 November 2011 Randall G. Hintz Chief, Operations Support Branch Operations Division US Army Corps of Engineers Overview MAINTENANCE PROJECTS Deep Draft Channels Shallow Draft Channels Coastal Inlets
More informationCHAPTER 4, SECTION 3 LATIN AMERICA PANAMA
CHAPTER 4, SECTION 3 LATIN AMERICA PANAMA ESSENTIAL QUESTION How do people and the environment impact each other? KEY TERMS Panama Canal-shipping canal across the Isthmus of Panama, linking the Atlantic
More informationDepartment of Environment and Natural Resources
Department of Environment and Natural Resources Brad Ives Assistant Secretary for Natural Resources brad.ives@ncdenr.gov 919-707-8620 Mitch Gillespie Assistant Secretary for Environment mitch.gillespie@ncdenr.gov
More informationThe Lower Prut Floodplain Natural Park (Romania)
The Lower Prut Floodplain Natural Park (Romania) Gabriela Costea Natural Sciences Museum Complex Galati (Romania) & member of the Scientific Council of the Lower Prut Floodplain Natural Park The Prut The
More informationMANAGING COASTAL HAZARDS THROUGH BENEFICIAL REUSE OF DREDGED SAND AND AN ADAPTIVE WORKS STRATEGY
MANAGING COASTAL HAZARDS THROUGH BENEFICIAL REUSE OF DREDGED SAND AND AN ADAPTIVE WORKS STRATEGY Isabelle Ghetti 1, B.Morgan 2, R.Massie 1, Gary Blumberg 2 1 Shoalhaven City Council, Nowra, NSW 2 Royal
More informationTREASURE OF COSTA RICA AND PANAMA OPTIONAL EXCURSIONS
TREASURE OF COSTA RICA AND PANAMA 2016-7 OPTIONAL EXCURSIONS CURU - NICOYA PENINSULA - COSTA RICA - CR1. CURU NATURE RESERVE By zodiacs and foot Duration: about 2.5 hours Note: Wet landing Min participants:
More informationDredging in Fowey Chapter 3 Post departure of the Lantic Bay
Dredging in Fowey Chapter 3 Post departure of the Lantic Bay Prior to the departure of the Lantic Bay the Harbour master Captain Mike Sutherland had obtained quotes from the main dredging contractors for
More informationGlobus Maritime Limited Trading Update and Financial Highlights for the Three Months and Nine Months Ended September 30, 2007.
Globus Maritime Limited Trading Update and Financial Highlights for the Three Months and Nine Months Ended September 30, 2007. Athens, Greece, November 15, 2007. Globus Maritime Limited (AIM: GLBS), a
More informationComplex of flood control structures of Saint Petersburg Facility S1, Saint Petersburg, Russia
The dams for water accumulation are intended to provide raw water to downstream consumers for plants for preparation of drinking water, agricultural irrigation and biological minimum. Following hydro-mechanical
More informationPort Cooperation & Logistic Development in Emerging Markets
New Exploration in the Transitional Era BIPC, 2017 Port Cooperation & Logistic Development in Emerging Markets Fernando Gamboa Director General of Ports Authorities Management & Development Coordination
More informationDay 25 Panama Canal Transit 3/26/2012
Day 25 Panama Canal Transit 3/26/2012 For the second time, we woke up early but not as early as last time we were scheduled to enter the Miraflores Lock at 6:30 am. We wanted to watch the approach and
More informationBiosphere reserves: a tool for the management of coastal zones and islands in the Latin American Pacific
Biosphere reserves: a tool for the management of coastal zones and islands in the Latin American Pacific MIGUEL CLÜSENER-GODT Director (a.i.), Division of Ecological and Earth Sciences Secretary (a.i.),
More informationEnvironmental Impact Assessment of the dredging operations and aids to navigation works in the Argentina s Santa Fe Confluencia waterway.
of the dredging operations and aids to navigation works in the Argentina s Santa Fe Confluencia waterway. LIC. CLAUDIO DANIELE cdaniele@estudioayd.com.ar Presented by Ing. Martín Civeira Study area Argentina
More informationPort Everglades Master/Vision Plan Update
1 Port Everglades Master/Vision Plan Update 3 rd Tenant & Stakeholder Meeting November 21, 2013 2 Agenda Project Process Overview Summary of the Market Assessments October 30 th Charrette Summary Industry
More information8.INFRASTRUCTURE #INVESTINGUATEMALA. Industry in Guatemala
8.INFRASTRUCTURE #INVESTINGUATEMALA Industry in Guatemala General information of the country Capital City Currency Exchange Rate (2013) Official Language Population Labor Force (2013) GDP (2013) FDI inflows
More information