1 AIRPORT DEVELOPMENT PLAN Design-Build Institute of America September 8, 2015

2 Lindbergh Field Page 2

3 Lindbergh Field Page 3

4 Lindbergh Field Page 4

5 San Diego International Airport Today 5

6 What is the Airport Development Plan? In 2006 a county-wide ballot measure to move the airport was defeated Therefore, SAN will continue in its current location for the foreseeable future The Airport Development Plan (ADP) will define optimal development at SAN 6

7 Defining the Terminal Development Boundaries Remote Passenger Processing SANDAG Intermodal Transit Center Cargo Rental Car Center Fixed Base Operator CA Least Tern Nesting Site 7 Area Available for Terminal Development 7

8 Common Elements in Alternatives Terminal 2-West Expansion Centralized FIS North Side Passenger Processing Center SANDAG Intermodal Transit Center California Least Tern Impacts Dedicated Airport Roadway Remain Overnight Aircraft Parking 8

9 Alternative 1 Ultimate Configuration Major Characteristics - Linear concept - Major commercial development opportunity - Maintains Terminal 2 East - International-capable gates up-front, in central location - Centralized marketplace immediately past security checkpoint Terminal 2 West Expansion New Terminal Alternative 1 T1 Parking Plaza Support Facilities T2 Parking Plaza (baseline) 9

10 Alternative 2 Ultimate Configuration Major Characteristics - Satellite concept - East concourse accessed by an elevated pedestrian bridge - International-capable gates in central location - Arrivals on highest level of the building Terminal 2 West Expansion New Terminal Alternative 2 T1 Parking Plaza Support Facilities T2 Parking Plaza (baseline) 10

11 Alternative 3 Ultimate Configuration Major Characteristics - Courtyard concept - International aircraft in west concourse - Large central marketplace to serve high-turn domestic aircraft Terminal 2 West Expansion New Terminal Alternative 3 T1 Parking Plaza Support Facilities T2 Parking Plaza (baseline) 11

12 Alternative 4 Ultimate Configuration Major Characteristics - Open-air courtyard concept - International aircraft along the southern sides of the concourses - Airfield access gates used by highest frequency aircraft Terminal 2 West Expansion New Terminal Alternative 4 T1 Parking Plaza Support Facilities T2 Parking Plaza (baseline) 12

13 Alternative 5 - Ultimate Configuration Terminal 2 West Extension Central FIS Major Characteristics - Hybrid linear concept - International-capable gates in central location - FIS in central location for easy connectivity to T2 and T1 - Continuous gate connectivity to T2 (for better common-use) - Balanced landside Support Facilities T2 Parking Plaza (baseline) 13 Additional Parking New Terminal Alternative 5 T1 Parking Plaza

14 Alternative 5 Interim Configuration 14

15 Terminal Alternatives Evaluation Goal Setting Methodology Evaluation Criteria Definition Goals and objectives defined to guide future airport development recommendations, for the following areas: Ground access Passenger terminal facilities Airfield/airspace Sustainability Land development Social responsibility Measurable criteria were established for each objective Evaluation Score and rank the alternatives Select Preferred development alternative Alternatives Development Alternatives through

16 Alternatives Evaluation Summary Results (Stakeholders and Technical Team) Alternative PAL 12 PAL14 Overall Ranking Note: The lower the score the higher the ranking 16

17 Rough Order of Magnitude Preliminary Costs ROM cost estimates include ADP projects only, including Dedicated Airport Roadway Alternative Capital Cost (2015 dollars) 1 $ 2.1 billion (+ future cost of replacing T2E) 2 $2.4 billion 3 $2.4 billion 4 $2.6 billion 5 $2.2 billion 17

18 Next Steps Continue public & stakeholder coordination Present Roadway Alternatives to Board (September 17, 2015 Board Meeting) Prepare preferred alternative for Board consideration (October 15, 2015 Board Meeting) Conduct environmental analysis 18

19 Questions? 19

20 Phase 1 Clear East Site 20

21 Phase 2 Build Southwest Gates with In-Terminal Admin Space; Demo T1 21

22 Phase 3A Build New Terminal Extension; Rebuild Rwy

23 Phase 3B Re-Occupy North T1 Gates 23

24 Phase 4 Build New FIS; Demo T2E; Connect T1 to T2 24

25 Phase 5 Build North Terminal Extension 25

Destination Lindbergh

Destination Lindbergh Technical Appendix 16 Destination Lindbergh Appendix Contents Destination Lindbergh... TA 16-2 2050 Regional Transportation Plan Destination Lindbergh Destination Lindbergh is a comprehensive planning

More information

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35 Runway 17-35 Airport Master Plan Runway 12-30 Brookings Regional Airport Table of Contents Table of Contents Chapter 1: Master Plan Goals... 1-1 1.1. Introduction... 1 1.2. Objective 1 Identify improvements

More information

FLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING

FLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY FLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING May 15, 2018 Master Plan Schedule Overview Progress Since Last Master Plan

More information

RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan

RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan Project Schedule Today Slide 40 Project Vision To provide an achievable, flexible, fiscally, and environmentally

More information

BNA Master Plan Update Community Advisory Committee Meeting No. 5

BNA Master Plan Update Community Advisory Committee Meeting No. 5 A Six Sigma Organization BNA Master Plan Update Community Advisory Committee Meeting No. 5 September 19, 2012 Introductions MNAA Staff RW Armstrong Team Albersman & Armstrong, Ltd. Atkins North America,

More information

Master Plan Update Community Advisory Committee Kick-off Meeting

Master Plan Update Community Advisory Committee Kick-off Meeting Nashville International Airport Master Plan Update Community Advisory Committee Kick-off Meeting September 13, 2018 Agenda Welcome and Introductions Master Plan Objectives Master Plan Process BNA Vision

More information

CHAPTER 4: ALTERNATIVES

CHAPTER 4: ALTERNATIVES MSP Long Term Comprehensive Plan Update Metropolitan Airports Commission 4.1 INTRODUCTION CHAPTER 4: ALTERNATIVES Several alternatives were developed and evaluated based on their capability to meet the

More information

City of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan. Public Workshop #2 April 19, 2018

City of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan. Public Workshop #2 April 19, 2018 City of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan Public Workshop #2 April 19, 2018 DISCUSSION TOPICS Introduction About the Master Plan Public Workshop #1 Recap

More information

BNA Master Plan Update Public Meeting No. 2

BNA Master Plan Update Public Meeting No. 2 A Six Sigma Organization BNA Master Plan Update Public Meeting No. 2 September 18, 2012 Agenda BNA Master Plan Update Consultants Status of the BNA Master Plan Update Workstation Boards Forecasts of Aviation

More information

Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway

Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway Master Plan Advisory Committee (MPAC) Alternatives September 28, 2017 AGENDA Review of Previous Work Ultimate Land

More information

Meeting Presentation. Sacramento International Airport Master Plan Update October 30, 2012

Meeting Presentation. Sacramento International Airport Master Plan Update October 30, 2012 Meeting Presentation Master Plan Update October 30, 2012 Agenda We encourage open discussion during today s meeting Team Goals Background (Airport Master Plans) Areas of Emphasis Schedule Special Concerns

More information

MASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4

MASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4 MASTER PLAN UPDATE Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT Meeting #4 December 14, 2017 Today s Agenda o Welcome o Introductions o Progress update o Alternatives analysis

More information

Ted Stevens Anchorage International Airport

Ted Stevens Anchorage International Airport Ted Stevens Anchorage International Airport 2014 MASTER PLAN UPDATE Executive Summary IN ASSOCIATION WITH: HDR DOWL HKM RIM Architects ATAC Ted Stevens Anchorage International Airport is planning for the

More information

What is the ABIA 2040 Master Plan?

What is the ABIA 2040 Master Plan? AUSTIN-BERGSTROM INTERNATIONAL AIRPORT What is the ABIA 2040 Master Plan? The ABIA 2040 Master Plan outlines the vision for how our airport will serve the expected 26+ million passengers by the year 2040.

More information

Ted Stevens Anchorage International Airport

Ted Stevens Anchorage International Airport Ted Stevens Anchorage International Airport 2014 MASTER PLAN UPDATE Executive Summary IN ASSOCIATION WITH: HDR DOWL HKM RIM Architects ATAC Ted Stevens Anchorage International Airport is planning for the

More information

Planning, Development and Environment Committee

Planning, Development and Environment Committee Page 1 of 7 MEMORANDUM TO: Planning, Development and Environment Committee FROM: Neil Ralston, Airport Planner Airport Development (726-8129) SUBJECT: 2035 MSP LONG TERM COMPREHENSIVE PLAN FORECAST, FACILITY

More information

CHAPTER 1 EXECUTIVE SUMMARY

CHAPTER 1 EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY 1 1 EXECUTIVE SUMMARY INTRODUCTION William R. Fairchild International Airport (CLM) is located approximately three miles west of the city of Port Angeles, Washington. The airport

More information

Tampa International Airport Master Plan Update. December 12, 2012

Tampa International Airport Master Plan Update. December 12, 2012 Tampa International Airport Master Plan Update December 12, 2012 1 Prior Presentation Consolidated rental car and people mover Decongest curbsides and roadways Enable rental car growth Gain long term parking

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 10 Preferred Inaugural Airport Concept 10.0 Introduction The Preferred Inaugural Airport Concept for SSA was developed by adding the preferred support/ancillary facilities selected in Section 9

More information

Technical Advisory Committee Briefing #3

Technical Advisory Committee Briefing #3 (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY Technical Advisory Committee Briefing #3 June 22, 2018 Master Plan Schedule Overview Coordination Review Recommended Remote 5-Gate Facility

More information

Airport Preliminary Master Plan Workshop Board of County Commissioners April 18, 2017

Airport Preliminary Master Plan Workshop Board of County Commissioners April 18, 2017 Airport Preliminary Master Plan Workshop Board of County Commissioners April 18, 2017 (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY Agenda (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR

More information

Kansas City Aviation Department. Community Listening Session

Kansas City Aviation Department. Community Listening Session Kansas City Aviation Department Community Listening Session Listening Session Purpose The Kansas City Aviation Department is moderating these community listening sessions in order to gather feedback from

More information

Alternatives Analysis EXECUTIVE SUMMARY

Alternatives Analysis EXECUTIVE SUMMARY Alternatives Analysis EXECUTIVE SUMMARY Alternative development plans were created as part of the Master Plan for Harrisburg International Airport. The aim is to provide sufficient capacity for projected

More information

FLL Master Plan Update Policy Advisory Committee (PAC) Briefing #2 July 10, 2017

FLL Master Plan Update Policy Advisory Committee (PAC) Briefing #2 July 10, 2017 FLL Master Plan Update Policy Advisory Committee (PAC) Briefing #2 July 10, 2017 (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY PAC Committee (PRELIMINARY DRAFT) WORK IN PROGRESS -

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 3 - Refinement of the Ultimate Airfield Concept Using the Base Concept identified in Section 2, IDOT re-examined

More information

Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport

Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport Re: Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport Los Angeles World Airports (LAWA) intends to submit

More information

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201

More information

Existing Conditions AIRPORT PROFILE Passenger Terminal Complex 57 air carrier gates 11,500 structured parking stalls Airfield Operations Area 9,000 North Runway 9L-27R 6,905 Crosswind Runway 13-31 5,276

More information

AIRPORT MASTER PLAN UPDATE

AIRPORT MASTER PLAN UPDATE AIRPORT MASTER PLAN UPDATE PENSACOLA INTERNATIONAL AIRPORT Technical Advisory Committee Meeting #2 June 20, 2017 Agenda» Introduction» Facility Requirements Airside Terminal Landside General Aviation Cargo

More information

FLL Master Plan Update Technical Advisory Committee (TAC) Briefing #1. September 28, 2016

FLL Master Plan Update Technical Advisory Committee (TAC) Briefing #1. September 28, 2016 FLL Master Plan Update Technical Advisory Committee (TAC) Briefing #1 September 28, 2016 TAC Committee Role: Internal Stakeholders To provide input on the master planning analysis from the technical and

More information

Forecast and Overview

Forecast and Overview Forecast and Overview DENVER INTERNATIONAL AIRPORT Overall goals of the (MPR): Work with DEN to refine the preferred airport development plan to guide the development over an approximate 25-year planning

More information

ENVISIONING AUSTIN s Airport of the Future

ENVISIONING AUSTIN s Airport of the Future ENVISIONING AUSTIN s Airport of the Future ABIA 2040 Master Plan Public Workshop #1 October 12, 2017 WHAT IS THE PURPOSE OF TODAY S WORKSHOP? Educate & Inform Solicit Input Answer Questions 2 WHAT IS A

More information

EXECUTIVE SUMMARY. Master Plan Update Phase 2/3 FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT 1. INTRODUCTION 2.

EXECUTIVE SUMMARY. Master Plan Update Phase 2/3 FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT 1. INTRODUCTION 2. MASTER PLAN UPDATE Phase 2/3 Draft Final Summary Report Report Issued 2010 in association with Prepared for Broward County Aviation Department Main Office 555 Airport Blvd., Suite 300 Burlingame, CA 94010

More information

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL

Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL Chapter Seven COST ESTIMATES AND FUNDING A. GENERAL This chapter delineates the recommended 2005 2024 Sussex County Airport Capital Improvement Program (CIP). It further identifies probable construction

More information

LAX Specific Plan Amendment Study (SPAS) Final EIR and Related Actions. Board of Airport Commissioners February 5, 2013

LAX Specific Plan Amendment Study (SPAS) Final EIR and Related Actions. Board of Airport Commissioners February 5, 2013 LAX Specific Plan Amendment Study (SPAS) Final EIR and Related Actions Board of Airport Commissioners February 5, 2013 1 Background The LAX Master Plan Program serves as the airport s long range development

More information

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved TABLE OF CONTENTS Description Page Number LIST OF ACRONYMS... a CHAPTER ONE INTRODUCTION General... 1-1 Study Objectives... 1-1 Public Involvement... 1-2 Issues to Be Resolved... 1-2 CHAPTER TWO EXISTING

More information

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES Over the term of the Master Amendment to the Airline Use and Lease Agreement, the Kansas City Aviation Department

More information

SAN JOSÉ INTERNATIONAL AIRPORT

SAN JOSÉ INTERNATIONAL AIRPORT SAN JOSÉ INTERNATIONAL AIRPORT NEAR-TERM TERMINAL CAPACITY ANALYSIS AIRPORT COMMISSION AUGUST 14, 2017 August 14, 2017 AGENDA 1. Forecast Review (with 14 MAP High Case) 2. Gate Requirements and Aircraft

More information

Fort Lauderdale Hollywood International Airport

Fort Lauderdale Hollywood International Airport ATLANTA, GEORGIA 1 2 ATLANTA, GEORGIA Fort Lauderdale Hollywood International Airport Master Plan to Master Plan Implementation Jamie McCluskie Director of Aviation Planning & Environmental Broward County

More information

TABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary.

TABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary. TABLE OF CONTENTS Section Page Section Page 1.0 INTRODUCTION... 1 1.1 Purpose of an... 1 1.2 Goals and Objectives... 1 1.3 Mission Statement... 2 1.4 Stakeholder/Public Involvement... 2 1.5 Major Deliverables...

More information

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER PETE FLAHERTY COMMISSIONER TOM FOERSTER CHAIRMAN DEPARTMENT OF AVIATION BARBARA HAFER COMMISSIONER STEPHEN A. GEORGE DIRECTOR ROOM M 134, TERMINAL BUILDING GREATER PITTSBURGH INTERNATIONAL AIRPORT PITTSBURGH,

More information

Los Angeles International Airport (LAX) Airside $907M

Los Angeles International Airport (LAX) Airside $907M Los Angeles International Airport (LAX) $3,948M Airside $907M Airfield Electrical Systems Rehabilitation Bradley West Core Renovation, East Ramp and Concourse Demolition Imperial Terminal Aircraft Parking

More information

Hartsfield Jackson Update prepared for:

Hartsfield Jackson Update prepared for: Hartsfield Jackson Update prepared for: September 6, 2013 Presented by: Shelley Lamar, Planning Manager Agenda ATL Overview Economic Impact Preparing for the Future Your Questions Airport overview Airport

More information

EXECUTIVE SUMMARY. KEY TAKEAWAYS The following summarizes key aspects of RASP analyses and findings:

EXECUTIVE SUMMARY. KEY TAKEAWAYS The following summarizes key aspects of RASP analyses and findings: EXECUTIVE SUMMARY The (RASP) for the San Diego County was prepared by the (the Authority) to assess the longrange capabilities of all public-use airports in the county with the goal of improving the performance

More information

GLOBAL CONGRESS PANEL DISCUSSION. Phil Brown Executive Director, Greater Orlando Aviation Authority August 18, 2015

GLOBAL CONGRESS PANEL DISCUSSION. Phil Brown Executive Director, Greater Orlando Aviation Authority August 18, 2015 GLOBAL CONGRESS PANEL DISCUSSION Phil Brown Executive Director, Greater Orlando Aviation Authority August 18, 2015 In the Beginning The Orlando Experience Past, Present and Future 1977 Today 1978 2013

More information

City of Monett, Missouri. Pride and Progress. Airport Master Plan Update. for the Monett Municipal Airport

City of Monett, Missouri. Pride and Progress. Airport Master Plan Update. for the Monett Municipal Airport City of Monett, Missouri Airport Master Plan Update for the Monett Municipal Airport Pride and Progress Airport Inventory Monett Municipal Airport (HFJ) Master Plan Update MoDOT Project Number: 08-098B-1

More information

The CLE Master Plan Includes:

The CLE Master Plan Includes: The CLE Master Plan Includes: An inventory of existing conditions Forecasting future demand and analyzing future needs Evaluating alternative development scenarios Preparing the Airport Layout Plan Preparing

More information

Austin-Bergstrom International Airport Master Plan Update

Austin-Bergstrom International Airport Master Plan Update FINAL REPORT Prepared for: City of Austin Department of Aviation 3600 Presidential Boulevard Austin, Texas 78719 Prepared by: P&D Aviation A Division of P&D Consultants, Inc. 999 Town & County Road, 4

More information

Transportation Research Board. Session Lessons Learned from Large Airport Development. Orlando Airport Experience

Transportation Research Board. Session Lessons Learned from Large Airport Development. Orlando Airport Experience Transportation Research Board Session 513 - Lessons Learned from Large Airport Development Orlando Airport Experience Agenda Airport Statistics and Background Capital Improvement Plan Lessons Learned Planning

More information

Implications of Construction Cost Escalation

Implications of Construction Cost Escalation Implications of Construction Cost Escalation 2007 ACI-NA Economics and Finance Conference James Gill, CPA Deputy Airport Director Finance, Business & Administration Raleigh-Durham Airport Authority Presentation

More information

PFC Quarterly Status Report September 30, 2016

PFC Quarterly Status Report September 30, 2016 PFC Quarterly Status Report September 0, 06 Public Agency: Greater Orlando Aviation Authority Use Airport: Orlando International Airport (MCO) Charge Expiration Date: $4.50 8//08 Total Collection Authority

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 1 - Introduction This report describes the development and analysis of concept alternatives that would accommodate

More information

The presentation was approximately 25 minutes The presentation is part of Working Group Meeting 3

The presentation was approximately 25 minutes The presentation is part of Working Group Meeting 3 This is the presentation for the third Master Plan Update Working Group Meeting being conducted for the Ted Stevens Anchorage International Airport Master Plan Update. It was given on Thursday March 7

More information

MASTER PLAN UPDATE GRANT NUMBER

MASTER PLAN UPDATE GRANT NUMBER T MASTER PLAN UPDATE D R AF GRANT NUMBER 3-48-0062-42 MAY 2015 1. Introduction... 1-1 1.1 History of Dallas Love Field... 1-1 1.2 Airport Setting... 1-2 1.2.1 DALLAS-FORT WORTH-ARLINGTON METROPOLITAN STATISTICAL

More information

July 21, Mayor & City Council Business Session KCI Development Program Process Update

July 21, Mayor & City Council Business Session KCI Development Program Process Update July 21, 2015 Mayor & City Council Business Session KCI Development Program Process Update History of KCI 2 Airport Funding KCI Improvements are Funded by Airlines & Travelers City tax revenues do not,

More information

Omaha Airport Authority Eppley Airfield

Omaha Airport Authority Eppley Airfield June 13, 2018 Omaha Airport Authority Eppley Airfield Terminal Development Program Industry Day Previous Master Plan Results 1996 2014 2 June 13, 2018 Eppley Airfield Terminal Development Program Industry

More information

Greater Orlando Aviation Authority

Greater Orlando Aviation Authority Greater Orlando Aviation Authority Orlando International Airport & Orlando Executive Airport Budgets Fiscal Year 2017-2018 Greater Orlando Aviation Authority Orlando, Florida Greater Orlando Aviation Authority

More information

Chapter 1: Introduction Draft

Chapter 1: Introduction Draft Chapter 1: Draft TABLE OF CONTENTS 1... 4 1.6.1 Stakeholder Engagement Plan... 10 Chapter 1 Page 2 TABLE OF EXHIBITS Exhibit 1.1-1 ABIA Annual Growth Since 1993... 5 Exhibit 1.4-1: ABIA Location Map...

More information

CVG Overview Connect with CVG March 29, 2017

CVG Overview Connect with CVG March 29, 2017 CVG Overview Connect with CVG March 29, 2017 Launching Point Strategic Plan CVG Launching Point Strategies for 2016 and Beyond Vision: Make travel through CVG and unforgettably positive experience Mission:

More information

Restoration of Historic Streetcar Services in Downtown Los Angeles

Restoration of Historic Streetcar Services in Downtown Los Angeles Restoration of Historic Streetcar Services in Downtown Los Angeles Alternatives Analysis Community Update Meeting November 3, 2011 Introduction Local lead agency: Metro Federal lead agency: Federal Transit

More information

Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis

Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis ITB MAIN TERMINAL DEPARTURES LEVEL & BOARDING AREAS A & G ALTERNATIVES ANALYSIS

More information

State of the Airport Robert S. Bowen, Executive Director October 18, 2018

State of the Airport Robert S. Bowen, Executive Director October 18, 2018 Robert S. Bowen, Executive Director October 18, 2018 A Year of Change The last year will be remembered as a period when the airlines, bolstered by a growing national economy, moderate fuel prices and changing

More information

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis Appendix B ULTIMATE AIRPORT CAPACITY & DELAY SIMULATION MODELING ANALYSIS B TABLE OF CONTENTS EXHIBITS TABLES B.1 Introduction... 1 B.2 Simulation Modeling Assumption and Methodology... 4 B.2.1 Runway

More information

CASE STUDY The New Guayaquil International Airport

CASE STUDY The New Guayaquil International Airport www.jacobs.com worldwide CASE STUDY The New Guayaquil International Airport Prepared for ICAO Airport Planning Seminar for the SAM Region Lima, Peru 10-14 Sep. 2018 September 11, 2018 Outline Existing

More information

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport Executive Summary MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport As a general aviation and commercial service airport, Fort Collins- Loveland Municipal Airport serves as an important niche

More information

Current and Forecast Demand

Current and Forecast Demand Existing Facilities Jacksonville International Airport (JIA) is served by a number of airside and landside facilities. There are two runways that serve the airport in an open V configuration. The Annual

More information

Saint Petersburg-Clearwater International Airport. Airspace & Instrument Approach Analysis

Saint Petersburg-Clearwater International Airport. Airspace & Instrument Approach Analysis Saint Petersburg-Clearwater International Airport Airspace & Instrument Approach Analysis February 23, 2005 Jeppesen Boeing Jeppesen Government / Military Services Group Airspace Services Division AIRSPACE

More information

EXECUTIVE SUMMARY FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT (FLL) MASTER PLAN UPDATE PHASE 1

EXECUTIVE SUMMARY FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT (FLL) MASTER PLAN UPDATE PHASE 1 Workshop Briefing Package Airport Master Plan Update, Phase I Fort Lauderdale-Hollywood International Airport October 18, 2005 Leigh Fisher Associates A Division of Jacobs Consultancy Inc. EXECUTIVE SUMMARY

More information

Table of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update

Table of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update Table of Contents 7.1. Airport Layout Plan (Existing Conditions)... 2 7.2. Airport Layout Plan (Future Conditions)... 3 7.3. Technical Data Sheet... 5 7.4. Commercial Terminal Area Drawing... 5 7.5. East

More information

General Aviation Master Plan Update

General Aviation Master Plan Update Peter O. Knight Airport Public Meeting #2 Peter O. Knight Airport Agenda Welcome and Introductions HCAA System of Airports Purpose of Public Meetings Master Plan Status Update Next Steps Q & A 2 Our System

More information

DRAFT. Airport Master Plan Update Sensitivity Analysis

DRAFT. Airport Master Plan Update Sensitivity Analysis Dallas Love Field Sensitivity Analysis PREPARED FOR: The City of Dallas Department of Aviation PREPARED BY: RICONDO & ASSOCIATES, INC. August 201 Ricondo & Associates, Inc. (R&A) prepared this document

More information

Port of Seattle Sea-Tac Airport Master Plan An Economic Engine for Washington State. Kurt Beckett Deputy Chief Executive Officer

Port of Seattle Sea-Tac Airport Master Plan An Economic Engine for Washington State. Kurt Beckett Deputy Chief Executive Officer Port of Seattle Sea-Tac Airport Master Plan An Economic Engine for Washington State Kurt Beckett Deputy Chief Executive Officer WA Ports A Unique Public Agency Mission: Create Jobs through Travel, Trade

More information

Westover Metropolitan Airport Master Plan Update

Westover Metropolitan Airport Master Plan Update Westover Metropolitan Airport Master Plan Update June 2008 INTRODUCTION Westover Metropolitan Airport (CEF) comprises the civilian portion of a joint-use facility located in Chicopee, Massachusetts. The

More information

RNP AR APCH Approvals: An Operator s Perspective

RNP AR APCH Approvals: An Operator s Perspective RNP AR APCH Approvals: An Operator s Perspective Presented to: ICAO Introduction to Performance Based Navigation Seminar The statements contained herein are based on good faith assumptions and provided

More information

LATAM Airlines Group presents technical airport infrastructure requirements for the Northeast hub based on study by the consulting firm Arup

LATAM Airlines Group presents technical airport infrastructure requirements for the Northeast hub based on study by the consulting firm Arup LATAM Airlines Group presents technical airport infrastructure requirements for the Northeast hub based on study by the consulting firm Arup Study ordered by the Group indicates the airport infrastructure

More information

Sunshine Coast Airport Master Plan September 2007

Sunshine Coast Airport Master Plan September 2007 Sunshine Coast Airport Master Plan September 2007 Contents CONTENTS... I ACKNOWLEDGEMENT... II DISCLAIMER... III 1 EXECUTIVE SUMMARY...IV 1 INTRODUCTION... 1 2 AVIATION DEMAND FORECAST... 5 3 AIRCRAFT

More information

Chapter 1: Introduction

Chapter 1: Introduction Chapter 1: TABLE OF CONTENTS 1... 4 1.1 Master Plan Study Content... 4 1.2 Purpose and Scope of Master Plan Study... 4 1.3 Airport History and Role... 6 1.4 Airport Location and Service Area... 6 1.5 ABIA

More information

Chapter 9: Financial Plan Draft

Chapter 9: Financial Plan Draft Chapter 9: Draft TABLE OF CONTENTS 9... 5 9.2.1 ABIA Accounting... 6 9.2.2 Legal Environment... 6 9.2.3 Governing Documents... 8 9.3.1 FAA AIP Grants... 13 9.3.2 Local ABIA Funds... 14 9.4.1 Defer or Delay

More information

Pinellas Tourist Development Council

Pinellas Tourist Development Council Network USA 2013 Air Service Development Conference St. Pete Pride Parade National Tourism Week Tony Jannus Aviation Summit - 2013 Tampa International Airport Volunteer Ambassadors Air Service Development

More information

World Class Airport For A World Class City. Airport Update

World Class Airport For A World Class City. Airport Update World Class Airport For A World Class City Airport Update MSY is the region s airport Serving LA, MS, & AL Airport Enplaned passengers (000s) MSY 5,569 Nearest airports (all non-hubs or small hubs) Baton

More information

SouthwestFloridaInternational Airport

SouthwestFloridaInternational Airport SouthwestFloridaInternational Airport SouthwestFloridaInternationalAirportislocatedinLee CountyalongtheGulfCoastofSouthFlorida,tenmiles southeastofthefortmyerscentralbusinessdistrict. Theprimaryhighwayaccesstotheairportfrom

More information

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development plans

More information

Norfolk International Airport

Norfolk International Airport Norfolk International Airport Master Plan Update Technical Advisory Committee Meeting #1 Community Advisory Committee Meeting #1 January 24, 2018 Agenda Project Background Introductions Overview of Airport

More information

Predicting a Dramatic Contraction in the 10-Year Passenger Demand

Predicting a Dramatic Contraction in the 10-Year Passenger Demand Predicting a Dramatic Contraction in the 10-Year Passenger Demand Daniel Y. Suh Megan S. Ryerson University of Pennsylvania 6/29/2018 8 th International Conference on Research in Air Transportation Outline

More information

An Overview of GMR Megawide Consortium s Unsolicited Proposal. March 2018

An Overview of GMR Megawide Consortium s Unsolicited Proposal. March 2018 s An Overview of GMR Megawide Consortium s Unsolicited Proposal March 2018 1 Metro Manila requires a multi-airport system and NAIA shall continue to play an anchor role in this system. Multi-Airport system

More information

ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS

ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS EXECUTIVE SUMMARY ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS PAGE NO. CHAPTER 1-INTRODUCTION... 1-1 1.01 General...1-1 1.02 Purpose and Scope of Study...1-1 1.03 The Planning Process...1-2

More information

Lake Tahoe Airport Master Plan

Lake Tahoe Airport Master Plan Lake Tahoe Airport Master Plan City Council Briefing October 20, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development

More information

City of Kansas City AIRPORT COMMITTEE BRIEFING. Major Renovation Evaluation for Kansas City International Airport.

City of Kansas City AIRPORT COMMITTEE BRIEFING. Major Renovation Evaluation for Kansas City International Airport. City of Kansas City AIRPORT COMMITTEE BRIEFING Major Renovation Evaluation for Kansas City International Airport February 2, 2016 1 Agenda Briefly review Exhibit K Process to establish Program Requirements

More information

Study Design Outline. Background. Overview. Desired Study Outcomes. Study Approach. Goals (preliminary) Recession History

Study Design Outline. Background. Overview. Desired Study Outcomes. Study Approach. Goals (preliminary) Recession History MIA BASELINE ACTIVITY FORECASTS, DERIVATIVE DATA AND FLEET MIX PROJECTIONS RESULTS SUMMARY ACCEPTANCE BRIEFING FOR THE AIRPORT AND SEAPORT COMMITTEE (ASC) JULY 15, 2010 Study Design Outline Background

More information

MASTER PLAN GEORGE BUSH INTERCONTINENTAL AIRPORT/HOUSTON. Houston Airport System Houston, Texas DRAFT TECHNICAL REPORT.

MASTER PLAN GEORGE BUSH INTERCONTINENTAL AIRPORT/HOUSTON. Houston Airport System Houston, Texas DRAFT TECHNICAL REPORT. in association with AirProjects Inc. Conway Consulting Gunda Corporation Quadrant Consultants RdlR Architects Sunland Group DRAFT TECHNICAL REPORT MASTER PLAN Prepared for Houston Airport System Houston,

More information

Love Field Modernization Program Update: Master Planning Recommendations

Love Field Modernization Program Update: Master Planning Recommendations Love Field Modernization Program Update: Master Planning Recommendations Briefing to the Council Transportation and Environment Committee April 28, 2008 1 1 Briefing Objective Discuss the background and

More information

Chapter 8.0 Implementation Plan

Chapter 8.0 Implementation Plan Chapter 8.0 Implementation Plan 8.1 Introduction This chapter is the culmination of the analytical work accomplished in the previous chapters. The result is a prioritized list of the essential projects.

More information

TERMINAL DEVELOPMENT PLAN

TERMINAL DEVELOPMENT PLAN 5.0 TERMINAL DEVELOPMENT PLAN 5.0 TERMINAL DEVELOPMENT PLAN Key points The development plan in the Master Plan includes the expansion of terminal infrastructure, creating integrated terminals for international,

More information

Dallas Love Field Update. Dallas City Council Briefing February 18, 2015

Dallas Love Field Update. Dallas City Council Briefing February 18, 2015 Dallas Love Field Update Dallas City Council Briefing February 18, 2015 Purpose Construction Update Impacts of Wright Amendment Repeal Increase in operations/passengers/ projections Concessions performance

More information

Merritt Island Airport

Merritt Island Airport TABLE OF CONTENTS CHAPTER 1 INTRODUCTION... 1-1 INTRODUCTION AND PROJECT OVERVIEW... 1-1 General Guidelines... 1-1 Prior Planning Documentation... 1-2 Key Issues... 1-2 Goals and Objectives... 1-2 Regulatory

More information

GSP TERMINAL IMPROVEMENT PROGRAM PRESS KIT

GSP TERMINAL IMPROVEMENT PROGRAM PRESS KIT About GSP MISSION STATEMENT At Greenville-Spartanburg International Airport (GSP), we begin each day fully committed to finding new ways to achieve our mission to provide the citizens of Upstate South

More information

Appendix D. FIS Facility Siting Alternatives

Appendix D. FIS Facility Siting Alternatives Feasibility Study for a Federal Inspection Service Facility at Long Beach Airport Appendix D. FIS Facility Siting Alternatives PLEASE NOTE: The information, analysis, assessments and opinions contained

More information

2012 AIRPORT MASTER PLAN 2016 ADDENDUM VOLUME 1 SUBMITTED ON: SEPTEMBER 22, 2017

2012 AIRPORT MASTER PLAN 2016 ADDENDUM VOLUME 1 SUBMITTED ON: SEPTEMBER 22, 2017 VOLUME 1 2012 AIRPORT MASTER PLAN 2016 ADDENDUM SUBMITTED ON: SEPTEMBER 22, 2017 VOLUME 1 CONTENTS SECTION 1 - INTRO AND AIRPORT CONTEXT SECTION 2 - FORECAST SECTION 3 - AIRFIELD FACILITIES AND DEMAND/CAPACITY

More information

PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM

PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM FREQUENTLY ASKED QUESTIONS September 2017 Master Plan Update: 1. What is a Master Plan Update? The objective of a Master Plan Update (MPU)