1 Transportation Research Board Session Lessons Learned from Large Airport Development Orlando Airport Experience
2 Agenda Airport Statistics and Background Capital Improvement Plan Lessons Learned Planning & Design Land Use Other Airport Statistics and Background
3 By The Numbers Orlando International Airport (Thru November 30, 2006) 13,300 Acres (5,400 hectares) 34.7 Million Annual Passengers 95,000 Average Daily Passengers 4 th Busiest O&D Domestic Airport Busiest Passenger Airport in the State of Florida 354,000 Annual Airport Operations Airport Today 4 Runways Landside Terminal 4 Airsides
4 Airside 1 Airside 2 Airside 3 Airside 4 Actual passenger traffic compared to forecast Million Annual Passengers (MAP) ,538,000 above Master Plan Forecast Actual Traffic Actual +3.5% 2002 Master Plan 2002 Bond Issue (High) 2002 Bond Issue 2002 Bond +3.0% 2002 Bond Issue (Low) Actual +3.5% Master Plan Bond Issue (High) Bond Issue Bond +3.0% Bond Issue (Low) Source: Actual-GOAA records, Forecast-Leigh Fisher Associates, John F. Brown Company. Contact: GOAA Marketing
5 Capital Improvement Plan Terminal Projects ( ) $4.1 Billion over 15 years Airsides 1 & 3 Rehabilitation Airside 4 Modifications/Rehabilitation North Terminal Capacity South Terminal Complex Security IT Improvements Hyatt Hotel Asset Preservation/R&R
6 Proposed South Terminal Proposed South Terminal Phase 1
7 Airfield Projects ( ) $1.0 Billion over 15 years Airfield Capacity/ Taxiway Projects Wildlife Attractant Mitigation Projects Secure Service Road Extension Asset Preservation/R&R Projects Roadway & Parking Projects ( ) $419 Million over 15 years Widen South Access Road Loop Road Signage Mitigate Cut Through Traffic Enplane/Deplane Drive Widen Tradeport Drive Extend Heintzelman Blvd. Expand Parking Asset Preservation/R&R Projects
8 Summary $ 5.7 Billion over 15 years $ 4.1 Billion - Terminal $ 1.0 Billion - Airfield s $ 419 Million - Roadway & Parking $ 159 Million - Other Includes $645 Million in Asset Preservation/R&R Projects Lessons Learned
9 Lessons Learned Planning and Design Land Use Other Lessons Learned Planning and Design 1. FLEXIBILITY! 2. Landside/Airside vs Unit Terminal Concepts 3. Evolution of the Airside Building 4. Capacity Analysis 5. Emerging Trends
10 1. FLEXIBILITY! Lessons Learned Planning and Design Land Overbuild when economically possible Three Level Terminal Ability to add additional curb Size of airsides have evolved Security Simple buildings targeted to be experienced from interior. Exterior enhanced with landscaping. One more reason to remain flexible!
11 Hurricane Charley August 13, :30 PM
12 Lessons Learned Planning and Design 2. Landside/Airside vs Unit Terminal Concepts Landside/airside with APM s used at MCO to place airsides in stable soil locations, minimize walking distance and to serve domestic O&D traffic Double Bag Handling & Security Screening South Terminal will offer hybrid concept with unit terminal and landside/airside elements Terminal A vs Terminal B
13 Double Bag Handling Airside 4 FIS Opened in ,500 Pax per/hr Modified once since 1990 Proposed South Terminal 120 Gates (ultimate) 48 Contact Gates 72 Gates by APM
14 Terminal A vs Terminal B (MCO 1981) B A September 1981 B A
15 Lessons Learned Planning and Design 3. Evolution of the Airside Building Size of Airside Configuration of Airside Airsides 1 & 3 Opened 1981
16 Airside 4 Opened 1990 Airside 2 Opened 2000 TRB Session 513 September - January 23,
17 4. Capacity Analysis Lessons Learned Planning and Design Moving target (example security checkponits) Find the weak links in the chain Routinely monitor peak hour statistics Balanced Facility Requirements Capacity Analysis Terminal Vertical Circulation Ticketing Lobby Terminal Roads and Ramps Security Check Point Entering and Exiting Weaves Baggage Claim Landside Terminal Curbs Baggage Make-up Garage Public Parking FIS Capacity
18 Enplaning and Deplaning Passenger Peak Hour Trends OIA - Peak Hour Trend Line Peak Hour Percentage January 2004 February 2004 March 2004 April 2004 May 2004 June 2004 July 2004 August 2004 September 2004 October 2004 November 2004 December 2004 January 2005 February 2005 March 2005 April 2005 May 2005 June 2005 Month July 2005 August 2005 September 2005 October 2005 November 2005 December 2005 January 2006 February 2006 March 2006 April 2006 May 2006 June 2006 July 2006 August 2006 September 2006 October 2006 Deplanement Pk.Hr. % Enplanement Pk.Hr. % March 2003 Enplanement Pk. 11% March 2003 Deplanement Pk. 10% Airside Activity Trends Seek to Balance Activity on all Airsides OIA - Scheduled Enplanements by Airside by Month Averaged Daily Scheduled Seats January 2004 February 2004 March 2004 April 2004 May 2004 June 2004 July 2004 August 2004 September 2004 October 2004 November 2004 December 2004 January 2005 February 2005 March 2005 April 2005 May 2005 June 2005 July 2005 August 2005 September 2005 October 2005 November 2005 December 2005 January 2006 February 2006 March 2006 April 2006 May 2006 June 2006 July 2006 August 2006 September 2006 October 2006 November 2006 December 2006 January 2007 Month Airside 1 Airside 2 Airside 3 Airside 4
19 Airport Activity Trends Scheduled Enplaning Seats January 2007 OIA Scheduled Seats - Overall January Enplanements 6,000 D a i l y S c C h o e u d n u t l e d 5,000 4,000 3,000 2,000 S e a t 1, Hour Of Day Sat Thr Tue Day of Week Airside Activity Trends Scheduled Deplaning Seats January 2007 OIA Scheduled Seats - Overall January Deplanements 6,000 D a i l y S c C h o e u d n u t l e d 5,000 4,000 3,000 2,000 S e a t 1, Hour Of Day Sat Thr Tue Day of Week
20 5. Emerging Trends Lessons Learned Planning and Design Disney Magical Express and remote Check-in Registered Traveler Rental Car Facilities Lessons Learned Land Use 1. Overlay Zoning Districts in cooperation with local governments Forecast airport build-out noise contours Single event noise levels Composite map Develop control zones 2. Wildlife Attractants
21 2020 DNL NOISE CONTOURS G reene Way Runways 55 DNL 60 DNL 65 DNL 70 DNL 75 DNL B oggy C reek Road Lmax NOISE CONTOURS - TYPICAL AIRCRAFT G reene Way Runways 75 dba 80 dba Boggy C reek Road
22 BoggyC reek Road G reene Way OPERATIONS AND LAND USE CONTROL ZONE LIMITS Zone B Zone C Zone D Zone E OIA/OEA Property Developments With Agreements With GOAA AREAS WITH HIGH POTENTIAL FOR REZONING City of Orlando Conservation Zoning G reene Way City of Orlando Hold Zoning Orange County Rural/Agricultural Zoning B oggy C reek Road Osceola County Agricultural Zoning
23 Wildlife Attractants January 2001 Prepare ALP supplement to address changes for drainage and wildlife attractant projects Lessons Learned Other 1. Management Tools Staff Committees Construction Construction Finance Oversight Design Review
24 Thank You!
Review of Airport Noise Issues East Airfield Development Area
Review of Airport Noise Issues East Airfield Development Area Orlando International Airport April 21, 2011 Agenda Review of Meeting Minutes from April 21 When last we met Airport Noise 101 Cyrus Callum
More informationPFC Quarterly Status Report September 30, 2016
PFC Quarterly Status Report September 0, 06 Public Agency: Greater Orlando Aviation Authority Use Airport: Orlando International Airport (MCO) Charge Expiration Date: $4.50 8//08 Total Collection Authority
More informationGREATER ORLANDO AVIATION AUTHORITY
GREATER ORLANDO AVIATION AUTHORITY Amendment to PFC Applications #7, 8, and 16 and New PFC Application #18 PUBLIC NOTICE June 7, 2016 1 P age Table of Contents PUBLIC NOTICE... 3 PROPOSED ACTIONS... 3
More informationTABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary.
TABLE OF CONTENTS Section Page Section Page 1.0 INTRODUCTION... 1 1.1 Purpose of an... 1 1.2 Goals and Objectives... 1 1.3 Mission Statement... 2 1.4 Stakeholder/Public Involvement... 2 1.5 Major Deliverables...
More informationBNA Master Plan Update Public Meeting No. 2
A Six Sigma Organization BNA Master Plan Update Public Meeting No. 2 September 18, 2012 Agenda BNA Master Plan Update Consultants Status of the BNA Master Plan Update Workstation Boards Forecasts of Aviation
More informationTable of Contents. Master Plan March 2014 TOC i Spokane International Airport
Table of Contents Page Chapter 1 Inventory 1. Introduction... 1 1 1.1 Community Profile... 1 2 1.1.1 Location and Setting... 1 1 1.1.2 Climate... 1 2 1.1.3 Socioeconomic Conditions... 1 5 1.1.4 Area Land
More informationBNA Master Plan Update Community Advisory Committee Meeting No. 5
A Six Sigma Organization BNA Master Plan Update Community Advisory Committee Meeting No. 5 September 19, 2012 Introductions MNAA Staff RW Armstrong Team Albersman & Armstrong, Ltd. Atkins North America,
More informationGreater Orlando Aviation Authority
Greater Orlando Aviation Authority Orlando International Airport & Orlando Executive Airport Budgets Fiscal Year 2017-2018 Greater Orlando Aviation Authority Orlando, Florida Greater Orlando Aviation Authority
More informationForecast and Overview
Forecast and Overview DENVER INTERNATIONAL AIRPORT Overall goals of the (MPR): Work with DEN to refine the preferred airport development plan to guide the development over an approximate 25-year planning
More informationSAN JOSÉ INTERNATIONAL AIRPORT
SAN JOSÉ INTERNATIONAL AIRPORT NEAR-TERM TERMINAL CAPACITY ANALYSIS AIRPORT COMMISSION AUGUST 14, 2017 August 14, 2017 AGENDA 1. Forecast Review (with 14 MAP High Case) 2. Gate Requirements and Aircraft
More informationAirport Preliminary Master Plan Workshop Board of County Commissioners April 18, 2017
Airport Preliminary Master Plan Workshop Board of County Commissioners April 18, 2017 (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY Agenda (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR
More informationFLL Master Plan Update Policy Advisory Committee (PAC) Briefing #2 July 10, 2017
FLL Master Plan Update Policy Advisory Committee (PAC) Briefing #2 July 10, 2017 (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY PAC Committee (PRELIMINARY DRAFT) WORK IN PROGRESS -
More informationKansas City Aviation Department. Community Listening Session
Kansas City Aviation Department Community Listening Session Listening Session Purpose The Kansas City Aviation Department is moderating these community listening sessions in order to gather feedback from
More informationSouthwestFloridaInternational Airport
SouthwestFloridaInternational Airport SouthwestFloridaInternationalAirportislocatedinLee CountyalongtheGulfCoastofSouthFlorida,tenmiles southeastofthefortmyerscentralbusinessdistrict. Theprimaryhighwayaccesstotheairportfrom
More informationAIRPORT MASTER PLAN UPDATE
AIRPORT MASTER PLAN UPDATE PENSACOLA INTERNATIONAL AIRPORT Technical Advisory Committee Meeting #2 June 20, 2017 Agenda» Introduction» Facility Requirements Airside Terminal Landside General Aviation Cargo
More informationDEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER
PETE FLAHERTY COMMISSIONER TOM FOERSTER CHAIRMAN DEPARTMENT OF AVIATION BARBARA HAFER COMMISSIONER STEPHEN A. GEORGE DIRECTOR ROOM M 134, TERMINAL BUILDING GREATER PITTSBURGH INTERNATIONAL AIRPORT PITTSBURGH,
More informationAirport Master Plan. Brookings Regional Airport. Runway Runway 17-35
Runway 17-35 Airport Master Plan Runway 12-30 Brookings Regional Airport Table of Contents Table of Contents Chapter 1: Master Plan Goals... 1-1 1.1. Introduction... 1 1.2. Objective 1 Identify improvements
More informationmsp macnoise.com MSP Noise Oversight Committee (NOC) November 17, 2010
MSP Noise Oversight Committee (NOC) November 17, 2010 Operations Update Technical Advisor s Report Summary MSP Complaints September October 2010 3,025 3,567 2009 6,350 6,001 Total Operations September
More informationGreater Orlando Aviation Authority Board Meeting. Wednesday, January 17, 2018
Greater Orlando Aviation Authority Board Meeting Wednesday, Award Recognition South Terminal Complex Phase 1 and Phase 2 Planning Overview Greater Orlando Aviation Authority AGENDA PASSENGER TRAFFIC
More informationExisting Conditions AIRPORT PROFILE Passenger Terminal Complex 57 air carrier gates 11,500 structured parking stalls Airfield Operations Area 9,000 North Runway 9L-27R 6,905 Crosswind Runway 13-31 5,276
More informationGerald R. Ford International Airport Authority Master Plan Update A World Class Gateway
Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway Master Plan Advisory Committee (MPAC) Alternatives September 28, 2017 AGENDA Review of Previous Work Ultimate Land
More informationGreater Orlando Aviation Authority Orlando International Airport One Jeff Fuqua Boulevard Orlando, Florida Memorandum TO: FROM:
Greater Orlando Aviation Authority One Jeff Fuqua Boulevard Orlando, Florida 32827-4399 Memorandum TO: FROM: Participating Airlines Phil Brown, Executive Director DATE: SUBJECT: Rate Methodology for FY
More informationNantucket Memorial Airport Commission. Master Plan Workshop. October 26, 2012
Nantucket Memorial Airport Commission Master Plan Workshop October 26, 2012 Agenda Introductions Master Plan 101 Airport Planning Issues Noise Abatement Activities Environmental Monitoring Public Outreach
More informationPunta Gorda Airport Master Plan Update
Punta Gorda Airport Master Plan Update Draft Executive Summary Prepared for: The Charlotte County Airport Authority January 2018 Charlotte County Airport Authority James Herston, Chair Robert D. Hancik,
More informationTampa International Airport Master Plan Update. December 12, 2012
Tampa International Airport Master Plan Update December 12, 2012 1 Prior Presentation Consolidated rental car and people mover Decongest curbsides and roadways Enable rental car growth Gain long term parking
More informationBURLINGTON INTERNATIONAL AIRPORT
BURLINGTON INTERNATIONAL AIRPORT VISION 2030 AIRPORT MASTER PLAN UPDATE Summary Presentation AIRPORT STAFF AND STUDY TEAM Robert McEwing, Director of Planning & Development Brad Worthen, Community Facilitator
More informationMaster Plan Phase 2 Workshop
Master Plan Phase 2 Workshop Tampa Airport: A Legacy of Innovation and Convenience Tampa Airport: A legacy of Innovation and Convenience The world s first airport people mover Tampa Airport: A legacy of
More information1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan
TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201
More informationCity of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan. Public Workshop #2 April 19, 2018
City of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan Public Workshop #2 April 19, 2018 DISCUSSION TOPICS Introduction About the Master Plan Public Workshop #1 Recap
More informationNoise Oversight Committee
Noise Oversight Committee July 22, 2015 Audio recordings are made of this meeting 1 Noise Oversight Committee July 22, 2015 Item 1 Review and Approve Draft Meeting Minutes Minutes from May 20, 2015 Noise
More informationMerritt Island Airport
TABLE OF CONTENTS CHAPTER 1 INTRODUCTION... 1-1 INTRODUCTION AND PROJECT OVERVIEW... 1-1 General Guidelines... 1-1 Prior Planning Documentation... 1-2 Key Issues... 1-2 Goals and Objectives... 1-2 Regulatory
More informationEXECUTIVE SUMMARY FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT (FLL) MASTER PLAN UPDATE PHASE 1
Workshop Briefing Package Airport Master Plan Update, Phase I Fort Lauderdale-Hollywood International Airport October 18, 2005 Leigh Fisher Associates A Division of Jacobs Consultancy Inc. EXECUTIVE SUMMARY
More informationCHAPTER 4: ALTERNATIVES
MSP Long Term Comprehensive Plan Update Metropolitan Airports Commission 4.1 INTRODUCTION CHAPTER 4: ALTERNATIVES Several alternatives were developed and evaluated based on their capability to meet the
More informationFLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING
(PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY FLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING May 15, 2018 Master Plan Schedule Overview Progress Since Last Master Plan
More informationFORECASTING FUTURE ACTIVITY
EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver
More informationLake Tahoe Airport Master Plan Public Meeting March 16, 2015
Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development plans
More informationLake Tahoe Airport Master Plan
Lake Tahoe Airport Master Plan City Council Briefing October 20, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development
More informationAirport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal
Airport Master Plan Rapid City Regional Airport October 2015 FAA Submittal Rapid City Regional Airport Master Plan Update Table of Contents Executive Summary... i Scope & Timeline... i Forecasts... i Preferred
More informationElevating the Upstate
Greenville-Spartanburg Int l Airport Elevating the Upstate SC Economic Developers Association October 12, 2012 Introduction/Presentation Outline Introductions Airport Overview Air Service Terminal Improvement
More informationMaster Plan Update Technical Advisory Committee Meeting
Nashville International Airport Master Plan Update Technical Advisory Committee Meeting February 14, 2019 Agenda Welcome and Introductions Aviation Activity Forecast Facility Requirements Alternatives
More informationMASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4
MASTER PLAN UPDATE Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT Meeting #4 December 14, 2017 Today s Agenda o Welcome o Introductions o Progress update o Alternatives analysis
More informationLand Use Policy Considerations
Land Use Policy Considerations Challenges to Implementing Successful Land Use Strategies at Airports ACRP Insight Event: Washington DC Stephen D. Van Beek, Ph.D. April 11, 2018 Land Use Policy Considerations
More informationJuly 21, Mayor & City Council Business Session KCI Development Program Process Update
July 21, 2015 Mayor & City Council Business Session KCI Development Program Process Update History of KCI 2 Airport Funding KCI Improvements are Funded by Airlines & Travelers City tax revenues do not,
More informationGreater Orlando Aviation Authority Board Meeting. Wednesday, December 20, 2017
Greater Orlando Aviation Authority Board Meeting Wednesday, Award Recognition South Terminal Complex Phase 1 Concessions Overview Greater Orlando Aviation Authority Board Presentation AGENDA SOUTH TERMINAL
More informationSTUDY WORK GROUP MEETING No. 4. July 12, 2017
STUDY WORK GROUP MEETING No. 4 July 12, 2017 Agenda Welcome and introductions Update of project schedule Brief overview of previous SWG meeting Introduction to airport development alternatives Comments,
More informationFUTURE PASSENGER PROCESSING. ACRP New Concepts for Airport Terminal Landside Facilities
FUTURE PASSENGER PROCESSING ACRP 07-01 New Concepts for Airport Terminal Landside Facilities In association with: Ricondo & Associates, TransSolutions, TranSecure RESEARCH Background Research Objective
More informationAIRPORT DEVELOPMENT PLAN. Design-Build Institute of America September 8, 2015
AIRPORT DEVELOPMENT PLAN Design-Build Institute of America September 8, 2015 Lindbergh Field - 1935 3 Page 2 Lindbergh Field - 1944 3 Page 3 Lindbergh Field - 1955 3 Page 4 San Diego International Airport
More informationImplications of Construction Cost Escalation
Implications of Construction Cost Escalation 2007 ACI-NA Economics and Finance Conference James Gill, CPA Deputy Airport Director Finance, Business & Administration Raleigh-Durham Airport Authority Presentation
More informationFort Lauderdale Hollywood International Airport
ATLANTA, GEORGIA 1 2 ATLANTA, GEORGIA Fort Lauderdale Hollywood International Airport Master Plan to Master Plan Implementation Jamie McCluskie Director of Aviation Planning & Environmental Broward County
More informationCity of Kansas City AIRPORT COMMITTEE BRIEFING. Major Renovation Evaluation for Kansas City International Airport.
City of Kansas City AIRPORT COMMITTEE BRIEFING Major Renovation Evaluation for Kansas City International Airport February 2, 2016 1 Agenda Briefly review Exhibit K Process to establish Program Requirements
More informationPITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM
PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM FREQUENTLY ASKED QUESTIONS September 2017 Master Plan Update: 1. What is a Master Plan Update? The objective of a Master Plan Update (MPU)
More informationERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS
EXECUTIVE SUMMARY ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS PAGE NO. CHAPTER 1-INTRODUCTION... 1-1 1.01 General...1-1 1.02 Purpose and Scope of Study...1-1 1.03 The Planning Process...1-2
More informationYakima Air Terminal/McAllister Field Airport Master Plan Update
Yakima Air Terminal/McAllister Field Airport Master Plan Update City of Yakima Work Session July 9, 2013 Meeting Goals Summarize the master plan recommendations. Discuss the decision-making process used
More information2017 Appropriation Budget Table of Contents Board Approved August 19, 2016
INDIANAPOLIS AIRPORT AUTHORITY 2017 APPROPRIATION BUDGET ORDINANCE NO. 2-2016 BOARD APPROVED AUGUST 19, 2016 2017 Appropriation Budget Table of Contents Board Approved August 19, 2016 1 Appropriation Summary
More information2. 1:45 to 1:50 Review and Approval of November 18, 2009 NOC Meeting Minutes
Minneapolis/St. Paul International Airport (MSP) Noise Oversight Committee (NOC) Meeting Agenda January 2, 21 1:3 P.M. Lindbergh Conference Room MAC General Office Building 64 28 th Avenue South Minneapolis,
More informationBend Municipal Airport Urban Renewal Plan. Tashman Johnson LLC Elaine Howard Consulting LLC
Bend Municipal Airport Urban Renewal Plan Tashman Johnson LLC Elaine Howard Consulting LLC Urban Renewal Background The purpose of urban renewal is to improve certain areas that are poorly developed or
More information2012 AIRPORT MASTER PLAN 2016 ADDENDUM VOLUME 1 SUBMITTED ON: SEPTEMBER 22, 2017
VOLUME 1 2012 AIRPORT MASTER PLAN 2016 ADDENDUM SUBMITTED ON: SEPTEMBER 22, 2017 VOLUME 1 CONTENTS SECTION 1 - INTRO AND AIRPORT CONTEXT SECTION 2 - FORECAST SECTION 3 - AIRFIELD FACILITIES AND DEMAND/CAPACITY
More informationFort Wayne International Airport Master Plan Study. Executive Summary
Fort Wayne International Airport Master Plan Study Executive Summary March 2012 Introduction Airport Background Forecast of Aviation Activity Development Plans Recommended Airfield & Access Development
More informationPresentation to the British Irish Airport s EXPO John Heffernan Chief Development Officer, Dublin Airport
Presentation to the British Irish Airport s EXPO John Heffernan Chief Development Officer, Dublin Airport 1 DUBLIN-LONDON 28.4 No.1 +2,200 MILLION PASSENGERS BUSIEST ROUTE IN EUROPE &No. 2 IN THE WORLD
More informationHartsfield Jackson Update prepared for:
Hartsfield Jackson Update prepared for: September 6, 2013 Presented by: Shelley Lamar, Planning Manager Agenda ATL Overview Economic Impact Preparing for the Future Your Questions Airport overview Airport
More informationAustin-Bergstrom International Airport Master Plan Update
FINAL REPORT Prepared for: City of Austin Department of Aviation 3600 Presidential Boulevard Austin, Texas 78719 Prepared by: P&D Aviation A Division of P&D Consultants, Inc. 999 Town & County Road, 4
More informationAirport Master Planning Process & Update
Airport Master Planning Process & Update David Stewart ICAO Airport Master Planning Task Force Subgroup Leader ICAO Airport Planning Seminar for the SAM Region Lima, Peru 10-14 Sep. 2018 1 Speaker: David
More informationHouston Airport System IAH Master Plan 2035 Summary
Summary INTRODUCTION The Houston Airport System owns/operates three airports George Bush Intercontinental Airport (IAH) the city s largest airport and global gateway, serving over 40 million passengers
More informationFinancial Feasibility Analysis Terminal Programming Study Des Moines Airport Authority
Financial Feasibility Analysis Terminal Programming Study Des Moines Airport Authority September 12, 2017 Contents 1. Funding Sources for Airport Projects 2. Financial Metrics 3. CIP Summary and Funding
More informationNoise Oversight Committee
Noise Oversight Committee March 18, 2015 Audio recordings are made of this meeting Noise Oversight Committee March 18, 2015 Item 1 Review and Approve Draft Meeting Minutes Minutes from January 21, 2015
More informationA.B. WON PAT INTERNATIONAL AIRPORT AUTHORITY, GUAM CAPITAL IMPROVEMENT PROJECTS FOR FISCAL YEARS THROUGH 2018 as of 02/22/18 I. ONGOING PROJECT NAME Bond Federal CIF Total Payment Balance 1 AIP 97 AIP
More informationAlternatives Analysis EXECUTIVE SUMMARY
Alternatives Analysis EXECUTIVE SUMMARY Alternative development plans were created as part of the Master Plan for Harrisburg International Airport. The aim is to provide sufficient capacity for projected
More informationENVISIONING AUSTIN s Airport of the Future
ENVISIONING AUSTIN s Airport of the Future ABIA 2040 Master Plan Public Workshop #1 October 12, 2017 WHAT IS THE PURPOSE OF TODAY S WORKSHOP? Educate & Inform Solicit Input Answer Questions 2 WHAT IS A
More informationGeneral Aviation Master Plan Update
Peter O. Knight Airport Public Meeting #2 Peter O. Knight Airport Agenda Welcome and Introductions HCAA System of Airports Purpose of Public Meetings Master Plan Status Update Next Steps Q & A 2 Our System
More informationNorfolk International Airport
Norfolk International Airport Master Plan Update Technical Advisory Committee Meeting #1 Community Advisory Committee Meeting #1 January 24, 2018 Agenda Project Background Introductions Overview of Airport
More informationGreater Orlando Aviation Authority Board Meeting. Wednesday, August 15, 2018
Greater Orlando Aviation Authority Board Meeting Wednesday, August 15, 2018 AWARDS APM/ITF BENEFITS North Terminal capacity relief o o Remote check-in availability Passenger drop-off areas Additional
More informationMaster Plan Update Community Advisory Committee Kick-off Meeting
Nashville International Airport Master Plan Update Community Advisory Committee Kick-off Meeting September 13, 2018 Agenda Welcome and Introductions Master Plan Objectives Master Plan Process BNA Vision
More informationGLOBAL CONGRESS PANEL DISCUSSION. Phil Brown Executive Director, Greater Orlando Aviation Authority August 18, 2015
GLOBAL CONGRESS PANEL DISCUSSION Phil Brown Executive Director, Greater Orlando Aviation Authority August 18, 2015 In the Beginning The Orlando Experience Past, Present and Future 1977 Today 1978 2013
More informationAviation Department Board Workshop. December 7, 2010
Aviation Department Board Workshop December 7, 2010 1 Agenda North Perry Airport (HWO) FLL Economic Impact & Traffic Update Terminal Area Forecast FLL Airport Layout Plan & Master Plan Update Runway 9R/27L
More informationCASE STUDY The New Guayaquil International Airport
www.jacobs.com worldwide CASE STUDY The New Guayaquil International Airport Prepared for ICAO Airport Planning Seminar for the SAM Region Lima, Peru 10-14 Sep. 2018 September 11, 2018 Outline Existing
More informationDRAFT. Master Plan RESPONSIBLY GROWING to support our region. Summary
Master Plan GROWING 2017-2037 RESPONSIBLY to support our region Summary DRAFT 2 1 Introduction Over the next three decades, Southern Ontario is set to experience significant growth its population will
More informationThe CLE Master Plan Includes:
The CLE Master Plan Includes: An inventory of existing conditions Forecasting future demand and analyzing future needs Evaluating alternative development scenarios Preparing the Airport Layout Plan Preparing
More informationDallas Love Field Update. Dallas City Council Briefing February 18, 2015
Dallas Love Field Update Dallas City Council Briefing February 18, 2015 Purpose Construction Update Impacts of Wright Amendment Repeal Increase in operations/passengers/ projections Concessions performance
More informationState of the Airport Robert S. Bowen, Executive Director October 18, 2018
Robert S. Bowen, Executive Director October 18, 2018 A Year of Change The last year will be remembered as a period when the airlines, bolstered by a growing national economy, moderate fuel prices and changing
More informationBuchanan Field. Airport Planning Program. Steering Committee. December 14, Master Plan FAR Part 150 Noise Study Strategic Business Plan
Airport Planning Program Master Plan FAR Part 150 Noise Study Strategic Business Plan Steering Committee December 14, 2006 Airport Planning Program Master Plan FAR Part 150 Noise Study Strategic Business
More informationOctober 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION
October 2014 BELLINGHAM INTERNATIONAL AIRPORT MASTER PLAN PRESENTATION The Master Plan Process Inventory Of Existing Conditions Complete. Forecasts Of Aviation Demand Complete. Facility Requirements Complete.
More informationTABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved
TABLE OF CONTENTS Description Page Number LIST OF ACRONYMS... a CHAPTER ONE INTRODUCTION General... 1-1 Study Objectives... 1-1 Public Involvement... 1-2 Issues to Be Resolved... 1-2 CHAPTER TWO EXISTING
More informationAirport Master Plan Update
Duttchessss Countty Airrporrtt Masstterr Plan Updatte Airport Master Plan Update Final Report Dutchess County Airport Town of Wappingers, New York C&S Engineers, Inc. 499 Col. Eileen Collins Blvd. Syracuse,
More informationTRACK: B TERMINAL/LANDSIDE
Salt Palace Convention Center TRACK: B TERMINAL/LANDSIDE WORKSHOP: 3 Title: Airlines and Airports Consolidation and Changing Faces Who is building the Terminals, Technology, and Flexibility? Moderator:
More informationCOMMERCIAL AND GENERAL AVIATION Historic and forecast FDOT aviation activity information on file for Pensacola Regional Airport:
Existing Facilities Pensacola Regional Airport is served by a number of airside and landside facilities. Two intersecting, grooved asphalt runways serve the airport. These runways are runway 17/35 (7,004
More informationFLL Master Plan Update Technical Advisory Committee (TAC) Briefing #1. September 28, 2016
FLL Master Plan Update Technical Advisory Committee (TAC) Briefing #1 September 28, 2016 TAC Committee Role: Internal Stakeholders To provide input on the master planning analysis from the technical and
More informationEXECUTIVE SUMMARY. Master Plan Update Phase 2/3 FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT 1. INTRODUCTION 2.
MASTER PLAN UPDATE Phase 2/3 Draft Final Summary Report Report Issued 2010 in association with Prepared for Broward County Aviation Department Main Office 555 Airport Blvd., Suite 300 Burlingame, CA 94010
More informationSession 6 Airport Finance 101 Funding Sources for Airports
Session 6 Airport Finance 101 Funding Sources for Airports 31 st Annual AAAE Basics of Airport Law Workshop and 2015 Legal Update November 1-3, 2015 Desk Reference Chapters 2, 19, 22 Frank J. San Martin
More informationBroward County Aviation Department Recommended Budget Fiscal Year 2019
Broward County Aviation Department Recommended Budget Fiscal Year 2019 Overview FY 2019 Key Operating Budget Highlights Industry and Airline Activity FLL Activity Comparison of Passenger Growth Rates Enplanement
More informationRNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan
RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan Project Schedule Today Slide 40 Project Vision To provide an achievable, flexible, fiscally, and environmentally
More informationLove Field Modernization Program Update: Master Planning Recommendations
Love Field Modernization Program Update: Master Planning Recommendations Briefing to the Council Transportation and Environment Committee April 28, 2008 1 1 Briefing Objective Discuss the background and
More informationNOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019
NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019 The City of Atlanta is providing an opportunity for public comment until April 25, 2019 related to the
More informationBrief Recap of Project to Date
CITY AND BOROUGH OF SITKA Rocky Gutierrez Airport (SIT) Terminal Improvements Project Brief Recap of Project to Date Schematic Design: Design Development Meetings June 26 & 27, 2018 Project Description
More informationBirmingham Airport 2033
Over the next 15 years, we will expand and improve the Airport to maximise our potential as a single runway airport by investing 500 million in new development. Our plans take account of our forecasted
More informationCOMMERCIAL AND GENERAL AVIATION
Existing Facilities Melbourne International Airport is served by three runways and a number of airside and landside facilities. The runways include Runway 4/22 (3,001 feet long by 75 feet wide), Runway
More informationCONSTRUCTION COMMITTEE MEETING AGENDA
CONSTRUCTION COMMITTEE MEETING AGENDA DATE: Tuesday, January 02, 2018 TIME: 8:30 a.m. PLACE: GOAA ANNEX BUILDING, 1ST FLOOR - CONFERENCE ROOMS (APOLLO/GEMINI/TAURUS), 5855 CARGO ROAD, ORLANDO INTERNATIONAL
More informationMeeting Presentation. Sacramento International Airport Master Plan Update October 30, 2012
Meeting Presentation Master Plan Update October 30, 2012 Agenda We encourage open discussion during today s meeting Team Goals Background (Airport Master Plans) Areas of Emphasis Schedule Special Concerns
More informationBrisbane Airport Ground Transport Operators Forum Tuesday 25 July, 2pm Brisbane Airport Meeting Room Ground Transport Operators
MEETING MINUTES Event: Date & Time: Venue: Attendees: Brisbane Airport Ground Transport Operators Forum Tuesday 25 July, 2017 @ 2pm Brisbane Airport Meeting Room Ground Transport Operators Agenda Item
More informationCONSTRUCTION COMMITTEE MEETING AGENDA
CONSTRUCTION COMMITTEE MEETING AGENDA DATE: Tuesday, February 13, 2018 TIME: 8:30 a.m. PLACE: GOAA ANNEX BUILDING, 1ST FLOOR - CONFERENCE ROOMS (APOLLO/GEMINI/TAURUS), 5855 CARGO ROAD, ORLANDO INTERNATIONAL
More informationMASTER PLAN GEORGE BUSH INTERCONTINENTAL AIRPORT/HOUSTON. Houston Airport System Houston, Texas DRAFT TECHNICAL REPORT.
in association with AirProjects Inc. Conway Consulting Gunda Corporation Quadrant Consultants RdlR Architects Sunland Group DRAFT TECHNICAL REPORT MASTER PLAN Prepared for Houston Airport System Houston,
More information