1 Build-Out Analysis (Beardsley Dr/Oldwoods Ave Need Study) Project Progress Meeting 2 August 13, :00 PM Pasco County Development Services Conference Room 1. Welcome/Introductions 2. Project Overview Schedule 3. Comments Received 4. Tasks Performed Alternatives Evaluated MOE Comparison VHT/Savings 5. Upcoming Tasks Develop Preferred Alternative Conceptual Roadway Alignment Document Findings 6. Questions/Feedback
2 PASCO COUNTY MPO Wesley Chapel Area Roadway Needs Study Build-Out Analysis Progress Meeting August 13, 2012 August 13,
3 Beardsley Dr./Oldwoods Ave. Need Study Schedule Comments Received Tasks Performed Upcoming Tasks Questions/Feedback August 13,
4 Project Overview Schedule Task May June July August September Task 1 Model Review Update Zdata Review Model Validation Initial Travel Demand Assessment Task 2: Alternative Evaluation Test 3 Additional Alternatives Execute Preferred Alternative Task 3: Meetings Progress Meeting Task 4: Documentation Final Report/Presentation August 13,
5 Beardsley Dr./Oldwoods Ave. Need Study Schedule Comments Provided Tasks Performed Upcoming Tasks Questions/Feedback August 13,
6 Comments Provided Lincks & Assoc. Socioeconomic Data Heidt Design Oldwoods Ave. from Meadow Pointe Blvd. to Wyndfields Blvd. Raysor Transportation Consulting Growth Projections Hillsborough County Connectivity Beardsley Dr. Design and Alignment Subdivision Collector Roadways August 13,
7 Comments Provided Beardsley Dr. Design and Alignment & Subdivision Collector Roadways Model Reflects Existing Alignment Facility Speed/Capacity: Roadway Facility Type # Description Capacity Per Lane [veh/hr] Speed [mph] S.R Divided Arterial Class Ia Oldwoods Ave. 41 Major Local Divided Roadway Beardsley Dr. 42 Major Local Undivided Roadway w/turn Bays August 13,
8 Beardsley Dr./Oldwoods Ave. Need Study Schedule Comments Provided Tasks Performed Upcoming Tasks Questions/Feedback August 13,
9 Task Performed Four Alternatives Evaluated Build-Out / No Build Build-Out / Oldwoods Avenue Only Build-Out / Beardsley Drive Only Build-Out / Beardsley Drive & Oldwoods Avenue August 13,
10 Build-Out / No-Build Scenario Legend 2-Lane Road 4-Lane Road 6-Lane Road 8-Lane Road 10-Lane Road August 13,
11 Build-Out / Oldwoods Avenue Only Legend 2-Lane Road 4-Lane Road 6-Lane Road 8-Lane Road 10-Lane Road August 13,
12 Build-Out / Beardsley Drive Only Legend 2-Lane Road 4-Lane Road 6-Lane Road 8-Lane Road 10-Lane Road August 13,
13 Build-Out / Beardsley Drive & Oldwoods Avenue Legend 2-Lane Road 4-Lane Road 6-Lane Road 8-Lane Road 10-Lane Road August 13,
14 Alternatives Evaluation MOE Comparison: Alternative VMT VHT Weighted V/C No-Build 3,005, , Build-Out Oldwoods Ave 2,982, , Build-Out Beardsley Dr 3,016, , Build-Out Beardsley Dr & Oldwoods Ave 3,034, , August 13,
15 Alternatives Evaluation VHT/Savings (Time Only) Comparison: Alternative VHT VHT Daily VHT Savings/ Savings/ 25 Year Reduction Reduction (1) Day (2) Year (3) Savings (4) No-Build 131, $0 $0 $0 Build-Out Oldwoods Ave 131, $917 $275,185 $4,791,842 Build-Out Beardsley Dr 128,262 3, $11,085 $3,325,408 $57,905,824 Build-Out Beardsley Dr & Oldwoods Ave 127, , $15,263 $4,578, $79,730, Arterial 125,541 5, $21,113 $6,333,986 $110,294,639 (1) Assumes Peak-to-Daily Ratio of 0.09 and BPR b Exponent of 10 (Source: User Benefit e Analysis s for Highways AASHTO) (2) Assumes Vehicle-occupancy of 1.3 and $14/hour (3) 300 days/year (4) 3% Discount Rate August 13,
16 Beardsley Dr./Oldwoods Ave. Need Study Schedule Comments Provided Tasks Performed Upcoming Tasks Questions/Feedback August 13,
17 Beardsley Dr./Oldwoods Ave. Need Study Upcoming Tasks Define Preferred Alternative Conceptual Roadway Alignment Document Findings August 13,
18 End of Presentation Questions? August 13,
1.2 Corridor History and Current Characteristics
SECTION 1 Description and Background of Study Area 1.1 Introduction This preliminary engineering report was prepared for the Alaska Department of Transportation and Public Facilities (ADOT&PF). It is part
More informationAPPENDIX J MODIFICATIONS PERFORMED TO THE TOR
APPENDIX J MODIFICATIONS PERFORMED TO THE TOR This appendix summarizes the modifications that were performed in years 2012 and 2017 to rectify calculation errors that were observed in the data presented
More informationProject Deliverable 4.1.3d Individual City Report - City of La Verne
Pomona Valley ITS Project Project Deliverable 4.1.3d Individual City Report - City of La Verne Prepared by: April 19, 2002 099017000.1 Copyright 2002, Kimley-Horn and Associates, Inc TABLE OF CONTENTS
More informationDOGWOOD AT VILLA AVENUE PROJECT
TRANSPORTATION IMPACT ANALYSIS DOGWOOD AT VILLA AVENUE PROJECT El Centro, California September 4, 2018 LLG Ref. 3-17-2782 TABLE OF CONTENTS SECTION PAGE Appendices... ii List of Figures... i List of Tables...
More informationPublic Open House. Chief Peguis Trail Project
Public Open House Chief Peguis Trail Project CHIEF PEGUIS TRAIL OPEN HOUSE Welcome! Please browse the display boards Project Engineers and City of Winnipeg representatives are available to address your
More informationForecast and Overview
Forecast and Overview DENVER INTERNATIONAL AIRPORT Overall goals of the (MPR): Work with DEN to refine the preferred airport development plan to guide the development over an approximate 25-year planning
More informationTraffic Analysis Final Report
SR-71 Widening Project Project Approval/Environmental Documentation Traffic Analysis Final Report Prepared for Caltrans District 7 August 2012 6 Hutton Centre Drive, Suite 700 Santa Ana, California 92707
More informationTRANSPORTATION ELEMENT
Transportation TRANSPORTATION ELEMENT Data, Inventory, and Analysis Prepared by Contents 1.0 INTRODUCTION... 1 2.0 EXISTING CONDITIONS... 1 2.1 Roadways... 1 2.1.1 Jurisdiction... 1 2.1.2 Functional Classification...
More informationMEMORANDUM. Lynn Hayes LSA Associates, Inc.
MEMORANDUM To: Lynn Hayes LSA Associates, Inc. Date: May 5, 217 From: Zawwar Saiyed, P.E., Senior Transportation Engineer Justin Tucker, Transportation Engineer I Linscott, Law & Greenspan, Engineers LLG
More informationTransAction Overview. Introduction. Vision. NVTA Jurisdictions
Introduction Vision NVTA Jurisdictions In the 21 st century, Northern Virginia will develop and sustain a multimodal transportation system that enhances quality of life and supports economic growth. Investments
More informationCRISIS COALITION. Regional Projects Analysis February 2, 2015
CRISIS COALITION Regional Projects Analysis February 2, 215 STUDY BACKGROUND Team of CRISIS Representatives, Parish Presidents and/or their Representatives, Legislators, and MPO Staff shortlisted 19 regional
More informationSan Mateo County Transportation Authority Board Meeting November 2, 2017 Item #10 1
San Mateo County Transportation Authority Board Meeting November 2, 2017 Item #10 1 OVERVIEW Brief recap from October Traffic Analysis Findings Draft Environmental Document Summarized Outcomes Questions
More informationHDR itrans Consulting Inc. 100 York Blvd., Suite 300 Richmond Hill, ON L4B 1J8 Tel: (905) Fax: (905)
!" # $ !" # $ Consulting Inc. 100 York Blvd., Suite 300 Richmond Hill, ON L4B 1J8 Tel: (905) 882-4100 Fax: (905) 882-1557 www.itransconsulting.com November 2009 %&'('$&$ 1. West Brampton Road Network...
More informationLake Erie Commerce Center Traffic Analysis
LOCATION: East of NYS Route 5 at Bayview Road Town of Hamburg Erie County, New York PREPARED BY: Wendel Companies 140 John James Audubon Parkway Suite 200 Amherst, New York 14228 January 2012 i ii Table
More informationTechnical Advisory Committee. May 14, 2013
Technical Advisory Committee May 14, 2013 1 Introductions and Review Review the three recommended Alternatives for detailed evaluation Next Steps Schedule and upcoming meetings Other discussion 2 Delayed
More informationLUDWIG RD. SUBDIVISION PROJECT TRAFFIC IMPACT ANALYSIS
LUDWIG RD. SUBDIVISION PROJECT TRAFFIC IMPACT ANALYSIS Prepared for Skip Coddington GSC Development, Inc PO Box 1623 Woodinville WA 9872 Prepared by 1141 NE 124 th St., #59 Kirkland, WA 9834 425.522.4118
More informationhauger bunch Town Center - Mixed Use Site 44+ Acres Outparcels/Major Retail US 98 South, Lakeland, Florida SITE
Town Center - Mixed Use Site 44+ Acres US 98 South, Lakeland, Florida I-4 & Tampa S Florida Ave Polk Parkway LAKELAND Lakeland Highlands Rd County Road 40 I-4 & Winter Haven Highland City Town Center Polk
More informationDirector King County Department of Transportation. King County Department of Transportation
Tolling in Washington State t Harold S. Taniguchi Director Why tolling Why Tolling? Gas tax down Electric collection technology Reduce peak demand and greenhouse gas emissions Tolling today in Washington
More informationThis page intentionally left blank
This page intentionally left blank Prepared for: Nevada Department of Transportation Prepared by: July 2015 This page intentionally left blank Table of Contents Executive Summary... ES-1 ES.1. HOV System
More informationOverview of Highway 37 Project. Novato Rotary November 4, 2016
Overview of Highway 37 Project Novato Rotary November 4, 2016 Project Location-Caltrans District 4 SR 37 Corridor Features Two to Four lane 21 mile corridor traversing Solano, Sonoma, and Marin Counties.
More informationProject Advisory Group. May 23, 2013
Project Advisory Group May 23, 2013 1 Introductions and Review Review the three recommended Alternatives for detailed evaluation Next Steps Schedule and upcoming meetings Other discussion 2 Delay the Open
More informationAppendix 4.1 J. May 17, 2010 Memorandum from CTPS to the Inter Agency Coordinating Group
Appendix 4.1 J May 17, 2010 Memorandum from CTPS to the Inter Agency Coordinating Group CTPS CENTRAL TRANSPORTATION PLANNING STAFF Staff to the Boston Region Metropolitan Planning Organization MEMORANDUM
More informationGeneral Assessment of Potential Transportation and Safety Impacts of CSXT Freight Relocation
MAY 2008 S-Line Grade Crossing General Assessment of Potential Transportation and Safety Impacts of CSXT Freight Relocation TABLE OF CONTENTS S-Line Grade Crossings 1.0 EXISTING CONDITIONS...1 1.1 TABLE
More informationFreight Study Phase II. Kick-Off Meeting
TxDOT El Paso Freight Study Phase II Kick-Off Meeting July 6, 2012 Overview Introduction of Team Introduction of Team Objectives of Study Study Tasks Methodology of Study Schedule Team Members TxDOT Jennifer
More informationSite Location and Setting
Memorandum Date: To: From: Subject: Kristy Le, Gary Black Steve Orem Santa Teresa County Park Historic Area Traffic and Parking Study Hexagon Transportation Consultants, Inc. has completed a traffic and
More informationCaliber Charter School VALLEJO, CA
Traffic Impact Study Final Report Caliber Charter School VALLEJO, CA 21 June 2016 Prepared for: Prepared by: Traffic Engineering & Transportation Planning This report has been prepared and certified by
More informationMemorandum. Roger Millar, Secretary of Transportation. Date: April 5, Interstate 90 Operations and Mercer Island Mobility
Memorandum To: From: The Honorable Dow Constantine, King County Executive; The Honorable Ed Murray, City of Seattle Mayor; The Honorable Bruce Bassett, City of Mercer Island Mayor; The Honorable John Stokes,
More informationRECENT SCENARIO PLANNING FOR THE REGIONAL FREEWAY AND HIGHWAY PROGRAM MARICOPA ASSOCIATION OF GOVERNMENTS
RECENT SCENARIO PLANNING FOR THE REGIONAL FREEWAY AND HIGHWAY PROGRAM MARICOPA ASSOCIATION OF GOVERNMENTS National Scenario Planning Peer Exchange July 10, 2012 2012, All Rights Reserved. 1 MAG Transportation
More informationPattullo Bridge Replacement Project
JULY 2018 PROJECT OVERVIEW Pattullo Bridge Replacement Project engage.gov.bc.ca/pattullobridge Artist s rendering of the proposed new Pattullo Bridge Pattullo Bridge Replacement Project 1 Priority Need
More informationEvaluation of Significant Transportation Projects in Northern Virginia Transportation District. HB 599 Ratings Overview NVTA - January 22, 2015
Evaluation of Significant Transportation Projects in Northern Virginia Transportation District HB 599 Ratings Overview NVTA - January 22, 2015 Study Approach NVTA and CTB nominate projects Define Project
More informationMETROBUS SERVICE GUIDELINES
METROBUS SERVICE GUIDELINES In the late 1990's when stabilization of bus service was accomplished between WMATA and the local jurisdictional bus systems, the need for service planning processes and procedures
More informationUS 380 FEASIBILITY STUDY
US 380 FEASIBILITY STUDY Denton County CSJ(s): 0135-10-061, 0135-10-062 Public Meeting(s): January 15 & 22, 2019 WELCOME US 380 Denton County Feasibility Study DALLAS DISTRICT PUBLIC MEETING January 15
More informationAppendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update
Appendix D Project Newsletters Tacoma Narrows Airport Master Plan Update This appendix contains the newsletters distributed throughout the project. These newsletters provided updates and information on
More informationAASHTO AS Presented to AASHTO T 8, June 13, 2017
AASHTO AS 13 0024 Support for the HSCOBS Technical Committee on Moveable Bridges (T-8) in a Technical Advisory Role for Specification Updates Span Lock Design Study Presented to AASHTO T 8, June 13, 2017
More informationMETROPOLITAN EVANSVILLE TRANSIT SYSTEM Part I: Comprehensive Operations Analysis Overview July 9 th, 2015 Public Information Meeting
METROPOLITAN EVANSVILLE TRANSIT SYSTEM Part I: Comprehensive Operations Analysis Overview July 9 th, 2015 Public Information Meeting AGENDA 5:30 5:40 Open House 5:40 6:30 Presentation Comprehensive Operations
More informationLaxon Terrace - Sarawia. Click to add title. Street Rail Level Crossing. Public Forum. December
Laxon Terrace - Sarawia Click to add title Street Rail Level Crossing Public Forum December 2012 www.aucklandtransport.govt.nz Overview of Presentation Objectives and Reasons for Separation Project Background
More informationProvincial Railway Technical Standards
GENERAL: INDEX: The standards and requirements listed in this document are intended for use on provincially regulated railway public grade crossings. These standards are considered the minimum requirements
More informationImagine the result. Bus Rapid Transit Feasibility Study. Laredo Urban Transportation Study. August 31 st, 2011
Imagine the result Laredo Urban Transportation Study August 31 st, 2011 Bus Rapid Transit Feasibility Study Prepared for: Laredo Urban Transportation Study Prepared by: ARCADIS U.S., Inc. 2410 Paces Ferry
More informationHonorable Members of the Mobility Solutions, Infrastructure and Sustainability Committee
Memorandum DATE August 10, 2018 CITY OF DALLAS TO Honorable Members of the Mobility Solutions, Infrastructure and Sustainability Committee SUBJECT Dallas Love Field Master Plan Update On Monday, August
More informationMaster Plan March Prepared for Northwest Florida Transportation Corridor Authority
Master Plan 2007 March 2007 Prepared for Northwest Florida Transportation Corridor Authority Prepared by: HDR Engineering, Inc. 09 Harrison Avenue Panama City, FL 3240-2726 In Association with: Cambridge
More informationDevelopment of SH119 BRT Route Pattern Alternatives for Tier 2 - Service Level and BRT Route Pattern Alternatives
Development of SH119 BRT Route Pattern Alternatives for Tier 2 - Service Level and BRT Route Pattern Alternatives June 1, 2018 Development of SH119 BRT Route Pattern Alternatives for Tier 2 - Service Level
More informationAustin-Bergstrom International Airport Master Plan Update
FINAL REPORT Prepared for: City of Austin Department of Aviation 3600 Presidential Boulevard Austin, Texas 78719 Prepared by: P&D Aviation A Division of P&D Consultants, Inc. 999 Town & County Road, 4
More informationOverview of Highway 37 Project. Napa County Board of Supervisors December 20, 2016
Overview of Highway 37 Project Napa County Board of Supervisors December 20, 2016 1 Project Location-Caltrans District 4 2 SR 37 Corridor Features 2 to 4 lane 21 mile corridor traversing Solano, Sonoma,
More informationSection II. Planning & Public Process Planning for the Baker/Carver Regional Trail began in 2010 as a City of Minnetrista initiative.
Section II Planning & Public Process Planning for the began in 2010 as a City of initiative. city staff began discussions with the Park District on the possibility of a north/south regional trail connection
More informationUS 19 Sunset Point Rd to Countryside Blvd.
Frontage Lanes Alternative Six-Lane Roadway Two-Lane, One-Way Frontage Lanes Close All Median Openings w/ Concrete Median Barrier Construct Within Existing Right-of-Way Status Update Construction started
More informationProject Deliverable 4.1.3f Individual City Report - City of San Dimas
Pomona Valley ITS Project Project Deliverable 4.1.3f Individual City Report - City of San Dimas Prepared by: April 19, 2002 099017000.1 Copyright 2002, Kimley-Horn and Associates, Inc TABLE OF CONTENTS
More informationCity of Solvang SUNNY FIELDS SPUR TRAIL STUDY
City of Solvang SUNNY FIELDS SPUR TRAIL STUDY project description The City of Solvang, in partnership with the County of Santa Barbara Public Works Department, is developing an alignment study for a proposed
More informationDENISON STREET EXTENSION. Transportation Committee. January 14, Feasibility Study
DENISON STREET EXTENSION Feasibility Study January 14, 2014 Transportation Committee Markham Transportation Strategic Plan (MTSP) analysis completed in 2012 reviewed transportation requirements to accommodate
More informationSTAGE 2 & 3 Pavement reconstruction within viaduct footprint, pavement widening and resurfacing N/S of viaduct footprint, sidewalk
STAGE 1 Viaduct removal, deck replacement on the River Bridge, and approach of the Chicago River Bridge north to Roscoe) Maintain local access roadways - 1 lane in each direction A signed alternate route
More informationAPPENDIX J TRAFFIC AND PARKING DEMAND STUDIES
APPENDIX J TRAFFIC AND PARKING DEMAND STUDIES Table of Contents Executive Summary... iv 1.0 Introduction... 1 2.0 Traffic Analysis Methodology and Significance Criteria... 4 2.1 Study Area Criteria...
More informationINTERSTATE 395 EXPRESS LANES NORTHERN EXTENSION TRAFFIC & TRANSPORTATION TECHNICAL REPORT SEPTEMBER 2016
INTERSTATE 395 EXPRESS LANES NORTHERN EXTENSION TRAFFIC & TRANSPORTATION TECHNICAL REPORT SEPTEMBER 2016 INTERSTATE 395 EXPRESS LANES NORTHERN EXTENSION Traffic and Transportation Technical Report City
More information2017 TBARTA Future Regional Priority Projects Adopted by TBARTA Board, December 9, 2016
2017 TBARTA Future Regional Priority Projects Adopted by TBARTA Board, December 9, 2016 Project numbers do not signify ranking they are for mapping identification purposes only. 1. 15th Street East The
More informationCharlotte Regional Express Lane Facilities: I-485 and US 74. North Carolina Turnpike Authority March 21, 2018
Charlotte Regional Express Lane Facilities: I-485 and US 74 North Carolina Turnpike Authority March 21, 2018 NC Turnpike Authority Overview Created in 2002 by the General Assembly Authorized to design,
More informationB. Congestion Trends. Congestion Trends
B. Congestion Trends Congestion Trends There are two types of congestion that impact mobility: recurring and non-recurring congestion. Recurring congestion is related to segments of roadway that are over
More informationMEMORANDUM. Bob Zagozda, Chief Financial Officer Westside Community Schools. Mark Meisinger, PE, PTOE Felsburg Holt & Ullevig. DATE: June 11, 2018
MEMORANDUM TO: Bob Zagozda, Chief Financial Officer Westside Community Schools FROM: Mark Meisinger, PE, PTOE Felsburg Holt & Ullevig DATE: June 11, 218 6-11-18 SUBJECT: Sunset Hills Elementary School
More informationPUBLIC INFORMATION SESSION #2
Highway 16, Highway 779 to Kapasiwin Road, Planning Study PUBLIC INFORMATION SESSION #2 Wednesday June 20, 2012 4 to 8 pm HIGHWAY 16 Highway 779 to Kapasiwin Road Functional Planning Study Blueberry Community
More informationWashington St. & Ash Coulee Dr./43 rd Ave Intersection Study
430 IACC Building Fargo, ND 58105 Tel 701-231-8058 Fax 701-231-1945 www.ugpti.org www.atacenter.org Washington St. & Ash Coulee Dr./43 rd Ave Intersection Study Final Report April 2007 Prepared for: City
More informationCoast to Coast Connector Summit
Project Partners Welcome to the Coast to Coast Connector Summit Winter Garden, Florida City Hall October 1, 2014 1 Why are we here? Objectives 1. Inform key stakeholders on the current state of the C2C
More informationSan Martin Boulevard over Riviera Bay Project Development & Environment (PD&E) Study Update PID A
San Martin Boulevard over Riviera Bay Development & Environment (PD&E) Study Update PID 001036A June 12, 2018 Location & Limits Unincorporated Pinellas County City of St. Petersburg 2 Overview Of Alternatives
More informationANCLOTE COASTAL TRAIL ALTERNATIVES ANALYSIS STUDY
ANCLOTE COASTAL TRAIL ALTERNATIVES ANALYSIS STUDY PASCO COUNTY MPO JULY 2015 PROJECT OVERVIEW... INTRODUCTION EXECUTIVE SUMMARY CONTEXT... TAMPA BAY AREA, PINELLAS, & PASCO COUNTY S MULTI-USE TRAIL PLANS
More informationArlington County Board Meeting Project Briefing. October 20, 2015
Arlington County Board Meeting Project Briefing October 20, 2015 Project Map 2 Project Context Only Interstate in the Country limited to HOV only traffic during rush hours Stoplight at the end of I-66
More informationAtlas of a regional transportation network: Oregon Metro's Mobility Corridor Atlas
Atlas of a regional transportation network: Oregon Metro's Mobility Corridor Atlas Matthew Hampton Oregon Metro February 25 th, 2013 Early experience with transportation Our region Charting a Different
More informationWelcome to the Downtown Fort Lauderdale Neighborhood Working Group Meeting. First meeting june 17, 2010
Welcome to the Downtown Fort Lauderdale Neighborhood Working Group Meeting First meeting june 17, 2010 State of the Project Draft Environmental Impact Statement Study Phase This study is NOT the final
More informationTransportation TRANSPORTATION PROJECTS
Transportation TRANSPORTATION PROJECTS Balls Ford Road Interchange Total Project Cost $142.9M This project includes the construction of a new diverging diamond interchange at Route 234 Bypass (Prince William
More informationEast Link Project Update. Maintenance of Traffic During Construction. April 21, 2015
East Link Project Update Maintenance of Traffic During Construction April 21, 2015 1 Agenda TFP project 242 Bellevue Way HOV Bellevue Way - Maintenance of Traffic During Construction Early Work Utilities
More informationPURPOSE AND NEED (CONCURRENCE POINT 1) NEW CANADA ROAD PROJECT FROM STATE ROUTE 1 (U.S. HIGHWAY 70) TO U.S. INTERSTATE 40
PURPOSE AND NEED (CONCURRENCE POINT 1) NEW CANADA ROAD PROJECT FROM STATE ROUTE 1 (U.S. HIGHWAY 70) TO U.S. INTERSTATE 40 Project Description The primary purpose of this project is to improve the major
More informationPDF compression, OCR, web optimization using a watermarked evaluation copy of CVISION PDFCompressor
o U.S. Department Washington Division Suite 501 Evergreen Plaza of Transportation 711 South Capitol Way Olympia, Washington 98501-1284 Federa' Highway (360) 753-9480 Administration (360) 753-9889 (FAX)
More informationAttachment G STREAM IMPACTS. Ridge Road Extension Alternatives Analysis
Attachment G STREAM IMPACTS for: Ridge Road Extension Alternatives Analysis PREPARED FOR: Pasco County Engineering Services Department PREPARED BY: NV5, INC. 6989 E. FOWLER AVENUE TAMPA, FLORIDA 33617
More information5.1 Traffic and Transportation
5.1 When it opens in 2009, the Bellevue Nickel Improvement Project will increase the number of vehicles able to travel through the study area, improve travel speeds, and improve safety by reducing the
More informationPedestrian Safety Review Spadina Avenue
STAFF REPORT ACTION REQUIRED Pedestrian Safety Review Spadina Avenue Date: October 13, 2015 To: Toronto and East York Community Council From: Director, Transportation Services, Toronto and East York District
More information10.0 Recommendations Methodology Assumptions
10.0 Recommendations To accommodate the projected growth of the I-526 corridor, this report has summarized potential improvement strategies that were separated into four categories, TDM, Modal, Traffic
More informationInterstate 90 and Mercer Island Mobility Study APRIL Commissioned by. Prepared by
Interstate 90 and Mercer Island Mobility Study APRIL 2017 Commissioned by Prepared by Interstate 90 and Mercer Island Mobility Study Commissioned by: Sound Transit Prepared by: April 2017 Contents Section
More informationTransportation Impact Assessment Paradise Shores RV Resort Development Stettler County, Alberta Progress Update February 2018 PO#
February 20, 2018 RV Sites Canada 300, 1933A 10 Avenue SW Calgary, AB T23C 0K3 Attn: Re: Rick Halpern Transportation Impact Assessment Paradise Shores RV Resort Development Stettler County, Alberta Progress
More informationWashington Dulles International Airport (IAD) Aircraft Noise Contour Map Update. 6th Working Group Briefing 1/7/19
Washington Dulles International Airport (IAD) Aircraft Noise Contour Map Update 6th Working Group Briefing 1/7/19 Study Purpose Agenda Background Summary of last stakeholder meetings Refresher on DNL,
More informationEvaluation of Ramp Meter Effectiveness for Wisconsin Freeways, A Milwaukee Case Study: Part 2, Ramp Metering Effect on Traffic Operations and Crashes
Evaluation of Ramp Meter Effectiveness for Wisconsin Freeways, A Milwaukee Case Study: Part 2, Ramp Metering Effect on Traffic Operations and Crashes Project identification number 92-45-17 Final Report
More informationFHWA Actions on Past Interstate Requests that were approved by the USRN were presented and conditions were lifted. FHWA Approval Date
SPECIAL COMMITTEE ON US ROUTE NUMBERING MEETING MINUTES FOR OCTOBER 17, 2013 AND REPORT TO SCOH OCTOBER 18, 2013 SHERATON DOWNTOWN DENVER, DENVER, COLORADO ADDENDUM OCTOBER 28, 2013 The meeting of the
More informationDRAFT TH AVE NE URBAN DESIGN MERIT PRESENTATION DPD# NOVEMBER 2017
DRAFT 11.08.17 4801 24TH AVE NE URBAN DESIGN MERIT PRESENTATION 17-002 DPD#3027312 16 NOVEMBER 2017 PROJECT BACKGROUND URBAN DESIGN ANALYSIS VACATION / NO-VACATION COMPARISON URBAN DESIGN MERIT INTRODUCTION
More informationMcLean Citizens Association Transportation Committee Project Briefing
McLean Citizens Association Transportation Committee Project Briefing November 10, 2015 Project Map 2 Project Context Only Interstate in the Country limited to HOV only traffic during rush hours Stoplight
More informationNovember 11, 2009 BY . Planning and Growth Management Department 110 Laurier Avenue West, 4 th Floor Ottawa, Ontario K1P 1J1. Dear Mr.
November 11, 2009 Planning and Growth Management Department 110 Laurier Avenue West, 4 th Floor Ottawa, Ontario K1P 1J1 BY E-MAIL Attention: Mr. Don Herweyer Dear Mr. Herweyer: Reference: Abbott-Fernbank
More informationPattullo Bridge Replacement Project
FEBRUARY 2019 PROJECT OVERVIEW Pattullo Bridge Replacement Project engage.gov.bc.ca/pattullobridge Artist s rendering of the proposed new Pattullo Bridge Pattullo Bridge Replacement Project 1 Priority
More informationGlasgow Street Traffic Review
Glasgow Street Traffic Review Recommendation That the Standing Policy Committee on Transportation recommend to City Council: 1. That the Administration proceed with removing the pinch points installed
More informationSunshine Coast Fixed Link Planning Study
Sunshine Coast Fixed Link Planning Study Prepared for BC Ministry of Transportation and Infrastructure 205 4946 Canada Way Burnaby, BC V5G 4H7 EXECUTIVE SUMMARY The Sunshine Coast is located northwest
More informationChapel Hill Transit: Short Range Transit Plan. Preferred Alternative DRAFT
: Short Range Transit Plan Preferred Alternative August 2018 Table of Contents Executive Summary... 1 Preferred Alternative... 3 Best Practices for Route Design... 3 Project Goals... 4 Preferred Alternative...
More informationDraft Concept Alternatives Analysis for the Inaugural Airport Program September 2005
Section 10 Preferred Inaugural Airport Concept 10.0 Introduction The Preferred Inaugural Airport Concept for SSA was developed by adding the preferred support/ancillary facilities selected in Section 9
More informationSelection of a Locally Preferred Alternative for the Interstate 405 Improvement Project Between State Route 55 and Interstate 605.
ORANGE COUNTY TRANSPORTATION AUTHORITY Selection of a Locally Preferred Alternative for the Interstate 405 Improvement Project Between State Route 55 and Interstate 605 PowerPoint San Diego Freeway (Interstate
More informationTallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016
Tallahassee International Airport Master Plan Technical Advisory Committee Meeting #2 October 19, 2016 Agenda Welcome / Introductions Master Plan Process and Project Status Forecast of Aviation Demand
More informationTransportation Improvement District (TID) Exercise New Castle County Unified Development Code
Transportation Improvement District (TID) Exercise New Castle County Unified Development Code Churchmans Crossing TID How should New Castle County deploy Transportation Improvement Districts (TIDs)? Site
More informationPrivate Crossing Treatments on the North Carolina Sealed Corridor
Private Crossing Treatments on the North Carolina Sealed Corridor Patrick Bien-aime 2013 National Highway-Rail Grade Crossing Safety Training Conference November 05, 2013 The National Transportation Systems
More informationPROJECTED UTILIZATION OF THE PROPOSED HOTEL
PROJECTED UTILIZATION OF THE PROPOSED HOTEL The supply and demand analysis included general overviews of the Frostburg, Maryland market area, a detailed analysis of the properties projected to provide
More informationRegional Fare Change Overview. Nick Eull Senior Manager of Revenue Operations Metro Transit
Regional Fare Change Overview Nick Eull Senior Manager of Revenue Operations Metro Transit Committee of the Whole April 5 th, 2017 Today s Presentation Fare change goals and considerations Public engagement
More informationEnhanced Time Based Separation
Enhanced Time Based Separation (etbs) Enhanced Time Based Separation (etbs) Evolving TBS from SESAR research TBS tool for Heathrow developed with Lockheed Martin (now Leidos) TBS tool deployed at Heathrow
More informationALBANY-HUDSON ELECTRIC TRAIL FEASIBILITY STUDY. Final Report OCTOBER 2011
ALBANY-HUDSON ELECTRIC TRAIL FEASIBILITY STUDY Final Report OCTOBER 2011 ALBANY-HUDSON ELECTRIC TRAIL FEASIBILITY STUDY Prepared for: Town of East Greenbush 225 Columbia Turnpike Rensselaer, New York 12144
More informationMEMORANDUM. for HOV Monitoring on I-93 North and the Southeast Expressway, Boston Region MPO, November, 2011.
MEMORANDUM Date: January 12, 2012 To: Congestion Management Process Files From: Seth Asante, Ryan Hicks, and Efi Pagitsas MPO Staff Re: Historical Trends: Travel Times and Vehicle Occupancy Levels for
More informationPinellas Suncoast Transit Authority Community Bus Plan
Pinellas Suncoast Transit Authority Community Bus Plan FINAL REPORT JANUARY 2014 Prepared by: TABLE OF CONTENTS Executive Summary... 2 Community Bus Plan Introduction... 22 Previous Studies... 25 Market
More informationAldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering
Aldridge Transportation Consultants, LLC Advanced Transportation Planning and Traffic Engineering John M.W. Aldridge, PE, PTOE, AICP 182 Chimney Rock Road Colorado Registered Professional Engineer Highlands
More informationEngagement Summary Report. Trans-Canada Highway 1 RW Bruhn Bridge and Approaches Project Community Engagement February 1 18, 2018.
Trans-Canada Highway 1 RW Bruhn Bridge and Approaches Project Community Engagement February 1 18, 2018 Engagement Summary Report April 2018 Prepared by Kirk & Co. Consulting Ltd. Trans-Canada Highway 1
More informationProposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street
STAFF REPORT ACTION REQUIRED Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street Date: March 12, 2007 To: From: Toronto and East York Community Council Director, Transportation Infrastructure
More informationRW Bruhn Bridge and Approaches Project
RW Bruhn Bridge and Approaches Project The Trans-Canada Highway 1 RW Bruhn Bridge and Approaches Project involves four-laning approximately 1.9 km of Highway 1 in Sicamous, including replacement of the
More informationMADERA COUNTY. Measure T & SB-1 Projects
MADERA COUNTY Measure T & SB-1 Projects Measure T Projects: Avenue 26/Road 29 Rehabilitation (Measure T/FLAP) Oakhurst Midtown Connector (Measure T/SB-1 LPP) North Fork Roundabout (Measure T/CMAQ) Road
More information1.0 PURPOSE OF AND NEED FOR ACTION
1.0 PURPOSE OF AND NEED FOR ACTION 1.1 NEED FOR ACTION Federal legislation initially designated Interstate 73 (I-73) as a high priority corridor in the Intermodal Surface Transportation Efficiency Act
More information