A History of the Construction of the Radial Expressway System in Cook County
|
|
- Roland Reeves
- 6 years ago
- Views:
Transcription
1 ILLINOIS ASSOCIATION OF STATE HIGHWAY ENGINEERS 2017 ANNUAL CONFERENCE SEPTEMBER 29, 2017 A History of the Construction of the Radial Expressway System in Cook County Andrew Plummer Transportation Consultant and Historian Cookexpressways.com
2 CHICAGO SUPERHIGHWAY PLAN APPROVED BY STATE, COUNTY AND CITY IHE This is the soon to be altered 1947 plan-that included combining of the Cook County Tristate and River routes into the Tri- State Tollway. Note that LSD is part of plan as is the never constructed Crosstown
3 NORTH LAKE SHORE DRIVE 1927 NEWLY CONSTRUCTED BOULEVARD AT OAK STREET LAND FILL USED TO CREATE ROOM FOR SWEEPING ROADWAY CURVE AND EXPANDED BEACH
4 NORTH LAKE SHORE DRIVE 1937 SOUTH END OF STATE IMPROVEMENT/EXTENSION AT MONTROSE AVE LOOKING NORTH BUILT TO STATE STANDARDS. FIRST COOPERATIVE APPROACH TO BUILDING LIMITED ACCESS ROADWAYS
5 SUPERHIGHWAY AND EXPRESSWAYS OPENED IN THE 1950 S Kingery Expressway/1950/3 miles Calumet Expressway/ /15 miles Edens Superhighway&Spur/ /17.4miles Calumet Skyway Bridge /1958/7 miles Illinois Tollway/1958/76 miles(in Cook)
6 INTERSECTION OF CALUMET AND KINGERY EXPRESSWAYS BUILT IN 1950 LOOKING NORTH, CONSTRUCTION STARTING IN I-394 TO SAUK TRAIL OPENED IN TO WEST CCHD ROW TO BE SOLD TO TOLLWAY. EXAMPLE OF QUINLANS RURAL BUILDING DECISION IN 1940
7 Building the Edens Superhighway OPENINGS From/To Date Builder Balmoral Ave. to Lake-Cook Rd Cook/Illinois Lake-Cook Rd. to Clavey Rd. Edens Spur to Tri-State Tollway 1958 Illinois 1958 Cook/Illinois Kostner Ave. to Foster Ave. Foster Ave. to Balmoral Ave Cook 1958 Cook
8 EDENS SUPERHIGHWAY MAIN DRAIN UNDER CONSTRUCTION IN 1948,THIRTEEN MILES OF EXPRESSWAY THAT OPENED IN DECEMBER TUNNELING TOOK PLACE WELL BEFORE STRUCTURES AND PAVING. ALL COOK EXPRESSWAY HAVE OWN AND SEPARATE DRAINAGE SYSTEM.
9 Sign on Edens Bridge over Cicero Ave. read EDENS SUPERHIGHWAY until 1980 s
10 EDENS AT DEMPSTER IN 1955 LOOKING SOUTH, DIAGONAL IS GROSS POINT RD.
11 THIS STRUCTURE BUILT IN 1957 WILL CARRY SIX LANES OF THE CALUMET SKYWAY BRIDGE AS THE ROADWAY APPROACHES THE 125 FOOT HIGH BRIDGE OVER THE CALUMET RIVER DPW
12 THIS IS THE NORTHWEST TOLLWAY IN THE SPRING OF 1959 LOOKING WEST OVER THE DESPLAINES OASIS BEFORE THE TOLLWAY BECAME A COMMUTER ROAD.
13 BUILDING THE CONGRESS EXPRESSWAY OPENINGS FROM/TO DATE BUILDER Mannheim to First Ave Cook Laramie to Ashland 1955 Illinois Ashland to Columbus 1956 Chicago Tri-State to Mannheim 1958 Cook First Ave. to Laramie 1960 Illinois
14 CONTINUOUS CONTROVERSY FROM 1920 ABOUT THE LOCATION ON THE CONGRESS ALIGNMENT AS TOO FAR SOUTH AND NOT ADJACENT TO RR EMBANKMENT
15 CONGRESS AT MANNHEIM IN THE SHORT SECTION EAST TO FIRST AVE WAS OPENED IN DEC OF 1954 BUT THE NEXT 2 MILES WEST WOULD TAKE ANOTHER 4 YEARS.
16 CONGRESS AT LARAMIE AVE TERMINUS IN NOVEMBER PORTALS FOR CTA TO GO UNDER AND RUN ON SOUTH SIDE OF EXPRESSWAY IN BACKGROUND. EXPRESSWAY WOULD TERMINATE HERE FOR THREE MORE YEARS.
17 CONGRESS LOOKING EAST FROM MANNHEIM IN THE SUMMER OF 1959-A YEAR AWAY FROM THE GRAND OPENING DPW
18 BUILDING THE NORTHWEST EXPRESSWAY OPENINGS From/To Date Builder Congress to Washington Blvd Chicago Washington to Hubbard 1959 Chicago Central Ave. to Tollway 1959 Cook Hubbard to Odgen 1960 Illinois Odgen to Armitage 1960 Chicago Armitage to Kostner 1960 Illinois Kostner to Central 1960 Cook
19 Northwest Route TWO OF THE NUMEROUS NORTHWEST ROUTE ALIGNMENTS THAT Avondale route selected OFTEN REPRESENTED CONFLICTING COOK COUNTY/CHICAGO 146 PROPOSALS. THESE ARE FROM 1945
20 THE COST OF THE NORTHWEST EXPRESSWAY AS WITH ALL THE EXPRESSWAYS WAS GENERALLY SPLIT EQUALLY AMONG THE THREE PARTIES. DPW
21 NORTHWEST EXPRESSWAY AT VAN BUREN BRIDGE WITH POST OFFICE AND CTA DOUGLAS ELEVATED IN BACKGROUND
22 THIS BEND IN THE NORTHWEST EXPRESSWAY WAS NECESSARY TO AVOID SAINT STANISLAUS CHURCH RECTORY-IT REQUIRED THE PURCHASE AND MOVEMENT OF THE C&NW RR TO SQUEEZE THE EXPRESSWAY BETWEEN THE TWO (SEE DOTTED LINE FOR ORIGINAL ALIGNMENT).
23 NORTHWEST EXPRESSWAY ABOVE ARMITAGE AVENUE IN 1958 WITH THE DAMEN AND WESTERN AVE. STRUCTURES IN THE BACKGROUND DOH
24 NORTHWEST EXPRESSWAY ABOVE EDENS JUNCTION- CICERO REROUTE IN THE FOREGROUND, RAILROAD STRUCTURE ON NW STARTED CCHD
25 THREE LEVEL STRUCTURE OF NORTHWEST EXPRESSWAY, MILWAUKEE AVE. & C&NW R.R. AT JEFFERSON PARK UNDER CONSTRUCTION IN 1959
26 BUILDING THE SOUTH (DAN RYAN)EXPRESSWAY From/To OPENINGS Date Builder 71 st 95 th Streets Congress 39 th 39 th 63 rd 63 rd 71 st /95 th 103 rd 1961 Cook 1962 Chicago 1962 Illinois 1962 Cook
27 South Rout SOUTH ROUTE OPTIONS UNDER South Route CONSIDERATION BEGINING 1947 proposal by city only IN moves THE it slightly 1920 S
28 NORTH END OF SOUTH ROUTE LOOKING NE AT DOWNTOWN. PART OF 2 MILES OF STRUCTURE BUILT BY CHICAGO
29 BUILDINGS OF ALL SHAPES AND SIZES WERE MOVED TO SAVE MONEY AND AUGMENT THE DEPLETED HOUSING STOCK
30 CIRCLE INTERCHANGE EARLY VERSIONS ENCIRCLED DOWNTOWN 1934 version had a Loop quadrangle with 24 parking towers that would hold 60,000 cars. It would be paid for with fed dollars and repaid with10 cent tolls and 25 parking fees The Chicago Automobile Club endorsed this plan in 1939 of high speed roads around the loop. Both plans assume a direct connection between superhighways and LSD.
31 CTA DOUGLAS LINE CAR LEANS INTO CURVE LEADING TO TEMPORARY STRUCTURE CONSTRUCTED IN 1954 TO MAKE ROOM FOR THE CONGRESS EXPRESSWAY KRAMBLES-PETERSON COLLECTION
32 CONGRESS EXPRESSWAY LOOKING WEST FROM POST OFFICE IN 1956-COMPLETION OF CIRCLE INTERCHANGE STILL SIX YEARS AWAY DOH
33 CONGRESS EXPRESSWAY LOOKING EAST ABOUT SAME TIME AS PREVIOUS PHOTO, SUBWAY PORTION UNDER INTERCHANGE USED OPEN CUT REST TUNNELED UNDER POST OFFICE AND TO CONNECTION WITH BREAKTHROUGH TO MILWAUKEE-DEARBORN LINE IN JANUARY OF 1956
34 THE BIG RAIN ON JUNE 12, INCHES OF RAIN FELL IN 4 HOURS IN THE SOUTH LOOP AREA FLOODING THE CONGRESS EXPRESSWAY AT HALSTED AND THE UNFINISHED SUBWAY TUNNEL AND PART OF THE DEARBORN STREET SUBWAY
35 THIS AUGUST 1958 PHOTO LOOKING NORTH AT THE ALMOST FINISHED CITY SECTION OF THE NORTHWEST EXPRESSWAY WITH COMPLETED CIRCLE RAMPS BEING USED AS TEMPORARY HALSTED BRIDGE BYPASS
36 CIRCLE INTERCHANGE LOOKING EAST IN LATE 1960 OR EARLY 1961 WITH THE NEW RAMPS UNDER THE HALSTED BRIDGE COMPLETE AND ALL RAMPS IN SOME STAGE OF CONSTRUCTION
37 THIS IS THE FULLY CONSTRUCTED CIRCLE INTERCHANGE IN EARLY DECEMBER OF LOOKING SOUTH AT THE ABOUT TO BE OPENED DAN RYAN EXPRESSWAY.
38 SOUTHWEST EXPRESSWAY CONSTRUCTION STARTED IN FALL OF 1963 AND IT OPENED ON OCTOBER 24, 1964 Construction underway near Ashland in early 1964
39 PLAN FOR RELOCATING THE DES PLAINES RIVER TO ACCOMMODATE THE LAWNDALE INTERCHANGE OF THE SOUTHWEST EXPRESSWAY
40
41 OPENING THE LAST OF THE EXPRESSWAYS IN COOK COUNTY Openings in 1960 s,1970 s and 1990 s Years sections opened and mileage in Cook I-57 Expressway / / 20.8 miles I-80 Expressway / 1963 / 6.8 miles I-290 Expressway / / 5.4 miles Rt 53 Expressway / / 8.3 miles Elgin-OHare Expressway / 1993 / 2.5 miles
Active Red Light Camera Approaches
1 Western Cermak SB 32 Lawrence Pulaski EB 2 Cermak Western EB 33 Central Irving Park SB 3 Western Peterson NB 34 Irving Park Central EB 4 Peterson Western SB 35 Western Lawrence SB 5 Irving Park Narragansett
More information2nd Annual Historic L Station Tour. November 19, Presented By: The Illinois Historic Preservation Agency
2nd Annual Historic L Station Tour November 19, 2000 Presented By: The Illinois Historic Preservation Agency With: Chicago-L.org The Chicago Design Consortium 2nd Annual Historic L Station Tour Guide Dearborn-Milwaukee
More informationMain Line System Recommendations
(Existing) Main Line System Recommendations This system recommendation focuses mobility investment in a central main line corridor proximate to I-290. A bus rapid transit (BRT) line at each end of the
More informationFARE MEDIA SALES OUTLETS
LEGEND: (*) - $20 Chicago Card available; (**) Touch-n- Go Location/$0 and $20 Chicago Card available; (T) Transit Card Vending Machine available. CTA Fare Media sales locations as of December 23, 2009.
More informationROLLER CURTAIN SIGN REQUEST GARAGE/TERMINAL. April 22, Date:
ROLLER CURTAIN SIGN REQUEST Date: April 22, 1985 _ TO: Transportation Director, Service Area Superintendent, Bus Service Area Superintendent, Training and Instruction Equipment Engineering and Maintenance
More informationSouthwest LRT Alignment Video Narration
Southwest LRT Alignment Video Narration September 2015 Southwest Light Rail Transit, a proposed extension of the METRO Green Line, will serve Minneapolis, St. Louis Park, Hopkins, Minnetonka and Eden Prairie.
More informationWelcome to the Downtown Fort Lauderdale Neighborhood Working Group Meeting. First meeting june 17, 2010
Welcome to the Downtown Fort Lauderdale Neighborhood Working Group Meeting First meeting june 17, 2010 State of the Project Draft Environmental Impact Statement Study Phase This study is NOT the final
More informationSears Centre Arena Julie Avis
September 24, 2009 MMA Event Sears Centre Arena Julie Avis Jesper Jorgensen Account Executive S 4000 Morgan Street, IL 60609 Phone: 773-843-2091 Fax: 773-843-2078 Mobile: 773-255-3255 Email: jesperjorgensen@clearchannel,com
More informationDirections. IBM Recovery Center One Evertrust Plaza Jersey City, NJ From World Trade Center site (Downtown New York City):
Directions IBM Recovery Center One Evertrust Plaza Jersey City, NJ 07302 1. Path Train From World Trade Center site (Downtown New York City): - Path Train service from World Trade Center site to Exchange
More informationISGS Data/Information for The Boring Company - Chicago Project
ISGS Data/Information for The Boring Company - Chicago Project Robert A. Bauer Engineering Geologist Illinois State Geological Survey 6 Sep 2018 Champaign, IL Proposes: A closed-loop pair of 12 foot diameter
More informationTransportation Guide
2018 schedules Transportation Guide train pass to go here POWER HOUR: 5:30-6:30 pm, Saturday - Monday! (appointments recommended) An opportunity to extend meetings an additional hour after the 5:30 pm
More informationGlenview/ Central/ Fairfield/ Everett/ Old Elm. Quentin 60% 49% 0% 45% 16% 40% 25% 47% 52% 0% 0%
How many municipalities involved? (number) How many member municipalities involved? (number and percent) 1 1 10 1 4 25% 4 6 67% 11 8 73% 2 8 25% 3 4 75% 6 9 67% 13 10 73% 12 13 92% 3 5 6 8 8 10 4 6 67%
More information2011 Illinois Department of Transportation. I-290 PHASE I STUDY Additional Round 1 Alternatives Descriptions
2011 Illinois Department of Transportation I- PHASE I STUDY Additional Round 1 s Descriptions www.dot.il.gov www.eisenhowerexpressway.com Blue Line I- > Blue Line Extension from CTA Terminal to Mannheim
More informationRoute 141 and I-44 Design-Build Project Community Involvement Group. March 21, 2016
Route 141 and I-44 Design-Build Project Community Involvement Group March 21, 2016 Purpose of CIG 1. Share information with major stakeholders 2. Keep stakeholders informed of the process 3. Reduce uncertainty
More information1.2 Corridor History and Current Characteristics
SECTION 1 Description and Background of Study Area 1.1 Introduction This preliminary engineering report was prepared for the Alaska Department of Transportation and Public Facilities (ADOT&PF). It is part
More informationMission Statement. Spur 601 Project Highlights
Mission Statement SPUR 601 is a TxDOT project dedicated to provide a safe, efficient, reliable new corridor to improve the mobility in east-central El Paso. The SPUR 601 team is working in partnership
More informationNCUTCD Proposal for Changes to the Manual on Uniform Traffic Control Devices
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 TECHNICAL COMMITTEE: ITEM NUMBER: TOPIC: ORIGIN OF REQUEST: AFFECTED SECTIONS OF MUTCD: NCUTCD Proposal for Changes
More information2954 WEST LAKE STREET KINZIE CORRIDOR
OFFERING MEMORANDUM 2954 WEST LAKE STREET KINZIE CORRIDOR Presented by: ZACH PRUITT President 312.766.4289 zpruitt@cawleychicago.com NICHOLAS SCHAEFER Vice President 312.766.4285 nschaefer@cawleychicago.com
More informationConnectivity is the new currency. -Mayor Pete Buttigieg, South Bend
2014 HDR Architecture, 2014 HDR, Inc., all rights reserved. Connectivity is the new currency. -Mayor Pete Buttigieg, South Bend What is it? Major capital investment to double track 16 miles of our railroad
More informationDRAFT. Public Meetings November 7, 9, 15, Year UTP Planning Effort Cost/Revenue Matrix FY FY 2026
Collin FM 2478 FM 1461 to US 380 (Prosper) US 380/McKinney Bypass Candidate Project; Collin Roadway Action Plan #3 $32,600,000 $32,600,000 A Collin FM 2514 East of Lavon Parkway to North of Drain Dr. Roadway
More informationSpecial Committee on U. S. Route Numbering
1 OF 8 Members: Special Committee on U. S. Route Numbering 2018 Spring Meeting Report to the Council on Highways and Streets Region 1 William Cass, New Hampshire DOT Region 2 Emanuel Banks, Arkansas DOT
More informationST. CLOUD LAKE WOBEGON TRAIL OPEN HOUSE
ST. CLOUD LAKE WOBEGON TRAIL OPEN HOUSE PROJECT INTRODUCTION Project partners: St. Cloud Area Planning Organiza on (APO) and the City of St. Cloud. The project area is approximately 2.5 miles long, extending
More informationFHWA Actions on Past Interstate Requests that were approved by the USRN were presented and conditions were lifted. FHWA Approval Date
SPECIAL COMMITTEE ON US ROUTE NUMBERING MEETING MINUTES FOR OCTOBER 17, 2013 AND REPORT TO SCOH OCTOBER 18, 2013 SHERATON DOWNTOWN DENVER, DENVER, COLORADO ADDENDUM OCTOBER 28, 2013 The meeting of the
More informationAppendix JK. Noise Barrier Visualizations. I-290 Eisenhower Expressway Cook County, Illinois. Prepared For: Illinois Department of Transportation
Appendix JK Noise Barrier Visualizations I-290 Eisenhower Expressway Cook County, Illinois Prepared For: Illinois Department of Transportation Prepared By: WSP Parsons Brinckerhoff September August 2016
More informationAviation, Rail, & Trucking 6-1
6-1 This chapter describes the services, facilities, and condition of air, rail, and trucking as components of the transportation system. These three intermodal areas have an impact on the factors to be
More informationThere was no new business. The next meeting will be in Charlotte, NC, November 21, The meeting adjourned at 6:15 PM.
Special Committee on U. S. Route Numbering Louisville, Kentucky Report to SCOH - May 29, 2014 The meeting was called to order by Mark McConnell, MS at 5:10 PM in the Jockey Club Room at the Downtown Marriott
More informationSpecial Committee on U. S. Route Numbering
Special Committee on U. S. Route Numbering Franklin, Tennessee- Franklin Marriott Cool Springs Monday May 21, 2018 5:30 PM (Central Daylight Time) Conference Call- Tel 1-888-585-9008, Conf. Room No. 191-374-518
More informationDon t know who represents you? Call aldermanic offices in your area or 311 to find out.
2007 Chicago Alderman Contact Information The community areas listed below should be used as a guide only. Many neighborhoods are represented by more than one alderman. Please call aldermanic offices in
More informationCAE003 N ', W ' Columbia St. US 80 (and Market St.) once continued straight west from here. Continue east on Market St.
West to east. San Diego to Viejas Casino. CAE001 N 32 42.68', W 117 10.26' Harbor Dr and Pacific Hwy. Terminus of US 80 from 1943 to 1953. Pacific Hwy was US 101. CAE002 N 32 42.67', W 117 10.10' Harbor
More informationNovember 21, 2012 Barbara Kelleher, (954)
November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related
More informationDamen Elston Fullerton Reconstruction, Intersection Improvements CDOT Project B-1-501
Damen Elston Fullerton Reconstruction, Intersection Improvements CDOT Project B-1-501 Bird s Eye View of Existing INTRODUCTION This project is part of the City s Building a New Chicago initiative in conjunction
More informationAdd-A-Lane Contract V. along a Section of I-95 includes 6 Bridges
Newton Needham Chamber of Commerce Add-A-Lane Contract V along a Section of I-95 includes 6 Bridges Project File No. 603711 July 29, 2014 1 Agenda Project Update Overview Bid and Contract Award Schedule
More informationSCOH Report. From. Special Committee on U.S. Route Numbering Annual Meeting
SCOH Report From Special Committee on U.S. Route Numbering Annual Meeting Friday, November 16, 2012 Meeting Minutes The Special Committee on U.S. Route Numbering and U.S. Bicycle Route Systems (USRN) convened
More information2075 W 43RD ST. CHICAGO, IL. chicago s largest industrial spec development
2075 W 43RD ST CHICAGO, IL chicago s largest industrial spec development EST. 2018 www.marinacrossings.com IMMEDIATE 633,057 SF AVAILABILITY PREMIER INFILL DEVELOPMENT IDEAL FOR: LAST-MILE FULFILLMENT
More informationNortheast Anthony Henday Drive Edmonton Ring Road Update. Strathcona Chamber of Commerce March 18, 2015
Northeast Anthony Henday Drive Edmonton Ring Road Update Strathcona Chamber of Commerce March 18, 2015 Project Background 2 Edmonton Ring Road Northwest opened Nov 2011 Northeast to open Oct 2016 Southwest
More informationMARCH 2016 NET RENT PER SF*
CHICAGO Bishop Plaza 4630 S. Bishop St. Chicago, IL 60609 1,000-2,379 $24 - $26 $8.77 $2,730 - $6,893 Highly visible Walmart-anchored center located in the famed shopping district of the Historic Union
More informationV. DATA COLLECTION PROGRAM
V. DATA COLLECTION PROGRAM As discussed in Section IV, an extensive data assembly and data collection program was undertaken to develop the data necessary to calibrate the existing Portway Extensions model
More informationI-579 Urban Open Space CAP Project. Final Land Development Plan (FLDP) Pittsburgh Department of City Planning
Final Land Development Plan (FLDP) I-579 Urban Open Space CAP Project Sports & Exhibition Authority (SEA) of the City of Pittsburgh and Allegheny County Project bounded by Chatham St. / Centre Ave. / Washington
More information2013 White Sox Summer Camp Driving Directions
2013 White Sox Summer Camp Driving Directions 6200 River Bend Drive - Lisle, IL 60532 Phone 630.324.8221 Fax 630.324.8265 www.bullssoxacademy.com Arlington Heights 7-8yrs June 24-June 28 1:00-4:00 PM 9-11yrs
More informationPRIORITIES COMMITTEE MEETING
PRIORITIES COMMITTEE MEETING Meeting Date: 05/13/14 Agenda Item #: 13.1 Northeast Anthony Henday Drive Update Report Purpose To update the Priorities Committee on the progress of the Northeast Anthony
More informationNEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release
NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov Major Operation: 36 massive beams will be placed at Sunland & I 10. Operation
More informationUrban Chicago New Construction & Proposed Multifamily Projects 3Q18
Urban Chicago New Construction & Proposed Multifamily Projects 3Q18 ID PROPERTY UNITS 2 Lathrop Homes Redevelopment 413 3 Wave Lakeview 207 5 Eight Eleven Uptown 3 7 Wicker Park Connection 146 10 2102
More informationWork in 2015 and Annual Mobility- Management Plan
Work in 2015 and Annual Mobility- Management Plan KPH-Turcot July 14, 2015 2 Presentation Outline Division into sectors Work in 2015 without disruptions West sector Center sector East sector South sector
More informationConscientious Technology
2017 Media Kit Conscientious Technology GreenSigns is not just our name, it is our way of doing business. Through strategic partnerships with energy suppliers, GreenSigns lowers our impact on the environment
More informationAttachment D: PHOTO LOG CITY OF ARCATA RAIL-WITH-TRAIL CONNECTIVITY PROJECT
01051-09004 Attachment D: PHOTO LOG CITY OF ARCATA RAIL-WITH-TRAIL CONNECTIVITY PROJECT DRAFT: June 30, 2010 Applicant: City of Arcata 736 F Street Arcata, CA 95521 Phone (707) 825-2154 Prepared by: Winzler
More information$1.00 N/A PD-64 1,230-6,870 $20 $1.99 $2,254 - $12,589 PD64 $1.94 N/A PD 64 $0.09 N/A PD 64 18,200 $14 $2.36 $24,812 C1-2
CHICAGO SF EST. EXP. EST. EST. EXP. GROSS EST. GROSS 60th & Kedzie NWC 5940-58 S. Kedzie Ave. Chicago, IL 60629 61st & Cottage Grove 801 E. 61st St. 62nd & Cottage Grove SEC 6251 S. Cottage Grove Ave.
More informationNew Orleans Public Belt Railroad Corporation Acquisition and Operation Exemption. Public Belt Railroad Commission of the City of New Orleans
This document is scheduled to be published in the Federal Register on 12/27/2017 and available online at https://federalregister.gov/d/2017-27931, and on FDsys.gov FR-4915-01-P SURFACE TRANSPORTATION BOARD
More informationProviding public transportation since 1999 between Washington and Milwaukee Counties
Providing public transportation since 1999 between Washington and Milwaukee Counties Background Information Started in 1999, funded by a three-year CMAQ grant. Employers and fare revenue covered local
More informationDon t know who represents you? Call aldermanic offices in your area or City Hall at (312) to find out.
2006 Chicago Alderman Contact Information The community areas listed below should be used as a guide only. Many neighborhoods are represented by more than one alderman. Please call aldermanic offices in
More informationWeekly East Tennessee Construction Report for May 31-June 6, 2018
Weekly East Tennessee Construction Report for May 31-June 6, 2018 Thursday, May 31, 2018 01:30pm ANDERSON COUNTY, SR 62 between Union Valley Road and SR 162: Motorists should be alert for possible lane
More informationGetting to The Juilliard School
Getting to The Juilliard School TRANSPORTATION FROM AREA AIRPORTS Airport Shuttles Super Shuttle (800) BLUE-VAN (800-258-3826) https://www.supershuttle.com/ NYC Airporter (718) 777-5111 http://www.nycairporter.com/
More informationFinal Drainage Letter Pikes Peak Community College Downtown Parking Lot Colorado Springs, Colorado
Final Drainage Letter Pikes Peak Community College Downtown Parking Lot Colorado Springs, Colorado Prepared for: Pikes Peak Community College 5775 South Academy Boulevard Colorado Springs, CO 80906-5422
More informationMembers: Guest(s): USRN DECISION CHANGE
AASHTO Special Committee on U.S. Route Numbering () Report to the Standing Committee on Highways (SCOH) Decisions & Meeting Minutes October 29, 2010 - Biloxi, Mississippi Members: Guest(s): Chair Don Vaughn,
More informationFlorida Department of TRANSPORTATION. First Coast Expressway
Florida Department of TRANSPORTATION First Coast Expressway What is the (FCE)? Multi-lane, limited access toll expressway Connects I-10 in Duval County to I-95 in St. Johns County How does FCE connect
More informationTHREE MILE PLAN TOWN OF SUPERIOR COLORADO
THREE MILE PLAN TOWN OF SUPERIOR COLORADO February 23, 2015 INTRODUCTION This document has been prepared by the Town of Superior, Colorado, to address the existing and proposed land uses within an approximate
More informationWilliamsburg Town Hall Meeting
Williamsburg Town Hall Meeting DEVELOPMENT UPDATE ORANGE COUNTY PLANNING DIVISION November 30, 2017 1 AREA CONTEXT FUTURE LAND USE MAP MEADOW WOODS MEADOW WOODS GINN PROPERTY ZONING MEADOW WOODS MEADOW
More informationSCOPE Chapter 2D shall Apply to Any Road or
SCOPE Chapter 2D shall Apply to Any Road or Street other then Low-Volume Roads, Expressways, and Freeways Low Volume Roads: Shall be a Facility Lying Outside Built-Up Areas & Having a Traffic Volume Less
More informationEXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015
EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley
More informationThe Missouri Department of Transportation is proposing to amend the state's five-year Statewide Transportation Improvement Program (STIP).
The Missouri Department of Transportation is proposing to amend the state's five-year Statewide Transportation Improvement Program (STIP). A 7-day public comment period regarding the amendment begins January
More informationGovernor s Mobility Plan. Corridors, Segments and Projects. Allied Junction Corridor 10/12/89
Governor s Mobility Plan Corridors, Segments and Projects 10/12/89 Allied Junction Corridor northern terminus of New Jersey Turnpike/Hudson County Extension Segment I-A - New Rail Spur from Bergen Line
More information2013 Regional Water System Improvements Program Public Hearing March 14, 2013
In support of Illinois Environmental Protection Agency State Revolving Fund Loan Application 2013 Regional Water System Improvements Program Public Hearing March 14, 2013 Village of Oak Lawn Customer Communities:
More informationI-70/I-71 Project Public Meeting Presented By
I-70/I-71 Project Public Meeting Presented By Ohio Department of Transportation ms consultants, inc. engineers, architects, planners MSI Design June 9, 2010 W e l c o m e Thom Slack Planning Administrator,
More informationSection 106 Update Memo #1 Attachment D. Traffic Diversion & APE Expansion Methodology & Maps
Section 106 Update Memo #1 Attachment D Traffic Diversion & APE Expansion Methodology & Maps I-65/I-70 North Split Interchange Reconstruction Project (Des. Nos. 1592385 & 1600808) Traffic Diversion and
More informationStudy Overview and Context
Study Overview and Context North Shore Coordination Plan Study Study Highlights Early 2016 to December 2017 Consultant team assistance Steering Committee review Two rounds of public open house events Project
More informationSENIOR CHAMPIONSHIPS
2016 HOTEL ROOM BLOCKS Marriott Hotels the Official Hotel of Illinois Swimming has discounted rates at the following properties for upcoming meets for Illinois Swimming members. SENIOR CHAMPIONSHIPS UNIVERSITY
More informationUnited States Department of the Interior National Park Service. Boundary Expansion Listed in National Register January 11, 2017
NPS Form 10900-a (Rev. 8/2002) OMB No. 10240018 United States Department of the Interior National Park Service Boundary Expansion Listed in National Register January 11, 2017 National Register of Historic
More informationGUIDE TO THE GREAT EASTERN TRAIL IN TENNESSEE
GUIDE TO THE GREAT EASTERN TRAIL IN TENNESSEE FIRST EDITION, SEPTEMBER 2011 Covers Section TN1 Base of Lookout Mountain to Soddy Daisy, TN THIS GUIDE IS NOT FOR SALE OR RESALE Guide To The Great Eastern
More informationWEEKLY PROVINCIAL HIGHWAY CONSTRUCTION UPDATE FOR THURSDAY, OCTOBER 6, 2016 The law is black and white. Slow to 60 km/hr in Work Zones.
NEW WORK PROJECT/WORK: Highway 354 near Dilke ESTIMATED COST: $3.4M START OF THIS YEAR'S CONSTRUCTION: October 1, 2016 DESCRIPTION: About 17 km of surfacing on Highway 354 from the junction with Highway
More information2017 TBARTA Future Regional Priority Projects Adopted by TBARTA Board, December 9, 2016
2017 TBARTA Future Regional Priority Projects Adopted by TBARTA Board, December 9, 2016 Project numbers do not signify ranking they are for mapping identification purposes only. 1. 15th Street East The
More informationEXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015
EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 35EXPRESS PROJECT OVERVIEW 2 SEGMENT 1 3 SOUTH OF I-635 May Shift northbound mainlane traffic east in the southeast quadrant Miscellaneous frontage
More informationDAILY PERCENT OF ALL PERCENT OF ALL CATEGORY BOARDINGS BOARDINGS STATIONS STATIONS ACCESSIBLE 190, % %
Table 1 Summary of Station Accessibility DAILY PERCENT OF ALL PERCENT OF ALL CATEGORY BOARDINGS BOARDINGS STATIONS STATIONS KEY STATIONS ACCESSIBLE 190,655 71.2% 72 29.9% PARTIALLY ACCESSIBLE 0 0.0% 0
More informationImportant Lane Closures, April 3 9, 2011
March 31, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 marcia.mcallister@dullesmetro.com Important Lane Closures, April 3 9, 2011 RESCHEDULED: Lane Shifts of Westbound Route 7 at Route
More informationINTERVIEW WITH ED ROGERS FOR THE FOREST PARK HISTORICAL SOCIETY-INTERVIEW BEGAN MIDSENTANCE, NO INTRODUCTIONS, DATE,
INTERVIEW WITH ED ROGERS FOR THE FOREST PARK HISTORICAL SOCIETY-INTERVIEW BEGAN MIDSENTANCE, NO INTRODUCTIONS, DATE, ETC. ER: previous was the town of Harlem, and Harlem has been around since 1853. It
More informationScore. Category. Access Aesthetics Community Resources
NO BUILD ALTERNATIVE The No Build Alternative is the do nothing option that is used for comparison to the build alternatives. The screening assumes no new facilities are constructed as part of the I-93
More information* New Meelng, needs your support
1 # Town / City General Area Day Time Mee5ng Loca5on Notes 1 Beloit, WI Wisconsin, South Mon 6:00p St. Paul's Episcopal Church, 212 W. Grand Avenue, Beloit, WI Park in rear / Use back door 2 Blue Island,
More informationREPRESENTATIVE ASSET PORTFOLIO» RECEIVER SERVICES // PROPERTY MANAGEMENT // BROKERAGE // GENERA L CONTRACTING
REPRESENTATIVE ASSET PORTFOLIO» RECEIVER SERVICES // PROPERTY MANAGEMENT // BROKERAGE // GENERA L CONTRACTING SELECT COMMERCIAL BROKERAGE PORTFOLIO MULTIFAMILY // RETAIL // OFFICE // INDUSTRIAL // SPECIAL
More informationThe Transportation Corridor Overlay District
The Transportation Corridor Overlay District The Transportation Corridor Overlay District is a policy framework under which certain potentially beneficial development proposals may be considered, given
More informationPUBLIC INFORMATION SESSION #2
Highway 16, Highway 779 to Kapasiwin Road, Planning Study PUBLIC INFORMATION SESSION #2 Wednesday June 20, 2012 4 to 8 pm HIGHWAY 16 Highway 779 to Kapasiwin Road Functional Planning Study Blueberry Community
More informationCorridor Management Committee Meeting. April 2, 2014
Corridor Management Committee Meeting April 2, 2014 1 Today s Topics Welcome Approval of Minutes Resolutions Response to March 26 CMC Questions Staff Recommendation on Project Scope and Budget Public Testimony
More information* New Meekng, needs your support
+ Maps 1 # Town / City General Area Day Time Mee5ng Loca5on Notes 1 Beloit, WI Wisconsin, South Mon 6:00p St. Paul's Episcopal Church, 212 W. Grand Avenue, Beloit, WI Park in rear / Use back door 2 Blue
More informationProposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street
STAFF REPORT ACTION REQUIRED Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street Date: March 12, 2007 To: From: Toronto and East York Community Council Director, Transportation Infrastructure
More informationCommunity Advisory Panel Meeting #
Community Advisory Panel Meeting # 6 02.13.19.. Agenda Welcome and Introductions Community Conversations City Council Meeting Debrief Review Citywide Tunnel Video (North Portal Only) Churchill Pedestrian
More informationAirport Planning Area
PLANNING AREA POLICIES l AIRPORT Airport Planning Area LOCATION AND CONTEXT The Airport Planning Area ( Airport area ) is a key part of Boise s economy and transportation network; it features a multi-purpose
More informationCall for Public Hearing August 2019 Service Changes
Call for Public Hearing August 2019 Service Changes Committee-of-the-Whole January 22, 2019 Rob Smith, AVP Service Planning & Scheduling 1 Recommendation To call a Public Hearing on March 12, 2019 for
More informationPublic Information Center August 12, 2010
Route 52 Causeway Bridge Replacement & Somers Point Circle Elimination Project Somers Point Atlantic County Public Information Center August 12, 2010 Ocean City Cape May County Presentation Overview General
More informationNDG-Westmount Neighbourhood Committee. November 16, 2015
NDG-Westmount Neighbourhood Committee November 16, 2015 2 Feedback on previous questions Order-in-Council 890-2010 - condition 8 The ministère des Transports must : Establish a buffer zone at the foot
More informationLake Erie Commerce Center Traffic Analysis
LOCATION: East of NYS Route 5 at Bayview Road Town of Hamburg Erie County, New York PREPARED BY: Wendel Companies 140 John James Audubon Parkway Suite 200 Amherst, New York 14228 January 2012 i ii Table
More informationA. From I-68 in Monongalia County, West Virginia to SR 6119 in Fayette County, Pennsylvania 1
Mon-Fayette Transportation Project A. From I-68 in Monongalia County, West Virginia to SR 6119 in Fayette County, Pennsylvania 1 The Mon/Fayette Transportation Project (MFTP) from I-68 in West Virginia
More informationNon-Motorized Transportation
Non-Motorized Transportation Non-motorized facilities are important components to the transportation system. They provide an environmentally-friendly, low-cost mode of travel. Some of the facilities can
More informationMAY 2016 NET RENT PER SF*
CHICAGO Bishop Plaza 4630 S. Bishop St. Chicago, IL 60609 1,000-2,379 $24 - $26 $8.77 $2,730 - $6,893 Highly visible Walmart-anchored center located in the famed shopping district of the Historic Union
More informationProject Start Date: Project Completion Date: July 1, Contractor: Mattson Construction Contact Information: Nate Lillemon
Date: 06-24-16 To: Derek Hackett, Public Information Officer From: Sunil Jeboo, Traffic Engineer Re: Road Closure for the Week of 06-27-16 (3236.1) 6 th Pump Station Western Ave. and 6 th SW Western Ave.
More information* Short term resurfacing projects are not included in this listing. 4T39.07 Project: Annual Rural County Sign Improvements, Genesee/Orleans Counties
New York State Department of Transportation 2008 Highway/Bridge Construction Projects * Short term resurfacing projects are not included in this listing. Genesee 4T39.07 Project: Annual Rural County Sign
More informationCell: (408) Release MA June 25, 2012
VTA NEWS CONTACT: Bernice Alaniz FOR IMMEDIATE RELEASE Cell: (408) 888-9983 Release MA 12 06 08 Bernice.Alaniz@vta.org June 25, 2012 Construction Activities Underway For BART Silicon Valley The Santa Clara
More informationCall for Public Hearing August 2019 Service Changes
Call for Public Hearing August 2019 Service Changes Operations, Safety & Security Committee January 8, 2019 Rob Smith, AVP Service Planning & Scheduling 1 Recommendation To call a Public Hearing on March
More informationLAS VARAS RANCH CA COASTAL TRAIL PROPOSED ALIGNMENT
LAS VARAS RANCH CA COASTAL TRAIL PROPOSED ALIGNMENT Santa Barbara Trails Council * Prepared by Ray Ford February 1,2012 The following notes accompany the Santa Barbara Trails Council map for the Las Varas
More informationBORDER WEST EXPRESSWAY (LOOP 375)
BORDER WEST EXPRESSWAY (LOOP 375) 2015 Project Update Agenda 1 2 3 4 Team Overview Project Details Questions 2 Teams Owner Texas Department of Transportation Independent Engineer HDR Engineering Atkins
More informationSTATUS OF PPP PROJECTS AS OF 05 OCTOBER 2011
1. Daang Hari SLEx Link Project P 1.956 B ROW P 177.3 M Publication of Invitation to Participate and Bid July 20, 27 $ 43.5 M IC P 10.635 M and August 3, 2011 New 4 kilometer, 4-lane paved toll road that
More informationPiestewa Peak/Dreamy Draw Trail Guide
Piestewa Peak/Dreamy Draw Trail Guide Trail #1A - Perl Charles Memorial Trail Length: 4.8 miles Elevation: 2,200 ft. - 1,340 ft. Difficulty: Moderate to difficult The Perl Charles trailhead is located
More informationSAVE THE DATE! 2007 Dates. April 24th, Northwest Portland Area Indian Health Board, Portland, OR (with i-link) Agenda
SAVE THE DATE! 2007 Dates March 7th, 2007 - Coeur d Alene Wellness Center April 24th, 2007 -, Portland, OR (with i-link) May 16th, 2007 - Seattle Indian Health Board, Seattle, WA Agenda 8:30 Welcome, Blessing,
More informationUpdate of MDX Open Road Tolling
Update of MDX Open Road Tolling Citizens Transportation Advisory Committee September 11, 2013 About MDX MDX is an agency of the state created by the State Legislature and the County Commission to assure
More information