1 INFRASTRUCTURE DEVELOPMENT IN THE NORTH-EAST INTERNATIONAL CONFERENCE ON CROSS-BORDER CONNECTIVITY NEW DELHI, MAY 12, 2014 Dr. Manoj Singh, Adviser (Transport) PLANNING COMMISSION, GOVERNMENT OF INDIA NEW DELHI

2

3 EXISTING RAIL NETWORK IN THE NORTH EAST State Broad Gauge Meter Gauge Total (Km) Arunachal Pradesh Assam 1, , Tripura Nagaland Manipur Mizoram Meghalaya Sikkim Total 1, , ,602.35

4 MASTER PLAN FOR THE DEVELOPMENT OF RAIL INFRASTRUCTURE IN THE NORTHEAST REGION

5 RAILWAYS : ON-GOING PROJECTS IN NORTH EAST ( ) New Line Gauge Conversion Doubling Total Projects in progress (Nos.) Of which, National Projects (Nos.) Throw forward (Rs. Crore) as on Of which, National Projects (Rs. Crore) 21,689 2,071 2,044 16,354 1,586-25,806 ($4.3 b) 17,940 ($3 b) Length of ongoing works (Km) 965 1, ,520 5

6 INVESTMENT IN N.E REGION OVER LAST 10 YEARS (NEW LINES, GAUGE CONVERSION & DOUBLING) Total Rs 15,629 Crs(Last 10yrs) (Including works in progress) Rs in Crore

7 ACHIEVEMENTS Year New Line Gauge Conversion Doubling

8 RECENT PROGRESS OF RAILWAY PROJECTS North Bank GC Project Rangiya-Rangapara North Dekargaon (Tezpur) (186 km) completed & operationalized on 4 th January Rangapara (N) North Lakhimpur (172 km) Target Completion: Mar Completed on March 31 st, North Lakhimpur-Murkongselek (154 km) TDC: Dec Engine Rolling Completed New Broad gauge line of Harmuti-Naharlagun (21.75 km): first connectivity to Arunachal Pradesh. TDC: March Completed on 4 th April, 2014 Train services started on April 7 th, New Broad gauge line of Dudhnoi-Mendipathar (19.75 km): first connectivity to Meghalaya (10 km) TDC: March Likely by mid May,

9 TARGETS OF NATIONAL RAILWAY PROJECTS Name of Project TDC Rangiya-Murkongselek with linked fingers (520 km) (Assam) Dec. 14 Lumding-Silchar, incl. Branch (GC) lines & MMs (421 km) (Assam, Manipur, Mizoram, Tripura) Mar. 15/ June. 16 Tetelia-Byrnihat (21.50 km) (Meghalaya) Jiribam- Tupul -Imphal (111km) (Manipur) Mar.15 Mar. 16/Mar.18 Kumarghat Agartala (109 km) (Tripura) June. 16 Agartala - Sabroom (112 km) (Tripura) Bogibeel Bridge with linking lines (73 km) (Assam) Bhairabi-Sairang (51.38 km) (Mizoram) Sivok-Rangpo (44.39 km) (Sikkim) Dimapur-Zubza (Kohima) (88 km) (Nagaland) Byrnihat-Shillong ( km) (Meghalaya) June.16 Dec.16 Not fixed Not fixed Not fixed Not fixed 9

10 INDO-MYANMAR RAIL CONNECTIVITY

11 RAIL PROJECTS IN MANIPUR

12 RAIL MAP OF MYANMAR

13 Myanmar: India s Land Bridge to ASEAN

14 BROAD PROJECT PARAMETERS OF INDO-MYANMAR RAIL CONNECTIVITY Imphal Moreh 111 Kms Rs Crores ($ 1 b) Moreh Kalay 130 Kms Rs Crores ($ 0.5 b) Possibility of funding by JICA, ADB, and other Multi-lateral Agencies;

15 Road Development in the North East Two Major Projects Going On Presently East West Corridor (Silchar in Assam to Porbandar in Gujarat) Completed length is 500 km (81%) Likely completion date : Dec Special Accelerated Road Development Project in the North East (SARDP-NE) Phase A 4,099 km (Project cost Rs.21,000 crore) Phase B 3,723 km (Only DPR approved) Arunachal Package (MoRTH, Arunachal PWD and BRO) 2,319 km (Rs.11,919 crore) Total Investment : Rs 40,000 crores ($ 7 b) 15

16 Item Progress of Phase A and Arunachal Package Total Length Target Work Sanctioned/ Awarded Roads Completed Phase A 4,099 2,505 1,214 Arunachal Package 2,319 1,341 (58%) 113 (5%) Total 6,418 3,846 (60%) 1,327 (21%) Targeted/Expected Date for Completion June, 2015/March2017 June, 2016/March2018 Upgrade National Highways connecting state capitals to 2/4 lane Connect 88 District Headquarters of NER by at least 2 lane roads Improve connectivity to neighbouring countries/border areas (In Kms) 16

17 International Road Gateways Moreh to Guwahati Moreh Imphal : NH km 2 lane road 3 hrs Imphal Jiribam Silchar : NH km 2 lane : 8 hrs Silchar Guwahati : East West Corridor 325 km 6 hrs Total : 700 kms : 17 hrs

18 Roads covered for improvement in Arunachal Pradesh under SARDP-NE Daporijo Koloriang Aalong GORGING PONGO MIGGING LUNGTE Yingkiong BISHING JIDO SINGA SAKRAM POINT Anini Roing Tezu To Srirampur Tawang TASHIGAONG LUMLA Bomdila Being improved to 2 lane by BRO under China Study Group(CSG) 229 Seppa NECHIPU BALIPARA Yupia ITANAGAR SILGHAT Ziro HOLONGI ZORAM Potin TAHILA 229 GOHPUR TATO RUPAI MAHADEVPUR TINSUKIA 52B JAIRAMPUR NAMCHIK AKAJAN DIBRUGARH Lalpul NORTH PANGSU PASS LAKHIMPUR 153 BIMLAPUR Hoj SIBSAGAR 52B 52B BANDER DEWA KANUBARI NUMALIGARH BILE PAKA Pasighat MARIYUNG PANGIN 229 BAME JONAI Khonsa BOMJIR Ext SADIA DHOLA Koronu Paya LEGEND :- CHOWKHAM 52 Changlang A. Roads under Arunachal Package 1. Trans Arunachal Highway(NH-229, 52 & 52B) 2. Roads connecting remaining 5 DHQs 3. Road stretches proposed on Annuity basis Hawai Baihata Charali GUWAHATI NAGAON TO SILCHAR ROUTE OF 4 LANE CONNECTIVITY OF ITANAGAR WITH EAST WEST CORRIDOR AT NAGAON B. Roads under Phase A Other National Highways East West Corridor DISTRICT HEADQUARTER TOWN

19 Airports in NE State Operational Non- Operational Assam 6 3 IAF, 3 AAI Arunachal Pradesh Pakyong Bagdogra Sikkim West Bengal 2-5 Manipur 1 - Meghalaya 1 1 Mizoram 1 1 Nagaland 1 - Tripura 1 3 Sikkim - - West Bengal 1* - Total Rupsi Tura Agartala Guwahati Shillong Meghalaya Kailashahar Kamalpur Khowai Tripura Shella Tezpur Assam Silchar Lengpui Ziro Dimapur Mizoram Turial Daparizo Dibrugargh North Lakhimpur (Lilabari) Jorhat Imphal Manipur * Bagdogra Airport, although in Eastern Region, is included as it is the gateway to North-East including Sikkim State Arunachal Pradesh Itanagar Along Pasighat Nagaland Chiethu/ Kohima LEGEND Tezu Operational (11+1) Non-Operational (12) Greenfield (3) 19

20 mmm 20

21 31 DHUBRI JOGIGHOPA SHISHUMARA DAIKHAWA CHILMARI I N D I A 31 31C DISPUR PANDU P SHILLONG 40 M E G H A L A Y A TEJPUR A S S A M 37 SILGHAT P INDO BANGLADESH 36 PROTOCOL ROUTES 53 KOHIMA NAGALAND HULIAN 6 2 HALDIA P B A N G L A D E S H GODAGARI SIRAJGANJ RAJSHAHI KOLKATA P 35 NAMKHANA BAGHABARI P KHULNA CHALNA P BAHADURABAD ARICHA P MONGLA ANGTIHARA DHAKA BARISAL BHAIRAB BAZAR NARAYANGANJ P KAUKHALI Bay of Bengal ZAKIGANJ SYLHET BHANGA KARIMGANJ MARKULI FENCHUGANJ SHERPUR AJMIRIGANJ AKHAURA CHANDPUR ASHUGANJ 44 TRIPURA AGARTALA 54 AIZWAL LAKHIPUR P MIZORAM 53 MANIPUR IMPHAL N Legend Declared National waterway Proposed National waterway Protocol route Road Rail NH 51 Protocol route distances Kolkata Silghat Km Kolkata - Karimganj Km Silghat- Karimganj 1410 Km Dhulian-Rajshahi Km Myanmar (Burma)

22 Proposed National Waterway (No 6) River Barak Bhanga Badarpur Silchar Stretch Km Bhanga - Lakhipur 121 Length 121 km Development cost -Rs Cr (at 2012 prices) Status: Declaration in process Bill likely to be introduced in Budget session

23 Airports Development ( ) - I Development of Airports at Pakyong New TDC: Dec Need resolution of land acquisition for AAI Colony, shifting of 16 local residences and approach road from Pakyong to Gangtok Itanagar State Govt. to provide land acquisition (1,037 acres), Rehabilitation, Compound Wall, Approach Road, Electricity/Water supply. PIL challenging site before Guwahati High Court Cheithu Alternative site needs to be selected by State Government Modernize selected Airports by AAI Guwahati Construction of 3 hangars for A-321. TDC Sep Dibrugarh Runway extension (32 acres land acquisition) Jorhat - Apron extension completed (30 Nov. 2013). New Terminal Building planned Shillong Upgradation at Barapani taken up. 32 acres defence land required. Work stopped (August 2012) due to local agitation Imphal : Notified international airport (14 Nov. 2013) with connectivity to South/East Asian countries. Extension of Apron & Boundary Wall Work going on Agartala New Terminal building in planning stage 23

24 Airports Development - II Airports in Arunachal Pradesh & Meghalaya (Non-operational) Operationalize Along, Daparizo, Passighat, Tezu, Ziro (Arunachal Pradesh) Daparijo (Arunachal Pradesh to sort out Land Acquisition Issues) Greenfield Airport in Tawang (Arunachal Pradesh) to be finalized after NOC from MoD Tura (Meghalaya) land acquisition issues. Average no. of departures per week from NE Airports increased sharply Larger and more regular air connectivity to NER, specifically within the region necessary. Guwahati being developed as a regional hub (Sept. 2014). Will help improve connectivity Intra-regional network in NE is weak and needs to be developed. NEC has invited bids (with VGF support) with little success so far Need to approve recommendations of Committee under Member (NE), PC on issues relating to air connectivity by Alliance Air. Shillong-Kolkata services resumed since 10 Jul. 2013, may be discontinued again by Alliance Air 24

25 Roads East West Corridor (NHAI) Completed length is 500 km (81%) Likely completion date : Dec Critical issues: Land availability. Likely to be resolved by State Govt. Guwahati Nalbari (14 km) (Assam) Maibong Harangajao (16 km) (Assam) Clearance for extraction of Mines & Minerals (State Govts.) SARDP-NE (MoRTH, State PWDs, BRO) Phase A 4,099 km (Project cost Rs.21,000 crore) Phase B 3,723 km (Only DPR approved) Arunachal Package (MoRTH, Arunachal PWD and BRO) 2,319 km (Rs.11,919 crore) 25

26 Item Progress of Phase A and Arunachal Package Total Length Target Work Sanctioned/ Awarded Roads Completed Phase A 4,099 2,505 1,214 Arunachal Package 2,319 1,341 (58%) 113 (5%) Total 6,418 3,846 (60%) 1,327 (21%) Targeted/Expected Date for Completion June, 2015/March2017 June, 2016/March2018 Work Sanctioned and Awarded Likely to be 5800 Km (84%) by March Steps taken to strengthen project execution: ADG (1), CE (3) at Guwahati, Agartala & Itanagar posted. Tripura PWD Engineers (7) seconded to Ministry for NH-44 work at Agartala PIU (2) at Guwahati, PIU (2) at Itanagar and PIU (1) at Agartala PIU (1) at Imphal to look after work of NH-53 & construction of 2 bridges Barak and Makru Non-strategic roads off-loaded from BRO (In Kms) 26

27 Agency-wise Re-Distribution of Road Lengths under SARDP-NE & Arunachal Package Agency Original Modified Phase 'A' Ar. Ar. Total Phase 'A' Package Package Total BRO PWD Ar. Pradesh Assam Manipur Meghalaya Mizoram Nagaland Sikkim Tripura NHAI MoRTH Total

28

29 Road Sector Issues Need for special focus on: Work on connecting Sikkim (NH-31A, Sivok-Gangtok-Nathula by BRO) has progressed at a slow pace. New TDC March 2016 Work on NH-44 has been stalled for quite some time. Need for fast pace after the re-distribution & being taken up by State PWD Work on NH-53 (Jiribam-Imphal) critical. Needs early completion Silchar Bridge being replaced with support from M/o DONER. Need for early completion of project Dhola Sadiya Bridge (river Brahmaputra) targeted for completion in Work going on well Road to Vijaynagar from Miao needs early sanction Construction of Bridge over Feni river (Tripura) connecting Bangladesh taken up with MEA support. Work should start early Replacement of all semi-permanent timber bridges in the region. Special focus and be funded by State Govts., along with Central assistance under SPA over next 3 years. A special scheme needs to be launched to complete this 29

30 Airports in NE State Operational Non- Operational Assam 6 3 IAF, 3 AAI Arunachal Pradesh Pakyong Bagdogra Sikkim West Bengal 2-5 Manipur 1 - Meghalaya 1 1 Mizoram 1 1 Nagaland 1 - Tripura 1 3 Sikkim - - West Bengal 1* - Total Rupsi Tura Agartala Guwahati Shillong Meghalaya Kailashahar Kamalpur Khowai Tripura Shella Tezpur Assam Silchar Lengpui Ziro Dimapur Mizoram Turial Daparizo Dibrugargh North Lakhimpur (Lilabari) Jorhat Imphal Manipur * Bagdogra Airport, although in Eastern Region, is included as it is the gateway to North-East including Sikkim State Arunachal Pradesh Itanagar Along Pasighat Nagaland Chiethu/ Kohima LEGEND Tezu Operational (11+1) Non-Operational (12) Greenfield (3) 30

31 Airports Development ( ) - I Development of Airports at Pakyong New TDC: Dec Need resolution of land acquisition for AAI Colony, shifting of 16 local residences and approach road from Pakyong to Gangtok Itanagar State Govt. to provide land acquisition (1,037 acres), Rehabilitation, Compound Wall, Approach Road, Electricity/Water supply. PIL challenging site before Guwahati High Court Cheithu Alternative site needs to be selected by State Government Modernize selected Airports by AAI Guwahati Construction of 3 hangars for A-321. TDC Sep Dibrugarh Runway extension (32 acres land acquisition) Jorhat - Apron extension completed (30 Nov. 2013). New Terminal Building planned Shillong Upgradation at Barapani taken up. 32 acres defence land required. Work stopped (August 2012) due to local agitation Imphal : Notified international airport (14 Nov. 2013) with connectivity to South/East Asian countries. Extension of Apron & Boundary Wall Work going on Agartala New Terminal building in planning stage 31

32 Airports Development - II Airports in Arunachal Pradesh & Meghalaya (Non-operational) Operationalize Along, Daparizo, Passighat, Tezu, Ziro (Arunachal Pradesh) Daparijo (Arunachal Pradesh to sort out Land Acquisition Issues) Greenfield Airport in Tawang (Arunachal Pradesh) to be finalized after NOC from MoD Tura (Meghalaya) land acquisition issues. Average no. of departures per week from NE Airports increased sharply Larger and more regular air connectivity to NER, specifically within the region necessary. Guwahati being developed as a regional hub (Sept. 2014). Will help improve connectivity Intra-regional network in NE is weak and needs to be developed. NEC has invited bids (with VGF support) with little success so far Need to approve recommendations of Committee under Member (NE), PC on issues relating to air connectivity by Alliance Air. Shillong-Kolkata services resumed since 10 Jul. 2013, may be discontinued again by Alliance Air 32

33 Inland Water Transport in the NE Region 891 Km National Waterway-2 on River Brahmaputra along with Indo-Bangladesh Protocol Route provides safe, cheap and eco friendly route for carriage of commodities Navigability of meter depth along with navigation aids and ten floating terminals maintained by IWAI 16 Floating terminals for passengers funded by MoS will be commissioned by March already operational Inland Water Port at Pandu developed with high level and low level jetties, two warehouses, Railway siding and open storage: Land for Connecting Road needs resolution with NFR/Govt. of Assam IWAI is developing: Ro-Ro facility at Dhubri and Hatsingimari (opposite bank of Brahmaputra) to reduce travel time of vehicles between Meghalaya and Dhubri in Assam which now have to go over Jogighopa bridge covering a distance of 220 km Vessel repair facility at Pandu (Guwahati). Assam Govt. to expedite transfer of land 33

34 I N D I A Aizwal I N D I A B A N G L A D E S H Lawngtlai Myeikwa (IM Border) Kaletwa Myanmar Bay of Bengal Paletwa Kolkata Sittwe 539 km Sea Sittwe Paletwa 158 km IWT Paletwa Kaletwa 67 km Road Kaletwa Myeikwa (IM Border) Myeikw a (IM Border) Lawngtl ai 62 km Road 100 km Road Lawngtlai Aizwal 334 km Road Kolkata Aizwal 1260 km Kyauktaw Sittwe 34

35 North East has special requirements of transport because of topographical challenges (hilly, landslides ) Transport Infrastructure benefits in NE States. It is provides neighbouring countries. Area: 0.26 million sq land and 46 million population. Partition: Distanced the NE Region to the rest of India by connecting countries to the narrow 27 km wide. 96 % of the boundary of region frame international burdens. Challenges for NE Region: Complete the progress of infrastructure in NE Region; Create institutional & functional mechanisms to sustain and maintain the infrastructure. Well Policy region for free movements of govt./service and from NE region to the international neighbour. 35

36 Agency-wise Re-Distribution of Road Lengths under SARDP-NE & Arunachal Package Agency Original Modified Phase 'A' Ar. Ar. Total Phase 'A' Package Package Total BRO PWD Ar. Pradesh Assam Manipur Meghalaya Mizoram Nagaland Sikkim Tripura NHAI MoRTH Total

37 Road Sector Issues Need for special focus on: Work on connecting Sikkim (NH-31A, Sivok-Gangtok-Nathula by BRO) has progressed at a slow pace. New TDC March 2016 Work on NH-44 has been stalled for quite some time. Need for fast pace after the re-distribution & being taken up by State PWD Work on NH-53 (Jiribam-Imphal) critical. Needs early completion Silchar Bridge being replaced with support from M/o DONER. Need for early completion of project Dhola Sadiya Bridge (river Brahmaputra) targeted for completion in Work going on well Road to Vijaynagar from Miao needs early sanction Construction of Bridge over Feni river (Tripura) connecting Bangladesh taken up with MEA support. Work should start early Replacement of all semi-permanent timber bridges in the region. Special focus and be funded by State Govts., along with Central assistance under SPA over next 3 years. A special scheme needs to be launched to complete this 37

38 Roads East West Corridor (NHAI) Completed length is 500 km (81%) Likely completion date : Dec Critical issues: Land availability. Likely to be resolved by State Govt. Guwahati Nalbari (14 km) (Assam) Maibong Harangajao (16 km) (Assam) Clearance for extraction of Mines & Minerals (State Govts.) SARDP-NE (MoRTH, State PWDs, BRO) Phase A 4,099 km (Project cost Rs.21,000 crore) Phase B 3,723 km (Only DPR approved) Arunachal Package (MoRTH, Arunachal PWD and BRO) 2,319 km (Rs.11,919 crore) 38

39 Item Progress of Phase A and Arunachal Package Total Length Target Work Sanctioned/ Awarded Roads Completed Phase A 4,099 2,505 1,214 Arunachal Package 2,319 1,341 (58%) 113 (5%) Total 6,418 3,846 (60%) 1,327 (21%) Targeted/Expected Date for Completion June, 2015/March2017 June, 2016/March2018 Work Sanctioned and Awarded Likely to be 5800 Km (84%) by March Steps taken to strengthen project execution: ADG (1), CE (3) at Guwahati, Agartala & Itanagar posted. Tripura PWD Engineers (7) seconded to Ministry for NH-44 work at Agartala PIU (2) at Guwahati, PIU (2) at Itanagar and PIU (1) at Agartala PIU (1) at Imphal to look after work of NH-53 & construction of 2 bridges Barak and Makru Non-strategic roads off-loaded from BRO (In Kms) 39

40 Agency-wise Re-Distribution of Road Lengths under SARDP-NE & Arunachal Package Agency Original Modified Phase 'A' Ar. Ar. Total Phase 'A' Package Package Total BRO PWD Ar. Pradesh Assam Manipur Meghalaya Mizoram Nagaland Sikkim Tripura NHAI MoRTH Total

41 Road Sector Issues Need for special focus on: Work on connecting Sikkim (NH-31A, Sivok-Gangtok-Nathula by BRO) has progressed at a slow pace. New TDC March 2016 Work on NH-44 has been stalled for quite some time. Need for fast pace after the re-distribution & being taken up by State PWD Work on NH-53 (Jiribam-Imphal) critical. Needs early completion Silchar Bridge being replaced with support from M/o DONER. Need for early completion of project Dhola Sadiya Bridge (river Brahmaputra) targeted for completion in Work going on well Road to Vijaynagar from Miao needs early sanction Construction of Bridge over Feni river (Tripura) connecting Bangladesh taken up with MEA support. Work should start early Replacement of all semi-permanent timber bridges in the region. Special focus and be funded by State Govts., along with Central assistance under SPA over next 3 years. A special scheme needs to be launched to complete this 41

42 Thank you

REGIONAL POLICY DIALOGUE ON STRENGTHENING TRANSPORT CONNECTIVITY IN SOUTHERN ASIA

REGIONAL POLICY DIALOGUE ON STRENGTHENING TRANSPORT CONNECTIVITY IN SOUTHERN ASIA REGIONAL POLICY DIALOGUE ON STRENGTHENING TRANSPORT CONNECTIVITY IN SOUTHERN ASIA Session 6: SOUTH ASIA ASEAN CONNECTIVITY TRANSIT AND TRADE FACILITATION AND DEVELOPMENT OF BORDER REGIONS 20 TH NOVEMBER,

More information

Northeast India (officially called North Eastern Region, NER) is the

Northeast India (officially called North Eastern Region, NER) is the SECTION - 3 ZONAL RAILWAY NFR (Const.) A Life Line In Connectivity And Infrastructure Development In North Eastern Region & Neighbouring Countries General Manager Northeast Frontier Railway (Construction)

More information

Accelerated Road Development Programme (SARDP-NE) and Border Highways under Border Area Development Programme (BADP) in Arunachal Pradesh

Accelerated Road Development Programme (SARDP-NE) and Border Highways under Border Area Development Programme (BADP) in Arunachal Pradesh Accelerated Road Development Programme (SARDP-NE) and Border Highways under Border Area Development Programme (BADP) in Arunachal Pradesh Suggested modifications by Government of Arunachal Pradesh December

More information

BY NHIDCL. 25 t h MAY, 2018

BY NHIDCL. 25 t h MAY, 2018 DEVELOPMENT OF ROAD INFRASTRUCTURE BY NHIDCL 25 t h MAY, 2018 NATIONAL HIGHWAYS & INFRASTRUCTURE DEVEOPMENT CORPORATION LTD. FAST PACE CONSTRUCTION OF NATIONAL HIGHWAYS AND OTHER INFRASTRUCTURE IN NE REGION

More information

Ministry of Development of North Eastern Region

Ministry of Development of North Eastern Region Ministry of Development of North Eastern Region Connecting India s North East with the mainstream: Joint Efforts with other line Ministries 7 Railway projects consisting of 3 New Lines and 4 Doublings

More information

Adequate infrastructure facilities are a pre requisite for industrial development. The infrastructure facilities available in Assam are as follows:

Adequate infrastructure facilities are a pre requisite for industrial development. The infrastructure facilities available in Assam are as follows: Assam Infrastructure The state Government also proposes to implement the scheme Integrated Infrastructure Development (IID) centers which is at difference stages of clearance from the authorities. The

More information

Helicopter Connectivity in North East

Helicopter Connectivity in North East Helicopter Connectivity in North East By: Pawan Hans Ltd. PAWAN HANS LTD. 1 Pawan Hans at a Glance PAWAN HANS LTD. - National Helicopter Carrier Equity Capital - Rs. 245.616 crores; GOI Rs.125.266 crores

More information

Outline. (1) JICA and India. (2) Infrastructure Development. (3) Cross-Border Connectivity

Outline. (1) JICA and India. (2) Infrastructure Development. (3) Cross-Border Connectivity 1 Outline (1) JICA and India (2) Infrastructure Development (3) Cross-Border Connectivity 2 Outline (1) JICA and India (2) Infrastructure Development (3) Cross-Border Connectivity 3 About JICA JICA is

More information

Travelling in Northeast India

Travelling in Northeast India Travelling in Northeast India Consisting of 7 states also called 'Seven Sisters' comprising of Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland and Tripura, North East India has some real

More information

APPROACH TO XI th FIVE YEAR PLAN IN RESPECT OF COMMUNICATION SECTOR UNDER PWD ARUNACHAL PRADESH

APPROACH TO XI th FIVE YEAR PLAN IN RESPECT OF COMMUNICATION SECTOR UNDER PWD ARUNACHAL PRADESH APPROACH TO XI th FIVE YEAR PLAN IN RESPECT OF COMMUNICATION SECTOR UNDER PWD ARUNACHAL PRADESH GOVERNMENT OF ARUNACHAL PRADESH PUBLIC WORKS DEPARTMENT ITANAGAR P : 0360-2212427 1 APPROACH TO XIth FIVE

More information

Development of Road Infrastructure in India

Development of Road Infrastructure in India Development of Road Infrastructure in India By Nirmal Jit Singh Director General (Road Development & Special Secretary) Ministry of Road Transport & Highways Road Network in India Total Road Length about

More information

Strengthening Transport Connectivity between CLMV-T and India: Opportunities and Challenges

Strengthening Transport Connectivity between CLMV-T and India: Opportunities and Challenges UNESCAP Workshop on CLMV-T, 9-10 October 2018 Strengthening Transport Connectivity between CLMV-T and India: Opportunities and Challenges Prabir De ASEAN-India Centre, RIS New Delhi 9 October 2018, Summit

More information

LIST OF RETAINED PROJECTS FROM PRIORITY LIST OF to PENDING FOR SANCTION FOR FUNDING UNDER NLCPR INDICATING IT S LATEST STATUS.

LIST OF RETAINED PROJECTS FROM PRIORITY LIST OF to PENDING FOR SANCTION FOR FUNDING UNDER NLCPR INDICATING IT S LATEST STATUS. Sl. No. LIST OF RETAINED PROJECTS FROM PRIORITY LIST OF 2003-04 to 2009-10 PENDING FOR SANCTION FOR FUNDING UNDER NLCPR INDICATING IT S LATEST STATUS. Departments/Name of Projects and name of Assembly

More information

TENTATIVE ITINERARY NEFIT TRADE DELEGATION TO ATTEND INVEST MYANMAR SUMMIT 2019

TENTATIVE ITINERARY NEFIT TRADE DELEGATION TO ATTEND INVEST MYANMAR SUMMIT 2019 TENTATIVE ITINERARY NEFIT TRADE DELEGATION TO ATTEND INVEST MYANMAR SUMMIT 2019 FOR THE PROMOTION OF BORDER TRADE, TOURISM, INVESMENT AND CO-OPERATION, DAY 1 AT NAY PYI TAW, MYANMAR FROM 25TH JANUARY 4

More information

Road Network in India, Public Private Partnership Financing & Case Study Narendra Sharma, SE(PPP), MoRT&H

Road Network in India, Public Private Partnership Financing & Case Study Narendra Sharma, SE(PPP), MoRT&H Road Network in India, Public Private Partnership Financing & Case Study 20.04.2018 Narendra Sharma, SE(PPP), MoRT&H Functions of Ministry of Road Transport and Highways, Govt. of India Formulation of

More information

Strengthening Transport Connectivity through Road Corridors in Bangladesh

Strengthening Transport Connectivity through Road Corridors in Bangladesh Strengthening Transport Connectivity through Road Corridors in Bangladesh Md. Moinuddin, Addl. Secretary Roads Transport and Highways Division, Bangladesh Contents Road corridors through Bangladesh Status

More information

CENTRALLY SPONSORED SCHEMES

CENTRALLY SPONSORED SCHEMES Year No. of Projects sanctioned No. of Projects Completed CENTRALLY SPONSORED SCHEMES Consolidate Statement of Projects of 10 th, 11 th & 12 th Five Year Plan No. of Projects under execution sanctioned

More information

esupersavernortheast Scheme Terms and Conditions

esupersavernortheast Scheme Terms and Conditions esupersavernortheast Scheme Terms and Conditions The terms and conditions of thescheme which explain the nature and scope of the relationship are detailed hereunder. The terms and conditions aresubject

More information

esupersavereconomy Scheme Terms and Conditions

esupersavereconomy Scheme Terms and Conditions esupersavereconomy Scheme Terms and Conditions The terms and conditions of the esupersaver EconomyScheme which explain the nature and scope of the relationship are detailed hereunder. The terms and conditions

More information

THE REPUBLIC OF THE UNION OF MYANMAR

THE REPUBLIC OF THE UNION OF MYANMAR THE REPUBLIC OF THE UNION OF MYANMAR MINISTRY OF TRANSPORT AND COMMUNICATIONS 5 th Meeting of the Working Group on the Trans-Asian Railway Network and Global Smart Rail Conference Current Status and Challenges

More information

Monitorable Targets & Milestones for INFRASTRUCTURE SECTOR : Planning Commission, Government of India

Monitorable Targets & Milestones for INFRASTRUCTURE SECTOR : Planning Commission, Government of India Page 1 of 1 S.No. Name of the Scheme Actual 2009-10 Expenditure in 2010-11 (Cumulative) (Rs. In Crores) Grand Total 2010-11 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1 CSI Airport Mumbai Target 570.00 982.00 1645.00

More information

Daily Current Affairs Capsule 19 th January 2019

Daily Current Affairs Capsule 19 th January 2019 Changing the way of learning Daily Current Affairs Capsule 19 th January 2019 1. Raksha Mantri Dedicates Diffo Bridge in Arunachal to The Nation Raksha Mantri Smt Nirmala Sitharaman inaugurated the 426.60

More information

2 AGATTI Airports Authority of India, Agatti Airport Controller

2 AGATTI Airports Authority of India, Agatti Airport Controller ANNEXURE D APPENDIX 1 LIST OF OPERATIONAL AIRPORTS (CIVIL) IN INDIA S.No. Name of the Airport Address Designation of the Head Office Phone E-Mail Address 1 AGARTALA Airports Authority of India, Agartala

More information

Welcome HAI Delegates

Welcome HAI Delegates Welcome HAI Delegates We fly for you Presentation by Dr. B P Sharma PAWAN HANS LIMITED Helicopter Industry: Indian Prospective MoCA-GoI New Civil Aviation Policy Pawan Hans Ltd-A Mini Ratna CPSE: A Profile

More information

Assistance to States for Developing Export Infrastructure and Allied Activities (ASIDE) Scheme of Ministry of Commerce & Industry, State Cell

Assistance to States for Developing Export Infrastructure and Allied Activities (ASIDE) Scheme of Ministry of Commerce & Industry, State Cell Assistance to States for Developing Export Infrastructure and Allied Activities (ASIDE) Scheme of Ministry of Commerce & Industry, State Cell implementation in the state of Assam Overview of ASIDE Scheme

More information

INTERNATIONAL PASSENGERS

INTERNATIONAL PASSENGERS ANNEXURE-IIIA INTERNATIONAL PASSENGERS SL. NO. AIRPORT (A) 20 INTERNATIONAL AIRPORTS 1 CHENNAI 460469 436463 5.5 3004920 2740981 9.6 2 KOLKATA 224130 211056 6.2 1321726 1238025 6.8 3 AHMEDABAD 194117 166655

More information

CITY PAIR WISE DOMESTIC PASSENGER TRAFFIC STATISTICS FOR THE MONTH OF AUGUST, 2015

CITY PAIR WISE DOMESTIC PASSENGER TRAFFIC STATISTICS FOR THE MONTH OF AUGUST, 2015 CITY PAIR WISE DOMESTIC PASSENGER TRAFFIC STATISTICS FOR THE MONTH OF AUGUST, 2015 PASSENGERS (IN NUMBER) SL. No. CITY 1 CITY2 PASSENGER TO CITY 2 PASSENGER FROM CITY 2 1 AGATTI ISLAND KOCHI 484 430 2

More information

Status of Integrated Transport in Bangladesh. Presented by Md. Ehsan-E-Elahi Joint Secretary Road Transport & Highways Division

Status of Integrated Transport in Bangladesh. Presented by Md. Ehsan-E-Elahi Joint Secretary Road Transport & Highways Division Status of Integrated Transport in Bangladesh Presented by Md. Ehsan-E-Elahi Joint Secretary Road Transport & Highways Division Outline An overview of transport system in Bangladesh Legal and policy environment

More information

MINISTRY OF SHIPPING

MINISTRY OF SHIPPING MINISTRY OF SHIPPING I. LAUNCH OF SAGARMALA PROGRAMME Objective Based on the vision of port-led development, focusing on logistics intensive industries, the programme aims to unlock the full potential

More information

PPP Days 2010 PPPs Lessons from the Last 18 Months

PPP Days 2010 PPPs Lessons from the Last 18 Months PPP Days 2010 PPPs Lessons from the Last 18 Months Rajiv B Lall March 22, 2010 1 Private Sector Participation (PSP) in India Works & Services Contracts Management Contracts Operation Concessions Build

More information

Sagarmala Development Company (SDC)

Sagarmala Development Company (SDC) Sagarmala Development Company (SDC) Sagarmala Programme moving from planning to implementation stage Projects under Sagarmala will be implemented by Central Ministries, State Governments, Ports / Agencies

More information

CITY PAIR WISE DOMESTIC PASSENGER TRAFFIC STATISTICS FOR THE MONTH OF SEPTEMBER, 2017 (Provisional )

CITY PAIR WISE DOMESTIC PASSENGER TRAFFIC STATISTICS FOR THE MONTH OF SEPTEMBER, 2017 (Provisional ) 1 AGRA DELHI 0 57 2 AGRA KHAJURAHO 94 0 3 AGRA VARANASI 0 410 4 AGATTI ISLAND KOCHI 863 956 5 AIZAWL AHMEDABAD 35 37 6 AIZAWL MUMBAI 203 178 7 AIZAWL KOLKATA 6591 6545 8 AIZAWL DELHI 701 604 9 AIZAWL GUWAHATI

More information

Largest hydropower potential in India. Railways as a new means of transport. Orchid paradise. Carpet making. Largest state in Northeast

Largest hydropower potential in India. Railways as a new means of transport. Orchid paradise. Carpet making. Largest state in Northeast Largest hydropower potential in India India s pent-up demand for electricity could be addressed by the state s potential 60,000 MW hydropower capacity. Currently, several hydro power projects are allocated

More information

HLTC (Economy Class) DLTC (Executiv e Class)

HLTC (Economy Class) DLTC (Executiv e Class) S No TABLE IV LTC Fares SECTOR & V.V HLTC (Economy Class) Base Fare DLTC (Executiv e Class) Base Fare Airline Fuel Charge 1 Agartala Guwahati 4831 10140 1850 2 Agartala Kolkata 3891 8506 1850 3 Agartala

More information

Airindia Domestic Fares (Apex & Instant Purchase Fares) TABLE IV LTC Fares updated as on TABLE IV- LTC Fares

Airindia Domestic Fares (Apex & Instant Purchase Fares) TABLE IV LTC Fares updated as on TABLE IV- LTC Fares Air India LTC-80 Fares updated as on 10 June 2013 S No Airindia Domestic Fares (Apex & Instant Purchase Fares) TABLE IV LTC Fares updated as on 10-06-2013 TABLE IV- LTC Fares SECTOR & V.V HLTC (Economy

More information

SITREP NO-110/ hours 32-20/2007-NDM-I Ministry of Home Affairs (Disaster Management Division) Dated, 18 TH September, 2007

SITREP NO-110/ hours 32-20/2007-NDM-I Ministry of Home Affairs (Disaster Management Division) Dated, 18 TH September, 2007 SITREP NO-110/2007 1700 hours 32-20/2007-NDM-I Ministry of Home Affairs (Disaster Management Division) Dated, 18 TH September, 2007 Subject: SOUTHWEST MONSOON-2007: DAILY FLOOD SITUATION REPORT SUMMARY

More information

India - State-wise Wastelands Distribution (Percentage to total geographical area)

India - State-wise Wastelands Distribution (Percentage to total geographical area) WASTELAND MAP 25-6 INDIA Figure. 1 Gullied/ Ravine land-medium ravine Gullied/Ravine land-deep/ very deep ravine Scrubland - Land with dense scrub Scrubland - Land with open scrub Waterlogged and marshy

More information

CITY PAIR WISE DOMESTIC PASSENGER TRAFFIC STATISTICS FOR THE MONTH OF JAN, 2017

CITY PAIR WISE DOMESTIC PASSENGER TRAFFIC STATISTICS FOR THE MONTH OF JAN, 2017 1 AGARTALA CHENNAI 664 1234 2 AGATTI ISLAND KOCHI 1138 1084 3 AGRA DELHI 0 49 4 AGRA KHAJURAHO 444 0 5 AGRA VARANASI 0 1054 6 AHMEDABAD BENGALURU 28184 27290 7 AHMEDABAD CHENNAI 21825 22674 8 AHMEDABAD

More information

Table-1.1 SEASONS, SOWING & HARVESTING PERIOD AND PRODUCTION. Five year Average Production ( to Harvesting Period.

Table-1.1 SEASONS, SOWING & HARVESTING PERIOD AND PRODUCTION. Five year Average Production ( to Harvesting Period. 1 1. PRODUCTION: The major potato producing States are Uttar Pradesh, West Bengal, Bihar, Gujarat, Madhya Pradesh, Punjab, Haryana and Assam. (Table-1.3). The details regarding seasonality, harvesting

More information

Network Size and Growth

Network Size and Growth 16.50 25.10 30.30 11.40 5.10 9.63 10.00 8.26 64.94 km 208.24 Overview Network Size and Growth At present, metro systems are operational in seven cities in India Bengaluru, Chennai, Delhi, Gurgaon, Jaipur,

More information

Nostalgic Tourism and Make in India with Special Reference to North-East India.

Nostalgic Tourism and Make in India with Special Reference to North-East India. IOSR Journal Of Humanities And Social Science (IOSR-JHSS) Volume 22, Issue 1, Ver. 3 (January 2017) PP 01-06 e-issn: 2279-0837, p-issn: 2279-0845. www.iosrjournals.org Nostalgic Tourism and Make in India

More information

MEMORANDUM OF UNDERSTANDING

MEMORANDUM OF UNDERSTANDING MEMORANDUM OF UNDERSTANDING 2017-18 AIRPORTS AUTHORITY OF INDIA AND MINISTRY OF CIVIL AVIATION Department of Corporate Planning & Management Services AIRPORTS AUTHORITY OF INDIA Annexure I Brief about

More information

CITY PAIR WISE DOMESTIC PASSENGER TRAFFIC STATISTICS FOR THE MONTH OF MARCH, 2017

CITY PAIR WISE DOMESTIC PASSENGER TRAFFIC STATISTICS FOR THE MONTH OF MARCH, 2017 1 AGARTALA CHENNAI 871 998 2 AGARTALA VISAKHAPATNAM 78 0 3 AGATTI ISLAND BENGALURU 0 17 4 AGATTI ISLAND KOCHI 898 928 5 AGRA DELHI 0 9 6 AGRA KHAJURAHO 93 0 7 AGRA VARANASI 0 323 8 AHMEDABAD BENGALURU

More information

Public Private Partnership (PPP) in Airport Infrastructure

Public Private Partnership (PPP) in Airport Infrastructure Public Private Partnership (PPP) in Airport Infrastructure By Secretary Ministry of Civil Aviation Government of India Conference of Chief Secretaries on PPP in Infrastructure 20 th May, 2006 PPP in Airport

More information

PHD Aviation Summit: Indian Civil Aviation Benefit Beyond Borders. February 18 th, Presented To:

PHD Aviation Summit: Indian Civil Aviation Benefit Beyond Borders. February 18 th, Presented To: KNOWLEDGE PARTNER PHD Aviation Summit: Indian Civil Aviation Benefit Beyond Borders February 18 th, 2016 Presented To: Shri Ashok Gajapathi Raju Pusapati Hon ble Minister of Civil Aviation Indian aviation

More information

TRANSPORT CANADA S NATIONAL TRADE CORRIDORS FUND. PNWER November 2018

TRANSPORT CANADA S NATIONAL TRADE CORRIDORS FUND. PNWER November 2018 TRANSPORT CANADA S NATIONAL TRADE CORRIDORS FUND PNWER November 2018 INVESTING IN CANADA PLAN EXISTING FUNDS Of the $180+ billion, 12-year Investing in Canada Plan, $10.1 billion has been dedicated to

More information

Which current trends are your best friends?

Which current trends are your best friends? Monday 9 October Which current trends are your best friends? Rear Admiral M. Khaled Iqbal Chairman Chittagong Port Authority Co-located with: Powered by: Created and produced by: Ocean the great connector

More information

TABLE IV- LTC Fares. DLTC (Executive Class) HLTC (Economy Class) S No SECTOR & V.V

TABLE IV- LTC Fares. DLTC (Executive Class) HLTC (Economy Class) S No SECTOR & V.V S No TABLE IV- LTC Fares SECTOR & V.V HLTC (Economy Class) Base Fare DLTC (Executive Class) Base Fare Airline Fuel Charge 1 Agartala Guwahati 4831 10140 1850 2 Agartala Kolkata 3891 8506 1850 3 Agartala

More information

¾Ö ÖÖÖÖ¼ÜÖ Ö ÖÖÊ ÔÜ ÒÜÃ Ü / VISAKHAPATNAM PORT TRUST {ÉÊ Ú{ÉJÉ / CIRCULAR NO. 338

¾Ö ÖÖÖÖ¼ÜÖ Ö ÖÖÊ ÔÜ ÒÜÃ Ü / VISAKHAPATNAM PORT TRUST {ÉÊ Ú{ÉJÉ / CIRCULAR NO. 338 ¾Ö ÖÖÖÖ¼ÜÖ Ö ÖÖÊ ÔÜ ÒÜÃ Ü / VISAKHAPATNAM PORT TRUST μööÿööμööÿö ¾Ö³ÖÖÖ / TRAFFIC DEPARTMENT --- ºÉÆ No.ITRA/SHIP/FPV ÊNÙ. Dt. 27.9.2012. {ÉÊ Ú{ÉJÉ / CIRCULAR NO. 338 ALL TRADE Ê É¹ÉªÉ Sub: Embarkation

More information

PRE FEASIBILITY REPORT TABLE OF CONTENTS

PRE FEASIBILITY REPORT TABLE OF CONTENTS PRE FEASIBILITY REPORT TABLE OF CONTENTS S. No Particulars Page No. 1 Project Background 33 2 Project Description 33 3 Site Analysis 41 4 Rehabilitation & Resettlement 44 5 Proposed Infrastructure 44 6

More information

WATER QUALITY INDEX OF RIVER WATER AT DIFFERENT LOCATIONS IN THE STATE OF ASSAM UNDER NWMP FOR JULY-2017

WATER QUALITY INDEX OF RIVER WATER AT DIFFERENT LOCATIONS IN THE STATE OF ASSAM UNDER NWMP FOR JULY-2017 WATER QUALITY INDEX OF RIVER WATER AT DIFFERENT LOCATIONS IN THE STATE OF UNDER NWMP FOR JULY-2017 STN Code Sampling Date Stn Name 1030 7/17/2017 BRAHAMPUTRA AT DIBRUGARH, PCBA 6.6 1.8 Nil 2000 BOD(Satisfied)

More information

Corridor of growth. Corridor Description and Rating NEW GURGAON. Areas Included:

Corridor of growth. Corridor Description and Rating NEW GURGAON. Areas Included: Corridor of growth Corridor Description and Rating Areas Included: NEW GURGAON Sectors 76, 77, 78, 79, 79A, 79B, 80, 81, 81A, 82, 82A, 83, 84, 85, 86, 88, 88A, 88B, 89, 89A, 90, 91, 92, 93, 95 and 95A

More information

ASSAM THE LAND OF RED RIVERS AND BLUE HILLS

ASSAM THE LAND OF RED RIVERS AND BLUE HILLS THE LAND OF RED RIVERS AND BLUE HILLS February 2018 Table of Content Executive Summary...3 Advantage State.....4 Assam Vision..5 Assam An Introduction......6 State Budget... 14 Infrastructure Status...15

More information

WATER QUALITY INDEX OF RIVER WATER AT DIFFERENT LOCATIONS IN THE STATE OF ASSAM UNDER NWMP FOR AUGUST-2017

WATER QUALITY INDEX OF RIVER WATER AT DIFFERENT LOCATIONS IN THE STATE OF ASSAM UNDER NWMP FOR AUGUST-2017 WATER QUALITY INDEX OF RIVER WATER AT DIFFERENT LOCATIONS IN THE STATE OF UNDER NWMP FOR AUGUST-2017 Remarks Final_Remark 1031 8/1/2017 BRAHAMPUTRA AT PANDU, PCBA 6.1 0.8 720 2000 BOD(Satisfied) Satisfactory

More information

Afghanistan. Supply, Installation, Rehabilitation, Construction Testing and Commissioning of Gardez To Khost Road in Afghanistan, Funded by USAID

Afghanistan. Supply, Installation, Rehabilitation, Construction Testing and Commissioning of Gardez To Khost Road in Afghanistan, Funded by USAID Gardez- Khost Road Project Afghanistan Supply, Installation, Rehabilitation, Construction Testing and Commissioning of Gardez To Khost Road in Afghanistan, Funded by USAID LBG B& V "JV" INR 3526.00 Million

More information

Global Sustainable Tourism Criteria Perspective Bangladesh. Akhtaruz Zaman Khan kabir CEO

Global Sustainable Tourism Criteria Perspective Bangladesh. Akhtaruz Zaman Khan kabir CEO Global Sustainable Tourism Criteria Perspective Bangladesh Akhtaruz Zaman Khan kabir CEO Geographic Location BANGLADESH TOURISM Official Name : The People's Republic of Bangladesh Geographical Location

More information

URBANIZATION IN THE HILL DISTRICTS OF ASSAM

URBANIZATION IN THE HILL DISTRICTS OF ASSAM 54 CHAPTER 3 URBANIZATION IN THE HILL DISTRICTS OF ASSAM 3.1 Process of Urbanization in the Hill Districts of Assam: An Overview: Urbanization has been considered as a distinct measuring-stick of prosperity

More information

Aero Expo 2016 Civil Aviation Convention & Exhibition Enhancing Regional & Remote Connectivity. November 18 th, 2016.

Aero Expo 2016 Civil Aviation Convention & Exhibition Enhancing Regional & Remote Connectivity. November 18 th, 2016. KNOWLEDGE PARTNER Aero Expo 2016 Civil Aviation Convention & Exhibition Enhancing Regional & Remote Connectivity November 18 th, 2016 Presented To: Shri Ashok Gajapathi Raju Pusapati Hon ble Minister of

More information

CITIZEN S CHARTER OF ASSAM URBAN WATER SUPPLY AND SEWERAGE BOARD, GUWAHATI-6.

CITIZEN S CHARTER OF ASSAM URBAN WATER SUPPLY AND SEWERAGE BOARD, GUWAHATI-6. CITIZEN S CHARTER OF ASSAM URBAN WATER SUPPLY AND SEWERAGE BOARD, GUWAHATI-6. The aim and purpose of this charter of Assam Urban Water Supply and Sewerage Board is to confirm publicity the service assurance

More information

ROAD DEVELOPMENT IN INDIA 2015

ROAD DEVELOPMENT IN INDIA 2015 ROAD DEVELOPMENT IN INDIA 2015 Research report with weekly newsletters and monthly updates Research Report 52 Weekly Newsletters 11 Monthly Updates India Infrastructure Research www.indiainfrastructure.com

More information

List of RCS Airports and routes Started under UDAN-1 & 2 20 Aug 2018

List of RCS Airports and routes Started under UDAN-1 & 2 20 Aug 2018 Sr. No Airport Commencement date Un served 1. ADAMPUR 01-May-18 2. BHATINDA 27-Apr-17 3. BIKANER (NAL) 26-Sep-17 4. JAISALMER 29-Oct-17 5. JALGAON 23-Dec-17 6. KANDLA 10-Jul-17 7. KOLHAPUR 08-Apr-18 8.

More information

11 th Annual Conference Road Development in India Telangana State Initiatives

11 th Annual Conference Road Development in India Telangana State Initiatives 11 th Annual Conference Road Development in India Telangana State Initiatives 24 th August 2016 New Delhi Bikshapathi Kondai Engineer in Chief R&B, Telangana State New Telangana State - Infrastructure

More information

ARUNACHAL PRADESH LAND OF THE RISING SUN

ARUNACHAL PRADESH LAND OF THE RISING SUN LAND OF THE RISING SUN November 2017 Table of Content Executive Summary...3 Advantage India.....4 Arunachal Pradesh An Introduction..5 Infrastructure Status.....14 Employment Opportunities... 27 Major

More information

SOUTHWEST MONSOON-2008: DAILY FLOOD SITUATION REPORT

SOUTHWEST MONSOON-2008: DAILY FLOOD SITUATION REPORT 32-20/2008-NDM-I Ministry of Home Affairs (Disaster Management Division) SITREP NO-131/2008 1700 hours Dated, 9 th October, 2008 Subject: SOUTHWEST MONSOON-2008: DAILY FLOOD SITUATION REPORT SUMMARY OF

More information

ASSAM THE LAND OF RED RIVERS AND BLUE HILLS

ASSAM THE LAND OF RED RIVERS AND BLUE HILLS (As on 9 June 2017) 1 Executive Summary 3 Advantage State.. 4 Assam Vision...5 Assam An Introduction....6 State Budget..14 Infrastructure Status..... 15 Industries...... 35 Doing Business in Assam.......

More information

Message from Chairman, Committee on Trade with ASEAN countries

Message from Chairman, Committee on Trade with ASEAN countries Issue: December 2017 Chairman s Pen In this issue of the newsletter on ASEAN+5, we highlight the ASEAN-India Connectivity Summit (AICS) with the theme of Powering Digital and Physical Linkages for Asia

More information

ASSAM THE LAND OF RED RIVERS AND BLUE HILLS

ASSAM THE LAND OF RED RIVERS AND BLUE HILLS 1 Executive Summary 3 Advantage State.. 4 Assam Vision...5 Assam An Introduction....6 State Budget..14 Infrastructure Status..... 15 Industries...... 35 Doing Business in Assam....... 53 State Acts & Policies....

More information

SOUTHWEST MONSOON-2008: DAILY FLOOD SITUATION REPORT

SOUTHWEST MONSOON-2008: DAILY FLOOD SITUATION REPORT 32-20/2008-NDM-I Ministry of Home Affairs (Disaster Management Division) SITREP NO-133/2008 1700 hours Dated, 11 th October, 2008 Subject: SOUTHWEST MONSOON-2008: DAILY FLOOD SITUATION REPORT SUMMARY OF

More information

Rural Tourism of North East India: Prospects and Challenges

Rural Tourism of North East India: Prospects and Challenges IOSR Journal Of Humanities And Social Science (IOSR-JHSS) Volume 23, Issue 2, Ver. 4 (February. 2018) PP 69-74 e-issn: 2279-0837, p-issn: 2279-0845. www.iosrjournals.org Rural Tourism of North East India:

More information

Indian Aviation Industry

Indian Aviation Industry Indian Aviation Industry Registered aircraft : 1600+ Aeroplanes : 1170+ Helicopters : 300+ Misc* : 150+ (*gliders, microlight, balloons etc.) However, around 900 or so are actually operating as many aircraft

More information

The winning states in each of the three award categories were as follows:

The winning states in each of the three award categories were as follows: WTTCII-HVS Tourism for Tomorrow Awards India, 5 December 2013 The World Travel & Tourism Council India Initiative (WTTCII) and HVS, the world s leading hospitality consulting and services organization,

More information

Investment Opportunities DMIC UP Region

Investment Opportunities DMIC UP Region Investment Opportunities DMIC UP Region PRESENTATION TO Japanese Business Mission BY Government of Uttar Pradesh (GoUP) Monday, February 04, 2008 1 The Region comprises of Greater Noida City & Taj Expressway

More information

COIMBATORE AREA RAPID TRANSPORT- CART

COIMBATORE AREA RAPID TRANSPORT- CART COIMBATORE AREA RAPID TRANSPORT- CART CART Monorail project PRESENTATED BY. Ramasamy Raveendran - Hon. Secretary Mahadevan Parasuraman - Consultant Sankrishnan - Chicago Coimbatore - A fast developing

More information

POLICY AND PROCEDURE MANUAL. 4. General Guidelines 3. Table of Contents. 1. Objective Scope Policy Annexure. 5.1.

POLICY AND PROCEDURE MANUAL. 4. General Guidelines 3. Table of Contents. 1. Objective Scope Policy Annexure. 5.1. HR / VS / 2011 : Table of Contents 1. Objective 3 2. Scope 3 3. Policy 3 4. General Guidelines 3 5. Annexure 5.1. Fare Chart 5 5.2. Expense Reimbursement Format 6 5.3. Two-wheeler per Rs/km 7 5.4. Daily

More information

Asian Highway. A vision for the Future. Country Presentation: Bangladesh. 6 th Working Group Meeting on Asian Highway Seoul, Korea

Asian Highway. A vision for the Future. Country Presentation: Bangladesh. 6 th Working Group Meeting on Asian Highway Seoul, Korea Asian Highway A vision for the Future 6 th Working Group Meeting on Asian Highway Seoul, Korea Country Presentation: Bangladesh 03 November 2015 Presentation Outline 1 Asian Highway(AH) 2 AH Network In

More information

Current Affairs MCQs 12 March 2018

Current Affairs MCQs 12 March 2018 Current Affairs MCQs 12 March 2018 Individual Test Series at Rs. 100 Only Q1. The first ever Indo-French Knowledge Summit held in which city? A. New Delhi B. Vishakapatnam C. Patna D. Lucknow Explanation:

More information

Notice of invitation of Counter proposals dated

Notice of invitation of Counter proposals dated Notice of invitation of Counter propoal dated 16.11.2017 Notice of invitation of Counter propoal againt Initial Propoal received up to 1700 hr on 09.11.2017 in 2 nd Round of Bidding for Selection Proce

More information

Joy & Secrets of. Tribal Frontier. FEB/Mar Highlights of the trip. Destinations. An Adventure with Sudhakar Selwyn

Joy & Secrets of. Tribal Frontier. FEB/Mar Highlights of the trip. Destinations. An Adventure with Sudhakar Selwyn Joy & Secrets of Tribal Frontier FEB/Mar 2020 An Adventure with Sudhakar Selwyn Highlights of the trip 1. Paya Village Home stay at Arunachal Pradesh 2. Konyak Tribals home visits 3. Explore the undiscovered

More information

Prashant Mavani, is an expert in current affairs analysis and holds a MSc in Management from University of Surrey (U.K.).

Prashant Mavani, is an expert in current affairs analysis and holds a MSc in Management from University of Surrey (U.K.). Prashant Mavani, is an expert in current affairs analysis and holds a MSc in Management from University of Surrey (U.K.). Above all he is a passionate teacher. The nation pays homage to Father of the

More information

L&T WESTERN ANDHRA TOLLWAYS LTD (A SUBSIDIARY OF L&T IDPL)

L&T WESTERN ANDHRA TOLLWAYS LTD (A SUBSIDIARY OF L&T IDPL) National Highways Authority of India (Ministry of Shipping, Road Transport & Highways) 4 Laning of the Existing 2 Lane Section from Km. 80.050 (Jadcherla) to Km. 135.740 (end of Kothakota Bypass) On NH-44

More information

16. COMMITTEE SECTION (T&T)

16. COMMITTEE SECTION (T&T) 16. COMMITTEE SECTION (T&T) 16.1 Functions of the Section: The Committee Section (Transport & Tourism) deals with the work pertaining to the Department-related Parliamentary Standing Committee on Transport,

More information

AIRPORTS AUTHORITY OF INDIA. Press Release

AIRPORTS AUTHORITY OF INDIA. Press Release AIRPORTS AUTHORITY OF INDIA Press Release New Delhi 19 th February, 2013 AAI & SITA held a Joint Press Conference to mark the implementation of Common Use Passenger System (CUPS), Common Use Self service

More information

Reference List for Cathodic Protection of LPG Mounded Bullets using AnodeFlex

Reference List for Cathodic Protection of LPG Mounded Bullets using AnodeFlex Reference List for Cathodic Protection of using AnodeFlex Cathodic Protection Projects Executed / Under Execution for 210 Nos Amounting to Total Value of Rs. 25.0 Crores (Bullet Dimensions ranging from:

More information

Exploring the Unexplored India: An Opportunity in Tourism Industry (With Special Reference to Eastern States in India)

Exploring the Unexplored India: An Opportunity in Tourism Industry (With Special Reference to Eastern States in India) Volume 10 Issue 10, April 2018 Exploring the Unexplored India: An Opportunity in Tourism Industry (With Special Reference to Eastern States in India) Dr. Laxmi Goritiyal Assistant Professor - Finance Vivekananda

More information

the total length of railway lines in the country and the length out of that electrified in terms of kilometre and percentage, State-wise;

the total length of railway lines in the country and the length out of that electrified in terms of kilometre and percentage, State-wise; GOVERNMENT OF INDIA MINISTRY OF RAILWAYS LOK SABHA STARRED QUESTION NO.334 TO BE ANSWERED ON 09.08.2017 DOUBLING AND ELECTRIFICATION OF RAILWAY LINES *334. SHRI B.S. YEDIYURAPPA: Will the Minister of RAILWAYS

More information

Japan India Cooperation on Railway Sector

Japan India Cooperation on Railway Sector Japan India Cooperation on Railway Sector 14 th October, 2015 IREE 2015 Takema Sakamoto Chief Representative India Office Japan International Cooperation Agency (JICA) 1 Contents 1. Overview and Strategy

More information

Civil Aviation. LTI The Trusted Training Institute for Competitive Exams (www.lticareer.com)

Civil Aviation. LTI The Trusted Training Institute for Competitive Exams (www.lticareer.com) Civil Aviation International Airports of India A Complete List Airports in India are managed by Airports Authority of India (AAI). It works under the Ministry of Civil Aviation and it is responsible for

More information

Tribal. Joy & Secrets of. Frontier. Mar Highlights of the trip. Destinations. An Adventure with Sudhakar Selwyn

Tribal. Joy & Secrets of. Frontier. Mar Highlights of the trip. Destinations. An Adventure with Sudhakar Selwyn Joy & Secrets of Tribal Frontier Mar 2019 An Adventure with Sudhakar Selwyn Highlights of the trip 1. Paya Village Home stay at Arunachal Pradesh 2. Konyak Tribals home visits 3. Explore the undiscovered

More information

Airports NOVEMBER For updated information, please visit

Airports NOVEMBER For updated information, please visit Airports NOVEMBER 1 Contents Advantage India Market overview and trends Growth drivers Success stories: Delhi, Mumbai Opportunities Useful information 2 Airports NOVEMBER Advantage India 2000 No of operational

More information

LAND VALUE CAPTURE FOR RAILWAY STATION DEVELOPMENT. Changing perception of Railways

LAND VALUE CAPTURE FOR RAILWAY STATION DEVELOPMENT. Changing perception of Railways LAND VALUE CAPTURE FOR RAILWAY STATION DEVELOPMENT Changing perception of Railways ABOUT IRSDC Chairman (Member Engg/ Rly Board) w.e.f Sep RLDA SHAREHOLDING 50% IRCON 50% BOARD OF DIRECTORS STRUCTURE Earlier,

More information

SECTOR ASSESSMENT (SUMMARY): Transport, and Information and Communication Technology - Air Transport 1

SECTOR ASSESSMENT (SUMMARY): Transport, and Information and Communication Technology - Air Transport 1 Air Transport Connectivity Enhancement Project (RRP BHU 44239-013) SECTOR ASSESSMENT (SUMMARY): Transport, and Information and Communication Technology - Air Transport 1 Sector Road Map 1. Sector Performance,

More information

Planned Procurement Opportunities Report. January 2019

Planned Procurement Opportunities Report. January 2019 HILLSBOROUGH COUNTY AVIATION AUTHORITY Planned Procurement Opportunities Report Prepared by the Procurement Department Overview The Planned Procurement Opportunities Report is updated and posted on the

More information

RAILWAY RECRUITMENT BOARD (RRB) EXAM - QUESTION PAPER SOLVED

RAILWAY RECRUITMENT BOARD (RRB) EXAM - QUESTION PAPER SOLVED RAILWAY RECRUITMENT BOARD (RRB) EXAM - QUESTION PAPER SOLVED 1. When was the first underground railway (Metro Railway) started? (a) 1982 (b) 1989 (c) 1984 (d) 1992 2. Shatabdi Express train was started

More information

Agenda Item 6-ATM Coordination - Airspace restructuring COLLABORATIVE AIRSPACE DESIGN AND MANAGEMENT. (Presented by Airports Authority of India)

Agenda Item 6-ATM Coordination - Airspace restructuring COLLABORATIVE AIRSPACE DESIGN AND MANAGEMENT. (Presented by Airports Authority of India) BOBASIO/6 IP/02 The Sixth ATS Coordination meeting of Bay of Bengal, Arabian Sea and Indian Ocean Region (BOBASIO/6) Eden Island, Seychelles, 2 nd November -4 th November 2016. Agenda Item 6-ATM Coordination

More information

GMR Infrastructure Limited, Q1-FY 11 Performance Highlights. Financial Highlights for Q (Rs. Cr.)

GMR Infrastructure Limited, Q1-FY 11 Performance Highlights. Financial Highlights for Q (Rs. Cr.) Press release Bangalore, 08 th Aug, 2010 GMR Infrastructure Limited, Q1-FY 11 Performance Highlights Financial Highlights for Q1 2010-11 (Rs. Cr.) Particulars 30th June 10 30th June 09 % change 31st March

More information

Railway Recruitment Board (RRB) Exam - Question Paper Solved

Railway Recruitment Board (RRB) Exam - Question Paper Solved Railway Recruitment Board (RRB) Exam - Question Paper Solved 1. When was the first underground railway (Metro Railway) started? (a) 1982 (b) 1989 (c) 1984 (d) 1992 2. Shatabdi Express train was started

More information

TO BE INTRODUCED IN LOK SABHA. Bill No. 93 of 2006

TO BE INTRODUCED IN LOK SABHA. Bill No. 93 of 2006 TO BE INTRODUCED IN LOK SABHA Bill No. 93 of 2006 THE NATIONAL WATERWAY (KAKINADA-PONDICHERRY STRETCH OF CANALS AND THE KALUVELLY TANK, BHADRACHALAM- RAJAHMUNDRY STRETCH OF RIVER GODAVARI AND WAZIRABAD-VIJAYAWADA

More information

DETAIL NOTE ON PROJECT

DETAIL NOTE ON PROJECT DETAIL NOTE ON PROJECT BRIEF DETAIL OF 400kv D/C OPGC JHARSUGUDA (SUNDARGARH) TRANSMISSION LINE BEING CONSTRUCTED BY ODISHA GENERATION PHASE II TRANSMISSION LIMITED (OGPTL) The government of India has

More information

PAWAN HANS HELICOPTERS LTD. Bank Payments To Suppliers

PAWAN HANS HELICOPTERS LTD. Bank Payments To Suppliers PAWAN HANS HELICOPTERS LTD. Bank Payments To Suppliers Location : Northern Region Payments for the period : 01/11/2009 to 30/11/2009 done through State Bank of India PARLIAMENT STREET SL Voucher No Narration