1 Chapter One PROJECT DESCRIPTION Environmental Impact Report Monterey Peninsula Airport 1.1 INTRODUCTION This Environmental Impact Report (EIR) analyzes and documents the potential environmental impacts resulting from proposed runway safety improvements at Monterey Peninsula Airport. The Lead Agency for this EIR, the Monterey Peninsula Airport District (MPAD), determined that the preparation of an EIR is warranted due to the presence of numerous environmental resources within the airport environs. The EIR process, as defined by the California Environmental Quality Act (CEQA) of 1970, as amended, requires the preparation of an objective, full-disclosure document to: Inform agency decision-makers and the general public of the potential direct and indirect environmental effects of a proposed action. Identify alternatives to the proposed project to reduce or lessen environmental impacts. Identify mitigation measures to reduce or eliminate any identified significant impacts. The MPAD has prepared this EIR to address the potential environmental impacts associated with proposed runway safety improvements at Monterey Peninsula Airport. In conformance with CEQA, this EIR addresses the potential individual and cumulative impacts of the proposed project. MPAD, as the lead agency, will review and consider the EIR in its decision to approve, revise, or deny the project. The MPAD was created in 1936 and is not incorporated into a city or the county, nor is it a public utility. The Airport District includes portions of Monterey, Pacific Grove, Del Monte Forest, Pebble Beach, Carmel-by-the-Sea, greater Carmel, Del Rey Oaks, Seaside, Sand City, the Monterey-Salinas Highway to Laureles Grade, and the west end of Carmel Valley. The District is governed by five publicly elected members to form a Board of Directors. 1-1

2 1.2 PROJECT LOCATION Monterey Peninsula Airport is a commercial service aviation facility located in the Monterey Bay Area approximately three miles east/southeast of downtown Monterey. The airport is located in Monterey County, approximately 100 miles south of San Francisco. Figure 1A depicts the airport in its regional setting. Figure 1B depicts the portions of the airport that are impacted by the proposed improvements. As discussed within the previous section, the airport is not incorporated into a city or a county, nor is it a public utility. The airport is bounded by the cities of Monterey and Del Rey Oaks as well as Monterey County. 1.3 PROJECT BACKGROUND The Federal Aviation Administration (FAA) has established design standards to ensure the safety, economy, efficiency, and longevity of an airport. These standards include criteria for runway safety areas (RSAs), which are defined as the surface surrounding the runway prepared or suitable for reducing the risk of damage to airplanes in the event of an aircraft landing short, landing long, or departing from the runway. Traditional RSAs consist of clear, graded, and grassed surfaces surrounding the perimeter of a runway. In the late 1990s and early 2000s, a series of aircraft accidents highlighted the need for airports to comply with RSA standards. These accidents, such as those in Little Rock, Arkansas and Chicago, Illinois, resulted in the loss of human life which stimulated the passage of H.R.3058, Transportation, Treasury, Housing and Urban Development, the Judiciary, the District of Columbia, and Independent Agencies Appropriations Act, 2006 which states: That not later than December 31, 2015, the owner or operator of an airport certificated under 49 United States Code (U.S.C.) shall improve the airport's runway safety areas to comply with the Federal Aviation Administration design standards required by 14 CFR Part 139. As a certificated airport, Monterey Peninsula Airport is required by 14 CFR Part 139 to comply with RSA standards to the fullest extent practicable. In 2007, the Monterey Peninsula Airport undertook an RSA Study in response to H.R and FAA Order , Runway Safety Area Program, which became effective October 1, The objective of the RSA program is to ensure that all RSAs at federally obligated airports conform to standards contained in FAA Advisory Circular (AC) 150/ , Airport Design, to the extent practicable. The purpose of the RSA study for Monterey Peninsula Airport was to first determine if the existing RSAs at the airport met FAA standards, and second, to examine the feasibility of meeting established RSA design standards for any runway end that does not meet FAA standards. The RSA study described the existing conditions regarding the runway safety areas for Runways 10L-28R and 10R-28L, and concluded that Runway 10L-28R meets RSA standards and Runway 10R-28L does not. By FAA standards, Runway 10R-28L requires an RSA that is 500 feet wide and extends 1,000 feet beyond the runway end for departures and 600 feet prior to the landing threshold for arrivals. 1 As depicted on Figure 1C, a limited, non-standard RSA is currently available for arrivals and departures on Runway 10R and for departures on Runway 28L. Arrivals to Runway 28L meet RSA standards due to 1 Refer to Appendix C for a description of the methodology used for defining the Airport Reference Code for Runway 10R-28L based on existing airport activity as well as forecasts prepared by the FAA. 1-2

3

4

5

6 the 1,033-foot displaced threshold. The Runway 28L departure and Runway 10R arrival and departure RSAs do not meet FAA standards. In instances where RSA standards are not met, FAA Order describes a series of alternatives that can be evaluated. As part of the Monterey Peninsula Airport RSA Study, initial alternatives were developed and potentially reasonable solutions intended to meet RSA standards were evaluated. The alternatives developed during the RSA study have since been refined, with input from the FAA, and a preferred development alternative has been selected. 1.4 PROJECT OBJECTIVE The objective of the proposed airport improvements is to enhance safety at Monterey Peninsula Airport by providing an aviation facility that complies with FAA RSA design standards. By law, FAA s highest aviation priority is the safe operation of the airport and the airway system. 2 As previously discussed, Runway 10R-28L does not meet FAA RSA design standards which were developed by the FAA to help protect lives and property, both in the air and on the ground. The need for the RSA improvements is supported by federal law, specifically P.L , Transportation, Treasury, Housing and Urban Development, the Judiciary, the District of Columbia, and Independent Agencies Appropriations Act, The need for the improvements is further supported due to the airport s role within the National Plan of Integrated Airport Systems (NPIAS) as a primary commercial service airport. The airport s designation as a commercial service airport translates to the airport s level of importance within the national aviation system. Forecasts and facility requirements contained within the NPIAS assume that the airport will continue to fulfill this defined role. In order to allow this, the airport needs to be able to accommodate the needs of the aviation community by providing a safe operating environment for all aircraft. 1.5 PROJECT DESCRIPTION The Monterey Peninsula Airport District is proposing improvements to Monterey Peninsula Airport that fully meet FAA RSA design standards. The development concept described in the following paragraphs is based on a refined version of Alternative 5 from the recently completed RSA study and is referred to in this study as the Project. The various components of the proposed development concept are depicted on Figure 1D and briefly described in the following paragraphs. The Project takes into account the various development constraints located beyond the existing runway ends and provides needed RSA while maximizing runway length. Development constraints beyond the existing runway ends include steep slopes off each runway end, numerous federal and state protected plant and animal species, and a Section 4(f) property (the U.S. Navy s Monterey Pines Golf Course) 3. 2 Refer to 49 USC Section 47101(a). 3 Section 4(f) of the Department of Transportation (DOT) Act, which was recodified and renumbered as Section 303(c) of 49 USC, provides that the Secretary of Transportation will not approve any program or project that requires the use of any publicly owned land from a historic site, public parks, recreation areas, or waterfowl and wildlife refuges of national, state, regional, or local importance unless there is no feasible and prudent alternative to the use of such land, and the project includes all possible planning to minimize harm resulting from the use. 1-3

7 Property acquisition in the vicinity of the airport is not feasible due to high acquisition costs. Taking into account these constraints, the sponsor-proposed action minimizes environmental impacts while maximizing the runway/rsa development area through the construction of two retaining walls. Construction of the retaining walls maximizes the runway/rsa development platform. (Locations of the retaining wall on the east end were determined through geotechnical analyses which provided the maximum wall height in this portion of airport property. The retaining wall on the west end of the runway was placed in a location which would allow the RSA improvements to remain on airport property.) As depicted on Figure 1D, improvements on the east end of the runway include the construction of a retaining wall approximately 250 feet beyond the existing Runway 28L end 4. The retaining walls will be staggered due to its height and geologic conditions in the area. Earthen fill will be placed behind the retaining wall to create a level surface that meets RSA slope requirements. A 390-foot engineered materials arresting system (EMAS) bed will be installed at the eastern end of the level surface. This EMAS bed length is considered equivalent to a 1,000-foot RSA when considering the types of aircraft which utilize Monterey Peninsula Airport. In lieu of a traditional graded RSA surface, EMAS has been used at numerous airports across the U.S. that are constrained by development, terrain, rivers, or other environmental features. The resistance provided by the EMAS system slows aircraft and allows them to come to a stop in a shorter distance. The EMAS bed is located 35 feet from the Runway 28L departure point to protect the EMAS bed from jet blast. Additional improvements on the east end of the runway relate to the relocation of the airport access road to the toe of the retaining wall, outside of the RSA. The retaining wall at the east end of the airport will be tiered and vegetated. The relocation of the access road provides added safety benefits as it removes the access road from the RSA and reduces the potential for runway incursions. FAA AC 50/ , Ground Vehicle Operations on Airports, supports the segregation of vehicle and aircraft operations at an airport. Improvements on the west end of the runway also include the construction of a retaining wall, installation of EMAS, and the relocation of the airport s existing access road beyond the RSA. The retaining wall would be of a much smaller scale than the east end retaining wall and would be constructed approximately 180 feet from the existing runway end. The length of the west end retaining wall is approximately 650 feet and will be a vertical structure approximately 20 feet tall. Placement of the retaining wall in this location allows improvements to remain on airport property. The area inside the retaining wall will be graded and filled and will contain the relocated access road as well as the EMAS. The landing threshold for Runway 10R is shifted approximately 425 feet east to allow for the placement of the 390-foot EMAS bed. Two new connector taxiways will provide access from the north and south sides of the airfield to the new runway end. To maintain as much of the existing takeoff and landing lengths as possible, declared distances are used. Figure 1D depicts the resultant runway lengths available for takeoff and landing in each direction. The declared distances reflect the required 600-foot RSA prior to landing as well as the substitution of EMAS for the 1,000-foot departure RSA. Additional information regarding declared distances is contained in 4 It was determined that construction of the retaining wall in this location would balance RSA needs with cost and environmental impact. Pushing the wall further east would dramatically increase the cost of the retaining wall and result in additional impacts to federal and state listed plant species. 1-4

8

9 Chapter Two, Section The alternative Project results in the airport maximizing the remaining runway length while providing an RSA that meets FAA RSA standards. 1.6 PROJECT SETTING As shown on Figure 1A, Monterey Peninsula Airport is located in Monterey County, California, adjacent to the cities of Monterey and Del Rey Oaks. The airport is located approximately 100 miles south of San Francisco, California. The following sections contain a description of the airport features. A description of the airport s environmental setting is contained within Chapter Three. Facilities at the airport can be divided into two distinct categories: airside facilities and landside facilities. Airside facilities include those directly associated with aircraft operations. Landside facilities include those necessary to provide an interface between surface and air transportation, and support aircraft servicing, storage, maintenance, and operational safety. Airside Facilities Airside facilities generally include, but are not limited to, runways, taxiways, connecting taxiways, airfield lighting, and navigational aids. As depicted on Figure 1E, Monterey Peninsula Airport is served by two runways. The primary runway, Runway 10R/28L, is 7,616 feet long and 150 feet wide and constructed of grooved asphalt. This runway is predominantly used by the commercial service and business jet activity at the airport. As stated in the table, Runway 28L has a displaced threshold of 1,000 feet. A displaced threshold is located at a point on the runway, other than the designated beginning of the runway, for landings. The portion of the runway behind the threshold is available for takeoffs in both directions and landings from the opposite direction. The parallel runway, Runway 10L/28R, is 3,513 feet long and 60 feet wide. In addition to the runways, there is also an extensive taxiway system to provide access to the various facilities at the airport. Table 1A summarizes the basic runway data for Monterey Peninsula Airport. Landside Facilities Landside facilities are essential to the daily operation of the airport and consist primarily of those facilities required to accommodate aircraft, pilots, and passengers while they are at the airport. Landside facilities at Monterey Peninsula Airport are depicted on Figure 1E. The airport terminal building houses Monterey Peninsula Airport District administrative offices and services for commercial airline service passengers. Passenger facilities include airline ticketing desks, baggage return area, rental car agents, a full service restaurant, departure area café and a gift shop. 1-5

10 TABLE 1A Runway Data Monterey Peninsula Airport Length (feet) Width (feet) Surface Material Pavement Strength (lbs.) Single Wheel Double Wheel Double Tandem Approach Aids EXISTING RUNWAYS 10R 28L 10L 28R 7,616 3, Asphalt, Grooved Asphalt 100, , ,000 12,500 N/A N/A VASI REIL None None MALSR PAPI Instrument Approach Procedures ILS/DME LOC/DME None None Displaced Threshold (feet) 0 1, Fixed Wing Aircraft Traffic Pattern Left Right Left Right MALSR Medium Intensity Approach Light System with Runway Alignment Indicator Lights PAPI Precision Approach Path Indicator VASI Visual Approach Slope Indicator Lights REIL Runway End Identifier Lights Source: Airport/Facility Directory, U.S. Department of Transportation, December 2009 Three fixed base operators (FBOs), each providing a wide range of aviation-related services are located at Monterey Peninsula Airport. The current FBOs include Del Monte and Monterey Jet Center, located west of the terminal building, and Monterey Bay Aviation, located on the north side of the airport. Fuel, avionics repair, aircraft maintenance, flight instruction, aircraft rental, and aircraft parking services are available from these tenants. Additionally, the airport has an airport rescue and firefighting (ARFF) station located on-site to provide fire suppression services in case of an emergency. 1.7 REQUIRED APPROVALS The following agencies will issue approvals and/or clearances for the proposed airport development projects. Monterey Peninsula Airport District. As the lead agency under CEQA, the Monterey Peninsula Airport District will certify the EIR. Federal Aviation Administration. The FAA will provide the following: clearance through under the National Environmental Policy Act of 1969 and grant funding through the Airport Improvement Program (AIP). U.S. Fish and Wildlife Service (USFWS). USFWS will assist with Federal Endangered Species Act Compliance and compliance with the requirements of the Migratory Bird Treaty Act during construction. California Department of Fish and Game (CDFG). CDFG will oversee California Endangered Species Act Compliance. California Department of Transportation (CalTRANS). CalTRANS will issue an encroachment permit for the access road connection with Highway

11

12 1.8 PROJECT OUTREACH This EIR was conducted parallel to an Environmental Assessment (EA) which was prepared in accordance with the requirements of the National Environmental Policy Act (NEPA) of The FAA was the lead agency for the preparation of the EA and a Finding of No Significant Impact (FONSI) was issued for the EA in August Agency outreach for the EA and EIR began with the submittal of a Notice of Preparation (NOP) to the State Clearinghouse in July Appendix B contains copies of the NOP transmittal materials to the State Clearinghouse and resource agencies. Public outreach for the documents consisted of a series of public workshops and maintenance of a project website. Public workshops were held on December 4, 2008 and June 25, The project website was kept up to date with the uploading of workshop materials and maintenance of a project schedule. Additionally, periodic updates were provided to the Monterey Peninsula Airport Board during the preparation of the EA and EIR. 1-7

CHAPTER 1 INTRODUCTION AND BACKGROUND

CHAPTER 1 INTRODUCTION AND BACKGROUND CHAPTER 1 INTRODUCTION AND BACKGROUND An Environmental Assessment (EA) evaluates the effects of a proposed Federal action on the surrounding environment and is prepared in compliance with the National

More information

II. Purpose and Need. 2.1 Background

II. Purpose and Need. 2.1 Background II. 2.1 Background The Metropolitan Washington Airports Authority is preparing an Environmental Assessment of potential environmental impacts associated with proposed enhancements to the Runway 4-22 and

More information

MASTER PLAN CONCEPT 1 DRAFT

MASTER PLAN CONCEPT 1 DRAFT The Airport Master Plan Update for Dallas Executive Airport has included the development of aviation demand forecasts, an assessment of future facility needs, and the evaluation of airport development

More information

Preliminary Findings of Proposed Alternative

Preliminary Findings of Proposed Alternative Preliminary Findings of Proposed Alternative The attached drawing provides a schematic layout of the proposed alternative that will be discussed on July 27, 2010. A full report will follow and should be

More information

CHAPTER 3 ALTERNATIVES CONSIDERED

CHAPTER 3 ALTERNATIVES CONSIDERED CHAPTER 3 ALTERNATIVES CONSIDERED 3.0 ALTERNATIVES The 2010 Stevensville Airport Master Plan contained five (5) airside development options designed to meet projected demands. Each of the options from

More information

Morristown Municipal Airport Runway 5-23 Rehabilitation Environmental Assessment

Morristown Municipal Airport Runway 5-23 Rehabilitation Environmental Assessment 1.0 INTRODCTION Morristown Municipal Airport (hereinafter referred to as MM or Airport ) is a busy general aviation reliever airport owned by the Town of Morristown and operated by DM AIRPORTS, LTD. (hereinafter

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 10 Preferred Inaugural Airport Concept 10.0 Introduction The Preferred Inaugural Airport Concept for SSA was developed by adding the preferred support/ancillary facilities selected in Section 9

More information

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013

Safety, Infrastructure, and Tenant Improvement Project. Public Hearing Informational Brochure February 26, 2013 New York State Department of Transportation Safety, Infrastructure, and Tenant Improvement Project Public Hearing Informational Brochure February 26, 2013 This DEIS/Draft EA evaluates the potential impacts

More information

Chapter 2 FINDINGS & CONCLUSIONS

Chapter 2 FINDINGS & CONCLUSIONS Chapter 2 FINDINGS & CONCLUSIONS 2.01 GENERAL Dutchess County acquired the airport facility in 1947 by deed from the War Assets Administration. Following the acquisition, several individuals who pursued

More information

DRAFT MASTER PLAN UPDATE

DRAFT MASTER PLAN UPDATE DRAFT MASTER PLAN UPDATE CHAPTER VI: AIRPORT LAYOUT PLAN NARRATIVE DRAFT REPORT APRIL 2017 PREPARED BY: Table of Contents WESTCHESTER COUNTY AIRPORT 6 AIRPORT LAYOUT PLAN NARRATIVE REPORT... 6-1 6.1 AGIS

More information

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES Recurring topics emerged in some of the comments and questions raised by members of the

More information

STAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D

STAFF REPORT. Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan. MEETING DATE: November 19, 2015 AGENDA ITEM: 7D STAFF REPORT SUBJECT: Airport Land Use Plan Consistency Review: Santa Barbara Airport Master Plan MEETING DATE: AGENDA ITEM: 7D STAFF CONTACT: Peter Imhof, Andrew Orfila RECOMMENDATION: Adopt findings

More information

Appendix D August 2001 RUNWAY SAFETY Revised March 2002 AREA DETERMINATION RUNWAY 17-35

Appendix D August 2001 RUNWAY SAFETY Revised March 2002 AREA DETERMINATION RUNWAY 17-35 Appendix D August 2001 RUNWAY SAFETY Revised March 2002 AREA DETERMINATION Master Plan Update RUNWAY 17-35 Hector International Airport SUFFICIENCY ANALYSIS Near the completion of the Master Plan Update

More information

CHAPTER 1 BACKGROUND AND PROPOSED ACTION

CHAPTER 1 BACKGROUND AND PROPOSED ACTION CHAPTER 1 BACKGROUND AND PROPOSED ACTION 1.0 INTRODUCTION An Environmental Assessment (EA) evaluates the effects of a proposed Federal action on the surrounding environment and is prepared in compliance

More information

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3 Airport Master Plan for Brown Field Municipal Airport PAC Meeting #3 Public Meeting #1 > 8/24/17 from 5:30 to 8:00 pm > 41 attendees signed-in > Comments: > EAA area > Environmental constraints > Focus

More information

Appendix F Cultural Resource Consultation

Appendix F Cultural Resource Consultation Appendix F Cultural Resource Consultation FAA Consultation Letter to the California State Historic Preservation Officer Response Letter from the California State Historic Preservation Officer STATE

More information

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Agenda > Introductions > Public Meetings Overview > Working Paper 3 - Facility Requirements > Working Paper 4 - Environmental Baseline

More information

CHAPTER 1: INTRODUCTION

CHAPTER 1: INTRODUCTION CHAPTER 1: INTRODUCTION Purpose and Scope The information presented in this report represents the study findings for the 2016 Ronan Airport Master Plan prepared for the City of Ronan and Lake County, the

More information

FAA Office of Airport Safety and Standards

FAA Office of Airport Safety and Standards FAA Office of Airport Safety and Standards Airport and Runway Safety and Technology Presented to: Pan American Regional Aviation Safety Team (PA-RAST) By: Michael Meyers, Deputy Manager Airport Engineering

More information

Preferred Alternative Summary

Preferred Alternative Summary Tacoma Narrows Airport Master Plan Update Preferred Alternative Summary The Preferred Alternative represents Pierce County s vision for the long-term development of the Tacoma Narrows Airport. This Alternative

More information

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development plans

More information

Update on the Aspen/Pitkin County Airport Improvements

Update on the Aspen/Pitkin County Airport Improvements Update on the Aspen/Pitkin County Airport Improvements and EA Process Public Information Meeting September 10, 2015 Meeting Objectives Explain what has changed since we had our last meeting and how it

More information

Agenda: SASP SAC Meeting 3

Agenda: SASP SAC Meeting 3 Agenda: SASP SAC Meeting 3 Date: 04/12/18 Public Involvement Plan Update Defining the System Recommended Classifications Discussion Break Review current system Outreach what we heard Proposed changes Classification

More information

Chippewa-Eau Claire Metropolitan Planning Area Long Range Transportation Plan

Chippewa-Eau Claire Metropolitan Planning Area Long Range Transportation Plan 1.2.7 2010 Eau Claire County Comprehensive Plan According to Eau Claire County s most recent comprehensive plan, the County will limit land use development adjacent to EAU in order to preserve the ability

More information

Alternatives. Introduction. Range of Alternatives

Alternatives. Introduction. Range of Alternatives Alternatives Introduction Federal environmental regulations concerning the environmental review process require that all reasonable alternatives, which might accomplish the objectives of a proposed project,

More information

CHAPTER 2.0 ALTERNATIVES

CHAPTER 2.0 ALTERNATIVES CHAPTER 2.0 ALTERNATIVES 2.1 INTRODUCTION 2.1.1 SCOPE OF THE ALTERNATIVES ANALYSIS This chapter summarizes the screening analysis conducted to identify the range of reasonable and practicable alternatives

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 3 - Refinement of the Ultimate Airfield Concept Using the Base Concept identified in Section 2, IDOT re-examined

More information

Lake Tahoe Airport Master Plan

Lake Tahoe Airport Master Plan Lake Tahoe Airport Master Plan City Council Briefing October 20, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development

More information

SAN FRANCISCO INTERNATIONAL AIRPORT

SAN FRANCISCO INTERNATIONAL AIRPORT 1 SAN FRANCISCO INTERNATIONAL AIRPORT Runway Safety Area Program ACI-NA Operations and Technical Affairs Conference April 7, 2011 RSA Status Completed RSA Studies Environmental Assessment ongoing and on

More information

Addendum - Airport Development Alternatives (Chapter 6)

Addendum - Airport Development Alternatives (Chapter 6) Bowers Field Addendum - Airport Development Alternatives (Chapter 6) This addendum to the Airport Development Alternatives chapter includes the preferred airside development alternative and the preliminary

More information

Introduction DRAFT March 9, 2017

Introduction DRAFT March 9, 2017 Chapter Overview The City of Redmond (City) initiated an update to the Airport Master Plan ( Plan ) to assess the facility and service needs of the Redmond Municipal Airport ( the Airport ) throughout

More information

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014 DRAFT FINAL REPORT AIRPORT MASTER PLAN Rifle Garfield County Airport Revised May 15, 2014 As required by Paragraph 425.B(4) of FAA Order 5100.38C, Airport Improvement Program (AIP) Handbook: The preparation

More information

For Airport Environmental Services. Date Released: August 27, 2018 Deadline for Submission: 5:00pm, September 17, 2018

For Airport Environmental Services. Date Released: August 27, 2018 Deadline for Submission: 5:00pm, September 17, 2018 COUNTY OF INYO REQUEST FOR QUALIFICATIONS For Airport Environmental Services Date Released: August 27, 2018 Deadline for Submission: 5:00pm, September 17, 2018 County of Inyo Public Works Department P.O.

More information

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport Executive Summary MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport As a general aviation and commercial service airport, Fort Collins- Loveland Municipal Airport serves as an important niche

More information

CHAPTER TWO THE PROPOSAL

CHAPTER TWO THE PROPOSAL CHAPTER TWO THE PROPOSAL 2.0 AIRPORT SPONSOR S PROPOSED PROJECT The Airport Sponsor s Proposed Project includes the following elements, which are depicted in Exhibit 2-1, Sponsor s Proposed Project: Expand

More information

Airports and UAS: Integrating UAS into Airport Infrastructure and Planning

Airports and UAS: Integrating UAS into Airport Infrastructure and Planning ACRP Problem Statement 17-03-09 Recommended Allocation: $500,000 Airports and UAS: Integrating UAS into Airport Infrastructure and Planning ACRP Staff Comments This is one of four UAS-themed problem statements

More information

CHAPTER FOUR AIRPORT ALTERNATIVES

CHAPTER FOUR AIRPORT ALTERNATIVES 4.0 INTRODUCTION CHAPTER FOUR The goal of the master planning process is to provide the City of New Smyrna Beach with an assessment of the adequacy and capabilities of the Airport as well as to identify

More information

Morristown Municipal Airport Runway 5-23 Rehabilitation Environmental Assessment

Morristown Municipal Airport Runway 5-23 Rehabilitation Environmental Assessment 2.0 PURPOSE AND NEED The Purpose and Need Statement in a NEPA document is a formal declaration of the overall goals and objectives of a proposed project. This statement documents the justification for

More information

CHAPTER 1 EXECUTIVE SUMMARY

CHAPTER 1 EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY 1 1 EXECUTIVE SUMMARY INTRODUCTION William R. Fairchild International Airport (CLM) is located approximately three miles west of the city of Port Angeles, Washington. The airport

More information

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005

Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Draft Concept Alternatives Analysis for the Inaugural Airport Program September 2005 Section 1 - Introduction This report describes the development and analysis of concept alternatives that would accommodate

More information

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update

Appendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update Appendix D Project Newsletters Tacoma Narrows Airport Master Plan Update This appendix contains the newsletters distributed throughout the project. These newsletters provided updates and information on

More information

Chapter Six ALP Drawings. Tacoma Narrows Airport. Master Plan Update

Chapter Six ALP Drawings. Tacoma Narrows Airport. Master Plan Update Chapter Six ALP Drawings Master Plan Update The master planning process for the (Airport) has evolved through efforts in the previous chapters to analyze future aviation demand, establish airside and landside

More information

Merritt Island Airport

Merritt Island Airport TABLE OF CONTENTS CHAPTER 1 INTRODUCTION... 1-1 INTRODUCTION AND PROJECT OVERVIEW... 1-1 General Guidelines... 1-1 Prior Planning Documentation... 1-2 Key Issues... 1-2 Goals and Objectives... 1-2 Regulatory

More information

Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES

Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES Chapter 4 AIRPORT DEVELOPMENT ALTERNATIVES Chapter Four Airport Development Alternatives Prior to formulating a development program for Ryan Airfield, it is important to consider development potential

More information

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906

Prepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906 Master Plan The preparation of this document was financed in part through a planning grant from the Federal Aviation Administration (FAA) as provided under Section 505 of the Airport and Airway Improvement

More information

Dallas Executive Airport

Dallas Executive Airport 648 DECLARED DISTANCE OPTION 1a DISPLACE 31 THRESHOLD BY 97 Considers RSA Limiting Factor No runway extensions 13 31 TORA 6,451 6,451 TODA 6,451 6,451 ASDA 5,958 6,451 LDA 5,958 6,354 Runway 17-35 (3,8

More information

Session Best Practices Amendments From Annex14, Volume I Annex 15. Runway Incursions Runway Excursions

Session Best Practices Amendments From Annex14, Volume I Annex 15. Runway Incursions Runway Excursions Session Best Practices Amendments From Annex14, Volume I Annex 15 Runway Incursions Runway Excursions Annex 15 AIP - Member States Report: Installation of ARRESTOR SYSTEMS Location - Runway End Industry

More information

Executive Summary This document contains the Master Plan for T. F. Green Airport. The goal of a master plan is to provide a framework of potential future airport development in a financially feasible manner,

More information

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved TABLE OF CONTENTS Description Page Number LIST OF ACRONYMS... a CHAPTER ONE INTRODUCTION General... 1-1 Study Objectives... 1-1 Public Involvement... 1-2 Issues to Be Resolved... 1-2 CHAPTER TWO EXISTING

More information

MEETING MINUTES Page 1 of 5

MEETING MINUTES   Page 1 of 5 Page 1 of 5 50178.000 May 26, 2009 PROJECT PROJECT NO. MEETING DATE ISSUE DATE Citizens Advisory Committee Meeting MEETING LOCATION MEETING PURPOSE Amy Eckland ISSUED BY SIGNATURE PARTICIPANT See attached

More information

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257 Form PDES 8 THE CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257 Summary of Duties: A Senior Airport Engineer performs the more difficult and

More information

JANUARY 2013 Friedman Memorial Airport Pomeroy, Chris

JANUARY 2013 Friedman Memorial Airport Pomeroy, Chris JANUARY 2013 Friedman Memorial Airport Pomeroy, Chris Friedman Memorial Airport / T-O Engineers Airport Alternatives Technical Analysis Table of Contents 1.0 Background and Purpose of Analysis... 1 1.1

More information

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include:

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include: 4.1 INTRODUCTION The previous chapters have described the existing facilities and provided planning guidelines as well as a forecast of demand for aviation activity at North Perry Airport. The demand/capacity

More information

Table of Contents. Overview Objectives Key Issues Process...1-3

Table of Contents. Overview Objectives Key Issues Process...1-3 Table of Contents Chapter One Introduction Overview...1-1 Objectives...1-1 Key Issues...1-2 Process...1-3 Chapter Two Inventory of Existing Conditions Airport Setting...2-1 Locale...2-1 Airport Surroundings...2-5

More information

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES INTRODUCTION An Airport Master Plan provides an evalua on of the airport s avia on demand and an overview of the systema c airport development that will best meet those demands. The Master Plan establishes

More information

COMMERCIAL AND GENERAL AVIATION

COMMERCIAL AND GENERAL AVIATION Existing Facilities Daytona Beach International Airport is served by a number of airside and landside facilities. The airport has three asphalt runways: Runway 07L/25R (10,500 feet long by 150 feet wide),

More information

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201

More information

1. Background and Proposed Action

1. Background and Proposed Action 1. Background and Proposed Action This chapter describes Hillsboro Airport and the planning background for the proposed project. The Port of Portland (the Port) is the sponsor for the Hillsboro Airport

More information

New Opportunities PUBLIC WORKSHOP. Venice Municipal. Bringing g the pieces together

New Opportunities PUBLIC WORKSHOP. Venice Municipal. Bringing g the pieces together Bringing g the PUBLIC WORKSHOP Venice Municipal Airport New Opportunities Presented for Venice City Council & Citizens of Venice September 25, 2009 Slide 1 Bringing g the Welcome & Introductions May 12th

More information

Source: Chippewa Valley Regional Airport ASOS, Period of Record

Source: Chippewa Valley Regional Airport ASOS, Period of Record Chapter 1 Inventory Runway wind coverage is the percentage of time a runway can be used without exceeding allowable crosswind velocities. Allowable crosswind velocities vary depending on aircraft size

More information

Summary of Committee Discussion/Questions Metropolitan Transportation Services Senior Planner Russ Owen presented this item.

Summary of Committee Discussion/Questions Metropolitan Transportation Services Senior Planner Russ Owen presented this item. Committee Report Business Item No. 2017-191 Transportation Committee For the Metropolitan Council meeting of September 13, 2017 Subject: Final Crystal Airport 2035 Long Term Comprehensive Plan (LTCP) Proposed

More information

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal Airport Master Plan Rapid City Regional Airport October 2015 FAA Submittal Rapid City Regional Airport Master Plan Update Table of Contents Executive Summary... i Scope & Timeline... i Forecasts... i Preferred

More information

Pierre Regional Airport Airport Master Plan. Kickoff Meeting April 7, 2017

Pierre Regional Airport Airport Master Plan. Kickoff Meeting April 7, 2017 Pierre Regional Airport Airport Master Plan Kickoff Meeting April 7, 2017 Agenda Introductions Airport Master Planning Planning Considerations Master Plan Elements Schedule Public Involvement Basics about

More information

FORECASTING FUTURE ACTIVITY

FORECASTING FUTURE ACTIVITY EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver

More information

FACILITY REQUIREMENTS SUMMARY OF KEY ISSUES OVERVIEW

FACILITY REQUIREMENTS SUMMARY OF KEY ISSUES OVERVIEW FACILITY REQUIREMENTS SUMMARY OF KEY ISSUES OVERVIEW This summary is intended to provide a brief overview of the key issues associated with conformance to FAA standards at Methow Valley State Airport.

More information

Appendix C AIRPORT LAYOUT PLANS

Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Appendix C AIRPORT LAYOUT PLANS Airport Master Plan Santa Barbara Airport As part of this Airport Master Plan, the Federal Aviation Administration (FAA) requires the development

More information

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017 Lopez Island Airport Master Plan Update Public Meeting June 15, 2017 Master Plan Update Team Reid Middleton/Everett, WA Shannon Kinsella, Project Manager Melania Haagsma, Project Engineer Mead & Hunt/Tulsa,

More information

Chapter 8.0 Implementation Plan

Chapter 8.0 Implementation Plan Chapter 8.0 Implementation Plan 8.1 Introduction This chapter is the culmination of the analytical work accomplished in the previous chapters. The result is a prioritized list of the essential projects.

More information

Hartford-Brainard Airport Potential Runway Closure White Paper

Hartford-Brainard Airport Potential Runway Closure White Paper Hartford-Brainard Airport Potential Runway 11-29 Closure White Paper June 2012 In recent years there has been discussion regarding the necessity of Runway 11-29 to the Hartford- Brainard Airport (HFD)

More information

Chapter 9 - AIRPORT SYSTEM DESIGN

Chapter 9 - AIRPORT SYSTEM DESIGN Chapter 9 - AIRPORT SYSTEM DESIGN 9.01 GENERAL This chapter discusses the development program for Dutchess County Airport to the year 2020. This airport system design is based upon the airport's existing

More information

JOHNSTON COUNTY AIRPORT AUTHORITY

JOHNSTON COUNTY AIRPORT AUTHORITY JOHNSTON COUNTY AIRPORT AUTHORITY REQUEST FOR QUALIFICATIONS FOR AIRPORT PLANNING SERVICES For JOHNSTON REGIONAL AIRPORT (JNX) 3149 Swift Creek Rd. Smithfield, NC 27577 PHIL LANIER AIRPORT DIRECTOR (919)

More information

1 PURPOSE AND NEED 1.1 INTRODUCTION

1 PURPOSE AND NEED 1.1 INTRODUCTION 1.1 INTRODUCTION 1 PURPOSE AND NEED This Environmental Assessment (EA) addresses projects at Juneau International Airport (JIA) that are the direct outcome of a Master Plan prepared for the airport and

More information

LOS ANGELES INTERNATIONAL AIRPORT MAY 2014

LOS ANGELES INTERNATIONAL AIRPORT MAY 2014 1. Purpose and Need 1.1 Introduction The City of Los Angeles, through its aviation department, Los Angeles World Airports (LAWA), proposes to construct improvements to the Runway Safety Area (RSA) for

More information

General Aviation Master Plan Update

General Aviation Master Plan Update Peter O. Knight Airport Public Meeting #2 Peter O. Knight Airport Agenda Welcome and Introductions HCAA System of Airports Purpose of Public Meetings Master Plan Status Update Next Steps Q & A 2 Our System

More information

6.1 INTRODUCTION 6.2 AIRSIDE ALTERNATIVES NORTH PERRY AIRPORT MASTER PLAN UPDATE RUNWAY LENGTH REQUIREMENTS SECTION 6: ALTERNATIVES ANALYSIS

6.1 INTRODUCTION 6.2 AIRSIDE ALTERNATIVES NORTH PERRY AIRPORT MASTER PLAN UPDATE RUNWAY LENGTH REQUIREMENTS SECTION 6: ALTERNATIVES ANALYSIS 6.1 INTRODUCTION In the previous chapter, facility needs for the 20-year planning horizon were identified. The next step in the planning process is to identify and evaluate the various ways certain facilities

More information

Yakima Air Terminal/McAllister Field Airport Master Plan Update

Yakima Air Terminal/McAllister Field Airport Master Plan Update Yakima Air Terminal/McAllister Field Airport Master Plan Update City of Yakima Work Session July 9, 2013 Meeting Goals Summarize the master plan recommendations. Discuss the decision-making process used

More information

CHAPTER 5 - FACILITY REQUIREMENTS

CHAPTER 5 - FACILITY REQUIREMENTS CHAPTER 5 - FACILITY REQUIREMENTS This chapter identifies the requirements for airfield and landside facilities to accommodate the forecast demand level. Facility requirements have been developed for the

More information

Runway Length Analysis Prescott Municipal Airport

Runway Length Analysis Prescott Municipal Airport APPENDIX 2 Runway Length Analysis Prescott Municipal Airport May 11, 2009 Version 2 (draft) Table of Contents Introduction... 1-1 Section 1 Purpose & Need... 1-2 Section 2 Design Standards...1-3 Section

More information

Yolo County Airport. ALP Narrative Report. April Prepared by Mead & Hunt, Inc. for the County of Yolo, California

Yolo County Airport. ALP Narrative Report. April Prepared by Mead & Hunt, Inc. for the County of Yolo, California Yolo County Airport ALP Narrative Report April 2016 Prepared by Mead & Hunt, Inc. for the County of Yolo, California Yolo County Airport ALP Narrative Report Prepared for the County of Yolo Mindi Nunes,

More information

Punta Gorda Airport Master Plan Update

Punta Gorda Airport Master Plan Update Punta Gorda Airport Master Plan Update Draft Executive Summary Prepared for: The Charlotte County Airport Authority January 2018 Charlotte County Airport Authority James Herston, Chair Robert D. Hancik,

More information

COMMERCIAL AND GENERAL AVIATION Historic and forecast FDOT aviation activity information on file for Pensacola Regional Airport:

COMMERCIAL AND GENERAL AVIATION Historic and forecast FDOT aviation activity information on file for Pensacola Regional Airport: Existing Facilities Pensacola Regional Airport is served by a number of airside and landside facilities. Two intersecting, grooved asphalt runways serve the airport. These runways are runway 17/35 (7,004

More information

ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS

ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS EXECUTIVE SUMMARY ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS PAGE NO. CHAPTER 1-INTRODUCTION... 1-1 1.01 General...1-1 1.02 Purpose and Scope of Study...1-1 1.03 The Planning Process...1-2

More information

TECHNICAL REPORT #7 Palm Beach International Airport Airport Layout Plan

TECHNICAL REPORT #7 Palm Beach International Airport Airport Layout Plan TECHNICAL REPORT #7 Palm Beach International Airport Airport Layout Plan Technical Report #7 Palm Beach International Airport Layout Plan Palm Beach International Airport Prepared for Palm Beach County

More information

Billy Bishop Toronto City Airport; Porter Airlines Proposal Review; Interim Results/Findings, Airbiz, 26 June 2013

Billy Bishop Toronto City Airport; Porter Airlines Proposal Review; Interim Results/Findings, Airbiz, 26 June 2013 Billy Bishop Toronto City Airport - Outstanding Questions for Transport Canada EXECUTIVE SUMMARY Transport Action has reviewed the reports published by Airbiz and LPS Avia Consulting and found that they

More information

AIRPORT LAYOUT PLAN FOR FRIEDMAN MEMORIAL REPLACEMENT AIRPORT - SITE 12 FRIEDMAN MEMORIAL AIRPORT AUTHORITY INDEX OF SHEETS SHEET TITLE

AIRPORT LAYOUT PLAN FOR FRIEDMAN MEMORIAL REPLACEMENT AIRPORT - SITE 12 FRIEDMAN MEMORIAL AIRPORT AUTHORITY INDEX OF SHEETS SHEET TITLE GOODING MUNICIPAL SOURCE: JeppView 3.6.3.1 (Printed May 19, 2010) MAGIC VALLEY REGIONAL BURLEY MUNICIPAL LOCATION MAP NTS - SITE 12 AIRPORT LAYOUT PLAN FOR FRIEDMAN MEMORIAL REPLACEMENT AIRPORT - SITE

More information

National Transportation Safety Board Washington, D.C

National Transportation Safety Board Washington, D.C E PLURIBUS UNUM NATIONAL TRA SAFE T Y N S PORTATION B OAR D National Transportation Safety Board Washington, D.C. 20594 Safety Recommendation Date: June 25, 2004 In reply refer to: A-04-48 through -50

More information

2015 PURDUE ROAD SCHOOL March 11, 2015

2015 PURDUE ROAD SCHOOL March 11, 2015 2015 PURDUE ROAD SCHOOL March 11, 2015 Runway Protection Zone (RPZ) Definition It is a trapezoidal shape formed off the end of a runway and its geometry it a function of the airport s aircraft approach

More information

Office of Airports. Overview of the FAA s. Federal Aviation Administration ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN

Office of Airports. Overview of the FAA s. Federal Aviation Administration ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN Overview of the FAA s Office of Airports Prepared for: Presented by: 2016 ACI-NA/AAAE Airport Board & Commissioners Conference Indianapolis, IN Eduardo Angeles Associate Administrator for Airports Date:

More information

GENERAL INSTRUCTIONS REQUEST FOR STATEMENTS OF QUALIFICATIONS (RFQ) ON-CALL AVIATION ENGINEERING SERVICES

GENERAL INSTRUCTIONS REQUEST FOR STATEMENTS OF QUALIFICATIONS (RFQ) ON-CALL AVIATION ENGINEERING SERVICES GENERAL INSTRUCTIONS REQUEST FOR STATEMENTS OF QUALIFICATIONS (RFQ) ON-CALL AVIATION ENGINEERING SERVICES The County of Montrose, Colorado is accepting Statements of Qualifications from qualified firms

More information

GENERAL INSTRUCTIONS REQUEST FOR STATEMENTS OF QUALIFICATIONS ON-CALL AVIATION PLANNING SERVICES

GENERAL INSTRUCTIONS REQUEST FOR STATEMENTS OF QUALIFICATIONS ON-CALL AVIATION PLANNING SERVICES GENERAL INSTRUCTIONS REQUEST FOR STATEMENTS OF QUALIFICATIONS ON-CALL AVIATION PLANNING SERVICES The County of Montrose, Colorado is accepting Statements of Qualifications from qualified firms to provide

More information

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN LAST UPDATE JULY 2013 Acknowledgements The preparation of this document was financed in part by a grant from the Federal Aviation Administration (Project No: 3-27-0000-07-10), with the financial support

More information

Chapter The All-new, World-class Denver International Airport Identify Describe Know Describe Describe

Chapter The All-new, World-class Denver International Airport Identify Describe Know Describe Describe Chapter 10 The aerospace subject is very large and diverse. As seen in previous chapters, there are many subject areas. So far you have learned about history, weather, space and aerodynamics. Now you will

More information

BOARD OF AIRPORT COMMISSIONERS

BOARD OF AIRPORT COMMISSIONERS 1 8/17/2018 8/21/2018 8/16/2018 i ElY MY Y I : JH MT BY...01,, III1*.ji,"1.111Los Angeles World Airports REPORT TO THE BOARD OF AIRPORT COMMISSIONERS Meeting Date: la Approved by: e1. "ampbell, Chief Airports

More information

APPENDIX E AIRFIELD PLANNING, DESIGN, & CONSTRUCTABILITY REVIEW

APPENDIX E AIRFIELD PLANNING, DESIGN, & CONSTRUCTABILITY REVIEW APPENDIX E AIRFIELD PLANNING, DESIGN, & CONSTRUCTABILITY REVIEW The identification, evaluation, and refinement of the airfield development alternatives were subject to a variety of planning, engineering,

More information

Winona Runway Shift Project

Winona Runway Shift Project Winona Runway Shift Project Sandy DePottey Dakota-Minnesota ADO Fall MnDOT FAAWorkshop St Cloud, Minnesota November 5, 2014 Update on 0 0 Challenges we faced The main runway 12/30 at Winona Municipal Airport

More information

Chapter 4 Airport Facility Requirements

Chapter 4 Airport Facility Requirements Chapter 4 Airport Facility Requirements Introduction CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-1 Organization of Materials CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-2 RPZ - ROAD RPZ - NON-AIRPORT

More information

AIRSIDE CAPACITY AND FACILITY REQUIREMENTS

AIRSIDE CAPACITY AND FACILITY REQUIREMENTS AIRSIDE CAPACITY AND FACILITY REQUIREMENTS This Section investigates the capacity of the airport, its ability to meet current demand, and the facilities required to meet forecasted needs as established

More information

Appendix 6.1: Hazard Worksheet

Appendix 6.1: Hazard Worksheet Appendix 6.1: Appendix 6.1: Ref. Condition, real or potential; that can cause injury, illness, etc. This is a prerequisite for an Airfield Hazards 1. Taxiway Geometry Direct access to runway from ramp

More information

TANZANIA CIVIL AVIATION AUTHORITY AIR NAVIGATION SERVICES INSPECTORATE. Title: CONSTRUCTION OF VISUAL AND INSTRUMENT FLIGHT PROCEDURES

TANZANIA CIVIL AVIATION AUTHORITY AIR NAVIGATION SERVICES INSPECTORATE. Title: CONSTRUCTION OF VISUAL AND INSTRUMENT FLIGHT PROCEDURES Page 1 of 8 1. PURPOSE 1.1. This Advisory Circular provides guidance to personnel involved in construction of instrument and visual flight procedures for publication in the Aeronautical Information Publication.

More information

Reliever Airports: NOISE ABATEMENT PLAN Flying Cloud Airport (FCM)

Reliever Airports: NOISE ABATEMENT PLAN Flying Cloud Airport (FCM) Reliever Airports: NOISE ABATEMENT PLAN Flying Cloud Airport (FCM) INTRODUCTION The Noise Abatement Plan (FCM Plan) for the Flying Cloud Airport has been prepared in recognition of the need to make the

More information