Demand Patterns; Geometric Design of Airfield Prof. Amedeo Odoni

Size: px
Start display at page:

Download "Demand Patterns; Geometric Design of Airfield Prof. Amedeo Odoni"

Transcription

1 Demand Patterns; Geometric Design of Airfield Prof. Amedeo Odoni Istanbul Technical University Air Transportation Management M.Sc. Program Airport Planning and Management Module 4 January 2016

2 Demand Patterns; Geometric Design of Airfield q Objective: Review (a) Airport Demand Patterns and (b) Geometric Design Specifications, as important background to lectures on Airport Planning q Topics: Airport Demand Patterns Variability of demand Some key observations Converting annual forecasts into monthly, daily and hourly ones Geometric Design Specifications ICAO and FAA Reference Codes Practical observations Examples of specifications and their rationale Page 2

3 Outline Airport Demand Patterns Variability of demand Some key observations Converting annual forecasts into monthly, daily and hourly ones q Geometric Design Specifications ICAO and FAA Reference Codes Practical observations Examples of specifications and their rationale Page 3

4 Airport Capacity Management: General Framework q Capacity management refers to the steps that an airport must take in order to offer sufficient capacity to match demand and provide an adequate Level of Service (LOS) q Demand management refers to interventions aimed at modifying demand; such interventions may be necessary if available capacity is not sufficient to ensure adequate LOS q To provide and manage capacity, it is necessary to understand well the characteristics of both demand and capacity on both airside and landside q The issues and the measures of LOS on airside and on landside are quite different Page 4

5 Variability of Airport Demand: Time-of-Day All airports experience time-of-day variability in demand intensity, for a number of reasons: Preference of travelers for certain times of the day (especially true for business travel) Natural times for flying on certain long-haul routes (e.g., most flights from Eastern United States to Europe depart between 4 PM and 11 PM) Curfews (typically due to noise restrictions) At all airports, the composition of demand (arrivals vs. departures, domestic vs. international, short-haul vs. longhaul, business vs. leisure) also varies by time-of-day Page 5

6 Variability of Airport Demand q Significant variability in demand may also exist with respect to: Day of the week (e.g., in the US, Saturday is the lowest day, Sunday is second lowest, while weekdays are similar to one another and have the highest demand) Month and season (e.g., summer vs. winter, high and low months, influence of religious or other holidays) Special events (e.g., sports, expos, etc.) Page 6

7 Outline Airport Demand Patterns Variability of demand Some key observations Converting annual forecasts into monthly, daily and hourly ones q Geometric Design Specifications ICAO and FAA Reference Codes Practical observations Examples of specifications and their rationale Page 7

8 Two Key Observations At mature airports (= those that have been operating for some years and have a relatively stable set of airline customers: Peaking patterns and demand variability at busy airports are typically very consistent from year to year, over periods of many years Flattening of daily and seasonal demand patterns: As annual demand grows, the peaks and valleys of daily demand profiles and seasonal demand profiles become less sharp At a few extremely congested airports (LHR, FRA, LGA) demand profiles are completely flat because of limits imposed by capacity constraints Page 8

9 Daily Demand Profile: Newark Aircraft Movements Page 9

10 Daily Demand Profile: Newark Aircraft Movements (% of Daily Movements) Page 10

11 Stability of Monthly Patterns: Total Movements at the 3 New York Airports Page 11

12 Stability of Monthly Patterns: No. of Passengers at NY JFK Page 12

13 Monthly Pax and Movements: Athens, Source: AIA (2012) Page 13

14 IST Total Demand: 2013 vs Peaking factor for the day (2013): 64/1151= or 5.6% For 2011: 65/950= or 6.8% Total: 2011: 950 movts; 2013: 1151 movts (+21%) [LHR=1350] Peak hour: 2011: 65 movts; 2013: 64 movts (-1%)

15 IST Arrivals Demand: 2013 vs Peaking factor for the day (2013): 33/572= or 5.8% 2011: 33/461= or 7.2% Totals: 2011: 461 arrs; 2013: 572 arrs (+24%) Peak hour: 2011: 33 arrs; 2013: 33 arrs (0%)

16 IST Departures Demand: 2013 vs Peaking factor for the day (2013): 36/579= or 6.2% 2011: 42/489= or 8.6% Totals: 2011: 489 deps; 2013: 579 deps (+18%) Peak hour: 2011: 42 deps; 2013: 36 deps (-14%)

17 Athens: Pax in Peak Hours of the Year as % of Annual Pax Source: AIA (2012) Page 17

18 Another Observation Business passenger trips least variability over a year International personal leisure trips highest variability Domestic less variable than international Example: New York s Airports, 2011 Airport Monthly Peaking* Passengers Monthly Peaking* Movements LaGuardia [high business] Newark [mostly domestic] JFK International [mostly intern l] *Monthly peaking = (Average no. per day during peak month)/ Average no. per day during entire year) Question: Why is peaking of passengers sharper than peaking of movements? Page 18

19 Outline Airport Demand Patterns Variability of demand Some key observations Converting annual forecasts into monthly, daily and hourly ones Geometric Design Specifications ICAO and FAA Reference Codes Practical observations Examples of specifications and their rationale Page 19

20 Converting Annual Forecasts Typically airport demand forecasts provide estimates of future annual number of passengers and annual number of movements For airport planning, design and management purposes, it is necessary to convert these annual forecasts into forecasts of Peak monthly demand Peak daily demand Peak hourly demand This can be done by developing conversion coefficients using historical data and our two key observations. [See Reference 2 for details.] Page 20

21 Converting Annual Forecasts [2] The value of the conversion coefficients depends on many things, such as: Overall size of demand Seasonality of traffic Peakiness of daily traffic Presence or absence of curfew hours Geographical location and time zone of airport One must also exercise judgment about potential changes in peaking as demand increases and circumstances change Page 21

22 Example: VERY ROUGH Calculation q Peak hour departing passengers when the New Airport will be handling 100 million passengers per year: 50 million x (1/365) x (1.19) x = 10,107 10,000 dep pax 1.19 = hypothetical peaking factor for 30 th busiest day (based on 2013 data for IST) = hypothetical daily peaking factor (based on 2013 data for IST) q The conversion coefficient in this example is: (1/365) x (1.19) x = [or %] Note: Total passengers in a peak day for a 100 million airport will exceed 300,000! [100 million x (1/365) x (1.19) = 326,000] Page 22

23 Detailed Records q Airport operators should Collect and maintain detailed historical records of operations Perform statistical analyses with the data Perform data mining to identify significant patterns and trends q Large databases developed by air navigation service providers (ANSP) and airlines are becoming increasingly common often available to airport operators and sometimes to researchers or the general public Page 23

24 References 1. de Neufville, R. and A. Odoni (2013) Airport Systems: Planning, Design and Management, 2 nd Edition, McGraw-Hill Education. [Chapter 21] 2. ACRP, Airport Cooperative Research Program (2012), Guidelines for Preparing Peak Period and Operational Profiles, Guidebook Report 03-12, prepared by HNTB in association with Oliver Wyman & TransSolutions, LLC., Transportation Research Board, Washington, DC. Page 24

25 Outline Airport Demand Patterns Variability of demand Some key observations Converting annual forecasts into monthly, daily and hourly ones q Geometric Design Specifications ICAO and FAA Reference Codes Practical observations Examples of specifications and their rationale Page 25

26 Airfield Design Specifications The two most-commonly used sources of geometric specifications for airfield design are: 1. ICAO Annex 14 ( Aerodromes ) [latest 2013, 6 th Edition] and many associated documents, esp. Aerodrome Design Manual, Parts FAA Advisory Circular 150/ ( Airport Design ) [latest: Sept. 2012] FAA updates of specifications are usually developed earlier than updates to ICAO Annex 14 (e.g., Group VI standards) Runway length requirements: AC 150/5325-4B Reference: de Neufville and Odoni, Ch. 9, Secs. 2- Page 26 3, 5-9

27 ICAO Aerodrome Reference Code Page 27

28 FAA Runway Design Code (RDC) Aircraft Approach Category (AAC) Approach Speed (AS) A: < 91 knots B: 91 <121 knots C: 121 <141 knots D: 141 <166 knots E: 166+ knots Airplane Design Group (ADG) Wingspan (WS) Tail Height (TH) I: < 49 ft <20 ft <15 m <6 m II: 49 <79 ft 20 <30 ft 15 <24 m 6 <9 m III: 79 <118 ft 30 <45 ft 24 <36 m 9 <13.5 m IV: 118 <171 ft 45 <60 ft 36 <52 m 13.5 <18.5 m V: 171 <214 ft 60 <66 ft 52 <65 m 18.5 <20 m VI: 214 <262 ft 66 <80 ft 65 <80 m 20 <24.5 m Page 28

29 A380 vs. B (79.8 m) (72.2 m) (24.1 m) (64.4 m) (70.6 m) (19.4 m) (560 tons) (396 tons) Page 29

30 Airport Reference Code (ARC) Determined by the most demanding aircraft (or design aircraft, or critical aeroplane ) that the airport is designed to serve The design aircraft need NOT be An aircraft which is currently using the airport An existing aircraft (can be a hypothetical future aircraft) Different runways may have different Runway Design Codes (RDC): ARC of entire airport will then be determined by the highest RDC available E.g., if RDC of Runway 1 is 4-E and of Runway 2 4-C, then ARC is 4-E Page 30

31 Outline Airport Demand Patterns Variability of demand Some key observations Converting annual forecasts into monthly, daily and hourly ones Geometric Design Specifications ICAO and FAA Reference Codes Practical observations Examples of specifications and their rationale Page 31

32 Remarks: ICAO and FAA Airport Reference Codes Practically all major commercial airports belong to the ICAO Code #4 class In practice, Outer Main Gear Wheel Span (ICAO) is dominated by Wing Span Similarly, Tail Height (FAA) is dominated by Wing Span ICAO Code Letters A-F Wing Spans correspond exactly to FAA Airplane Design Groups I-VI wingspans Most geometric specifications for airports are determined by the Wing Span of the most demanding aircraft Page 32

33 787-8 A A Page 33

34 Reference Codes of Wide-Body Aircraft Page 34

35 Wide-Body Aircraft: Range vs. Seating Capacity Page 35

36 Examples of Geometric Specifications (ICAO Annex 14) C D E F Runway width Taxiway width Runway centerline to taxiway centerline Runway centerline to holdline Taxiway centerline to taxiway centerline Taxiway centerline to object Taxilane centerline to object Code #4 aircraft; distances are in meters; assumes instrument runway at sea level Page 36

37 Outline Airport Demand Patterns Variability of demand Some key observations Converting annual forecasts into monthly, daily and hourly ones Geometric Design Specifications ICAO and FAA Reference Codes Practical observations Examples of specifications and their rationale Page 37

38 Rationale for Dimensional Specifications The rationale for many of the dimensional specifications in the ICAO Annex 14 is provided in the Aerodrome Design Manual, Doc 9157 (Part 1: Runways, Part 2: Taxiways) The Aerodrome Design Manual can also be used to estimate dimensional specifications for accommodating future aircraft development (e.g., Code Letter G) The rationale for some of the FAA s dimensional specifications can be found in Appendices 8 (Runways) and 9 (Taxiways) of older versions (e.g., 1989) of the FAA s Airport Design advisory circular (AC 150/ ) Page 38

39 ICAO: Taxiway Centerline to Taxiway Centerline S = WS + C + Z For Code F, WS=80 m, C=4.5 m, Z=13 m; therefore S=97.5 m Page 39

40 Single lane vs. dual lane access to stands Source: FAA AC 150/ (1989 edition) Note as well: Taxiway centerline to taxiway centerline: 1.2x(wingspan of most demanding a/c) + 10 ft (3m) Taxiway centerline to object: 0.7x(wingspan of most demanding a/c) + 10 ft (3m) Page 40

41 Questions? Comments? Page 41

Airfield Geometric Design Prof. Amedeo Odoni

Airfield Geometric Design Prof. Amedeo Odoni Airfield Geometric Design Prof. Amedeo Odoni Istanbul Technical University Air Transportation Management M.Sc. Program Air Transportation Systems and Infrastructure Module 5 May 25, 2015 Objective and

More information

Airfield Geometric Design Prof. Amedeo Odoni

Airfield Geometric Design Prof. Amedeo Odoni Airfield Geometric Design Prof. Amedeo Odoni Istanbul Technical University Air Transporta5on Management M.Sc. Program Air Transporta5on Systems and Infrastructure Module 4 28 April 2014 Objective and Outline!

More information

Airport Characteristics. Airport Characteristics

Airport Characteristics. Airport Characteristics Airport Characteristics Amedeo R. Odoni September 5, 2002 Airport Characteristics Objective To provide background and an overview on the diversity of airport characteristics Topics Discussion of geometric

More information

Airfield Capacity Prof. Amedeo Odoni

Airfield Capacity Prof. Amedeo Odoni Airfield Capacity Prof. Amedeo Odoni Istanbul Technical University Air Transportation Management M.Sc. Program Air Transportation Systems and Infrastructure Module 10 May 27, 2015 Airfield Capacity Objective:

More information

Introduction to Airports and Their Characteristics Prof. Amedeo Odoni

Introduction to Airports and Their Characteristics Prof. Amedeo Odoni Introduction to Airports and Their Characteristics Prof. Amedeo Odoni Istanbul Technical University Air Transportation Management M.Sc. Program Air Transportation Systems and Infrastructure Module 3 May

More information

The offers operators increased capacity while taking advantage of existing airport infrastructure. aero quarterly qtr_03 10

The offers operators increased capacity while taking advantage of existing airport infrastructure. aero quarterly qtr_03 10 The 747 8 offers operators increased capacity while taking advantage of existing airport infrastructure. 14 aero quarterly qtr_03 10 Operating the 747 8 at Existing Airports Today s major airports are

More information

CEE 5614 and CEE Aircraft Classifications. Spring 2013

CEE 5614 and CEE Aircraft Classifications. Spring 2013 CEE 5614 and CEE 4674 Aircraft Classifications Dr. Antonio A. Trani Professor Civil and Environmental Engineering Spring 2013 1 Material Presented The aircraft and the airport Aircraft classifications

More information

Runway Length Analysis Prescott Municipal Airport

Runway Length Analysis Prescott Municipal Airport APPENDIX 2 Runway Length Analysis Prescott Municipal Airport May 11, 2009 Version 2 (draft) Table of Contents Introduction... 1-1 Section 1 Purpose & Need... 1-2 Section 2 Design Standards...1-3 Section

More information

Tallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016

Tallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016 Tallahassee International Airport Master Plan Technical Advisory Committee Meeting #2 October 19, 2016 Agenda Welcome / Introductions Master Plan Process and Project Status Forecast of Aviation Demand

More information

CEE Quick Overview of Aircraft Classifications. January 2018

CEE Quick Overview of Aircraft Classifications. January 2018 CEE 5614 Quick Overview of Aircraft Classifications Dr. Antonio A. Trani Professor Civil and Environmental Engineering January 2018 1 Material Presented The aircraft and its impact operations in the NAS

More information

Growing Size and Complexity Prof. Amedeo Odoni

Growing Size and Complexity Prof. Amedeo Odoni Growing Size and Complexity Prof. Amedeo Odoni Istanbul Technical University Air Transportation Management M.Sc. Program Airport Planning and Management Module 3 January 2016 Growing Size and Complexity

More information

FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT ENVIRONMENTAL IMPACT STATEMENT DRAFT

FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT ENVIRONMENTAL IMPACT STATEMENT DRAFT D.3 RUNWAY LENGTH ANALYSIS Appendix D Purpose and Need THIS PAGE INTENTIONALLY LEFT BLANK Appendix D Purpose and Need APPENDIX D.3 AIRFIELD GEOMETRIC REQUIREMENTS This information provided in this appendix

More information

Advisory Circular (AC)

Advisory Circular (AC) Advisory Circular (AC) Certification of Transport Category Aeroplanes On Narrow Runways File No. 5009-6-525 AC No. 525-014 RDIMS No. 528471-V3 Issue No. 01 Issuing Branch Aircraft Certification Effective

More information

Airport Characteristics: Part 2 Prof. Amedeo Odoni

Airport Characteristics: Part 2 Prof. Amedeo Odoni Airport Characteristics: Part 2 Prof. Amedeo Odoni Istanbul Technical University Air Transportation Management M.Sc. Program Air Transportation Systems and Infrastructure Module 4 May 25, 2015 Outline

More information

STUDY WORK GROUP MEETING No. 3. November 29, 2016

STUDY WORK GROUP MEETING No. 3. November 29, 2016 STUDY WORK GROUP MEETING No. 3 November 29, 2016 Agenda Welcome and introductions Update project schedule Brief overview of previous SWG meeting Update on aviation forecasts Introduction to airfield demand/capacity

More information

Boeing Airplane Overview

Boeing Airplane Overview Boeing Airplane Overview Yonglian Ding, PE Boeing Airport Compatibility Engineering Nov 29, 2016 BOEING is a trademark of Boeing Management Company. Copyright 2016 Boeing. All rights reserved. Agenda Aircraft

More information

Aircraft Classifications. Dr. Antonio Trani and Julio Roa Department of Civil and Environmental Engineering.

Aircraft Classifications. Dr. Antonio Trani and Julio Roa Department of Civil and Environmental Engineering. Aircraft Classifications Dr. Antonio Trani and Julio Roa Department of Civil and Environmental Engineering. January 2018 1 Material Presented The aircraft and the airport Aircraft classifications Aircraft

More information

Recent amendment to Annex 14, Volume I and an update on PANS-Aerodromes

Recent amendment to Annex 14, Volume I and an update on PANS-Aerodromes Recent amendment to Annex 14, Volume I and an update on PANS-Aerodromes Yong Wang Chief, Airport Operations and Infrastructure, ICAO Overview Adoption of Amendment 14 to Annex 14, Volume I Update on PANS-Aerodromes

More information

Benchmarking Airport Airside Performance: FRA vs. EWR

Benchmarking Airport Airside Performance: FRA vs. EWR Benchmarking Airport Airside Performance: FRA vs. EWR Amedeo Odoni, Thomas Morisset, MIT Alexander Zock, Wilhelm Drotleff, ECAD ATM Research & Development Seminar Berlin, June 14, 2011 Compare airside

More information

AIRSIDE CAPACITY AND FACILITY REQUIREMENTS

AIRSIDE CAPACITY AND FACILITY REQUIREMENTS AIRSIDE CAPACITY AND FACILITY REQUIREMENTS This Section investigates the capacity of the airport, its ability to meet current demand, and the facilities required to meet forecasted needs as established

More information

Chapter 4 Airport Facility Requirements

Chapter 4 Airport Facility Requirements Chapter 4 Airport Facility Requirements Introduction CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-1 Organization of Materials CHAPTER 4 AIRPORT FACILITY REQUIREMENTS MAY 2013-2 RPZ - ROAD RPZ - NON-AIRPORT

More information

FACILITY REQUIREMENTS SUMMARY OF KEY ISSUES OVERVIEW

FACILITY REQUIREMENTS SUMMARY OF KEY ISSUES OVERVIEW FACILITY REQUIREMENTS SUMMARY OF KEY ISSUES OVERVIEW This summary is intended to provide a brief overview of the key issues associated with conformance to FAA standards at Methow Valley State Airport.

More information

TABLE OF CONTENTS. Washington Aviation System Plan Update July 2017 i

TABLE OF CONTENTS. Washington Aviation System Plan Update July 2017 i TABLE OF CONTENTS Chapter 1 Overview... 1-1 1.1 Background... 1-1 1.2 Overview of 2015 WASP... 1-1 1.2.1 Aviation System Performance... 1-2 1.3 Prior WSDOT Aviation Planning Studies... 1-3 1.3.1 2009 Long-Term

More information

CHAPTER 1 BACKGROUND AND PROPOSED ACTION

CHAPTER 1 BACKGROUND AND PROPOSED ACTION CHAPTER 1 BACKGROUND AND PROPOSED ACTION 1.0 INTRODUCTION An Environmental Assessment (EA) evaluates the effects of a proposed Federal action on the surrounding environment and is prepared in compliance

More information

Table of Contents. Master Plan March 2014 TOC i Spokane International Airport

Table of Contents. Master Plan March 2014 TOC i Spokane International Airport Table of Contents Page Chapter 1 Inventory 1. Introduction... 1 1 1.1 Community Profile... 1 2 1.1.1 Location and Setting... 1 1 1.1.2 Climate... 1 2 1.1.3 Socioeconomic Conditions... 1 5 1.1.4 Area Land

More information

AN INTRODUCTION TO PANS-AERODROMES (Doc 9981)

AN INTRODUCTION TO PANS-AERODROMES (Doc 9981) AN INTRODUCTION TO PANS-AERODROMES (Doc 9981) ADCI TF/1-PPT/5 Joseph CHEONG, Technical Officer, Aerodromes Section, ICAO Montreal REFERENCES: PANS - AERODROMES ANWP-8322 ANWP-8379 ANWP-8669 (not available)

More information

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3

Airport Master Plan for. Brown Field Municipal Airport PAC Meeting #3 Airport Master Plan for Brown Field Municipal Airport PAC Meeting #3 Public Meeting #1 > 8/24/17 from 5:30 to 8:00 pm > 41 attendees signed-in > Comments: > EAA area > Environmental constraints > Focus

More information

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include:

According to FAA Advisory Circular 150/5060-5, Airport Capacity and Delay, the elements that affect airfield capacity include: 4.1 INTRODUCTION The previous chapters have described the existing facilities and provided planning guidelines as well as a forecast of demand for aviation activity at North Perry Airport. The demand/capacity

More information

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3

Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Airport Master Plan for Montgomery-Gibbs Executive Airport PAC Meeting #3 Agenda > Introductions > Public Meetings Overview > Working Paper 3 - Facility Requirements > Working Paper 4 - Environmental Baseline

More information

Airport Planning and Management Page 1. Introduction Anne Graham (2001) Ch. 1 in Managing Airports: An International Perspective pp. 1-8.

Airport Planning and Management Page 1. Introduction Anne Graham (2001) Ch. 1 in Managing Airports: An International Perspective pp. 1-8. Airport Planning and Management Page 1 Istanbul Technical University Airport Planning and Management March 2015 Course Outline Day 1 Module 1 (4 hours) Introduction to the Airport Business Introduction

More information

Predicting a Dramatic Contraction in the 10-Year Passenger Demand

Predicting a Dramatic Contraction in the 10-Year Passenger Demand Predicting a Dramatic Contraction in the 10-Year Passenger Demand Daniel Y. Suh Megan S. Ryerson University of Pennsylvania 6/29/2018 8 th International Conference on Research in Air Transportation Outline

More information

Chapter 5 Facility Requirements

Chapter 5 Facility Requirements Chapter 5 Facility Requirements 50 INTRODUCTION This chapter describes the airside and landside facility requirements necessary to accommodate existing and forecasted demand in accordance with Federal

More information

Airline Schedule Development Overview Dr. Peter Belobaba

Airline Schedule Development Overview Dr. Peter Belobaba Airline Schedule Development Overview Dr. Peter Belobaba Istanbul Technical University Air Transportation Management M.Sc. Program Network, Fleet and Schedule Strategic Planning Module 18 : 1 April 2016

More information

Runway Roughness Evaluation- Boeing Bump Methodology

Runway Roughness Evaluation- Boeing Bump Methodology FLIGHT SERVICES Runway Roughness Evaluation- Boeing Bump Methodology Michael Roginski, PE, Principal Engineer Boeing Airport Compatibility Engineering ALACPA XI Seminar, Santiago, Chile September 1-5,

More information

I R UNDERGRADUATE REPORT. National Aviation System Congestion Management. by Sahand Karimi Advisor: UG

I R UNDERGRADUATE REPORT. National Aviation System Congestion Management. by Sahand Karimi Advisor: UG UNDERGRADUATE REPORT National Aviation System Congestion Management by Sahand Karimi Advisor: UG 2006-8 I R INSTITUTE FOR SYSTEMS RESEARCH ISR develops, applies and teaches advanced methodologies of design

More information

Consideration will be given to other methods of compliance which may be presented to the Authority.

Consideration will be given to other methods of compliance which may be presented to the Authority. Advisory Circular AC 139-10 Revision 1 Control of Obstacles 27 April 2007 General Civil Aviation Authority advisory circulars (AC) contain information about standards, practices and procedures that the

More information

Airport Master Planning Process & Update

Airport Master Planning Process & Update Airport Master Planning Process & Update David Stewart ICAO Airport Master Planning Task Force Subgroup Leader ICAO Airport Planning Seminar for the SAM Region Lima, Peru 10-14 Sep. 2018 1 Speaker: David

More information

Financing Airport Development Prof. Amedeo Odoni

Financing Airport Development Prof. Amedeo Odoni Financing Airport Development Prof. Amedeo Odoni Istanbul Technical University Air Transportation Management M.Sc. Program Airport Planning and Management Module 21 January 2016 Financing Airport Development

More information

Airport Obstruction Standards

Airport Obstruction Standards Airport Obstruction Standards Dr. Antonio Trani Department of Civil and Environmental Engineering Virginia Tech Outline of this Presentation Obstructions to navigation around airports Discussion of Federal

More information

CHAPTER 5 - FACILITY REQUIREMENTS

CHAPTER 5 - FACILITY REQUIREMENTS CHAPTER 5 - FACILITY REQUIREMENTS This chapter identifies the requirements for airfield and landside facilities to accommodate the forecast demand level. Facility requirements have been developed for the

More information

EXTENDED-RANGE TWIN-ENGINE OPERATIONS

EXTENDED-RANGE TWIN-ENGINE OPERATIONS EXTENDED-RANGE TWIN-ENGINE OPERATIONS 1. Introduction Extended range operations by aircraft with two turbine power units (ETOPS or EROPS) are sometimes necessary to permit twin engine aircraft to operate

More information

AIRPORT PLANNING. Joseph K CHEONG. Lima, September 2018

AIRPORT PLANNING. Joseph K CHEONG. Lima, September 2018 AIRPORT PLANNING Joseph K CHEONG Technical Officer, Airport Operations & Infrastructure, ICAO HQ Secretary, Aerodrome Design and Operations Panel Lima, September 2018 TOPICS THE AVIATION SYSTEM CHICAGO

More information

Facility Requirements

Facility Requirements C H A P T E R T H R E E Facility Requirements 3.0 OVERVIEW Airport planning for facility requirements is based upon addressing any existing issues and accommodating the probable demand that may occur over

More information

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN

Document prepared by MnDOT Office of Aeronautics and HNTB Corporation. MINNESOTA GO STATE AVIATION SYSTEM PLAN LAST UPDATE JULY 2013 Acknowledgements The preparation of this document was financed in part by a grant from the Federal Aviation Administration (Project No: 3-27-0000-07-10), with the financial support

More information

Study Committee Meeting. September 2015

Study Committee Meeting. September 2015 W ki P T / Working Paper Two/ Study Committee Meeting September 2015 Agenda Introductions and Opening Comments Project Overview, Process, and Schedule Review Materials from Working Paper Two Comments,

More information

Capacity Analysis & Facility Requirements

Capacity Analysis & Facility Requirements CHAPTER C Capacity Analysis & Facility Requirements 1. Introduction This chapter considers the ability of facilities at Friedman Memorial Airport (SUN) to accommodate existing and projected activity. Current

More information

CHAPTER 3 FACILITY REQUIREMENTS

CHAPTER 3 FACILITY REQUIREMENTS CHAPTER 3 FACILITY REQUIREMENTS 3.1 INTRODUCTION To properly plan for the future requirements of Newport News/Williamsburg International Airport, it is necessary to translate the forecasts of aviation

More information

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014

DRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014 DRAFT FINAL REPORT AIRPORT MASTER PLAN Rifle Garfield County Airport Revised May 15, 2014 As required by Paragraph 425.B(4) of FAA Order 5100.38C, Airport Improvement Program (AIP) Handbook: The preparation

More information

Runway Roughness Evaluation- Boeing Bump Methodology

Runway Roughness Evaluation- Boeing Bump Methodology FLIGHT SERVICES Runway Roughness Evaluation- Boeing Bump Methodology Michael Roginski, PE, Principal Engineer Boeing Airport Compatibility Engineering ALACPA X Seminar, Mexico City, Mexico September 30-

More information

The Airline Airport Relationship Prof. Amedeo Odoni

The Airline Airport Relationship Prof. Amedeo Odoni The Airline Airport Relationship Prof. Amedeo Odoni Istanbul Technical University Air Transportation Management M.Sc. Program Airport Planning and Management Module 09 January 2016 The Airline-Airport

More information

4.0 AIRFIELD CAPACITY & FACILITY REQUIREMENTS

4.0 AIRFIELD CAPACITY & FACILITY REQUIREMENTS 4.0 AIRFIELD CAPACITY & FACILITY REQUIREMENTS A key step in the Airport Master Plan (AMP) process is determining future requirements for airport facilities that will allow for airside and landside development

More information

Runway Roughness Evaluation- Boeing Bump Methodology

Runway Roughness Evaluation- Boeing Bump Methodology FLIGHT SERVICES Runway Roughness Evaluation- Boeing Bump Methodology Michael Roginski, PE, Principal Engineer Boeing Airport Compatibility Engineering ALACPA X Seminar, Mexico City, Mexico September 3-

More information

Merritt Island Airport

Merritt Island Airport TABLE OF CONTENTS CHAPTER 1 INTRODUCTION... 1-1 INTRODUCTION AND PROJECT OVERVIEW... 1-1 General Guidelines... 1-1 Prior Planning Documentation... 1-2 Key Issues... 1-2 Goals and Objectives... 1-2 Regulatory

More information

Public Information Meeting. September 2015

Public Information Meeting. September 2015 W ki P O & T / Working Papers One & Two/ Public Information Meeting September 2015 Agenda Introductions and Opening Comments Project Overview, Process, and Schedule Review Materials from Working Papers

More information

Session. Arrester Systems, Declared Distances and Runway Excursion Prevention

Session. Arrester Systems, Declared Distances and Runway Excursion Prevention Session Arrester Systems, Declared Distances and Runway Excursion Prevention 1 Runway Excursion Toronto, Canada August 2, 2005 200 meters from end of runway 2 American Airlines Flight 331, Norman Manley

More information

Chippewa-Eau Claire Metropolitan Planning Area Long Range Transportation Plan

Chippewa-Eau Claire Metropolitan Planning Area Long Range Transportation Plan 1.2.7 2010 Eau Claire County Comprehensive Plan According to Eau Claire County s most recent comprehensive plan, the County will limit land use development adjacent to EAU in order to preserve the ability

More information

Airport Compatibility

Airport Compatibility Presented by Dan COHEN-NIR Programs Director Airbus Americas Holdings Inc. www.airbusamericas.com Airport Compatibility Opportunities and Challenges Airport Challenges & Aircraft Design Challenge: Prepare

More information

FACILITY REQUIREMENTS CHAPTER

FACILITY REQUIREMENTS CHAPTER FACILITY REQUIREMENTS CHAPTER Introduction This chapter presents requirements for airside, landside, terminal, and support facilities to meet aviation demand at RNO over the next 20 years. Facilities are

More information

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017

Lopez Island Airport Master Plan Update. Public Meeting June 15, 2017 Lopez Island Airport Master Plan Update Public Meeting June 15, 2017 Master Plan Update Team Reid Middleton/Everett, WA Shannon Kinsella, Project Manager Melania Haagsma, Project Engineer Mead & Hunt/Tulsa,

More information

What's your fleet mix for design?

What's your fleet mix for design? What's your fleet mix for design? (Hint: it's not the Airport Master Plan s fleet mix) Presented to: By: 4 States Airport Conference Brian M. Tompkins, P.E., C.M. State Airport Engineer Iowa Dan E. Wilson,

More information

Airport Master Plan Update

Airport Master Plan Update Duttchessss Countty Airrporrtt Masstterr Plan Updatte Airport Master Plan Update Final Report Dutchess County Airport Town of Wappingers, New York C&S Engineers, Inc. 499 Col. Eileen Collins Blvd. Syracuse,

More information

Technical Advisory Committee Meeting February 29, 2016

Technical Advisory Committee Meeting February 29, 2016 Technical Advisory Committee Meeting February 29, 2016 Meeting Agenda Introduction Recap of Planning Process Project Status Goals and Objectives Forecasts of Aviation Demand Overview of Facility Requirements

More information

Chapter III - Demand/Capacity and Facility Requirements

Chapter III - Demand/Capacity and Facility Requirements Chapter III - Demand/Capacity and Facility Requirements The facility requirements identified in this chapter are summarized on Exhibit III.1. The future requirements serve to determine which airport facilities

More information

AIRPORT WITH NO RUNWAYS IS A MALL

AIRPORT WITH NO RUNWAYS IS A MALL RUNWAY EXTENSION INITIATIVE AT FT. LAUDERDALE HOLLYWOOD INTERNATIONAL AIRPORT ISMAEL IZZY BONILLA DEPUTY DIRECTOR BROWARD COUNTY AVIATION AUTHORITY AIRPORT WITH NO RUNWAYS IS A MALL Runway Business Case

More information

AIRPORT OPERATIONS TABLE OF CONTENTS

AIRPORT OPERATIONS TABLE OF CONTENTS AIRPORT OPERATIONS TABLE OF CONTENTS Module 1 Understanding the Airport... 3 1.0 Understanding the Airport...5 1.1 Overview of the Air Transport System...6 1.1.1 The Importance of the Air Transportation

More information

Assignment 7: Airport Geometric Design Standards

Assignment 7: Airport Geometric Design Standards CEE 4674: Airport Planning and Design Spring 2018 Date Due: March 23, 2018 Instructor: Trani Problem 1 Assignment 7: Airport Geometric Design Standards An airport is designing a new pier terminal to accommodate

More information

Master Plan Update Technical Advisory Committee Meeting

Master Plan Update Technical Advisory Committee Meeting Nashville International Airport Master Plan Update Technical Advisory Committee Meeting February 14, 2019 Agenda Welcome and Introductions Aviation Activity Forecast Facility Requirements Alternatives

More information

Airline Scheduling Optimization ( Chapter 7 I)

Airline Scheduling Optimization ( Chapter 7 I) Airline Scheduling Optimization ( Chapter 7 I) Vivek Kumar (Research Associate, CATSR/GMU) February 28 th, 2011 CENTER FOR AIR TRANSPORTATION SYSTEMS RESEARCH 2 Agenda Airline Scheduling Factors affecting

More information

4. Demand/Capacity Assessment and Facility Requirements

4. Demand/Capacity Assessment and Facility Requirements 4. This chapter presents an evaluation of the existing airfield facilities, buildings, and other facilities at the Airport and an assessment of their potential use under the demand scenarios defined for

More information

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35

Airport Master Plan. Brookings Regional Airport. Runway Runway 17-35 Runway 17-35 Airport Master Plan Runway 12-30 Brookings Regional Airport Table of Contents Table of Contents Chapter 1: Master Plan Goals... 1-1 1.1. Introduction... 1 1.2. Objective 1 Identify improvements

More information

Chapter 3 FACILITY REQUIREMENTS

Chapter 3 FACILITY REQUIREMENTS Chapter 3 FACILITY REQUIREMENTS Chapter Three Facility Requirements To properly plan for the future of Ryan Airfield, it is necessary to translate forecast aviation demand into the specific types and quantities

More information

DRAFT MASTER PLAN UPDATE

DRAFT MASTER PLAN UPDATE DRAFT MASTER PLAN UPDATE CHAPTER VI: AIRPORT LAYOUT PLAN NARRATIVE DRAFT REPORT APRIL 2017 PREPARED BY: Table of Contents WESTCHESTER COUNTY AIRPORT 6 AIRPORT LAYOUT PLAN NARRATIVE REPORT... 6-1 6.1 AGIS

More information

Airport charges structure - engagement session. Brian Woodhead

Airport charges structure - engagement session. Brian Woodhead Airport charges structure - engagement session Brian Woodhead 20 January 2015 1 Engagement session agenda 1) Welcome Brian Woodhead 14:00 14:10 a) Introductions b) Objectives and why we are reviewing the

More information

CATCODE ] CATCODE

CATCODE ] CATCODE Runways. FAC: 1111 CATCODE: 111111 OPR: AFCEC/COS OCR: AF/A3O-A 1.1. Description. The runway is the paved surface provided for normal aircraft landings and take offs. Runways are classified as either Class

More information

Airport Evolution and Capacity Forecasting

Airport Evolution and Capacity Forecasting Internet: www.gap-projekt.de Contact: info@gap-projekt.de Airport Evolution and Capacity Forecasting Branko Bubalo GAP/B Research Project branko.bubalo@googlemail.com partner/sponsor: 8 th GARS Aviation

More information

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved

TABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved TABLE OF CONTENTS Description Page Number LIST OF ACRONYMS... a CHAPTER ONE INTRODUCTION General... 1-1 Study Objectives... 1-1 Public Involvement... 1-2 Issues to Be Resolved... 1-2 CHAPTER TWO EXISTING

More information

ADVISORY CIRCULAR AC-AD-005

ADVISORY CIRCULAR AC-AD-005 GHANA CIVIL AVIATION AUTHORITY ADVISORY CIRCULAR AC-AD-005 AERODROME QUALITY DATA SYSTEM GENERAL Ghana Civil Aviation Authority (GCAA) Advisory Circulars from Aerodrome Safety and Standards (ASAS) contain

More information

Boeing Product Update

Boeing Product Update Boeing Product Update Agenda Market Outlook Boeing Product Impact to Airports 777X Folding Wingtip Boeing Airport Compatibility Group 2 Regulatory Effort Market Outlook (Latin America) Boeing Product

More information

Assignment 3: Runway Length and EMAS Design. Aircraft Engine Remarks. CFM56-7B20/-7B22/-7B24 developing 20,000 lb of thrust at sea level

Assignment 3: Runway Length and EMAS Design. Aircraft Engine Remarks. CFM56-7B20/-7B22/-7B24 developing 20,000 lb of thrust at sea level CEE 4674: Airport Planning and Design Spring 2014 Solution! Assignment 3: Runway Length and EMAS Design Instructor: Trani Problem 1 A new airport to be constructed near Mexico City airport would like to

More information

AIRPORT MASTER PLAN FOR. charles B. WHEELER DOWNTOWN AIRPORT KANSAS CITY, MISSOURI

AIRPORT MASTER PLAN FOR. charles B. WHEELER DOWNTOWN AIRPORT KANSAS CITY, MISSOURI AIRPORT MASTER PLAN FOR charles B. WHEELER DOWNTOWN AIRPORT KANSAS CITY, MISSOURI Prepared For The City of Kansas City, Missouri By Coffman Associates, Inc. January 2004 "The contents of these documents

More information

Addendum - Airport Development Alternatives (Chapter 6)

Addendum - Airport Development Alternatives (Chapter 6) Bowers Field Addendum - Airport Development Alternatives (Chapter 6) This addendum to the Airport Development Alternatives chapter includes the preferred airside development alternative and the preliminary

More information

Facility Requirements

Facility Requirements 4. This chapter presents the airside and landside facility requirements necessary to accommodate existing and forecasted demand at Erie International Airport (ERI or the Airport) in accordance with Federal

More information

Chapter 4 Airport Capacity Assessment and Identification of Facility Needs

Chapter 4 Airport Capacity Assessment and Identification of Facility Needs Chapter 4 Airport Capacity Assessment and Identification of Facility Needs 4.1 Introduction The purpose of the airport capacity assessment and identification of facility needs is to evaluate the single

More information

Terms of Reference for rulemaking task RMT.0704

Terms of Reference for rulemaking task RMT.0704 Terms of Reference for rulemaking task Runway Surface Condition Assessment and Reporting ISSUE 1 Issue/rationale The International Civil Aviation Organization (ICAO), through State Letters AN 4/1.2.26-16/19

More information

TRANSPORTATION RESEARCH BOARD. Preparing and Using Airport Design Day Flight Schedules. Wednesday, July 18, :00-3:30 PM ET

TRANSPORTATION RESEARCH BOARD. Preparing and Using Airport Design Day Flight Schedules. Wednesday, July 18, :00-3:30 PM ET TRANSPORTATION RESEARCH BOARD Preparing and Using Airport Design Day Flight Schedules Wednesday, July 18, 2018 2:00-3:30 PM ET Purpose Discuss research from the Airport Cooperative Research Program (ACRP)

More information

1. Background and Proposed Action

1. Background and Proposed Action 1. Background and Proposed Action This chapter describes Hillsboro Airport and the planning background for the proposed project. The Port of Portland (the Port) is the sponsor for the Hillsboro Airport

More information

Fuel Burn Impacts of Taxi-out Delay and their Implications for Gate-hold Benefits

Fuel Burn Impacts of Taxi-out Delay and their Implications for Gate-hold Benefits Fuel Burn Impacts of Taxi-out Delay and their Implications for Gate-hold Benefits Megan S. Ryerson, Ph.D. Assistant Professor Department of City and Regional Planning Department of Electrical and Systems

More information

3.0 Facility Requirements

3.0 Facility Requirements 3.0 Facility Requirements The facility requirements chapter includes an assessment of the aviation and non-aviation components of Rickenbacker International Airport (LCK) including the runway and taxiway

More information

CEE 4674 Airport Planning and Design. Antonio A. Trani Julio Roa. Punta Cana Ecological Foundation Summer I, 2013

CEE 4674 Airport Planning and Design. Antonio A. Trani Julio Roa. Punta Cana Ecological Foundation Summer I, 2013 CEE 4674 Airport Planning and Design Antonio A. Trani Julio Roa Punta Cana Ecological Foundation Summer I, 2013 CEE 4674 - Course Information CEE This course is oriented to those engineering students who

More information

Evaluation of Alternative Aircraft Types Dr. Peter Belobaba

Evaluation of Alternative Aircraft Types Dr. Peter Belobaba Evaluation of Alternative Aircraft Types Dr. Peter Belobaba Istanbul Technical University Air Transportation Management M.Sc. Program Network, Fleet and Schedule Strategic Planning Module 5: 10 March 2014

More information

Chapter 5 Facility Requirements

Chapter 5 Facility Requirements Chapter 5 Facility Requirements 5.0 INTRODUCTION The Facility Requirements chapter of this Sustainable Master Plan Update describes airside and landside facilities, which are needed to accommodate existing

More information

Airport Systems: Planning, Design, and Management

Airport Systems: Planning, Design, and Management Airport Systems: Planning, Design, and Management Richard de Neufville AmedeoR. Odoni McGraw-Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New Delhi San Juan Seoul Singapore

More information

3.1 Facility Requirements Overview Airfield Facility Requirements... 1

3.1 Facility Requirements Overview Airfield Facility Requirements... 1 Table of Contents 3.1 Overview... 1 3.2 Airfield... 1 Airspace Capacity...1 Airside Capacity... 2 Aircraft Mix Index... 3 Arrivals Percentage... 4 Touch-and-Go Percentage... 4 Taxiway Access Factors...

More information

NOISE ABATEMENT PROCEDURES

NOISE ABATEMENT PROCEDURES 1. Introduction NOISE ABATEMENT PROCEDURES Many airports today impose restrictions on aircraft movements. These include: Curfew time Maximum permitted noise levels Noise surcharges Engine run up restrictions

More information

Global Runway Safety Simposium

Global Runway Safety Simposium Global Runway Safety Simposium A DIFFERENT PERSPECTIVE OF SAFETY AND ITS RELATIONSHIP WITH SURROUNDINGS Costantino Pandolfi LIMA, 11/21/2017 Italian Civil Aviation Authority ICAO ADOP Member Panel 8 New

More information

Regional Jets ,360 A319/ , , , ,780

Regional Jets ,360 A319/ , , , ,780 Excel Tab Name: Seats (18 MAP) PASSENGER AIRLINE FLIGHT SCHEDULE CALCULATION RECORD Summary 17.2 MAP flight schedule* (with Southwest Airlines B737-800s changed to B737-700s) Number of Total Seats Avg.

More information

Chapter 5. Facility Requirements

Chapter 5. Facility Requirements Chapter 5 Facility Requirements Chapter 5 Facility Requirements INTRODUCTION The Baseline Forecast was used to determine facility requirements. Chapter 4 produced a forecast of traffic volumes expected

More information

Department of Transportation, Federal Aviation Administration (FAA). SUMMARY: Under this notice, the FAA announces the submission deadline of

Department of Transportation, Federal Aviation Administration (FAA). SUMMARY: Under this notice, the FAA announces the submission deadline of This document is scheduled to be published in the Federal Register on 10/02/2017 and available online at https://federalregister.gov/d/2017-21045, and on FDsys.gov [4910-13] DEPARTMENT OF TRANSPORTATION

More information

Overview ICAO Standards and Recommended Practices for Aerodrome Safeguarding

Overview ICAO Standards and Recommended Practices for Aerodrome Safeguarding Overview ICAO Standards and Recommended Practices for Aerodrome Safeguarding References The Convention on International Civil Aviation (Chicago Convention) ICAO SARPS Annex 14 Vol. I, 7 th Edition, July

More information