1 2017 Work and Launch of the Next Phase Information meeting, Montréal-Ouest September 14, 2017

2 2 Presentation Outline Work progress Launch of the next phase Mitigation measures Dismantling Communications A-20 westbound under new boulevard Pullman May 2017

3 3 Work Progress 50 % completed 1,000 workers More than 20 structures under construction 12 permanent structures will be completed in temporary bridges in 2017 View looking east from the Turcot Interchange May 2017

4 4 Work Progress Temporary and permanent retaining walls: over 46,000 m 2 Concrete dismantled: over 56,000 m 3 Concrete pavement: over m 3 View looking east of the Turcot Yards May 20

5 5 Launch of the Next Phase End of 2017 Highlights: Transfer of A-15 traffic in the De La Vérendrye area Transfer of A-20 / R-136 (A-720) eastbound traffic in the heart of the Turcot Interchange Transfer of A-720 / A-20 westbound traffic between the Ville-Marie Tunnel and the Montréal-Ouest Interchange

6 6 Timeline Launching the Next Phase Main steps in launching the next phase ongoing until 2019

7 7 Preliminary Steps Existing Geometry De La Vérendrye

8 8 Preliminary Steps New Geometry De La Vérendrye New layout

9 9 Preliminary Steps A-15 Northbound Route 2 Possible congestion

10 10 Preliminary Steps Closure of A-15 N. toward A-20 W. 8 weeks starting mid- September

11 11 Preliminary Steps Other Route Detour via A-20 westbound

12 12 Preliminary Steps Partial Closure A-20 Eastbound 2 lanes / 3

13 13 Transfer of A-15 southbound traffic New Geometry New layout

14 14 Transfer of A-15 southbound traffic A-15 Southbound Route 2 A-15 southbound entrance from boul. De La Vérendrye

15 15 Transfer of A-15 southbound traffic A-15 Southbound Route - Detour

16 16 Transfer of eastbound traffic Existing Geometry

17 17 Transfer of eastbound traffic New Geometry Relocated exit to the right Relocated road section Relocated exit New layout Closure of Notre-Dame entrance

18 18 Transfer of eastbound traffic Eastbound Route 4 interchanged access Decision point

19 19 Transfer of eastbound traffic Eastbound Route Interchanged access 1 3 lanes available Decision point 2 lanes available 1

20 20 Transfer of eastbound traffic Eastbound Route 3

21 21 Transfer of westbound traffic Existing Geometry

22 22 Transfer of westbound traffic Existing Geometry Closure of A-720 westbound Closed entrance Closed entrance New layout Possible congestion

23 23 Transfer of westbound traffic Westbound Route 3 lanes available 2 lanes available Temporary entrance Possible congestion Counter-flow traffic

24 24 Transfer of westbound traffic Rue Rose-de-Lima Temporary Entrance Ramp

25 25 Transfer of westbound traffic Westbound Route Rue Saint-Jacques exit closed R-136 westbound toward A-15 southbound exit closed 1

26 26 Transfer of westbound traffic A-15 S. toward A-20 W./R-136 E. Route Possible congestion 1 1 Decision point

27 27 Transfer of westbound traffic A-15 N. toward A-20 W. Route 1 Decision point Possible congestion

28 28 Transfer of westbound traffic A-15 N. toward A-20 W. Route Slowdown Upstream exit

29 29 Transfer of westbound traffic Existing Geometry

30 30 Transfer of westbound traffic New Geometry Relocated exit to the right Relocated road section Relocated exit New layout Closure of Notre-Dame entrance

31 31 Transfer of westbound traffic Westbound Route 1 2 Exit relocated to the right 3 1 2

32 32 Transfer of westbound traffic Westbound Route 1 3 Temporary entrance 1 2

33 33 Transfer of A-20 E. traffic toward A-15 N. New Geometry (in December) New layouts

34 34 Transfer of A-20 E. traffic toward A-15 N. Eastbound Route (in December) Interchanged access 4 Decision point 2 1

35 35 Transfer of A-20 E. traffic toward A-15 N. Eastbound Route (in December)

36 36 Transfer of A-20 E. traffic toward A-15 N. A-20 E. toward A-15 N. Route (in December) 1 2

37 37 Turcot Interchange Existing Geometry

38 38 Turcot Interchange New Geometry

39 39 Traffic calming measures Construction of 28 temporary structures to maintain traffic Opening of 3 temporary entrance ramps Reserved lane for public transport on rue Rose-de-Lima Installation of 4 temporary traffic lights Reprogramming of more than 30 traffic lights Modifications on a dozen intersections/local streets Police presence at first Use of mobile variable message signs Public transit measures deployed by Mobility Montréal

40 40 Mitigation measures for public transportation Reserved bus lanes rue Rose-de-Lima northbound, between rue Saint-Jacques and rue Saint-Antoine Ouest New Rue Notre-Dame Ouest, rue Saint-Patrick and rue Sherbrooke Ouest A-20 eastbound in Dorval / Lachine Agrignon Interchange bypass road Addition of bus and train service Park and ride Train station and bus terminal developments or work Canal de Lachine train station Annexed to Terminus Centre-Ville

41 41 Dismantling of infrastructures Schedule: From November 2017 to early summer 2018 Many closures to come on the freeway system: 20 to 25 weekends

42 42 How to stay informed Website: Twitter Monthly e-newsletter (subscriptions on the Turcot Website) Telephone: Neighbourhood Committees (open to the public) Sud-Ouest : October 10, 2017 NDG-Westmount : October 16, 2017

43 43 Questions

44 44 Preliminary Steps De La Vérendrye Area

Neighbourdhood Committee NDG-Westmount. October 16, 2017

Neighbourdhood Committee NDG-Westmount. October 16, 2017 Neighbourdhood Committee NDG-Westmount October 16, 2017 2 Presentation Outline Requests from Committee members Feedback on questions Green strip consultations Work update and obstacles Work progress Phase

More information

Neighbourhood Committee NDG - Westmount. September 12, 2016

Neighbourhood Committee NDG - Westmount. September 12, 2016 Neighbourhood Committee NDG - Westmount September 12, 2016 2 Presentation Outline Requests from the committee members Feedback on previous questions Work update and hindrance of the Turcot Project Ministry

More information

NDG-Westmount Neighbourhood Committee. November 16, 2015

NDG-Westmount Neighbourhood Committee. November 16, 2015 NDG-Westmount Neighbourhood Committee November 16, 2015 2 Feedback on previous questions Order-in-Council 890-2010 - condition 8 The ministère des Transports must : Establish a buffer zone at the foot

More information

NDG/Westmount Neighbourhood Committee. May 16, 2016

NDG/Westmount Neighbourhood Committee. May 16, 2016 NDG/Westmount Neighbourhood Committee May 16, 2016 2 Presentation Outline Feedback on previous questions What s new on the Turcot website Public consultations online Reconstruction of Saint-Jacques overpass

More information

Work in 2015 and Annual Mobility- Management Plan

Work in 2015 and Annual Mobility- Management Plan Work in 2015 and Annual Mobility- Management Plan KPH-Turcot July 14, 2015 2 Presentation Outline Division into sectors Work in 2015 without disruptions West sector Center sector East sector South sector

More information

Neighbourdhood Committee NDG-Westmount-Montréal-Ouest. February 6, 2018

Neighbourdhood Committee NDG-Westmount-Montréal-Ouest. February 6, 2018 Neighbourdhood Committee NDG-Westmount-Montréal-Ouest February 6, 2018 2 Presentation Outline Feedback on questions Traffic Monitoring Work update and closures Reconstruction of Saint-Jacques bridge Dismantling

More information

Night work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road

Night work update: Hills M2 Motorway and westbound on ramp at Pennant Hills Road T 1800 997 057 (free call) E enquiries@northconnex.com.au PO Box 343 Pennant Hills NSW 1715 northconnex.com.au 28 April 2017 Ref: N0075M Night work update: and westbound on ramp at Dear resident, NorthConnex

More information

AGENDA ITEM I-6 Public Works

AGENDA ITEM I-6 Public Works AGENDA ITEM I-6 Public Works STAFF REPORT City Council Meeting Date: 8/6/2018 Staff Report Number: 18-150-CC Informational Item: Update on the Willow Road and highway 101 interchange construction, upcoming

More information

Concord Road Interchange. Standard hours of work

Concord Road Interchange. Standard hours of work Artist impression of the Concord Road interchange, Concord - concept only WestConnex s M4 East will extend the M4 Motorway with two new 5.5 kilometre tunnels from Homebush to Haberfield, providing a bypass

More information

Guide to. Road Construction Projects

Guide to. Road Construction Projects Guide to Road Construction Projects 2018 Spring is here and so is road construction season. This year PennDOT District 11-0 will invest an estimated $208 million on 68 projects to improve, preserve or

More information

Welcome to the Business Owners Task Force. Perry Leonard Blagg Tire and Service President/COO

Welcome to the Business Owners Task Force. Perry Leonard Blagg Tire and Service President/COO Welcome to the Business Owners Task Force Perry Leonard Blagg Tire and Service President/COO Safety: West Nile Virus Alyssa Tenorio NorthGate Constructors Public Information Manager West Nile Virus Carried

More information

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov August 31, 18 No closures scheduled for Labor Day weekend. Traffic lane patterns

More information

The Regional Municipality of Halton. Chair and Members of the Planning and Public Works Committee. PW Royal Bank of Canada Canadian Open

The Regional Municipality of Halton. Chair and Members of the Planning and Public Works Committee. PW Royal Bank of Canada Canadian Open Approved - Planning and Public Works - Jun 15, 2016 Adopted - Regional Council - Jun 22, 2016 The Regional Municipality of Halton Report To: From: Chair and Members of the Planning and Public Works Committee

More information

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015

EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 EXTERNAL COMMUNICATIONS COMMITTEE MEETING APRIL 2015 35EXPRESS PROJECT OVERVIEW 2 SEGMENT 1 3 SOUTH OF I-635 May Shift northbound mainlane traffic east in the southeast quadrant Miscellaneous frontage

More information

November 21, 2012 Barbara Kelleher, (954)

November 21, 2012 Barbara Kelleher, (954) November 21, 2012 Barbara Kelleher, (954) 777-4090 barbara.kelleher@dot.state.fl.us BROWARD COUNTY TRAFFIC IMPACT REPORT November 26 to November 30, 2012 FORT LAUDERDALE -- Construction and maintenance-related

More information

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS

35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT UPDATE FOR DENTON COUNTY COMMISSIONERS 35EXPRESS PROJECT OVERVIEW 2 ABOUT THE 35EXPRESS PROJECT 3 DESIGN-BUILD TEAM 4 PROJECT PARTNERS Great partnerships make this project work Collaboration

More information

I-10 West and Sunland Park Drive southbound will close July 13 at night. Detour onto North Mesa will be required.

I-10 West and Sunland Park Drive southbound will close July 13 at night. Detour onto North Mesa will be required. NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov I-10 West and Sunland Park Drive southbound will close July 13 at night. Detour

More information

A. CONCLUSIONS OF THE FGEIS

A. CONCLUSIONS OF THE FGEIS Chapter 11: Traffic and Parking A. CONCLUSIONS OF THE FGEIS The FGEIS found that the Approved Plan will generate a substantial volume of vehicular and pedestrian activity, including an estimated 1,300

More information

Pardon Our Dust Public Information Meeting

Pardon Our Dust Public Information Meeting Pardon Our Dust Public Information Meeting Robert G. Ridgell, P.E. Virginia Department of Transportation, Fredericksburg District Area Construction Engineer July 12, 2018 Project Team and Leadership Virginia

More information

TECHNICAL BRIEFING WORK ON THE RÉSEAU EXPRESS MÉTROPOLITAIN APRIL 25, 2018

TECHNICAL BRIEFING WORK ON THE RÉSEAU EXPRESS MÉTROPOLITAIN APRIL 25, 2018 TECHNICAL BRIEFING WORK ON THE RÉSEAU EXPRESS MÉTROPOLITAIN APRIL 25, 2018 2018-2019 SCHEDULE Project progress Contract signed with the winning consortia on April 12, 2018 Project office set up for the

More information

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov March 31, 2017 This Sunday, I 10 East traffic lanes will switch onto new lanes.

More information

I-10 will close overnight Sunday through Thursday next week. Crews continue to make progress on Sunland s new bridges and ramps.

I-10 will close overnight Sunday through Thursday next week. Crews continue to make progress on Sunland s new bridges and ramps. NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Rebecca Reyes (915) 790-4205 Rebecca.Reyes@txdot.gov I-10 will close overnight Sunday through Thursday next week. Crews continue to make

More information

Cell: (408) Release MA June 25, 2012

Cell: (408) Release MA June 25, 2012 VTA NEWS CONTACT: Bernice Alaniz FOR IMMEDIATE RELEASE Cell: (408) 888-9983 Release MA 12 06 08 Bernice.Alaniz@vta.org June 25, 2012 Construction Activities Underway For BART Silicon Valley The Santa Clara

More information

Important Lane Closures, April 3 9, 2011

Important Lane Closures, April 3 9, 2011 March 31, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 marcia.mcallister@dullesmetro.com Important Lane Closures, April 3 9, 2011 RESCHEDULED: Lane Shifts of Westbound Route 7 at Route

More information

Full I-35E Mainlane Closure at Beckley Avenue - July 27-30

Full I-35E Mainlane Closure at Beckley Avenue - July 27-30 July 20, 2018 Media Contact: Keith Bilbrey Public Involvement Manager The Southern Gateway Project kbilbrey@kstrategies.com 972-989-9995 Full I-35E Mainlane Closure at Beckley Avenue - July 27-30 DALLAS

More information

All closures this week happen at night, including full closures of Mesa and I-10

All closures this week happen at night, including full closures of Mesa and I-10 NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov May 25, 2018 North Mesa Tuesday, May 29 through Thursday, May 31 9 p.m. each

More information

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018

CONTACT: Nichole Lawrence CELL: FOR IMMEDIATE RELEASE Wednesday March 28, 2018 FOR IMMEDIATE RELEASE Wednesday March 28, 2018 CONTACT: Nichole Lawrence CELL: 731-225-6041 West Tennessee Construction March 28-April 4, 2018 Per TDOT Specifications, there will be no temporary lane closures

More information

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015

EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 EXTERNAL COMMUNICATIONS TEAM MEETING MARCH 2015 1 SEGMENT 1 2 THE WISHBONE Connects the TEXpress Managed Toll System to the 35Express Managed Toll System Limits: Crown Road (near Royal Lane) to Valley

More information

Hospital Link Project Project Update Winter 2018

Hospital Link Project Project Update Winter 2018 Hospital Link Project Project Update Winter 2018 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction of the Hospital Link facility is open

More information

Monthly Traffic Update

Monthly Traffic Update Brisbane Airport Corporation Monthly Traffic Update PAGE 1 ISSUE 26 DECEMBER 2009 Northern Access Road Project opens 3 December Brisbane Airport Corporation (BAC) is pleased to announce that after two

More information

GROUPE IMMOBILIER SANTÉ MCGILL Chantal Sorel (Vice-President and MUHC Project Director, SNC-Lavalin)

GROUPE IMMOBILIER SANTÉ MCGILL Chantal Sorel (Vice-President and MUHC Project Director, SNC-Lavalin) GOOD NEIGHBOURLY RELATIONS COMMITTEE MUHC Glen site: Construction and Roadwork MINUTES OF PROCEEDINGS Meeting held on Tuesday, June 18, 2013 Committee members in attendance VILLE DE MONTRÉAL Sébastien

More information

Frequently Asked Questions on the Route 29 Solutions Improvements Projects

Frequently Asked Questions on the Route 29 Solutions Improvements Projects Frequently Asked Questions on the Route 29 Solutions Improvements Projects Background What are the Route 29 Solutions improvement projects? These projects include the Route 29/250 Interchange ( Best Buy

More information

Possible traffic snarls ahead for 60 Freeway with lane/ramp closures on the weekends in Diamond Bar

Possible traffic snarls ahead for 60 Freeway with lane/ramp closures on the weekends in Diamond Bar Possible traffic snarls ahead for 60 Freeway with lane/ramp closures on the weekends in Diamond Bar A construction truck drives along the newly paved westbound 60 freeway Lemon Avenue on-ramp in City of

More information

Route 29 Solutions Projects

Route 29 Solutions Projects Your guide to the Route 29 Solutions Projects For full details & continued engagement please visit www.route29solutions.org The Route 29 Solutions Package is a $230 million investment into the improvement

More information

NEW TRAFFIC SEPARATION SCHEMES

NEW TRAFFIC SEPARATION SCHEMES E 4 ALBERT EMBANKMENT LONDON SE1 7SR Telephone: +44 (0)20 7735 7611 Fax: +44 (0)20 7587 3210 NEW TRAFFIC SEPARATION SCHEMES COLREG.2/Circ.65 23 May 2014 1 The Maritime Safety Committee, at its ninety-third

More information

Palm Beach County Traffic Report July 13 through July 20, 2012

Palm Beach County Traffic Report July 13 through July 20, 2012 For Immediate Release July 13, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report July 13 through July 20, 2012 Palm Beach County Palm Beach County traffic will be

More information

Capital Beltway HOT Lanes Project

Capital Beltway HOT Lanes Project New Travel Choices Ahead Some things can t wait for traffic Capital Beltway HOT Lanes Project Project Update August 16, 2011 Major Milestones Reached Some things can t wait for traffic Project over 75%

More information

JANUARY MODERNIZATION UPDATE: MAJOR PROJECTS ON TAP AT LAX AS NEW YEAR BEGINS

JANUARY MODERNIZATION UPDATE: MAJOR PROJECTS ON TAP AT LAX AS NEW YEAR BEGINS For Immediate Release January 2, 2018 Contact: Charles H. Pannunzio (424) 646-5260 JANUARY MODERNIZATION UPDATE: MAJOR PROJECTS ON TAP AT LAX AS NEW YEAR BEGINS Access to Parking Structure 4 from the Upper/Departure

More information

Long water shutdown scheduled for Tuesday, September 18

Long water shutdown scheduled for Tuesday, September 18 Thank you for your interest in the Center City Connector Streetcar. In this weekly update, you ll find information about ongoing construction for the 1st phase of utility work in Pioneer Square. Utility

More information

NEW TRAFFIC SEPARATION SCHEMES

NEW TRAFFIC SEPARATION SCHEMES E 4 ALBERT EMBANKMENT LONDON SE1 7SR Telephone: +44 (0)20 7735 7611 Fax: +44 (0)20 7587 3210 NEW TRAFFIC SEPARATION SCHEMES COLREG.2/Circ.65 23 May 2014 1 The Maritime Safety Committee, at its ninety-third

More information

A VISION FOR I-95. January 12, Delaware Department of Transportation

A VISION FOR I-95. January 12, Delaware Department of Transportation A VISION FOR I-95 January 12, 2011 Delaware Department of Transportation The East Coast s Main Street Along with SR 1, the most significant highway in Delaware 29 miles to I ".', 2 Sponsoring / Cooperating

More information

As the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required.

As the Toronto Transit Commission (TTC) operates a transit service on Bay Street, City Council approval of this report is required. REPORT FOR ACTION Construction Staging Area - 81 Bay Street Date: December 11, 2017 To: Toronto and East York, Community Council From: Acting Director, Transportation Services Toronto and East York District

More information

State Route 8 Corridor. Northern Summit County s Path to Success

State Route 8 Corridor. Northern Summit County s Path to Success State Route 8 Corridor Northern Summit County s Path to Success Construction Guide: 2008-2009 State Route 8 corridor work description State Route 8 Corridor 10 projects $262 million With its close proximity

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE Aug. 10, 2018 CONTACT: Darragh Frye 540 899 4119 (office) 540 907 8409 (cell) Darragh.Frye@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT August 12 August 18, 2018 All

More information

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov Major Operation: 36 massive beams will be placed at Sunland & I 10. Operation

More information

Road Construction Ahead January-April 2015 NORTHWEST REGION

Road Construction Ahead January-April 2015 NORTHWEST REGION NORTHWEST REGION 1 Interstate 64 Augusta, Nelson, Albemarle counties: Installing communications conduit in median for active traffic management system on Afton Mountain. Periodic left-shoulder closures,

More information

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov A daytime lane closure on Mesa all week is needed to complete Sunday s demo

More information

Construction Update. ODOT District Two Construction Update. For Immediate Release Thursday, October 18, Lucas County

Construction Update. ODOT District Two Construction Update. For Immediate Release Thursday, October 18, Lucas County Construction Update Contact: The District Two Public Information Office at (419) 373-4428 or email D02.PIO@dot.ohio.gov For Immediate Release Thursday, October 18, 2018 ODOT District Two Construction Update

More information

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015

FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 June 19, 2015 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report June 19 through June 26, 2015 TREASURE COAST Construction and maintenance-related lane

More information

Constructor: Joseph B. Fay

Constructor: Joseph B. Fay 1 1 2 OWNER: PENNDOT Engineering District 11-0 City of Pittsburgh Design Consultant: SAI Consulting Engineers KTA-Tator Constructor: Joseph B. Fay Construction Manager: Michael Baker Construction Inspection:

More information

FDOT Treasure Coast Traffic Report through

FDOT Treasure Coast Traffic Report through FDOT Treasure Coast Traffic Report 02 26 16 through 03 04 16 Kathleen Dempsey Fri 2/26/2016 2:56 PM To:Kathleen Dempsey ; 1 attachment 355 KB CR 714_Median Access Modifications.pdf;

More information

GO 10 is planning to switch I 10 Eastbound traffic lanes after Sunland Park. The switch is set for Sunday, April 2. Details continue to develop.

GO 10 is planning to switch I 10 Eastbound traffic lanes after Sunland Park. The switch is set for Sunday, April 2. Details continue to develop. GO 10 is planning to switch I 10 Eastbound traffic lanes after Sunland Park. The switch is set for Sunday, April 2. Details continue to develop. I-10 & Mesa Continuous Until further notice The right turn-only

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Aug , 2016 RELEASE: IMMEDIATE Aug. 12, 2016 CONTACT: Kelly Hannon 540-374-3344 (office) 540-656-0321 (cell) Kelly.Hannon@VDOT.Virginia.Gov Stafford County Tina Bundy 540-899-4560 (office) 540-907-8325 (cell) Tina.Bundy@VDOT.Virginia.Gov

More information

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014

April 4, 2014 Chuck McGinness, FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 April 4, 2014 Chuck McGinness, 954-777-4090 Chuck.McGinness@dot.state.fl.us FDOT TREASURE COAST TRAFFIC REPORT April 4 through April 11, 2014 TREASURE COAST Construction and maintenance-related lane closures

More information

September 1, 2017 I-10 night closures scheduled for September hour full closure of I-10 West happens Sunday, Sept. 10

September 1, 2017 I-10 night closures scheduled for September hour full closure of I-10 West happens Sunday, Sept. 10 NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Rebecca Reyes (915) 790-4205 Rebecca.Reyes@txdot.gov September 1, 2017 I-10 night closures scheduled for September 5-7. 27-hour full

More information

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS

For Immediate Release Christine Girardin January 19, 2018 SUMTER COUNTY FLORIDA S TURNPIKE AND I-75 INTERCHANGE IMPROVEMENTS TRAFFIC ADVISORY For Immediate Release Christine Girardin 407-264-3069 January 19, 2018 Central and West Central Florida Weekly Lane Closures and Work Zone Advisory OCOEE Florida s Turnpike announces lane

More information

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell)

RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye (office) (cell) RELEASE: IMMEDIATE Oct. 6, 2017 CONTACT: Darragh Copley Frye 540-899-4019 (office) 540-907-8409 (cell) Darragh.Frye@VDOT.Virginia.Gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT October 8 October 14,

More information

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release.

NEWS RELEASE. EL PASO DISTRICT Jennifer Wright (915) a TxDOT Project For immediate release. NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Jennifer Wright (915) 790-4340 Jennifer.Wright3@txdot.gov January 18, 2017 Mesa Continuous for 6 weeks The following closures started

More information

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT

VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT RELEASE: IMMEDIATE July 27, 2018 CONTACT: Tina Bundy 540 899 4560 (office) 540 907 8325 (cell) Tina.Bundy@VDOT.Virginia.gov VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT July 29 August 4, 2018 All work

More information

FDOT Treasure Coast Traffic Impact Report

FDOT Treasure Coast Traffic Impact Report July 22, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report July 22 through July 29, 2016 TREASURE COAST Construction and maintenance-related lane

More information

Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street

Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street STAFF REPORT ACTION REQUIRED Proposed Bicycle Lanes on Yonge Street from Queens Quay to Front Street Date: March 12, 2007 To: From: Toronto and East York Community Council Director, Transportation Infrastructure

More information

East Link Project Update. Maintenance of Traffic During Construction. April 21, 2015

East Link Project Update. Maintenance of Traffic During Construction. April 21, 2015 East Link Project Update Maintenance of Traffic During Construction April 21, 2015 1 Agenda TFP project 242 Bellevue Way HOV Bellevue Way - Maintenance of Traffic During Construction Early Work Utilities

More information

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016

FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 March 25, 2016 Chuck McGinness, 954-777-4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report March 25 through April 1, 2016 TREASURE COAST Construction and maintenance-related

More information

Milestone: Bridge to Nowhere scheduled for demolition Aug 14

Milestone: Bridge to Nowhere scheduled for demolition Aug 14 NEWS RELEASE a TxDOT Project For immediate release EL PASO DISTRICT Blanca Del Valle (915) 790-4341 Blanca.DelValle@txdot.gov August 12, 16 Milestone: Bridge to Nowhere scheduled for demolition Aug 14

More information

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015

May 1, 2015 Meredith Cruz, (561) Palm Beach County Traffic Report May 1 through May 8, 2015 May 1, 2015 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 1 through May 8, 2015 Palm Beach County Palm Beach County traffic will be affected this week by ongoing

More information

Georgia 400 Tolls to End Friday, November 22 Toll collection scheduled to end after rush hour

Georgia 400 Tolls to End Friday, November 22 Toll collection scheduled to end after rush hour www.peachpass.com NOVEMBER 2013 Georgia 400 Tolls to End Friday, November 22 Toll collection scheduled to end after rush hour In This Issue GA 400 Tolls End on November 22 Lanes Closures for GA 400/I-85

More information

Construction underway. STATUS: 229 5,190 5,419 5,305 STIP REFERENCE #FR /01/2013

Construction underway. STATUS: 229 5,190 5,419 5,305 STIP REFERENCE #FR /01/2013 FREDERICK COUNTY STATE HIGHWAY ADMINISTRATION -- Frederick County -- Line 1 PROJECT: I-7, Baltimore National Pike INTERSTATE CONSTRUCTION PROGRAM DESCRIPTION: Widen I-7 east of MD 355 to east of MD 144

More information

Northeast Corridor Transportation Update

Northeast Corridor Transportation Update Northeast Corridor Transportation Update Presented by: Stuart Basham Division 10 Planning Engineer North Carolina Department of Transportation October 2, 2014 Today s presentation includes: I-485 Outer

More information

A63 Castle Street, Hull HullBID Network Lunch 24 August 2017

A63 Castle Street, Hull HullBID Network Lunch 24 August 2017 A63 Castle Street, Hull HullBID Network Lunch 24 August 2017 James D Leeming Senior Project Manager What we will cover today? Introduction to Highways England and the Road Investment Strategy A63 Scheme

More information

Day and night work: Hills M2 Motorway tunnel portals and Coral Tree Drive electrical substation

Day and night work: Hills M2 Motorway tunnel portals and Coral Tree Drive electrical substation T 1800 997 057 (free call) E enquiries@northconnex.com.au PO Box 343 Pennant Hills NSW 1715 northconnex.com.au 2 July 2018 Ref: N0202 Day and night work: Hills M2 Motorway tunnel portals and Coral Tree

More information

NEW 2 ROUTES LEAVING FROM THE AIRPORT

NEW 2 ROUTES LEAVING FROM THE AIRPORT STARTING JANUARY 8, 08 Terminus Station Métro station de métro Station Transfert de station correspondance Station Intermodal intermodale station hours / day 7 days / week Ascenseur Elevator Ascenseur

More information

Palm Beach County Traffic Report August 24 through August 31, 2012

Palm Beach County Traffic Report August 24 through August 31, 2012 For Immediate Release August 24, 2012 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report August 24 through August 31, 2012 Palm Beach County Palm Beach County traffic will

More information

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule

- Countywide - Roadway Cone Zone / Lane Closure / Sidewalk Repair Schedule Report for Monday, September 10, 2018 through Monday, September 17, 2018 S. Perry Park Rd. (DC105) and Red Rocks Dr. Intersection Improvements Safety improvements on the S. Perry Park Road (DC 105) and

More information

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015

FDOT Treasure Coast Traffic Impact Report October 9 through October 16, 2015 From: Kathleen Dempsey To: Kathleen Dempsey Subject: FDOT Treasure Coast Traffic Report 10 09 15 through 10 16 15 Date: Friday, October 09, 2015 2:10:36 PM Attachments: image003.png CR 714_Median Construction

More information

TRAFFIC ALERT FOR DECEMBER 10-14, 2018 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR DECEMBER 10-14, 2018 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE December 7, 2018 CONTACT: Sandy Myers 540-332-9201 (office) STA18 187 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

PRIORITIES COMMITTEE MEETING

PRIORITIES COMMITTEE MEETING PRIORITIES COMMITTEE MEETING Meeting Date: 05/13/14 Agenda Item #: 13.1 Northeast Anthony Henday Drive Update Report Purpose To update the Priorities Committee on the progress of the Northeast Anthony

More information

5.1 Traffic and Transportation

5.1 Traffic and Transportation 5.1 When it opens in 2009, the Bellevue Nickel Improvement Project will increase the number of vehicles able to travel through the study area, improve travel speeds, and improve safety by reducing the

More information

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg)

Exit 136 (Centreport Parkway/Stafford County) to Exit 130 (Route 3/Fredericksburg) RELEASE: IMMEDIATE Feb. 22, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT Feb. 24 March 2, 2019 All work is scheduled weather permitting. Real-time information

More information

Construction Staging Area Blue Jays Way (357 King Street West)

Construction Staging Area Blue Jays Way (357 King Street West) REPORT FOR ACTION Construction Staging Area Blue Jays Way (357 King Street West) Date: June 8, 2018. To: Toronto and East York Community Council From: Acting Director, Transportation Services, Toronto

More information

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place.

Route 29 Business Replacing bridge over river and railroad in Altavista. Signed detour in place. EASTER 2019 VDOT will lift most lane closures for holiday travel from noon Friday, April 19 until noon Tuesday, April 23. However, motorists may encounter semi-permanent work zones or travel delays in

More information

Strategies to keep people and goods moving in and through Seattle. SR 99 Closure and the Seattle Squeeze

Strategies to keep people and goods moving in and through Seattle. SR 99 Closure and the Seattle Squeeze Strategies to keep people and goods moving in and through Seattle SR 99 Closure and the Seattle Squeeze 2018-2024 Puget Sound Regional Council Transportation Policy Board January 10, 2019 How we get around

More information

Day and night time road closures and traffic changes on Campbell Street and surrounding streets, St Peters from Monday 9 April to Friday 13 April

Day and night time road closures and traffic changes on Campbell Street and surrounding streets, St Peters from Monday 9 April to Friday 13 April New M5 Work notification 4 April 2018 Day and night time road closures and traffic changes on Campbell Street and surrounding streets, St Peters from Monday 9 April to Friday 13 April A significant amount

More information

Public Information Center August 12, 2010

Public Information Center August 12, 2010 Route 52 Causeway Bridge Replacement & Somers Point Circle Elimination Project Somers Point Atlantic County Public Information Center August 12, 2010 Ocean City Cape May County Presentation Overview General

More information

PennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects

PennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects PennDOT Announces 2016 Allegheny County Highway and Bridge Improvement Projects Pittsburgh - PennDOT is pleased to announce the 2016 Allegheny County transportation improvement project list for state-owned

More information

For personal use only

For personal use only 11 October 2018 September Quarter Update 2018 Transurban today released its September quarter 2018 update. During the period, Average Daily Traffic (ADT) increased by 3.3%, with growth across all markets.

More information

KING STREET TRANSIT PILOT

KING STREET TRANSIT PILOT KING STREET TRANSIT PILOT Update toronto.ca/kingstreetpilot #kingstreetpilot UPDATE Average streetcar travel times in continued to show similar trends as first observed in November. The most significant

More information

2 ROUTES LEAVING FROM THE AIRPORT

2 ROUTES LEAVING FROM THE AIRPORT STARTING JUNE 8, 08 Terminus Station Métro station de métro Station Transfert de station correspondance Station Intermodal intermodale station 4 hours / day 7 days / week Ascenseur Elevator Ascenseur Orange

More information

STARTING AUGUST 27, ROUTES LEAVING FROM THE AIRPORT. Terminus at Lionel-Groulx. Only one stop 25 to 35 minutes See in timetable

STARTING AUGUST 27, ROUTES LEAVING FROM THE AIRPORT. Terminus at Lionel-Groulx. Only one stop 25 to 35 minutes See in timetable STARTING AUGUST 7, 08 Airport/ Downtown Terminus Station Métro station de métro Station Transfert de station correspondance Station Intermodal intermodale station 4 hours / day 7 days / week Ascenseur

More information

October 31, 2014 Chuck McGinness, (954)

October 31, 2014 Chuck McGinness, (954) From: McGinness, Charles To: McGinness, Charles Subject: FDOT Broward County Traffic Impact Report 10 31 14 through 11 07 14 Date: Friday, October 31, 2014 2:59:04 PM Attachments: image002.png October

More information

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg)

Exit 148 (Quantico) to Exit 133 (Route 17/Fredericksburg) RELEASE: IMMEDIATE March 1, 2019 CONTACT: Darragh Frye 540-907-8409 (mobile) VDOT HOT SPOTS IN THE FREDERICKSBURG DISTRICT March 3 March 9, 2019 All work is scheduled weather permitting. Real-time information

More information

Memorandum. To: From: cc: Date: November 7, Re: 1.0 Purpose and Organization of this Addendum. 2.0 Project Description

Memorandum. To: From: cc: Date: November 7, Re: 1.0 Purpose and Organization of this Addendum. 2.0 Project Description Memorandum To: From: cc: Laura Prickett, Horizon Water and Environment Analette Ochoa and Wana Chiu, WRECO Parag Mehta, Kimley Horn Date: November 7, 2017 Re: Santa Cruz Route 1 Tier I and Tier II HOV

More information

Liste de disponibilités

Liste de disponibilités Liste de disponibilités DISPONIBILITÉS LOCATION DE BUREAUX / OFFICE LEASING AVAILABILITIES Photo Adresse Description Min p.c./s.f. Max p.c/s.f. Prix / Price 4480, Côte-de-Liesse, Town of Mount Royal PROMOTION:

More information

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY

FOR IMMEDIATE RELEASE Fiorella Teodista January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY TRAFFIC ADVISORY FOR IMMEDIATE RELEASE Fiorella Teodista 954-934-1130 January 5, 2018 SOUTH FLORIDA AND TREASURE COAST WEEKLY LANE CLOSURES AND WORK ZONE ADVISORY FORT LAUDERDALE Florida s Turnpike announces

More information

MEMORANDUM. Open Section Background. I-66 Open Section Study Area. VDOT Northern Virginia District. I-66 Project Team. Date: November 5, 2015

MEMORANDUM. Open Section Background. I-66 Open Section Study Area. VDOT Northern Virginia District. I-66 Project Team. Date: November 5, 2015 MEMORANDUM To: VDOT Northern Virginia District From: I-66 Project Team Date: November 5, 2015 Subject: Open Section Background The purpose of this technical memorandum is to provide narrative and technical

More information

Viaduct Demolition at Girard Interchange

Viaduct Demolition at Girard Interchange i-95news summer/fall 2015 2015 Stay current with construction at the Cottman Avenue, Betsy Ross Bridge/Aramingo Avenue and Girard Avenue interchanges at. PennDOT is enhancing communications with its I-95

More information

TRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District

TRAFFIC ALERT FOR FEBRUARY 11-15, 2019 Highway Work Zones in the Staunton District RELEASE: IMMEDIATE February 8, 2019 CONTACT: Sandy Myers 540-332-9201 (office) STA19 027 540-292-2500 (cell) Sandy.Myers@VDOT.virginia.gov Ken Slack 540-332-9264 (office) 540-414-5670 (cell) Ken.Slack@VDOT.virginia.gov

More information

5.7 Local road upgrades

5.7 Local road upgrades 5.7 Local road upgrades Local roads around the St Peters interchange and the intersection of Campbell Road and Euston Road would be upgraded to ensure safe and efficient connections with the New M5, and

More information

State Project Reconstruction I-84

State Project Reconstruction I-84 State Project 151-273 Reconstruction I-84 Waterbury, Connecticut FROM WASHINGTON STREET TO PIERPONT ROAD I-84 Constructors J.V. Robert Turner Area Engineer Ken Fargnoli District Engineer John Dunham Assistant

More information

CALIFORNIA HIGH-OCCUPANCY VEHICLE LANE DEGRADATION ACTION PLAN

CALIFORNIA HIGH-OCCUPANCY VEHICLE LANE DEGRADATION ACTION PLAN CALIFORNIA DEPARTMENT OF TRANSPORTATION CALIFORNIA HIGH-OCCUPANCY VEHICLE LANE DEGRADATION ACTION PLAN Prepared by Division of Traffic Operations Office of Traffic Management Submitted to Federal Highway

More information

I-270 Bridge Renovation at New Florissant Road

I-270 Bridge Renovation at New Florissant Road I-270 Bridge Renovation at New Florissant Road What is the problem? The I-270 bridge over New Florissant Road in north St. Louis County is more than 50 years old. It is classified as structurally deficient

More information