1 Huntsville International Airport Master Plan Update June 28, 2017
2 Agenda Welcome and introductions Master planning process Inventory of existing conditions Forecasts of aviation demand Facility requirements Project schedule Next steps/action items Your thoughts 2
3 Master Planning Process HMCAA Briefing HMCAA Briefing HMCAA Briefing HMCAA Briefing 3
4 Inventory of Existing Conditions Huntsville International Airport
5 Inventory of Existing Conditions Airport characteristics and local profile Airport access, transportation, and parking Landside facilities Airfield facilities Operational characteristics Support facilities Security and airspace Utilities and infrastructure Environmental factors 5
6 Project Study Area Small-Hub Commercial Service Airport 7,000 acres Parallel runway system capable of handling large commercial aircraft Interstate access Jetplex Industrial Park Over 2,882 acres available for immediate development Foreign Trade Zone #83 International Intermodal Center 6
7 Existing Airfield Facilties 7
8 Terminal Area Huntsville International Airport
9 HSV Terminal Developments $25.9 million baggage claim expansion opens AirTran service SWA/AirTran merger and loss of service to HSV GLO service start Fall 2016 Impact of mergers on direct flight destinations Flights decreased Total seats available increased Source: HMCAA Financial Statements 9
10 HSV Terminal Area Robust and flexible terminal area Land availability Landside/ highway access Airfield and apron capacity Airspace clearances and ATCT views 10
11 Terminal Area 11
12 Terminal Building 12
13 Forecasts of Aviation Demand Huntsville International Airport
14 Importance of Forecasts Develop a realistic assessment of market conditions and market performance Address unique local conditions not fully considered in national and macro level forecast efforts Provide a benchmark for comparing current facilities against a reasonable estimate of future demand to define future facility needs 14
15 Factors and Opportunities Sharp fuel price increases after Hurricane Katrina damaged Gulf Coast refineries (August 2005) Economic Recession (late 2000s) Hurricane Matthew: airline cancellations and temporary aircraft relocations to HSV (October 2016) Local trends are important as they provide airport-specific information that may support the selection of preferred forecasts Generation Air Transportation System (NextGen) initiatives 15
16 Industry Wide Development Trends Airline Mergers American/US Airways (2013) SWA/AirTran (2011) United/Continental (2010) Delta/Northwest (2008) Airlines load factors highest in history (84.5+% ) Remote check-in options decrease on-site ticketing Flights decreased in number Total seats per flight higher 16
17 Historical Enplanements ( ) 700,000 Unadjusted Terminal Area Forecast Enplanements 600, , , , , ,
18 Forecast Summary Passenger Enplanements Based Aircraft Aircraft Operations 18
19 Air Cargo Huntsville International Airport
20 Panalpina Overview Panalpina supports 18 operations a week to/from HSV Occupies an on ramp facility at HSV Huntsville is a closed operation Panalpina does not board freight for other freight forwarders, with the 20
21 Top 25 Global Freight Forwarders Rank Provider 1 DHL Supply Chain & Global Forwarding 2 Kuehne + Nagel 3 DB Schenker Logistics 4 Sinotrans 5 Panalpina 6 Nippon Express 7 CEVA Logistics 8 Expeditors International of Washington 9 UPS Supply Chain Solutions 10 SDV (Bolloré Group) 11 DSV A/S 12 Kintetsu World Express 13 Agility Rank Provider 14 Pantos Logistics 15 C.H. Robinson 16 Hellmann Worldwide Logistics 17 Damco 18 Kerry Logistics 19 UTi Worldwide 20 Yusen Logistics 21 Toll Holdings 22 Geodis 23 Logwin 24 Sankyu 25 BDP International Source: Armstrong & Associates,
22 Rail Overview HMCAA operates an intermodal facility for Norfolk Southern Railway at HSV CSX and NS provide a rail link between east coast ports Interchanges with western rail carriers (UP and BNSF) providing service from both US coasts FedEx, UPS and Amazon utilize rail intermodal today with expectations of expanding use in the future 22
23 Key Industry Sectors Automotive Cold Chain Pharmaceutical Aerospace Live Animal Shipments E-Commerce 23
24 Global E-Commerce Fast Growing Industry Segment According to e-marketer, 15-16% year-overyear through 2020 Cross border retail volumes will increase at a rate of 25% between 2015 and 2020, rising from $300 billion to $900 billion Significant volumes of growth is occurring between U.S., China and Europe (Panalpina supports these lanes) Establishing an e-commerce strategy will require a partnership between the airport, Panalpina, and major retailers to align efforts to capture business in HSV 24
25 Global Cargo Growth Projections The forecasts continue to favor air cargo growth: The International Air Transport Association projects 4.1% CAG ( ) International market forecast specialist Sandler Research projects 5.97% growth each year ( ) The Boeing Company projects 4.2% CAG ( ) Leading international market research firm Technavio projects 4.57% ( ) 25
26 High Growth Cargo Forecast ( ) HSV 20-Year Forecast Based on 5% Growth Rate Across UPS/FedEx and Non-Permitted Carriers and 8% Growth Rate for Panalpina Year Total UPS/FedEx (Pounds) Panalpina (Pounds) Non-Permitted Carriers (Pounds) Total All Carriers (Pounds) ,999, ,699, , ,461, ,249, ,355, , ,405, ,512, ,263, , ,615, ,787, ,524, , ,194, ,077, ,246, , ,250, ,381, ,546, , ,900, ,700, ,550,472 1,020, ,271, ,035, ,394,510 1,071, ,501, ,386, ,226,070 1,125, ,738, ,756, ,204,156 1,181, ,142, ,144, ,500,489 1,240, ,885, ,551, ,300,528 1,302, ,154, ,978, ,804,570 1,368, ,151, ,427, ,228,935 1,436, ,093, ,899, ,807,250 1,508, ,214, ,394, ,791,830 1,583, ,769, ,913, ,455,177 1,662, ,031, ,459, ,091,591 1,745, ,297, ,032, ,018,918 1,833, ,884, ,634, ,580,432 1,924, ,139, ,265, ,146,866 2,021, ,433,995 26
27 Forecast of Cargo Facilities Year New Facilities Panalpina (Pounds) ,699, ,355, ,263, ,524, ,246, ,546, Yes 310,550, ,394, ,226, ,204, ,500, Yes 456,300, ,804, ,228, ,807, ,791, ,455, Yes 724,091, ,018, ,580, ,146,866 The new facilities shown indicate the year in which a new building will need to be delivered for occupancy in order to support the forecasted increase in cargo volumes. 27
28 Additional Considerations, Making the Forecast a Reality The availability of significant industrial property that can be developed at/near HSV provides a great deal of flexibility in planning for the utilization of this industrial land. The planning must take into consideration several prospects: Development of land at/near the HSV by air cargo derived occupiers Development of land at/near the HSV by logistics service providers or other global freight forwarders who utilize the Norfolk Southern Intermodal Terminal as a foundation for their logistics service activities while routing air cargo to/from other gateway or major airports 28
29 Additional Considerations, Making the Forecast a Reality Development of land at/near the HSV for use in supporting the aerospace and space/flight support Development of land at/near the HSV for use in expanding maintenance, repair and overhaul activities by existing or new service providers who would create a new MRO hub at HSV Development of land at/near the HSV for a new campus for global delivery and fulfillment of high volumes of e-commerce. This campus would include high volume sortation facilities, last mile sortation facilities and aggregation/de-aggregation facilities to support merging shipment from disparate retailers or manufacturers for outbound or from inbound flights 29
30 Facility Requirements Huntsville International Airport
31 Facility Requirements Passenger Terminal Area Air Cargo Facilities Airfield Capacity and Configuration Design Aircraft Identification Runway Length Analysis Runway Strength Analysis Airfield Design Standards Analysis Airfield Lighting, Markings and Signage, and Navigational Aids Parking and Terminal Access General Aviation Facilities Support Facilities Utilities Airspace and Obstruction to Air Navigation Land Area Requirements 31
32 Terminal Area Requirements Huntsville International Airport
33 HSV Terminal Analysis Areas Review for Chokepoints and Activity Triggers Consideration of Passenger Convenience / Wayfinding 33
34 Terminal Level of Service IATA Performance guidelines are generally based on a combination of Space & Time OVER DESIGN Goal for this effort was selected as the upper half of Optimum LOS LOS SUBOPTIMUM OPTIMUM LOS SUBOPTIMUM LOS UNDER-PROVIDED LOS LOS 34
35 Terminal Demand: Passengers Demand Requirements are based on the busiest hour of the average day of the busiest month New Flight Schedules and Passenger Counts maximum of 10 arriving or departing flights and 601 passengers boarding / arriving maximum of 14 arriving or departing flights and 1,080 passengers boarding / arriving Sources: Approved Forecasts; MAPS / Appendix A 35
36 Terminal Access Road The loop roadway is sufficient to accommodate traffic to the curbfront, parking, and rental car facilities through
37 Public Parking Current Public Parking totals approximately 4,000 spaces 65% in deck, 35% surface lots Current parking should meet total demand to 2026 By 2036, additional public parking of approximately 1,200 spaces will be needed 37
38 Rental Car Parking / Storage Rental Cars have current issues with adequate space for ready and return parking By 2036, they will need about double the 296 spaces currently allocated Storage and service facilities will need to be updated and expanded 38
39 Terminal Curbfront Current Level of Service is optimum in all areas By 2036, the curbfront demand will increase by about 40% overall Future level of service should remain optimum, with some reallocation of spaces 39
40 Curbside: Future Trends Transportation Network Issues Permits / Regulations Revenue Recognition Effects / Impacts - Fewer shared ride vans Fewer public transit rides Less use of Rental Cars (-5% to -10%) Less use of airport parking (-5% to -10%) Source: TRN News July / August
41 Questions / Discussion Break
42 HSV Check-In: Counters Four current airlines use 27 of the 30 available ticket positions Current agent positions are able to provide a optimum or better level of service through 2036 Space for new airlines may be needed in the future, adding another 5-8 positions Additional lobby space projected in the latter half of the planning period 42
43 HSV Check-In: Kiosks Three of the current airlines provide a total of 12 kiosk check-in locations Current agent positions are able to provide a optimum level of service through 2026 Space for new airlines may be needed in the future, adding another 3-8 kiosk positions Additional queuing space projected in the latter half of the planning period 43
44 Check-In: Future Trends 44
45 HSV Checked Baggage Screening 45
46 HSV Checked Baggage Screening 46
47 HSV Passenger Screening Current configuration allows for three lanes of passenger screening HSV has a higher portion of Pre-Check participation than many other airports Current lanes are able to provide a optimum or better level of service to 2026 Key components of demand are keeping within optimum wait times and facilitating Pre-Check Additional queuing space projected in the latter half of the planning period 47
48 HSV Passenger Screening 48
49 Questions / Discussion Break
50 HSV Aircraft Parking Current apron configuration allows for a variety of aircraft to park and load simultaneously 12 of the 14 gate positions are served by boarding bridges Current gates may meet the needs of HSV through 2036, dependent on fleet mix Source: HSV Apron rehab and bridge replacement drawings 2016 Common or shared use of gates by airlines increases capacity 50
51 HSV Holdrooms Holdrooms are available for each of the gate positions needed through 2036 Current holdrooms are well sized to allow flexible use of gates and maintain Optimum or better level of service Ground boarding gates 11 and 12 have space avaible for holdroom expansion if needed HSV Apron rehab and bridge replacement drawings
52 HSV Concourse Circulation HSV Apron rehab and bridge replacement drawings
53 HSV Concessions HSV has a suitable level of service in current concessions based on ACI Benchmarking study in 2015 for small hub airports similar to HSV The hotel provides more food and beverage choices in the non-secure area than comparable sized airports Additions to sterile (concourse) area concessions would be expected in the latter half of the planning period Some currently vacant space allows for flexibility in the future for concessions and support uses 53
54 HSV Baggage Claim Current bag claim devices provide all the capacity needed for claim frontage through 2036 The baggage system has the capacity to keep wait times to between 7 to 20 minutes The baggage unloading area for airline use is able to meet capacity requirements through 2036 Source: HSV Apron rehab and bridge replacement drawings
55 HSV Passenger Convenience Processes are less subject to provided by others (Airlines, TSA) Check-In / Ticketing Security Screening Passenger Boarding Checked Baggage Claim 55
56 HSV Passenger Convenience Waiting Experiences are more Electrical Outlets Wi-Fi Access Privacy / Entertainment Options Level of Amenities and Concessions 56
57 Questions / Discussion Break
58 Airfield Design Critical Aircraft Boeing 747-8F Aircraft Approach Category 141 to <166 knots Airplane Design Group (ADG) Tail height 66 to <80 feet Wingspan 214 to <262 feet 58
59 General Aviation Requirements ~ 53,300 SY of general aviation transient apron inventory (additional 2,300 SY over 20 years) ADG I up to ADG IV aircraft Taxilane object free area limits space for ADG III and IV Construct 15 conventional hangars over 20 years Construct 59 T-hangars over 20 years (~ 6 buildings) ~ 9,500 SF of general aviation terminal space is needed over 20 years 59
60 Support Facilities Aircraft Rescue and Firefighting meets requirements New ARFF station with flexibility to meet Index D Aircraft fuel storage Expand fuel farm to meet future demand Approximately 814,690 gallons of Jet-A storage would be needed by the end of the 20- year planning period. Airport maintenance Storage facilities Expansion to be considered near current location 60
61 Land Area Requirements Development envisioned for study may require additional property acquisition Land use compatibility Future development needs Obtain control over an runway projection zone (RPZ) Avigation easements will be assessed based upon the results of the land use analysis Continue working with area communities to ensure prevention of incompatible land uses 61
62 Schedule 62
63 Public Information Meeting #1 63
64 Next Steps Public information meeting 1 (June 28 th ) Capacity assessment and facility requirements Airport alternatives Committee Meeting (November 14 th ) Public information meeting 2 (November 14 th ) 64
65 Your thoughts... 65
AIRPORT MASTER PLAN UPDATE
AIRPORT MASTER PLAN UPDATE PENSACOLA INTERNATIONAL AIRPORT Technical Advisory Committee Meeting #2 June 20, 2017 Agenda» Introduction» Facility Requirements Airside Terminal Landside General Aviation Cargo
More information1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan
TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201
More informationCurrent and Forecast Demand
Existing Facilities Jacksonville International Airport (JIA) is served by a number of airside and landside facilities. There are two runways that serve the airport in an open V configuration. The Annual
More informationCHAPTER 1 EXECUTIVE SUMMARY
CHAPTER 1 EXECUTIVE SUMMARY 1 1 EXECUTIVE SUMMARY INTRODUCTION William R. Fairchild International Airport (CLM) is located approximately three miles west of the city of Port Angeles, Washington. The airport
More informationTallahassee International Airport Master Plan. Technical Advisory Committee Meeting #2 October 19, 2016
Tallahassee International Airport Master Plan Technical Advisory Committee Meeting #2 October 19, 2016 Agenda Welcome / Introductions Master Plan Process and Project Status Forecast of Aviation Demand
More informationBNA Master Plan Update Community Advisory Committee Meeting No. 5
A Six Sigma Organization BNA Master Plan Update Community Advisory Committee Meeting No. 5 September 19, 2012 Introductions MNAA Staff RW Armstrong Team Albersman & Armstrong, Ltd. Atkins North America,
More informationFORECASTING FUTURE ACTIVITY
EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver
More informationSAN JOSÉ INTERNATIONAL AIRPORT
SAN JOSÉ INTERNATIONAL AIRPORT NEAR-TERM TERMINAL CAPACITY ANALYSIS AIRPORT COMMISSION AUGUST 14, 2017 August 14, 2017 AGENDA 1. Forecast Review (with 14 MAP High Case) 2. Gate Requirements and Aircraft
More informationTable of Contents. Master Plan March 2014 TOC i Spokane International Airport
Table of Contents Page Chapter 1 Inventory 1. Introduction... 1 1 1.1 Community Profile... 1 2 1.1.1 Location and Setting... 1 1 1.1.2 Climate... 1 2 1.1.3 Socioeconomic Conditions... 1 5 1.1.4 Area Land
More informationTable of Contents. Overview Objectives Key Issues Process...1-3
Table of Contents Chapter One Introduction Overview...1-1 Objectives...1-1 Key Issues...1-2 Process...1-3 Chapter Two Inventory of Existing Conditions Airport Setting...2-1 Locale...2-1 Airport Surroundings...2-5
More informationSTUDY WORK GROUP MEETING No. 4. July 12, 2017
STUDY WORK GROUP MEETING No. 4 July 12, 2017 Agenda Welcome and introductions Update of project schedule Brief overview of previous SWG meeting Introduction to airport development alternatives Comments,
More informationBNA Master Plan Update Public Meeting No. 2
A Six Sigma Organization BNA Master Plan Update Public Meeting No. 2 September 18, 2012 Agenda BNA Master Plan Update Consultants Status of the BNA Master Plan Update Workstation Boards Forecasts of Aviation
More informationAirport Master Plan. Brookings Regional Airport. Runway Runway 17-35
Runway 17-35 Airport Master Plan Runway 12-30 Brookings Regional Airport Table of Contents Table of Contents Chapter 1: Master Plan Goals... 1-1 1.1. Introduction... 1 1.2. Objective 1 Identify improvements
More informationNorfolk International Airport
Norfolk International Airport Master Plan Update Technical Advisory Committee Meeting #1 Community Advisory Committee Meeting #1 January 24, 2018 Agenda Project Background Introductions Overview of Airport
More informationTABLE OF CONTENTS. General Study Objectives Public Involvement Issues to Be Resolved
TABLE OF CONTENTS Description Page Number LIST OF ACRONYMS... a CHAPTER ONE INTRODUCTION General... 1-1 Study Objectives... 1-1 Public Involvement... 1-2 Issues to Be Resolved... 1-2 CHAPTER TWO EXISTING
More informationChapter 1. Inventory
Chapter 1. Inventory Chapter 1. INVENTORY The collection and inventory of data pertinent to James M. Cox Dayton International Airport (DAY) is the initial step in a Master Plan Study and serves as the
More informationTampa International Airport Master Plan Update. December 12, 2012
Tampa International Airport Master Plan Update December 12, 2012 1 Prior Presentation Consolidated rental car and people mover Decongest curbsides and roadways Enable rental car growth Gain long term parking
More informationCHAPTER 5: Landside Facility Requirements and Development Concepts
CHAPTER 5: Landside Facility Requirements and Development Concepts Overview Implementation of the preferred intermediate-term (10-year) and long-term (20-year) airside alternatives will have a significant
More informationDRAFT FINAL REPORT AIRPORT MASTER PLAN. Rifle Garfield County Airport Revised May 15, 2014
DRAFT FINAL REPORT AIRPORT MASTER PLAN Rifle Garfield County Airport Revised May 15, 2014 As required by Paragraph 425.B(4) of FAA Order 5100.38C, Airport Improvement Program (AIP) Handbook: The preparation
More informationSTUDY WORK GROUP MEETING No. 3. November 29, 2016
STUDY WORK GROUP MEETING No. 3 November 29, 2016 Agenda Welcome and introductions Update project schedule Brief overview of previous SWG meeting Update on aviation forecasts Introduction to airfield demand/capacity
More informationKansas City Aviation Department. Update to Airport Committee Customer Service
Kansas City Aviation Department Update to Airport Committee Customer Service 1 Perspective An estimated 800,000 people participated in the Royals Word Series Parade On average 883,000 airline passengers
More informationGerald R. Ford International Airport Authority Master Plan Update A World Class Gateway
Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway Master Plan Advisory Committee (MPAC) Alternatives September 28, 2017 AGENDA Review of Previous Work Ultimate Land
More informationMaster Plan Update Community Advisory Committee Kick-off Meeting
Nashville International Airport Master Plan Update Community Advisory Committee Kick-off Meeting September 13, 2018 Agenda Welcome and Introductions Master Plan Objectives Master Plan Process BNA Vision
More informationBirmingham Airport 2033
Over the next 15 years, we will expand and improve the Airport to maximise our potential as a single runway airport by investing 500 million in new development. Our plans take account of our forecasted
More informationThe CLE Master Plan Includes:
The CLE Master Plan Includes: An inventory of existing conditions Forecasting future demand and analyzing future needs Evaluating alternative development scenarios Preparing the Airport Layout Plan Preparing
More informationCHAPTER 4: ALTERNATIVES
MSP Long Term Comprehensive Plan Update Metropolitan Airports Commission 4.1 INTRODUCTION CHAPTER 4: ALTERNATIVES Several alternatives were developed and evaluated based on their capability to meet the
More informationRNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan
RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan Project Schedule Today Slide 40 Project Vision To provide an achievable, flexible, fiscally, and environmentally
More informationERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS
EXECUTIVE SUMMARY ERIE INTERNATIONAL AIRPORT MASTER PLAN TABLE OF CONTENTS PAGE NO. CHAPTER 1-INTRODUCTION... 1-1 1.01 General...1-1 1.02 Purpose and Scope of Study...1-1 1.03 The Planning Process...1-2
More informationTABLE OF CONTENTS. Washington Aviation System Plan Update July 2017 i
TABLE OF CONTENTS Chapter 1 Overview... 1-1 1.1 Background... 1-1 1.2 Overview of 2015 WASP... 1-1 1.2.1 Aviation System Performance... 1-2 1.3 Prior WSDOT Aviation Planning Studies... 1-3 1.3.1 2009 Long-Term
More informationSouthwestFloridaInternational Airport
SouthwestFloridaInternational Airport SouthwestFloridaInternationalAirportislocatedinLee CountyalongtheGulfCoastofSouthFlorida,tenmiles southeastofthefortmyerscentralbusinessdistrict. Theprimaryhighwayaccesstotheairportfrom
More informationTechnical Advisory Committee Meeting February 29, 2016
Technical Advisory Committee Meeting February 29, 2016 Meeting Agenda Introduction Recap of Planning Process Project Status Goals and Objectives Forecasts of Aviation Demand Overview of Facility Requirements
More informationAirport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal
Airport Master Plan Rapid City Regional Airport October 2015 FAA Submittal Rapid City Regional Airport Master Plan Update Table of Contents Executive Summary... i Scope & Timeline... i Forecasts... i Preferred
More informationTABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary.
TABLE OF CONTENTS Section Page Section Page 1.0 INTRODUCTION... 1 1.1 Purpose of an... 1 1.2 Goals and Objectives... 1 1.3 Mission Statement... 2 1.4 Stakeholder/Public Involvement... 2 1.5 Major Deliverables...
More informationPrepared By: Mead & Hunt, Inc Port Lansing Road Lansing, MI 48906
Master Plan The preparation of this document was financed in part through a planning grant from the Federal Aviation Administration (FAA) as provided under Section 505 of the Airport and Airway Improvement
More informationWhat is an Airport Master Plan?
What is an Airport Master Plan? The goal of a master plan is to provide the framework needed to guide future airport development that will cost-effectively satisfy aviation demand, while considering potential
More informationExecutive Summary DRAFT
TABLE OF CONTENTS 1. Introduction... 6 2. Aviation Forecasts... 7 3. Demand/Capacity and Facility Requirements... 10 4. Terminal Demand/Capacity Analysis... 14 5. Landside Development Needs... 17 6. Support
More informationMeeting Summary ABE Master Plan Project Advisory Group (PAG) Meeting #3 August 15, Shannon Eibert, C&S Companies
Meeting Summary ABE Master Plan Project Advisory Group (PAG) Meeting #3 August 15, 2017 Prepared by: File: Attendees: Shannon Eibert, C&S Companies N93.012.001 See Sign-In List A third meeting was held
More informationPunta Gorda Airport Master Plan Update
Punta Gorda Airport Master Plan Update Draft Executive Summary Prepared for: The Charlotte County Airport Authority January 2018 Charlotte County Airport Authority James Herston, Chair Robert D. Hancik,
More informationPORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting August 23, 2016
PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting August 23, 2016 DATE: TO: FROM: Michael Ehl, Director, Airport Operations Wayne Grotheer, Director, Aviation Project
More informationPlanning, Development and Environment Committee
Page 1 of 7 MEMORANDUM TO: Planning, Development and Environment Committee FROM: Neil Ralston, Airport Planner Airport Development (726-8129) SUBJECT: 2035 MSP LONG TERM COMPREHENSIVE PLAN FORECAST, FACILITY
More informationGSP TERMINAL IMPROVEMENT PROGRAM PRESS KIT
About GSP MISSION STATEMENT At Greenville-Spartanburg International Airport (GSP), we begin each day fully committed to finding new ways to achieve our mission to provide the citizens of Upstate South
More informationDraft Concept Alternatives Analysis for the Inaugural Airport Program September 2005
Section 10 Preferred Inaugural Airport Concept 10.0 Introduction The Preferred Inaugural Airport Concept for SSA was developed by adding the preferred support/ancillary facilities selected in Section 9
More informationFUTURE PASSENGER PROCESSING. ACRP New Concepts for Airport Terminal Landside Facilities
FUTURE PASSENGER PROCESSING ACRP 07-01 New Concepts for Airport Terminal Landside Facilities In association with: Ricondo & Associates, TransSolutions, TranSecure RESEARCH Background Research Objective
More informationTable of Contents. List of Tables. Cincinnati/Northern Kentucky International Airport 2035 Master Plan Update
Table of Contents 7.1. Airport Layout Plan (Existing Conditions)... 2 7.2. Airport Layout Plan (Future Conditions)... 3 7.3. Technical Data Sheet... 5 7.4. Commercial Terminal Area Drawing... 5 7.5. East
More informationAppendix D Project Newsletters. Tacoma Narrows Airport. Master Plan Update
Appendix D Project Newsletters Tacoma Narrows Airport Master Plan Update This appendix contains the newsletters distributed throughout the project. These newsletters provided updates and information on
More informationThe demand/capacity analysis was performed utilizing Federal Aviation Administration (FAA) publications, including the following:
Chapter Three To properly plan for the future of Monterey Regional Airport, it is necessary to examine the capacities of the key airport systems. This chapter uses the results of the forecasts prepared
More informationExecutive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport
Executive Summary MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport As a general aviation and commercial service airport, Fort Collins- Loveland Municipal Airport serves as an important niche
More informationMASTER PLAN UPDATE. Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT. Meeting #4
MASTER PLAN UPDATE Planning Advisory Committee (PAC) FRESNO YOSEMITE INTERNATIONAL AIRPORT Meeting #4 December 14, 2017 Today s Agenda o Welcome o Introductions o Progress update o Alternatives analysis
More informationElevating the Upstate
Greenville-Spartanburg Int l Airport Elevating the Upstate SC Economic Developers Association October 12, 2012 Introduction/Presentation Outline Introductions Airport Overview Air Service Terminal Improvement
More informationTO: Planning Advisory Committee (PAC) Members RE: Pangborn Airport Master Plan PAC Meeting #4 Presentation Material DATE: July 18, 2017
TO: Planning Advisory Committee (PAC) Members RE: Pangborn Airport Master Plan PAC Meeting #4 Presentation Material DATE: July 18, 2017 Please find attached for your review prior to the PAC Meeting #4,
More informationGreater Orlando Aviation Authority Orlando International Airport One Jeff Fuqua Boulevard Orlando, Florida Memorandum TO: FROM:
Greater Orlando Aviation Authority One Jeff Fuqua Boulevard Orlando, Florida 32827-4399 Memorandum TO: FROM: Participating Airlines Phil Brown, Executive Director DATE: SUBJECT: Rate Methodology for FY
More informationAppendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis
Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis ITB MAIN TERMINAL DEPARTURES LEVEL & BOARDING AREAS A & G ALTERNATIVES ANALYSIS
More informationSavannah / Hilton Head International Airport Master Plan Update
EXECUTIVE SUMMARY Savannah / Hilton Head International Airport Master Plan Update Prepared for: The Savannah Airport Commission Prepared by: URS Corporation In Association With: RS&H and Ruth and Associates,
More informationPLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) - MEETING #4
MASTER PLAN ADVISORY COMMITTEE (MPAC) - MEETING #4 MASTER PLAN ADVISORY COMMITTEE (MPAC) MEETING #4 AGENDA & ACTION ITEMS Date/Time: Location: Monday, March 19, 2018 from 1:30-3:30 p.m. Thun Field Airport
More informationCVG Overview Connect with CVG March 29, 2017
CVG Overview Connect with CVG March 29, 2017 Launching Point Strategic Plan CVG Launching Point Strategies for 2016 and Beyond Vision: Make travel through CVG and unforgettably positive experience Mission:
More informationPublic Information Meeting. September 2015
W ki P O & T / Working Papers One & Two/ Public Information Meeting September 2015 Agenda Introductions and Opening Comments Project Overview, Process, and Schedule Review Materials from Working Papers
More informationCity of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan. Public Workshop #2 April 19, 2018
City of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan Public Workshop #2 April 19, 2018 DISCUSSION TOPICS Introduction About the Master Plan Public Workshop #1 Recap
More informationWelcome to the Boise Airport Master Plan Update Open House
Welcome to the Boise Airport Master Plan Update Open House Get the facts and sign up for the Master Plan Update newsletter at http://www.iflyboise.com/about-boi/master-plan/ What does the Master Plan Update
More informationMaster Plan Update Technical Advisory Committee Meeting
Nashville International Airport Master Plan Update Technical Advisory Committee Meeting February 14, 2019 Agenda Welcome and Introductions Aviation Activity Forecast Facility Requirements Alternatives
More informationCapacity Planning Overview
Capacity Planning Overview Brazil Strategic Airport Capacity Improvement Project August 2016 1. Capacity Primer Capacity Basics Capacity is how much stuff something holds Measurement depends on the stuff
More informationNORTHERN ROCKIES REGIONAL AIRPORT Terminal Expansion ANALYSIS 31 st August 2012
NORTHERN ROCKIES REGIONAL AIRPORT Terminal Expansion ANALYSIS 31 st August 2012 INTRODUCTION The purpose of this report is to analysis the current schedule of operations and assumptions within the 2010
More informationState of the Airport Robert S. Bowen, Executive Director October 18, 2018
Robert S. Bowen, Executive Director October 18, 2018 A Year of Change The last year will be remembered as a period when the airlines, bolstered by a growing national economy, moderate fuel prices and changing
More informationNOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019
NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019 The City of Atlanta is providing an opportunity for public comment until April 25, 2019 related to the
More informationOmaha Airport Authority Eppley Airfield
June 13, 2018 Omaha Airport Authority Eppley Airfield Terminal Development Program Industry Day Previous Master Plan Results 1996 2014 2 June 13, 2018 Eppley Airfield Terminal Development Program Industry
More informationWestover Metropolitan Airport Master Plan Update
Westover Metropolitan Airport Master Plan Update June 2008 INTRODUCTION Westover Metropolitan Airport (CEF) comprises the civilian portion of a joint-use facility located in Chicopee, Massachusetts. The
More informationAirlake Airport 2035 Long Term Comprehensive Plan (LTCP)
Airlake Airport 2035 Long Term Comprehensive Plan (LTCP) Public Informational Meetings August 9 & 10, 2017 Draft LTCP Overview Briefing Agenda Airport Role & Context Existing Conditions & Previous Plan
More informationDEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER
PETE FLAHERTY COMMISSIONER TOM FOERSTER CHAIRMAN DEPARTMENT OF AVIATION BARBARA HAFER COMMISSIONER STEPHEN A. GEORGE DIRECTOR ROOM M 134, TERMINAL BUILDING GREATER PITTSBURGH INTERNATIONAL AIRPORT PITTSBURGH,
More informationBlue Grass Airport (LEX) serves the needs of a multi-county area that
SUMMARY BACKGROUND This Master Plan Update balances needed airport improvements with the goals of the community and arrived at a consensus on how to best meet future demand without sacrificing those natural
More information3.9 AIRPORT SUPPORT FACILITIES
3.9 AIRPORT SUPPORT FACILITIES This section details additional airfield facilities that may be required over the next 20 years. 3.9.1 Airport Rescue and Fire Fighting (ARFF) Station GEG is certified under
More informationaircargo center Charlotte Charlotte Your Cargo Connection Connecting The Carolinas to the World
Charlotte aircargo center Connecting The Carolinas to the World Charlotte Looking for an affordable alternative to Atlanta and Washington? Consider Charlotte Air Cargo Center for your cargo connections.
More informationPublic Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport
Re: Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport Los Angeles World Airports (LAWA) intends to submit
More informationMONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES
MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES Recurring topics emerged in some of the comments and questions raised by members of the
More informationMASTER PLAN UPDATE GRANT NUMBER
T MASTER PLAN UPDATE D R AF GRANT NUMBER 3-48-0062-42 MAY 2015 1. Introduction... 1-1 1.1 History of Dallas Love Field... 1-1 1.2 Airport Setting... 1-2 1.2.1 DALLAS-FORT WORTH-ARLINGTON METROPOLITAN STATISTICAL
More informationCharles H. Ada II Executive Manager A.B. Won Pat International Airport Guam
Charles H. Ada II Executive Manager A.B. Won Pat International Airport Guam ABOUT THE GUAM AIRPORT Autonomous instrumentality of the Government of Guam; created in 1975 by P.L. 13-57; only commercial
More information8.0 AIRPORT LAYOUT PLANS
8.0 AIRPORT LAYOUT PLANS This chapter presents a detailed graphic and narrative description of the selected development concept for General Mitchell International Airport (MKE). The plans package presented
More informationExecutive Summary This document contains the Master Plan for T. F. Green Airport. The goal of a master plan is to provide a framework of potential future airport development in a financially feasible manner,
More informationPublic Workshop #7 Land Use Planning June 28, 2016
Public Workshop #7 Land Use Planning June 28, 2016 Land Use Planning and Vision 2040 What is Land Use Planning in the context of the Vision 2040 process? Vision 2040 Aeronautical Development Land Use Compatibility
More informationEXHIBIT E to Signatory Airline Agreement for Palm Beach International Airport RATE AND FEE SCHEDULE
EXHIBIT E to Signatory Airline Agreement for Palm Beach International Airport RATE AND FEE SCHEDULE SECTION I - DEFINITIONS The following words, terms and phrases used in this Exhibit E shall have the
More informationTERMINAL DEVELOPMENT PLAN
5.0 TERMINAL DEVELOPMENT PLAN 5.0 TERMINAL DEVELOPMENT PLAN Key points The development plan in the Master Plan includes the expansion of terminal infrastructure, creating integrated terminals for international,
More informationFort Wayne International Airport Master Plan Study. Executive Summary
Fort Wayne International Airport Master Plan Study Executive Summary March 2012 Introduction Airport Background Forecast of Aviation Activity Development Plans Recommended Airfield & Access Development
More informationForecast and Overview
Forecast and Overview DENVER INTERNATIONAL AIRPORT Overall goals of the (MPR): Work with DEN to refine the preferred airport development plan to guide the development over an approximate 25-year planning
More informationElement 640 State of Rhode Island Airport System Plan - Overview
Element 640 State of Rhode Island Airport System Plan - Overview This document represents the Rhode Island Airport Corporation s (RIAC) plan for the state airport system (ASP). The plan establishes state
More informationChapter 2 FINDINGS & CONCLUSIONS
Chapter 2 FINDINGS & CONCLUSIONS 2.01 GENERAL Dutchess County acquired the airport facility in 1947 by deed from the War Assets Administration. Following the acquisition, several individuals who pursued
More informationmsp macnoise.com MSP Noise Oversight Committee (NOC) November 17, 2010
MSP Noise Oversight Committee (NOC) November 17, 2010 Operations Update Technical Advisor s Report Summary MSP Complaints September October 2010 3,025 3,567 2009 6,350 6,001 Total Operations September
More informationIntroduction DRAFT March 9, 2017
Chapter Overview The City of Redmond (City) initiated an update to the Airport Master Plan ( Plan ) to assess the facility and service needs of the Redmond Municipal Airport ( the Airport ) throughout
More informationAppendix 6.1: Hazard Worksheet
Appendix 6.1: Appendix 6.1: Ref. Condition, real or potential; that can cause injury, illness, etc. This is a prerequisite for an Airfield Hazards 1. Taxiway Geometry Direct access to runway from ramp
More information2012 AIRPORT MASTER PLAN 2016 ADDENDUM VOLUME 1 SUBMITTED ON: SEPTEMBER 22, 2017
VOLUME 1 2012 AIRPORT MASTER PLAN 2016 ADDENDUM SUBMITTED ON: SEPTEMBER 22, 2017 VOLUME 1 CONTENTS SECTION 1 - INTRO AND AIRPORT CONTEXT SECTION 2 - FORECAST SECTION 3 - AIRFIELD FACILITIES AND DEMAND/CAPACITY
More informationMeeting Presentation. Sacramento International Airport Master Plan Update October 30, 2012
Meeting Presentation Master Plan Update October 30, 2012 Agenda We encourage open discussion during today s meeting Team Goals Background (Airport Master Plans) Areas of Emphasis Schedule Special Concerns
More informationNOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018
NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018 LAWTON-FORT SILL REGIONAL AIRPORT LAWTON, OKLAHOMA PASSENGER FACILITY CHARGE PROPOSED
More informationSTUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES
INTRODUCTION An Airport Master Plan provides an evalua on of the airport s avia on demand and an overview of the systema c airport development that will best meet those demands. The Master Plan establishes
More informationGeneral Aviation Master Plan Update
Peter O. Knight Airport Public Meeting #2 Peter O. Knight Airport Agenda Welcome and Introductions HCAA System of Airports Purpose of Public Meetings Master Plan Status Update Next Steps Q & A 2 Our System
More informationStudy Committee Meeting. September 2015
W ki P T / Working Paper Two/ Study Committee Meeting September 2015 Agenda Introductions and Opening Comments Project Overview, Process, and Schedule Review Materials from Working Paper Two Comments,
More informationAirport Master Plan Update
Duttchessss Countty Airrporrtt Masstterr Plan Updatte Airport Master Plan Update Final Report Dutchess County Airport Town of Wappingers, New York C&S Engineers, Inc. 499 Col. Eileen Collins Blvd. Syracuse,
More informationPLU Airport Master Plan. Master Plan Advisory Committee (MPAC) Meeting #2 October 16, 2016
PLU Airport Master Plan Master Plan Advisory Committee (MPAC) Meeting #2 October 16, 2016 Meeting Agenda 1. Introductions and Contacts [10 Minutes] 2. Plan Overview and MPAC Role [20 Minutes] 3. MPAC Visioning
More informationJOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012
1. Introduction The Federal Aviation Administration (FAA) recommends that airport master plans be updated every 5 years or as necessary to keep them current. The Master Plan for Joslin Field, Magic Valley
More informationLandside Safety Programs
Landside Safety Programs Ali Ousmane Mahamane AVN 1160- Aviation Safety Spring 2013 The paper is about the landside safety programs. Landside facilities are facilities related to ground access, vehicle
More informationPITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM
PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM FREQUENTLY ASKED QUESTIONS September 2017 Master Plan Update: 1. What is a Master Plan Update? The objective of a Master Plan Update (MPU)
More informationaircargo center Charlotte Charlotte Your Cargo Connection Connecting The Carolinas to the World
Charlotte aircargo center Connecting The Carolinas to the World Charlotte Looking for an affordable alternative to Atlanta and Washington? Consider Charlotte Air Cargo Center for your cargo connections.
More informationGreater Orlando Aviation Authority
Greater Orlando Aviation Authority Orlando International Airport & Orlando Executive Airport Budgets Fiscal Year 2017-2018 Greater Orlando Aviation Authority Orlando, Florida Greater Orlando Aviation Authority
More informationECONOMIC DEVELOPMENT INCENTIVES AND PROGRAMS. Provide Airport Encroachment Protection. Standardize Ad Valorem Tax Exemptions
ECONOMIC MASTER PLAN Florida s airport industry indicates the following programs are needed to maximize its impact on the State s economy: AIRPORT SECURITY Develop Model Security Plan for General Aviation
More information