1 METHOD OF WORKING PLAN MOWP: ISSUE NO: DATE OF ISSUE: AMENDMENT NO. YORG 14/01 Version 1 9 February AERODROME: Orange Airport PROJECT DESCRIPTION: Runway 11/29 Extension, Runway 04/22 Extension, Taxiway A & B Part Pavement Renewal, Apron Extension and Extension of Runway Lighting DATES: Approval of MOWP: 21 Mar 2014 Commencement of Works: 24 March 2014 Completion of Works: 17 April 2015 Expiry of MOWP: 1 May 2015 CONTENTS Page 1 Title Page 1 2 Works Information 2 3 Restrictions to Aircraft Operations 3 4 Restrictions to Works Organisation 6 5 Administration 9 6 Authority 10 7 Drawings Illustrating Stages 1 to Distribution List Page 1 of 14

2 2. WORKS INFORMATION 2.1 MOWP Authority ORANGE AIRPORT No changes to this Method of Working Plan can be made without the approval of the Airport Manager and Safety Coordinator named in this MOWP. 2.2 Description of work This MOWP covers Airside Works in two areas of the Orange Aerodrome:- Stage 1 (Work Area A) Runway 11/29 is to be extended by 210m to the Northwest. This includes New Pavement, Lighting and Secondary Illuminated Wind Direction Indicator and relocation of Signal Area. Runway 04/22 is to be extended by 135m to the Southwest. Stage 2 (Work Area B) Provide a new apron at the western side of the RPT Apron (including 100m of Taxiway B). This includes Pavement Renewal, Pavement extension and relocation of taxiway lights. 2.3 Execution of Work The project commenced in March 2014 and is expected to be completed by the end of April The actual date and time of commencement of each stage of the works will be notified by NOTAM, which will be issued at least 48 hours before work commences. No two stages can be worked on concurrently Timing, estimated, subject to weather. If dates and times change, a new Notam will be issued advising of these changes. Stage 1 (Work Area A) 24 March 2014 to 18 February 2015 Stage 2 (Work Area B) 19 February 2015 to 2 April Hours of Work The works will be conducted Monday to Friday between the hours of 07:30 and 17:00, with no work on Saturdays, Sundays or public holidays. Page 2 of 14

3 2.5 Work during inclement Weather ORANGE AIRPORT Work may continue during rain and poor visibility at the discretion of Airport WSO and Safety Co-ordinator. 3. RESTRICTIONS TO AIRCRAFT OPERATIONS 3.1 General Stage 1 (Work Area A) The Western Threshold on Runway 11 will be displaced by 270m for the entire period of the works in this stage. The Take Off Distance Available (TODA) will be reduced to 1727m for Runway 11 and 1676m for Runway 29. The Landing Distance (LDA) on Runway 29 will be reduced to 1606m. The Landing Distance on Runway 11 will be reduced to 1406m, as indicated in Annexure A1. This will be covered by a NOTAM. To achieve the above men and equipment will vacate the western end of the Runway within Work Area A during specific aircraft landing on runway 11 and landing and departing 29 for aircraft over 10,000kg MTOW or other aircraft that make a specific request. Distances RUNWAY TORA TODA ASDA LDA m 1727m 1606m 1406m m 1676m 1606m 1606m The Precision Approach Path Indicator System (PAPI) will not be available on Runway 11 during this stage of the works and will be included in the Notam. Runway 04/22 will be closed during this stage of the works. This will be covered by a NOTAM. Stage 2 (Work Area B) As indicated in Annexure B the Western end of the Apron will be closed for works to be undertaken. Access to the Apron will not be available via Taxiway B. All Ops are to use Taxiway A during this stage. This will be covered by a NOTAM. 3.2 Emergencies During Stage 1 if a pilot declares an inflight emergency then men and equipment will be vacated from the works area and the full runway of 1606m will be available for landing. Page 3 of 14

4 3.3 NOTAM The actual dates, times of commencement and duration of all work will be confirmed by NOTAM issued at least 48 hours before work commences. The following NOTAM will apply. STAGE 1 NOTAMN A YORG B Local time C XXXXXX Local time E THR RWY 11 DISP 270m and RWY length reduced 70m due WIP. RWY 11, TORA 1606m, TODA 1727m, ASDA 1606m, LDA 1406m, RWY 29, TORA 1606m, TODA 1676m, ASDA 1606m, LDA 1606m Runway 11 PAPI and RTIL not available. Pilots are to give advanced radio notification of landing and departure. TXY B not available between RWY and TXY D NOTAMN A YORG B Local Time C XXXXXX E RWY 04/22 closed due WIP. NOTAMN A YORG B XXXXXX Local Time C XXXXXX E PRI IWI & Signal circle relocated to northern side of 11/29. Sec IWI relocated approximately 530m west of PRI IWI. STAGE 2 NOTAMN A YORG B XXXXXX Local Time C XXXXXX E TXY B west of Apron and east of TXY C not available due WIP. Access to apron via TXY A. Page 4 of 14

5 3.4 Marking the Unserviceable Area All work areas will be marked in accordance with the standards in MOS Part 139 Aerodromes Chapter 8 and 9. Standard Unserviceability markers, markings and lights will be provided as shown on Annexures A, B & C. The displaced threshold will be marked by markings and lights as shown on Annexure A. No aircraft, whether under power or tow, is to enter any closed work area unless authorised by WSO. 4. RESTRICTIONS TO THE WORKS ORGANISATION 4.1 General During all stages all works vehicles are to remain behind the limits of work safety area defined by a row of orange cones and orange lights when they are in place. The hours of work on site will be from 07:30 to 17:00 Monday to Friday local time. All plant or works equipment will be kept outside aircraft movement areas and under OLS outside working hours. 4.2 Works Commencement This Method of Working Plan is not an approval to commence works. The Airport Manager or Safety Co-ordinator are the only persons that can approve the commencement of any stage of work 4.3 Access to the Works Site All personnel associated with the work shall be bound by any instructions issued by the WSO who may refuse access to persons likely, in their opinion, to compromise aircraft safety on the aerodrome. All personnel will at all times be required to wear safety vests while in the works area. The maximum height of vehicles and equipment for Stage 1 of the works is to be 4m. Higher vehicles can be used during the works with the permission of the WSO. The vehicles and plant used for these works are to display clearly visible amber rotating beacons. Access to the Works Areas in all three stages shall be via the following:- Stage 1 (Work Area A) All Vehicles and deliveries will be via Gate A as shown on Annexure D Page 5 of 14

6 Stage 2 (Work Area B) All Vehicles and deliveries will be via Gate B as shown on Annexure D There will be an Orange City Council Gate Operator who will be in radio contact with the WSO at all times. Vehicles that require access to the site must be authorised by the WSO and comply with the requirements of the MOS 139. No vehicle will be allowed access or egress through any other gate except as approved by the Safety Coordinator and/or WSO. Vehicles and plant moving between the access gate and the works site must follow the route specified on Annexure D or as directed by WSO. 4.4 Marking the Unserviceable Area All work areas will be marked in accordance with the standards in MOS Part 139 Aerodromes Chapter 8 and 9. Unserviceability markers and markings will be provided as shown in the Annexures A, B, C & D. 4.5 Electrical Services and Control Cables The Works Organisation, Orange City Council, before the commencement of any works, will check the location of any electrical services and control cables with the Orange Airport Manager. The existing runway and wiring circuits within the works area are to be protected from damage. Any damage must be notified immediately to the Works Safety Officer and Safety Co-ordinator. 4.6 Airport Security A Special Event Zone (SEZ ) has been approved for Stage 1. This SEZ is for the construction of the Extension of Runways 11/29 and 04/22. The SEZ allows for the large number of contractors not requiring a ASIC and minimises the time for these construction works to proceed. All gates that access the airside of Orange Airport are to be manned and remain closed and secure during the period of these works. The Orange City Council Gate Operator will be required to maintain a log of all access to and from the airside. Another SEZ has been approved for Stages 2 being for the new apron on the western side of the RPT apron. The gate is to be manned and kept secure during Stage 2 works and a log kept of all access to and from the airside. Page 6 of 14

7 4.7 Airport Emergencies Under certain aircraft emergency situations, access to the airside of the airport including the work site will not be allowed. Men and equipment will vacate the works area at the direction of the WSO or Safety Co-ordinator at any time upon the announcement of Emergency, Emergency, Emergency, vacate airside work area to muster point. Because of the unpredictable nature of emergency situations it is not possible to give advance warning of these occurrences. 4.8 Pavement Cleanliness The contractor is to ensure that aircraft pavements used or crossed during the works are kept clean and free of debris. A sweeper, approved by the Airport Manager, is to be kept on call at all times whilst works are in progress. 4.9 Operation of Cranes A permit must be obtained prior to the erection of any crane on the airport. Permits will be available from the Works Safety Officer and will be valid for a single operation only Excavations All excavations adjacent to the active runway must be filled at the end of each day s work. No trench may be left open and unattended or unprotected at any stage No Smoking A no smoking rule applies at all times on the airside of the airport Parking of Private Vehicles Only vehicles and plant actually engaged in the work will be permitted Airside. All other vehicles must be parked at a site pre-arranged with the Airport Manager Waste Disposal and Environment Protection Any putrescible waste generated at the site is to be placed in secure rubbish bins and removed from the site at the end of each days works. The contractor must ensure that all other waste is contained within the site and not free to blow around the airport. Builders waste must be removed well clear of the runway and taxiway system to a site directed by the Works Safety Officer. Page 7 of 14

8 4.14 Completion of works Page 8 of 14 At the completion of works the contractor is to remove all equipment and rubbish from the work site and from the airside, ensure all pavements are clean and restore any damaged areas to the satisfaction of the Works Safety Officer Drug and Alcohol Testing CASA may undertake drug and alcohol testing of anyone working airside. 5. ADMINISTRATION 5.1 Project Coordination The Airport Manager is Kel Gardiner Orange City Council ph: The Project Coordinator / Project Manager is Mr Wayne Harris Orange City Council ph: The Safety Coordinator is Mr Neil Absolon Orange City Council ph: All questions relating to the technical aspect of this project should be directed to the Safety Co-ordinator or Airport Manager. 5.2 Works Organisation ORANGE CITY COUNCIL, CIVIC CENTRE, 135 BYNG ST, ORANGE NSW 2800 Ph: Fax; ; council@orange.nsw.gov.au Mr Garry Styles General Manager ph: Mr Chris Devitt Director ph: Safety Coordinator/Works Safety Officer Safety Coordinator Mr Neil Absolon Orange City Council ph: Work Safety Officer Mr Max Wicks Orange City Council ph Any queries about the conditions contained in this Method of Working Plan or the effect of the works on aircraft operations should be directed to the Safety Coordinator. All communication with aircraft during the works must be through the Work Safety Officer. An appropriately trained and qualified Works Safety Officer will be appointed by the Safety Coordinator to look after the works. The Works Safety Officers is responsible for ensuring that the works, insofar as they affect the safe operation of aircraft, are conducted in accordance with this MOWP

9 and the functions of a Works Safety Officer MOS Part Aerodromes, Chapter 10, Section In particular, the Works Safety Officers will be responsible for: ensuring that works are carried out in accordance with the conditions set out in this Method of Working Plan placement and removal of airport markers, markings and lights in accordance with the requirements of this Method of Working Plan initiating and cancelling work related NOTAM ensuring that a Works Safety Officer is present at all times during the works briefing of the works party and contractors on the safety precautions applicable during the works other duties as specified in Orange Aerodrome Manual 6. AUTHORITY 6.1 Conduct of Works All works must be carried out in accordance with the standards set down in the Civil Aviation Safety Authority publication entitled Manual of Standards (MOS) Part 139 Aerodromes and the specific conditions laid down in this Method of Working Plan. Any temporary work on the movement area must comply with the standards found in MOS Part 139 Aerodromes. 6.2 Variation 6.3 Expiry The approval of the Airport Manager must be obtained before any variation is made to this Method of Working Plan or associated NOTAM. This Method of Working Plan will expire on 1 May 2015 unless otherwise amended or extended. 6.4 Approval The Method of Working Plan is issued by Orange Airport in accordance with the Civil Aviation Safety Regulations Part 139 and the Manual of Standards Part 139 Aerodromes issued by the Civil Aviation Safety Authority and the Orange Airport Manual. This MOWP dated 9 February 2015 has been approved by Kel Gardiner Airport Manager Page 9 of 14

10 Page 10 of 14

11 Page 11 of 14

12 Page 12 of 14

13 7. DISTRIBUTION Names and Contact Details Name Position Address Phone Mobile Kel Gardiner Aerodrome Manager Orange City Council, PO Box 35, Orange John Goldsmith Aerodrome Supervisor Orange City Council, PO Box 35, Orange Neil Absolon Works Safety Officer Orange City Council, PO Box 35, Orange Pat Hannah Mrs Slavica Despotovic CASA Aerodrome Inspector Regional Express Flight Operations & NSW Air Ambulance Hangar 131 Cirrus Place, Bankstown Airport NSW Orange Aero Club RAAF Fax Air Services Aviation Relations Manager Royal Flying Doctor Service Denis Crossley Base Manager Hangar, 394 Ross Smith Av, Mascot Josh Devitt Project Manager - Civil Orange City Council, jdevitt@orange.nsw.gov.au Alliance executive@allianceairlines.com.au Max Wicks Work Safety Officer Orange City Council mwicks@orange.nsw.gov.au Page 13 of 14

14 John Omrod Airport Reporting Officer Jamie Nicol Virgin Regional Airport Manager Page 14 of 14

Vancouver Airport Authority. Contractor Safety Management Program [CSMP] Airside Contractor & Construction Safety

Vancouver Airport Authority. Contractor Safety Management Program [CSMP] Airside Contractor & Construction Safety Vancouver Airport Authority Contractor Safety Management Program [CSMP] Airside Contractor & Construction Safety - 2017 CSMP Contractor Expectations - 2017 i Contents Contents Contents Introduction ii

More information

Major Runway/Taxiway Maintenance Work Bangalore International Airport (Devanahalli) (08 MAR 2012 TO 04 MAY 2012)

Major Runway/Taxiway Maintenance Work Bangalore International Airport (Devanahalli) (08 MAR 2012 TO 04 MAY 2012) AIRAC AIP SUPPLEMENT TEL: 91-11-24632950 Extn: 2219/2233 AFS : VIDDYXAX FAX : 91-11-24615508 Email: gmais@aai.aero INDIA AERONAUTICAL INFORMATION SERVICE AIRPORTS AUTHORITY OF INDIA RAJIV GANDHI BHAVAN

More information

PART H SECTION 3 GENERAL REQUIREMENTS AND PROCEDURES GOVERNING THE EXECUTION OF WORKS ON OR ADJACENT TO AIRSIDE OPERATIONAL AREAS

PART H SECTION 3 GENERAL REQUIREMENTS AND PROCEDURES GOVERNING THE EXECUTION OF WORKS ON OR ADJACENT TO AIRSIDE OPERATIONAL AREAS H-3-1 PART H SECTION 3 GENERAL REQUIREMENTS AND PROCEDURES GOVERNING THE EXECUTION OF WORKS ON OR ADJACENT TO AIRSIDE OPERATIONAL AREAS 1. Regulations 1.1 These requirements are intended to ensure that

More information

Method of Working Plan Busselton Margaret River Regional Airport Upgrade

Method of Working Plan Busselton Margaret River Regional Airport Upgrade Method of Working Plan Busselton Margaret River Regional Airport Upgrade MOWP Number: YBLN 02/17 MOWP Issue Date: 12 October 2017 MOWP Revision: Rev 6 MOWP Revision Date: 21 ebruary 2018 Works Commencement:

More information

(a) it has been licensed for the purpose, and save in accordance with the conditions prescribed in such licence; or

(a) it has been licensed for the purpose, and save in accordance with the conditions prescribed in such licence; or PART - XI Aerodromes 78. Licensing of Aerodromes (1) No aerodrome shall be used as a regular place of landing and departure by a scheduled air transport service or for a series of landings and departures

More information

Low Visibility Operations

Low Visibility Operations Airside Operational Instruction 21 Uncontrolled when printed Page 0 of 7 1 LOW VISIBILITY OPERATIONS Policy East Midlands Airport (EMA) is committed to providing facilities and procedures to enable aircraft

More information

SAFETY NOTICE OPERATIONAL AND SAFETY PLAN FOR THE CONSTRUCTION OF NEW GENERAL AVIATION HANGAR FACILITY BRIEFING NOTES DURATION 6 MONTHS

SAFETY NOTICE OPERATIONAL AND SAFETY PLAN FOR THE CONSTRUCTION OF NEW GENERAL AVIATION HANGAR FACILITY BRIEFING NOTES DURATION 6 MONTHS SAFETY NOTICE OPERATIONAL AND SAFETY PLAN FOR THE CONSTRUCTION OF NEW GENERAL AVIATION HANGAR FACILITY BRIEFING NOTES START DATE 20 th April 2015 END DATE 11 TH September 2015 DURATION 6 MONTHS Issue 1

More information

IRELAND AERONAUTICAL INFORMATION SERVICE IRISH AVIATION AUTHORITY BALLYCASEY CROSS SHANNON CO. CLARE Tel Fax

IRELAND AERONAUTICAL INFORMATION SERVICE IRISH AVIATION AUTHORITY BALLYCASEY CROSS SHANNON CO. CLARE Tel Fax IRELAND AERONAUTICAL INFORMATION SERVICE IRISH AVIATION AUTHORITY BALLYCASEY CROSS SHANNON CO. CLARE Tel +353 61 703750 Fax +353 61 366245 DUBLIN AIRPORT (EIDW) RUNWAY 10/28 UPGRADE PHASE 1 AND PHASE 2

More information

Form No. OPS-20 Issue No. 01 Airport Safety Induction Revision No. 01

Form No. OPS-20 Issue No. 01 Airport Safety Induction Revision No. 01 Form No. OPS-20 Issue No. 01 Airport Safety Induction Revision No. 01 As the Airport operator, Archerfield Airport Corporation Pty Ltd ( AAC ) has a responsibility to provide a safe work environment for

More information

AIRFIELD OPERATIONAL INSTRUCTION 26 GENERAL AVIATION OPERATIONS

AIRFIELD OPERATIONAL INSTRUCTION 26 GENERAL AVIATION OPERATIONS AIRFIELD OPERATIONAL INSTRUCTION 26 GENERAL AVIATION OPERATIONS Return to Contents Page Liverpool John Lennon Airport 0 20161012LJAAOI26V6.0pdf AIRFIELD OPERATIONAL INSTRUCTION 26 GENERAL AVIATION OPERATIONS

More information

PERTH AIRPORT TERMINAL 4 APRON TAXIWAY REALIGNMENT AND TAXIWAYS DELTA, BRAVO AND WHISKEY CATEGORY III UPGRADE DRAFT METHOD OF WORKING PLAN

PERTH AIRPORT TERMINAL 4 APRON TAXIWAY REALIGNMENT AND TAXIWAYS DELTA, BRAVO AND WHISKEY CATEGORY III UPGRADE DRAFT METHOD OF WORKING PLAN Reference Number YPPH 007-17 Date of DRAFT Issue 12 th May2017 Amendment Number Date of Amendment CONTENTS: PERTH AIRPORT TERMINAL 4 APRON TAXIWAY REALIGNMENT AND TAXIWAYS DELTA, BRAVO AND WHISKEY CATEGORY

More information

Effective: AUSTRALIAN INTERNATIONAL AIRSHOW AVALON 2019, AVALON AIRPORT 19 FEBRUARY - 5 MARCH 2019, IFR OPERATIONS AVALON AIRPORT

Effective: AUSTRALIAN INTERNATIONAL AIRSHOW AVALON 2019, AVALON AIRPORT 19 FEBRUARY - 5 MARCH 2019, IFR OPERATIONS AVALON AIRPORT AUSTRALIA AERONAUTICAL INFORMATION SERVICE AIRSERVICES AUSTRALIA GPO BOX 367, CANBERRA ACT 2601 Phone: 02 6268 4874 Email: aim.editorial@airservicesaustralia.com Effective: AIP SUPPLEMENT (SUP) H 02/19

More information

Airport Operating Standard. Transfer of Explosive Cargo

Airport Operating Standard. Transfer of Explosive Cargo Airport Operating Standard Transfer of Explosive Cargo June 2018 Contents Introduction 2 Responsibilities 3 Approvals 4 Safe distances 6 Preferred aircraft parking position 7 Handling agent vehicular

More information

BEDFORD AERODROME LANDING REQUEST FORM

BEDFORD AERODROME LANDING REQUEST FORM BEDFORD AERODROME LANDING REQUEST FORM To request a landing at Bedford Aerodrome please complete the table below, print and sign the form, then email or fax it to us with a copy of your aircraft insurance

More information

Runway Crossings at Brisbane International Airport

Runway Crossings at Brisbane International Airport Runway Crossings at Brisbane International Airport All instructions to cross runways will be issued by Ground on 121.7 MHz All runway crossings require a specific CROSSING clearance. Runway Crossing Requirements

More information

Blackbushe Airport Terms & Conditions

Blackbushe Airport Terms & Conditions EGLKT&C v2 2018.02.01 Page 1 of 5 Blackbushe Airport Terms & Conditions 1. DEFINITIONS "Airport" means all that area comprising Blackbushe Airport at Camberley, Surrey which is operated by or under the

More information

GRANDE PRAIRIE AIRPORT. Reduced Visibility Operations Plan

GRANDE PRAIRIE AIRPORT. Reduced Visibility Operations Plan GRANDE PRAIRIE AIRPORT Reduced Visibility Operations Plan Amended November 8, 2017 Distribution List: (Updates to the Reduced Visibility Operations Plan will be circulated to this list.) Name and Title

More information

Airport Rules and Regulations

Airport Rules and Regulations Airport Rules and Regulations 10/10/2017 Contents 1 General information... 3 2 Users information... 3 2.1 Accessibility... 3 2.2 Emergency numbers... 3 2.3 Safety Department... 4 2.4 Security Control Centre...

More information

PART F SECTION 2 RESPONSIBILITIES AND ACTIONS

PART F SECTION 2 RESPONSIBILITIES AND ACTIONS F-2-1 AIRPORT OPERATIONS MANUAL AIRFIELD OPERATIONS 31 January 2011 PART F SECTION 2 RESPONSIBILITIES AND ACTIONS 1. Overview 1.1 This section outlines the responsibilities and actions of the airport organizations

More information

THE CIVIL AVIATION AUTHORITY OF THAILAND. Aeronautical Information Service Department AIP SUPPLEMENT

THE CIVIL AVIATION AUTHORITY OF THAILAND. Aeronautical Information Service Department AIP SUPPLEMENT THE CIVIL AVIATION AUTHORITY OF THAILAND AIRAC Phone: 66 02 568 8831 Fax: 66 02 576 1903 Aeronautical Information Service Department AIP SUPPLEMENT AFTN: VTBAYOYX E-mail: aisthai@caat.or.th 333/105 Lak

More information

Aerodrome Manual Part 3 Airport Technical Information

Aerodrome Manual Part 3 Airport Technical Information Aerodrome Manual Part 3 Airport Technical Information AERODROME MANUAL Part 3 Technical Information Contents Part 3 Section PART 3 TECHNICAL INFORMATION 1 Aerodrome Licence 1-1 2 Aerodrome Location and

More information

Advisory Circular CT

Advisory Circular CT (CAA logo, name of the country, etc.) Advisory Circular CT-42-009 SUBJECT: Airport Movement Area and Related Facilities Maintenance DATE: MM/YYYY ASSOCIATED RULES According with (name of the country) Civil

More information

EGSL ANDREWSFIELD EGSL AD 2.1 AERODROME LOCATION INDICATOR AND NAME EGSL AD 2.2 AERODROME GEOGRAPHICAL AND ADMINISTRATIVE DATA

EGSL ANDREWSFIELD EGSL AD 2.1 AERODROME LOCATION INDICATOR AND NAME EGSL AD 2.2 AERODROME GEOGRAPHICAL AND ADMINISTRATIVE DATA UNITED KINGDOM AIP AD 2.EGSL-1 26 May 2016 EGSL ANDREWSFIELD EGSL AD 2.1 AERODROME LOCATION INDICATOR AND NAME EGSL ANDREWSFIELD EGSL AD 2.2 AERODROME GEOGRAPHICAL AND ADMINISTRATIVE DATA 1 ARP coordinates

More information

2 Definitions Ardmore Airport Limited. Ardmore Airport Limited, as owner and operator. Airside Driving Permit.

2 Definitions Ardmore Airport Limited. Ardmore Airport Limited, as owner and operator. Airside Driving Permit. 1 Background Ardmore Airport Limited is required under the Civil Aviation Act 1990 and Civil Aviation Authority rule part 139 to establish and implement procedures for limiting and controlling access of

More information

SUPPLEMENTARY CONDITIONS APPLICABLE TO TOWER CRANES 2012

SUPPLEMENTARY CONDITIONS APPLICABLE TO TOWER CRANES 2012 SUPPLEMENTARY CONDITIONS APPLICABLE TO TOWER CRANES 2012 TO BE READ IN CONJUNCTION WITH THE CPA MODEL CONDITIONS FOR THE HIRING OF PLANT (2011) EXPLANATORY NOTE: The purpose of these Supplementary Conditions

More information

LELYSTAD AIRPORT PILOT S INFORMATION

LELYSTAD AIRPORT PILOT S INFORMATION LELYSTAD AIRPORT PILOT S INFORMATION This information bulletin contains a summary of the most relevant operational information for pilot s. Always check the AIP, the AIP SUP and NOTAM s for the latest

More information

Darley Moor Airfield Flying Orders

Darley Moor Airfield Flying Orders Darley Moor Airfield Flying Orders (Last Revised - August 2013) PLEASE CHECK AMENDMENTS FOR DETAILS OF LATEST REVISIONS AMENDMENTS REVISION 13 th AUGUST 2013 DETAILS Where required (prop-wash) pull aircraft

More information

TERRACE-KITIMAT AIRPORT SOCIETY APRON MANAGMENT PLAN

TERRACE-KITIMAT AIRPORT SOCIETY APRON MANAGMENT PLAN TERRACE-KITIMAT AIRPORT SOCIETY 2018-19 APRON MANAGMENT PLAN Table of Contents List of Effective Pages... 3 Manual Distribution and Amendment Procedures... 5 Record of Amendments... 5 Apron Management

More information

Guideline: Rules and appropriate practices for disabled aircraft removal

Guideline: Rules and appropriate practices for disabled aircraft removal Guideline for the Airport Community Guideline: Rules and appropriate practices for disabled aircraft removal Date of issue: May 2018 GUIDELINE-OCD001-R0 TABLE OF CONTENTS 1. Purpose and Scope... 3 2. Definitions

More information

ADVISORY CIRCULAR ON CALCULATION OF DECLARED DISTANCES

ADVISORY CIRCULAR ON CALCULATION OF DECLARED DISTANCES Page 1 of 6 1. PURPOSE This Advisory circular (AC) provides guidance to operators to calculated declared distances at aerodrome for safe use of runway and promulgation of aeronautical data to the aeronautical

More information

AERODROME MANUAL. (name) AIRPORT

AERODROME MANUAL. (name) AIRPORT AERODROME MANUAL (name) AIRPORT (MM/YYYY) () (FIRST PUBLISHED IN 1999) Airport Certificate The airport certificate will be found on the next page. Amendment date: 06/2008 (Airport Operator Name) Page 2

More information

OPERATIONAL SAFETY POLICY GROUND RUNNING OF AIRCRAFT MARCH This document is uncontrolled when printed

OPERATIONAL SAFETY POLICY GROUND RUNNING OF AIRCRAFT MARCH This document is uncontrolled when printed OPERATIONAL SAFETY POLICY GROUND RUNNING OF AIRCRAFT MARCH 2015 Produced by Melbourne Airport in the interest of Airport Safety and Security Printed on Maine Recycled Digital Paper Table of Contents SECTION

More information

TANZANIA CIVIL AVIATION AUTHORITY SAFETY REGULATION CHECKLIST FOR INSPECTION OF SURFACE MOVEMENT GUIDANCE CONTROL SYSTEM (SMGCS)

TANZANIA CIVIL AVIATION AUTHORITY SAFETY REGULATION CHECKLIST FOR INSPECTION OF SURFACE MOVEMENT GUIDANCE CONTROL SYSTEM (SMGCS) Page 1 of 11 AERODROME NAME: ICAO REFERENCE CODE: TRAFFIC DENSITY CLASS: (see Note 3) VISIBILITY CONDITION: (see Note 3) AERODROME INSPECTOR: DATE: S/N ICAO A SURFACE MOVEMENT GUIDANCE CONTROL SYSTEM 1

More information

Air Accident Investigation Unit Ireland

Air Accident Investigation Unit Ireland Air Accident Investigation Unit Ireland INCIDENT REPORT Boeing 737-8AS, EI-EBE, Cork Airport, Ireland 22 July 2009 Tourism and Sport An Roinn Iompair Turasóireachta Agus Spóirt Boeing 737-8AS EI-EBE Cork

More information

Control of Cranes and Other Temporary Obstacles

Control of Cranes and Other Temporary Obstacles United Kingdom Overseas Territories Aviation Circular OTAC 139-27 140-11 171-8 172-11 178-10 Control of Cranes and Other Temporary Obstacles Issue 1 1 June 2018 Effective on issue GENERAL Overseas Territories

More information

Section 32 TABLE OF CONTENTS Airfield and Aircraft Operations. 32.A General B Aircraft

Section 32 TABLE OF CONTENTS Airfield and Aircraft Operations. 32.A General B Aircraft Section 32 TABLE OF CONTENTS Airfield and Aircraft Operations Section: Page 32.A General... 32-1 32.B Aircraft... 32-4 32-i THIS PAGE INTENTIONALLY LEFT BLANK 32-i SECTION 32 Airfield and Aircraft Operations

More information

LELYSTAD AIRPORT PILOT S INFORMATION

LELYSTAD AIRPORT PILOT S INFORMATION LELYSTAD AIRPORT PILOT S INFORMATION This information bulletin contains a summary of the most relevant operational information for pilot s. Always check the AIP, the AIP SUP and NOTAM s for the latest

More information

TITLE PAGE. Method of Working Plan Melbourne Airport. Runway Maintenance to Runway 16/34 and Runway 09/27. Method of Working Plan: YMML 2018/4

TITLE PAGE. Method of Working Plan Melbourne Airport. Runway Maintenance to Runway 16/34 and Runway 09/27. Method of Working Plan: YMML 2018/4 TITLE PAGE Method of Working Plan: YMML 2018/4 Date of issue: March 2018 Method of Working Plan Melbourne Airport Runway Maintenance to Runway 16/34 and Runway 09/27 Important Dates: Date of Approval April

More information

STATUTORY INSTRUMENTS. S.I. No. 855 of 2004 IRISH AVIATION AUTHORITY (AIR TRAFFIC SERVICE SYSTEMS) ORDER, 2004

STATUTORY INSTRUMENTS. S.I. No. 855 of 2004 IRISH AVIATION AUTHORITY (AIR TRAFFIC SERVICE SYSTEMS) ORDER, 2004 STATUTORY INSTRUMENTS S.I. No. 855 of 2004 IRISH AVIATION AUTHORITY (AIR TRAFFIC SERVICE SYSTEMS) ORDER, 2004 PUBLISHED BY THE STATIONERY OFFICE DUBLIN To be purchased directly from the GOVERNMENT PUBLICATIONS

More information

Consideration will be given to other methods of compliance which may be presented to the Authority.

Consideration will be given to other methods of compliance which may be presented to the Authority. Advisory Circular AC 139-10 Revision 1 Control of Obstacles 27 April 2007 General Civil Aviation Authority advisory circulars (AC) contain information about standards, practices and procedures that the

More information

AERODROME MARKINGS AND SIGNALIZATION

AERODROME MARKINGS AND SIGNALIZATION 1. Introduction AERODROME MARKINGS AND SIGNALIZATION This article will present the main aerodrome markings and signalization on runways and taxiways. 2. Runway Markings This chapter will show the runway

More information

Aerodrome Manual. ICAO/FAA Comprehensive Aerodrome Certification Inspector Workshop. Presented To: Caribbean States By: FAA Office of Airports

Aerodrome Manual. ICAO/FAA Comprehensive Aerodrome Certification Inspector Workshop. Presented To: Caribbean States By: FAA Office of Airports ICAO/FAA Comprehensive Aerodrome Certification Inspector Workshop Presented To: Caribbean States By: FAA Office of Airports OBJECTIVE Development of an Aerodrome Manual (AM). 2 ICAO ANNEX 14 - SECTION

More information

Civil Aviation Administration - Denmark Regulations for Civil Aviation

Civil Aviation Administration - Denmark Regulations for Civil Aviation Civil Aviation Administration - Denmark Regulations for Civil Aviation BL 5-4 Regulations on sightseeing flights Edition 5, 13 June 1997 In pursuance of 72, subsection 2 of 75, and 78 and 82 of the Air

More information

Sample Regulations for Water Aerodromes

Sample Regulations for Water Aerodromes Sample Regulations for Water Aerodromes First Edition (unedited version) March 2015 Notice to users: This document is an unedited version which is made available to the public for convenience. Its content

More information

EGWN AD 2.1 LOCATION INDICATOR AND NAME EGWN - HALTON EGWN AD AERODROME GEOGRAPHICAL AND ADMINISTRATIVE DATA. 3 5nm SE of Aylesbury

EGWN AD 2.1 LOCATION INDICATOR AND NAME EGWN - HALTON EGWN AD AERODROME GEOGRAPHICAL AND ADMINISTRATIVE DATA. 3 5nm SE of Aylesbury UK MIL AIP AD 2 - EGWN - 1-1 04 AUG 05 EGWN AD 2.1 LOCATION INDICATOR AND NAME EGWN - EGWN AD 2.2 - AERODROME GEOGRAPHICAL AND ADMINISTRATIVE DATA 1 ARP Co-ordinates and site at AD: 2 Direction and distance

More information

RECONSTRUCT/REHABILITATE TRANSIENT APRON AND TAXIWAY 'A' PHASING PLAN - PHASE 1

RECONSTRUCT/REHABILITATE TRANSIENT APRON AND TAXIWAY 'A' PHASING PLAN - PHASE 1 PHASING PLAN - PHASE 1 2 Weeks PHASE 1 SCOPE OF WORK Phase 1 consists of the reconstruction of a portion of Taxiway 'A' and the crack seal and seal coat of the North Apron. The portion of Taxiway 'A' to

More information

SECTION 32. Airfield and Aircraft Operations

SECTION 32. Airfield and Aircraft Operations SECTION 32 Airfield and Aircraft Operations 32.A Airfields General. 32.A.01 The following safety requirements shall be in addition to the airfield's safety requirements. When an airfield has safety requirements

More information

AERODROME LIGHTING SYSTEM

AERODROME LIGHTING SYSTEM AERODROME LIGHTING SYSTEM 1. Introduction This chapter will show the wide variety of approach lighting systems before the runway threshold and systems present on runways. 2. Runway approach ramps 2.1.

More information

OVERSEAS TERRITORIES AVIATION REQUIREMENTS (OTARs)

OVERSEAS TERRITORIES AVIATION REQUIREMENTS (OTARs) OVERSEAS TERRITORIES AVIATION REQUIREMENTS (OTARs) Part 171 AERONAUTICAL TELECOMMUNICATION SERVICES Published by Air Safety Support International Ltd Air Safety Support International Limited 2005 First

More information

AOP 11 Low Visibility Procedures (LVP s) (Aerodrome Operating Procedure)

AOP 11 Low Visibility Procedures (LVP s) (Aerodrome Operating Procedure) AOP 11 Low Visibility Procedures (LVP s) (Aerodrome Operating Procedure) Produced by Airfield Services Document Author Operations Support Manager Contents 1 SECTION 1 - LOW VISIBILITY PROCEDURES (LVP S)...

More information

Ground Vehicle Operations Training READING REGIONAL AIRPORT

Ground Vehicle Operations Training READING REGIONAL AIRPORT Ground Vehicle Operations Training READING REGIONAL AIRPORT October 22, 2014 Airport Operations Area (AOA) Movement Areas Non-Movement Areas Non-Movement Area Markings Never cross solid line with out ATC

More information

Sample Civil Aviation Regulations for Aerodromes (AGA)

Sample Civil Aviation Regulations for Aerodromes (AGA) Sample Civil Aviation Regulations for Aerodromes (AGA) First Edition (unedited version) November 2013 Notice to users: This document is an unedited version which is made available to the public for convenience.

More information

Part 105. Parachuting - Operating Rules. CAA Consolidation. 15 December Published by the Civil Aviation Authority of New Zealand

Part 105. Parachuting - Operating Rules. CAA Consolidation. 15 December Published by the Civil Aviation Authority of New Zealand Part 105 CAA Consolidation 15 December 2012 Parachuting - Operating Rules Published by the Civil Aviation Authority of New Zealand DESCRIPTION Part 105 prescribes rules relating to parachute operations,

More information

CIVIL AVIATION AUTHORITY, PAKISTAN OPERATIONAL CONTROL SYSTEMS CONTENTS

CIVIL AVIATION AUTHORITY, PAKISTAN OPERATIONAL CONTROL SYSTEMS CONTENTS CIVIL AVIATION AUTHORITY, PAKISTAN Air Navigation Order No. : 91-0004 Date : 7 th April, 2010 Issue : Two OPERATIONAL CONTROL SYSTEMS CONTENTS SECTIONS 1. Authority 2. Purpose 3. Scope 4. Operational Control

More information

Effective: MILITARY EXERCISE WALLABY 2018 SHOALWATER BAY TRAINING AREA (SWBTA) 19 SEPTEMBER 17 NOVEMBER 2018

Effective: MILITARY EXERCISE WALLABY 2018 SHOALWATER BAY TRAINING AREA (SWBTA) 19 SEPTEMBER 17 NOVEMBER 2018 AUSTRALIA AERONAUTICAL INFORMATION SERVICE AIRSERVICES AUSTRALIA GPO BOX 367, CANBERRA ACT 2601 Phone: 02 6268 4874 Email: aim.editorial@airservicesaustralia.com Effective: AIP SUPPLEMENT (SUP) H 53/18

More information

GUIDELINES FOR THE PREPARATION OF A "PLAN OF CONSTRUCTION OPERATIONS (PCO)"

GUIDELINES FOR THE PREPARATION OF A PLAN OF CONSTRUCTION OPERATIONS (PCO) GUIDELINES FOR THE PREPARATION OF A "PLAN OF CONSTRUCTION OPERATIONS (PCO)" GHANA CIVIL AVIATION AUTHORITY January 2009 (First Edition) 1. Introduction The "Plan of Construction Operations (PCO)" is part

More information

Dates: Date of Approval Date Works

Dates: Date of Approval Date Works Method of Working Plan: YMML 2017/4 Date of Issue: November 2017 Method of Working Plan Melbourne Airport Foxtrot Apron Works Dates: Important Date of Approval Date Works 15 th January 2018 Commence Date

More information

TO SAFETY REGULATION DIVISION NR T.04 AVIATION HOUSE HAWKINS STREET. DUBLIN 2 Tel Fax AFTN EIDWYOYX

TO SAFETY REGULATION DIVISION NR T.04 AVIATION HOUSE HAWKINS STREET. DUBLIN 2 Tel Fax AFTN EIDWYOYX NOTICE IRELAND TO SAFETY REGULATION DIVISION NR T.04 AERODROME IRISH AVIATION AUTHORITY ISSUE 4 AVIATION HOUSE LICENCE DATE 15.12.09 HAWKINS STREET HOLDERS DUBLIN 2 Tel +353 1 6718655 Fax +353 1 6774068

More information

NATS Swanwick. Interface Agreement. Owners: General Manager LTC Swanwick. General Manager xxxxx Airport

NATS Swanwick. Interface Agreement. Owners: General Manager LTC Swanwick. General Manager xxxxx Airport - 1 - NATS Swanwick Interface Agreement between TERMINAL CONTROL (LTC), SWANWICK And NATS xxxxxx AIRPORT Owners: General Manager LTC Swanwick General Manager xxxxx Airport APPROVED BY Title Name Signature

More information

Republika e Kosovës Republika Kosovo Republic of Kosovo. Autoriteti i Aviacionit Civil Autoritet Civilnog Vazduhoplovstva Civil Aviation Authority

Republika e Kosovës Republika Kosovo Republic of Kosovo. Autoriteti i Aviacionit Civil Autoritet Civilnog Vazduhoplovstva Civil Aviation Authority Republika e Kosovës Republika Kosovo Republic of Kosovo Autoriteti i Aviacionit Civil Autoritet Civilnog Vazduhoplovstva Civil Aviation Authority The Director General of Civil Aviation Authority of Kosovo,

More information

INTERNATIONAL FIRE TRAINING CENTRE

INTERNATIONAL FIRE TRAINING CENTRE INTERNATIONAL FIRE TRAINING CENTRE RFFS SUPERVISOR INITIAL LICENSING OF AERODROMES CHAPTER 8 THE MINIMUM REQUIREMENTS TO BE MET IN THE PROVISION OF RESCUE AND FIRE FIGHTING SERVICES AT UK LICENSED AERODROMES

More information

Airside Vehicle Control Manual

Airside Vehicle Control Manual Reference No: 9004MKY Version 4 27 September 2017 MACKAY AIRPORT PTY LTD ACN 132 228 534 9004_MKY_MAPLAirsideVehicleControlManualV4_EffectiveDate_27/09/2017_ReviewDate_27/09/2018 Foreword The Mackay Airport

More information

Surname:... Name of company:... Registration No:... Place of Registration:... Any other SCAA Approval held (quote Approval No.)...

Surname:... Name of company:... Registration No:... Place of Registration:... Any other SCAA Approval held (quote Approval No.)... SEYCHELLES CIVIL AVIATION AUTHORITY AIR OPERATOR S CERTIFICATE AND EASA PART M, SUBPART G APPLICATION Please complete the form in BLOCK CAPITALS using black or dark blue ink. Part A Submission of Application

More information

ICAO Aerodrome s Manual. AERODROME S INSPECTOR WORKSHOP St. Maarten, MAHO June 2012

ICAO Aerodrome s Manual. AERODROME S INSPECTOR WORKSHOP St. Maarten, MAHO June 2012 ICAO Aerodrome s Manual AERODROME S INSPECTOR WORKSHOP St. Maarten, MAHO 11-15 June 2012 Objectives - Identify the requirements listed in Annex 14 regarding the development and maintenance of an aerodrome

More information

OPERATIONAL AND AIRCRAFT RESTRICTIONS

OPERATIONAL AND AIRCRAFT RESTRICTIONS Method of Working Plan: YMML 2017/4 Date of Issue: January 2017 Method of Working Plan Melbourne Airport Foxtrot Apron Works Amendment No.2 Dates: Important Date of Approval 9 th January 2018 Date Works

More information

AERODROME OPERATING MINIMA

AERODROME OPERATING MINIMA Title: Determination of Aerodrome Operating Minima Page 1 of 8 AERODROME OPERATING MINIMA 1. PURPOSE 1.1 The purpose of this Advisory Circular is to provide methods to be adopted by operators in determining

More information

INTERNATIONAL FIRE TRAINING CENTRE

INTERNATIONAL FIRE TRAINING CENTRE INTERNATIONAL FIRE TRAINING CENTRE LOW CATEGORY AERODROME SUPERVISOR INITIAL AERODROME CATEGORISATION Throughout this note he means he/she and his means his/hers. It is considered that all of the document

More information

Penalty for failure to surrender the identity card is an infringement fee of $500 or a $1000 fine on summary conviction

Penalty for failure to surrender the identity card is an infringement fee of $500 or a $1000 fine on summary conviction Aviation Security Service PO Box 53008 Auckland Airport Phone: 255 6000 SAFETY & SECURITY RULES -PLEASE READ- IDENTITY CARDS (Issued by Aviation Security Service) Persons wishing to access the Security

More information

Northrepps Aerodrome FLYING ORDER BOOK 2018

Northrepps Aerodrome FLYING ORDER BOOK 2018 Northrepps Aerodrome FLYING ORDER BOOK 2018 This document must be read and signed by all Club pilots when they first join and at the beginning of each subsequent calendar year. All student pilots must

More information

Airport Access Charges

Airport Access Charges Moorabbin Airport Airport Access Charges Effective from 1 May 2017 Moorabbin Airport Corporation 66 Bundora Parade MENTONE VIC 3194 Ph: 03 8587 8000 Fax: 03 9587 1782 Email: admin@moorabbinairport.com.au

More information

USE OF REMOTELY PILOTED AIRCRAFT AND MODEL AIRCRAFT IN AVIATION

USE OF REMOTELY PILOTED AIRCRAFT AND MODEL AIRCRAFT IN AVIATION luo Regulation 1 (10) OPS M1-32 Issued: 4 December 2018 Enters into force: 7 December 2018 Validity: indefinitely Legal basis: Aviation Act (864/2014), Sections 5, 9 and 57 Act on Transport Services (320/2017),

More information

Part 171. Aeronautical Telecommunication Services - Operation and Certification. CAA Consolidation. 10 March 2017

Part 171. Aeronautical Telecommunication Services - Operation and Certification. CAA Consolidation. 10 March 2017 Part 171 CAA Consolidation 10 March 2017 Aeronautical Telecommunication Services - Operation and Certification Published by the Civil Aviation Authority of New Zealand DESCRIPTION Part 171 provides the

More information

East Midlands Airport 2018 Aerodrome Manual

East Midlands Airport 2018 Aerodrome Manual East Midlands Airport 2018 Aerodrome Manual Version 1.0 Not Valid after 31 st December 2018 Department Operations Document Owner Operations Director (Accountable Manager) Document Administrator Ops Development

More information

PART XIII - AIR TRANSPORT SERVICES

PART XIII - AIR TRANSPORT SERVICES PART XIII - AIR TRANSPORT SERVICES 134. Scheduled Air Transport Services- (1) No person shall operate any Scheduled air transport service from, to, in, or across India except with the permission of the

More information

CIVIL AVIATION REGULATIONS PART 10 COMMERCIAL AIR TRANSPORT BY FOREIGN AIR OPERATORS WITHIN FEDERATED STATES OF MICRONESIA

CIVIL AVIATION REGULATIONS PART 10 COMMERCIAL AIR TRANSPORT BY FOREIGN AIR OPERATORS WITHIN FEDERATED STATES OF MICRONESIA CIVIL AVIATION REGULATIONS PART 10 COMMERCIAL AIR TRANSPORT BY FOREIGN AIR OPERATORS WITHIN FEDERATED STATES OF MICRONESIA FEDERATED STATES OF MICRONESIA 2001 [THIS PAGE INTENTIONALLY LEFT BLANK] 10-ii

More information

Steve Parry has left for pastures new and you can contact Richie Gallagher on Steve s old mobile number

Steve Parry has left for pastures new and you can contact Richie Gallagher on Steve s old mobile number Issue 11 Volume 1 / Issue 9 October 2017 Welcome to the latest edition of Aerodrome Safety Central. The newsletter is published on a quarterly basis and includes articles on Airfield news, Work in Progress

More information

CHANGE CONTROL PROCEDURE

CHANGE CONTROL PROCEDURE CHANGE CONTROL PROCEDURE Page - 1 - of 9 Revision Record Date Revision By Approver Description 13/02/15 V1.0 Jez Davis Jez Davis Original Issue 23/03/15 V2.0 Jez Davis Jez Davis Amended following CAA SARG

More information

Mackay Airport Pty Ltd AIRPORT OPERATIONS MANUAL

Mackay Airport Pty Ltd AIRPORT OPERATIONS MANUAL Mackay Airport Pty Ltd AIRPORT OPERATIONS MANUAL Reference No: 9000MKY Version 6 24 November 2016 ACN 132 228 534 PART 0 SECTION 01 FOREWORD Mackay Airport Pty Ltd (MAPL) owns and manages Mackay Airport

More information

ARP N W m. Rwy 21 Thr Elev N W. (GUND Elevation 172) 153 M. 853m x 27m.

ARP N W m. Rwy 21 Thr Elev N W. (GUND Elevation 172) 153 M. 853m x 27m. 09 27 UK AIP (28 Jul 11) AD 2-EGPT-2-1 AERODROME CHART - ICAO ARP 562628N 0032226W AD ELEV 397FT PERTH/SCONE EGPT GUND (Geoid Undulation) = The height of the Geoid (MSL) above the Reference Elipsoid (WGS

More information

AERONAUTICAL INFORMATION CIRCULAR 13/15

AERONAUTICAL INFORMATION CIRCULAR 13/15 NAV CANADA 28 MAY 15 AERONAUTICAL INFORMATION CIRCULAR 13/15 Intention of Circular INABILITY OF AIR TRAFFIC CONTROLLERS TO ISSUE CLEARANCES (Replaces AIC 26/13) This Aeronautical Information Circular (AIC)

More information

AERODROME ADVISORY CIRCULAR

AERODROME ADVISORY CIRCULAR GOVERNMENT OF INDIA CIVIL AVIATION DEPARTMENT OFFICE OF THE DIRECTOR GENERAL OF CIVIL AVIATION AD AC NO. 1 of 2006 14 th Sept.2006 AERODROME ADVISORY CIRCULAR SUBJECT: GUIDELINES FOR PREPARATION & MAINTENANCE

More information

It is essential that planning take full account of air safety and efficiency of operations.

It is essential that planning take full account of air safety and efficiency of operations. Airspace Protection Airspace Protection It is essential that planning take full account of air safety and efficiency of operations. 7.1 INTRODUCTION Obstacles near an airport, whether they are natural

More information

HIGHLANDS AND ISLANDS AIRPORTS LIMITED

HIGHLANDS AND ISLANDS AIRPORTS LIMITED HIGHLANDS AND ISLANDS AIRPORTS LIMITED ARRANGEMENTS FOR FLIGHTS OUTSIDE OFFICIAL OPENING HOURS The term Company or HIAL Group applies to Highlands and Islands Airport Limited (HIAL) and any subsidiary

More information

GAWLER AIRFIELD OPERATIONAL GUIDELINES

GAWLER AIRFIELD OPERATIONAL GUIDELINES By-Law 7 GAWLER AIRFIELD OPERATIONAL GUIDELINES Applicability This document replaces all other documents relating to flying operations at the Gawler Airfield. It takes effect from 26/04/2016. These guidelines

More information

COMMISSION REGULATION (EU) No 255/2010 of 25 March 2010 laying down common rules on air traffic flow management

COMMISSION REGULATION (EU) No 255/2010 of 25 March 2010 laying down common rules on air traffic flow management L 80/10 Official Journal of the European Union 26.3.2010 COMMISSION REGULATION (EU) No 255/2010 of 25 March 2010 laying down common rules on air traffic flow management (Text with EEA relevance) THE EUROPEAN

More information

Access to and security of the airport

Access to and security of the airport 1(8) Access to and security of the airport Table of contents 1. General... 2 2. Traffic... 2 3. Safety... 2 4. Security... 2 4.1 Access to authorisation areas... 2 4.2 Authorisation documents... 3 4.2.1

More information

GUYANA CIVIL AVIATION REGULATION PART X- FOREIGN OPERATORS.

GUYANA CIVIL AVIATION REGULATION PART X- FOREIGN OPERATORS. Civil Aviation 1 GUYANA CIVIL AVIATION REGULATION PART X- FOREIGN OPERATORS. REGULATIONS ARRANGEMENT OF REGULATIONS 1. Citation. 2. Interpretation. 3. Applicability of Regulations. PART A GENERAL REQUIREMENTS

More information

GOVERNMENT GAZETTE REPUBLIC OF NAMIBIA

GOVERNMENT GAZETTE REPUBLIC OF NAMIBIA GOVERNMENT GAZETTE OF THE REPUBLIC OF NAMIBIA r N$383u WINDHOEK- 15 August 1997 No 1637 CONTENTS Page GENERAL NOTICE No 211 Proposed Civil Aviation Regulations: Part 141 -Organisations: Aviation Training

More information

AIRSIDE VEHICLE CONTROL HANDBOOK

AIRSIDE VEHICLE CONTROL HANDBOOK AIRSIDE VEHICLE CONTROL HANDBOOK BANKSTOWN AND CAMDEN AIRPORTS Revised September 2016 CONTENTS Contents... 2 INTRODUCTION... 3 DEFINITIONS... 4 ADA REQUIREMENTS... 6 1. AUTHORITY TO DRIVE AIRSIDE AND THE

More information

AERODROME LICENCE APPLICATION PROCESS

AERODROME LICENCE APPLICATION PROCESS 0000180111 Page 2 Why is a Licence Required? An aerodrome licence is required for a site if it is intended to facilitate operations by commercial transport aircraft, other aerial work other than rotorcraft,

More information

Effective: PERTH AIRPORT AIRSIDE SURFACE MONITORING FOR FORRESTFIELD AIRPORT LINK TUNNELLING

Effective: PERTH AIRPORT AIRSIDE SURFACE MONITORING FOR FORRESTFIELD AIRPORT LINK TUNNELLING AUSTRALIA AERONAUTICAL INFORMATION SERVICE AIRSERVICES AUSTRALIA GPO BOX 367, CANBERRA ACT 2601 Phone: 02 6268 4874 Email: aim.editorial@airservicesaustralia.com Effective: AERONAUTICAL INFORMATION CIRCULAR

More information

United Kingdom Civil Aviation Authority

United Kingdom Civil Aviation Authority Proposed Changes to CAA Scheme of s United Kingdom Civil Aviation Authority 1 INTRODUCTION 1.1 Details of revisions proposed to apply from 1 April 2017 are shown in red within this Enclosure. Current charges

More information

EVTA AD 2.1 AERODROME LOCATION INDICATOR AND NAME EVTA AD 2.2 AERODROME GEOGRAPHICAL AND ADMINISTRATIVE DATA

EVTA AD 2.1 AERODROME LOCATION INDICATOR AND NAME EVTA AD 2.2 AERODROME GEOGRAPHICAL AND ADMINISTRATIVE DATA 18 NOV 2010 AIP LATVIA EVTA AD 2-1 18 NOV 2010 Note: The following sections in this chapter are intentionally left blank: AD-2.11, AD-2.14, AD-2.15, AD-2.16, AD- 2.19, AD-2.20, AD-2.21, AD-2.23 EVTA AD

More information

LELYSTAD AIRPORT PILOT S INFORMATION

LELYSTAD AIRPORT PILOT S INFORMATION LELYSTAD AIRPORT PILOT S INFORMATION This information bulletin contains a summary of the most relevant operational information for pilot s. Always check the AIP, the AIP SUP and NOTAM s for the latest

More information

Airside Driving Policy

Airside Driving Policy Owner: Eibhlin McGrath Creation Date: May 2011 Last Updated: 14-09-2015 Version: 2.2 Document Number AMUVP-03 September 2015 Document No.: AMUVP-03 1 CONTENTS Document Control... 3 Airside Driving Policy...

More information

Part 101 Gyrogliders and Parasails, Unmanned Aircraft (Including Balloons), Kites, and Rockets Operating Rules

Part 101 Gyrogliders and Parasails, Unmanned Aircraft (Including Balloons), Kites, and Rockets Operating Rules Part 101 Compliance Matrix (To be used with Part 102 matrix when making application for a certificate under Part 102) The Rule references in this compliance matrix have been extracted from the Civil Aviation

More information

CIVIL AVIATION REQUIREMENTS SECTION 4 AERODROME STANDARDS & LICENSING SERIES 'B' PART VI 22 ND MARCH 2012 EFFECTIVE: FORTHWITH

CIVIL AVIATION REQUIREMENTS SECTION 4 AERODROME STANDARDS & LICENSING SERIES 'B' PART VI 22 ND MARCH 2012 EFFECTIVE: FORTHWITH GOVERNMENT OF INDIA OFFICE OF DIRECTOR GENERAL OF CIVIL AVIATION TECHNICAL CENTRE, OPP SAFDARJANG AIRPORT, NEW DELHI CIVIL AVIATION REQUIREMENTS SECTION 4 AERODROME STANDARDS & LICENSING SERIES 'B' PART

More information

Telephone No. 2:4622495 Telegraphic Address: Commercial : AIRCIVIL NEW DELHI Aeronautical : VIDDYAYX E Mail: dri@dgca.nic.in Fax : 01124629221 GOVERNMENT OF INDIA AERONAUTICAL INFORMATION SERVICES DIRECTOR

More information

AIRPORT PROCEDURE AIR 002

AIRPORT PROCEDURE AIR 002 INDEX 1. Objective and Scope of Application...2 2. References...2 3. DEFINITIONS...2 4. GENERAL PROVISIONS...3 5. GENERAL AVIATION SLOT MANAGEMENT - G.A.S.M...3 6. AIRCRAFT APRONS AND STANDS...3 7. PPR