1

2 Love Field Modernization Program Update: Master Planning Recommendations Briefing to the Council Transportation and Environment Committee April 28,

3 Briefing Objective Discuss the background and overview of the Love Field Modernization Program development process. Present the recommendations of the Master Plan effort (Terminal Area Redevelopment Program Study). Discuss Implementation, Project delivery. Recommendations and Next Steps. 2 2

4 Background Review The 5-Party Agreement to Repeal the Wright Amendment. Flight restrictions phased out by Limit Love Field capacity to 20 gates. Southwest Airlines 16 gates American and Continental Airlines 2 gates each The City must develop the Love Field Modernization Program, and invest a minimum of $150 M and a maximum of $200 M. The Love Field Modernization Program. Implements the 20-gate limit through reduced terminal size. Costs will be charged to airline rate base. City and Southwest Airlines will cooperate to determine the best methods to design, fund and manage the project. 3 3

5 Existing Terminal Area North Concourse: Southwest Training, Provisioning, CBS, Ground Service Equip East Concourse: American 3 Gates, Continental 2 Gates East Ramp: DHL General Aviation/Mfg: Gulfstream & Bombardier West Concourse: Southwest Gates ,000 sq ft, 43 gates. 20 gates active. Walking Distances: 1500 to farthest gates. Mid-1950 s terminal design & construction. Concession space insufficient for future passenger growth. Security systems must be retrofitted. Baggage systems lack automation and are labor intensive 4 4

6 Love Field Modernization Program Goals Comply with 5-Party Agreement and Wright Amendment Reform Act of Modernize the Terminal to Serve the Community and Traveling Public Efficiently and with Excellent Customer Service. 5 5

7 Love Field Modernization Program Objectives Work collaboratively with Southwest and our other airlines, per the 5-Party Agreement. Planning Development Agreement Achieve Efficiencies. Balance facility size to its needs (currently using half of available 860K square feet) System and Operational Processes Environmental Sustainability Upgrade to Current Design Standards with Flexibility to Adjust to Future Needs. Current, Future Security Requirements and Passenger Processing Technologies Passenger Flow, Congestion, Delay Customer Service and Concession Revenue Opportunities Achieve Schedule Goal: October 13, Affordable design Efficient financing strategy Effective delivery strategies 6 6

8 Overview of the Love Field Modernization Program Development Process Five Steps to Implementation: Master Plan (April 2008) (TODAY S DISCUSSION) Road Map for developing the Love Field Modernization Program Environmental Actions Determination Facilities Requirements: Spatial, Functional, Level of Service Conceptual Design Implementation: Project Financing, Development, Delivery Development Agreement Term Sheet (JUNE) Development Agreement (October 2008) Agreement on implementation, control and oversight Agreement on funding and financing means and methods Agreement on lease and use during project and after completion Design Development (Winter 2009) Determine financially feasible concept, project budget. Procurement and Construction (Fall 2009) Completion and Move-in Under normal development process Summer, Ability to achieve 2014 completion goal will require a creative approach to development. 7 7

9 Master Plan Terminal Area Redevelopment Program Study (TARPS) Scope of Study: Investigate Environmental Issues, documentation needed. Verify Traffic Forecasts of 2001 Master Plan and 2006 Update. Determine Facility Spatial, Landside Traffic, Parking Requirements. Recommend Architectural Standards, Passenger Level of Service Standards, Technical Design Standards. Determine Layout of Terminal and Support Facilities in Terminal Area. Determine Conceptual Layout and Potential Cost Range. Study Completed April 2008 Findings, Recommendations Follow 8 8

10 Master Plan Major Findings & Recommendations Environmental Issues and Documentation Needed Findings Project Construction will not exceed emissions thresholds. Project will result in more efficient facility operation and will not increase impact. Action Items: General Conformity Applicability Analysis submitted to FAA FAA advised its intent to determine no significant impact from project Documentation pending, in support of a Categorical Exclusion from National Environmental Protection Act (NEPA) requirements. 9 9

11 Master Plan Major Findings & Recommendations Passenger and Aircraft Traffic Forecasts TARPS forecast methodology: See Appendix page for detailed information. Design Level Enplanement Forecast: Annual 5,865,580 Peak Month 697,442 Average Day 22,498 Peak Hour 2,250 Forecasts considered reasonable by airlines & and consistent with FAA forecasts

12 Master Plan Major Findings & Recommendations Facilities Requirements and Standards Level Of Service International Air Transport Association standard LOS FLOWS DELAYS COMFORT A Excellent Free None Excellent B High Stable Very Few High C Good* Stable Acceptable Good D Adequate* Unstable Acceptable for Short Periods Adequate E Inadequate Unstable Unacceptable Inadequate F Unacceptable System Breakdown Unacceptable Unacceptable *Note: Level C = standard minimum, Level D = peak periods Comparison service levels: LOS A - passengers would be able to move freely through the terminal facility without experiencing any delays in their movements and feel comfortable in doing so (High Cost). LOS E - passenger movements would be congested, uncomfortable and delays would be recognized as unacceptable (Low Cost). LOS C is recommended as the minimum design objective, as it represents good service level at a reasonable cost

13 Master Plan Major Findings & Recommendations Facilities Requirements and Standards Space requirements to accommodate enplanement forecasts See Appendix page 32 for detailed Space Program. Overall 602,000 sq. ft. Concession space tripled Future Parking expansion Design Level of Service (LOS) Proposed space results in upgrade to LOS C. LOS C = good service at reasonable cost 12 12

14 Master Plan Major Findings & Recommendations Concepts and Cost Range Considerations: 5-Party Agreement caps cost at $200 M. City and Southwest can agree to exceed the cap if desired. Agreement to exceed cap determined through negotiation of Project Development Agreement. Concept Development Approach: New terminal site examined. Southeast of existing terminal (East Ramp). Space limitations and added cost of new infrastructure made concept not feasible. Three concepts developed for existing terminal site. Allows economical re-use of portions of existing facility. All three concepts exceed the $200 M cap

15 Master Plan Major Findings & Recommendations Concepts: Option A Meets the requirements of the 5-Party Agreement. Demolish down to 20 gates. East Concourse Portions of North Concourse Walking distance remains 1500 ft to farthest gate. Remodel remaining gates and enlarge concession space. 16 gates in West Concourse 4 gates in North Concourse Ticketing and Security Screening capacity enhancements. Minimal Bag Claim, Curbside and Roadway enhancements. Lowest cost option exceeds the cap at $357 M

16 Option A OPTION A Scope Renovate West Concourse for 16 total SWA gates Temporary Gates on North Concourse to allow phased renovation of West, then become permanent location for AA and CO New T-Point and EDS Screening No work to Terminal Building or Curbside New Construction Existing Facilities 15 15

17 Master Plan Major Findings & Recommendations Concepts: Option B Renovate West Concourse (12 gates). Demolish East, and existing North Concourses. Construct new North Concourse (8 gates). Requires airlines to operate at 2 concourses Splits passenger traffic between 2 concourses Requires duplication of concessions for each concourse Walking distance decreases to 1384 ft to farthest gate New Ticketing Hall Renovate Main Terminal Lobby Expanded Passenger Screening Checkpoint Baggage Screening consolidated into one system for all airlines Expand Bag Claim Expand Curbside Highest cost of the 3 options ($608 M)

18 Option B OPTION B Scope Renovate and Expand West Concourse for 12 total SWA gates Demo North Concourse and rebuild in new location with 8 Gates New Ticket Hall Bag Claim Expansion Curbside Expansion Terminal Renovation New Construction Existing Facilities 17 17

19 Master Plan Major Findings & Recommendations Concepts: Option C Achieves all facility objectives (page 6). Construct single new 20-gate concourse. More efficient use of available Terminal Area site (smallest footprint) All airlines, passengers in same concourse Enables central concession area accessible by all passengers Walking distance reduces to 1,096 ft to farthest gate New Ticketing Hall Renovate Main Terminal Lobby Expanded Passenger Screening Checkpoint Baggage Screening consolidated into one system for all airlines Expand Bag Claim Expand Curbside Layout efficiency contributes to passenger convenience and Level of Service C. Cost $571 M. Exceeds Option A by $214 M, or 60%

20 Option C OPTION C Scope Demolish East, North and West Concourses and replace with new North Concourse with 20 gates New Ticket Hall Expanded Bag Claim Expanded Curbside Terminal Renovation New Construction Existing Facilities 19 19

21 Master Plan: Major Findings & Recommendations Concept Development: Performance Comparison Matrix Option A meets/exceeds target for 5 of 12 terminal requirements. Option B meets/exceeds target for 9 of 12 terminal requirements. Option C meets/exceeds target for 10 of 12 terminal requirements. Performance Requirements Performance Target Existing A Option B C Terminal Facilities Ticketing Counter Position Self-Service Devices Ticketing Curbside Positions Bag Claim (area sf) 12,500 19,000 19,000 23,400 23,400 Bag Claim (frontage lf) Passenger Security Checkpoints to to to 14 EDS Screening Devices to Concessions 73,013 20,400 29,100 73,000 75,000 Gate Holdroom (avg. sf/gate) 2,250 1,835 1,835 2,250 2,250 Landside Facilities Arrivals Curb 1, Departures Curb Commercial Curb

22 Master Plan: Major Findings & Recommendations Evaluation Matrix Score Range = = least desirable 5 = most desirable Option C score 46% higher than Option A Matrix supports Option C as preferred concept Option A B C Implementation Time To Implement Operational Complexity Customer Inconvenience Cost of Overall Program Operations Operational Efficiency Estimated Relative O&M Cost Customer Convenience Curbside Ticketing SSCP Holdrooms Concessions and Amenities Baggage Claim Walk Distance SUMMARY

23 Master Plan Major Findings & Recommendations Level of Service and Cost Comparison: Service component Option A B C Check-in Queue Area Gate Hold Room Baggage Claim Circulation and Waiting Areas Total Average LOS D C C Evaluation Matrix Score Planning Cost $357 M $608 M $571 M Preferred Option XX 22 22

24 Master Plan Major Findings & Recommendations Concept Development Planning Costs: Costs are very preliminary. More accurate project costs to be determined during design development (Winter, 2009), based on provisions of Project Development Agreement, to be approved by City Council

25 Implementation & Project Delivery Implementation As stated on page 3, the City and Southwest Airlines will cooperate to determine the best methods to design, fund and manage the project (5-Party Agreement). A Project Development Agreement (PDA) between the City and Southwest will represent agreement on the best methods. See outline of PDA, Appendix pages PDA to be proposed to City Council for approval. Term Sheet to Council for approval June,

26 Implementation & Project Delivery Schedule Efficiencies: Schedule goal (page 7) is the date of full repeal Oct, Terminal capacity needed for forecast passenger traffic However, projected completion date under normal City development process Opportunity for Cost and Schedule Efficiencies: Significant project elements can be assigned in the Project Development Agreement to Southwest Airlines. Creation of a Local Government Corporation (LGC) is a means provided by state statute, of assigning LFMP development to a third party. May be created to aid and act on behalf of the City to accomplish any governmental purpose of the City. LGC has power to contract and to issue debt to be secured by airlines. LGC to be proposed for City Council approval in June,

27 Implementation & Project Delivery Local Government Corporation (LGC) Addresses Project Challenges: Project Financing Vehicle for issuing bonds secured by airlines (rather than airport revenues). Demanding schedule for 2014 completion Empowered by state to contract and assign project development to third party: Enables fast-track procurement and delivery methods; Preserves City Council approvals and governance. Project cost containment Costs to be borne by airlines. Allows airline co-management of costs through negotiated PDA. Project complexity Demolition of existing, and construction of new facilities while still in use. Maintaining growing operations of 3 airlines and 2 major concessionaires throughout project. Extensive construction phasing and tenant relocations. Successfully used for recent City project. Mercantile/Forest City Project developed under an LGC. City has also financed other public projects managed by 3 rd party entities: Performing Arts Center, American Airlines Center

28 Recommendations Summary Recommend the City Council approve the Terminal Area Redevelopment Program Study (TARPS) as the master plan for the Love Field Modernization Program (LFMP). Provides viable concepts which: Comply with the 5-Party Agreement; Accommodate passenger levels forecast to nearly 12 million annual passengers by 2014; Provide a Level of Service standard C. Recommend the City Council approve Option C as the preferred concept to be developed further, pending final recommendation after design and budget development pursuant to a Project Development Agreement (PDA), to be negotiated between the City and Southwest Airlines. Term Sheet defining terms of proposed PDA to Council for approval June, Final recommendation to Council for Terminal Concept Option C approval

29 Next Steps City Council approval of Terminal Area Redevelopment Program Study as the Master Plan for the Love Field Modernization Program. City Council Agenda for approval May 21, Develop proposal to create a Local Government Corporation (LGC) as a means of developing the Love Field Modernization Program in the most efficient and cost effective manner possible. City Council Agenda for approval June 25, Negotiate a Project Development Agreement (PDA) with Southwest Airlines, for City Council approval, to enable commencement of design development. Term Sheet of agreement to City Council for approval June 25, Recommendation on Terminal Concept to City Council for approval June 25,

30 Appendix Passenger Traffic Forecast Methodology Facilities Space Program 32. Project Development Agreement Outline

31 Master Plan Major Findings & Recommendations Passenger and Aircraft Traffic Forecasts 2006 Update of the 2001 Master Plan estimated the effects which might result from the proposed repeal of the Wright Amendment. Data used as the basis for the TARPS forecast. FAA Terminal Area Forecast (TAF) for Love Field: Standard forecasting model used to test validity of airport-specific forecast. Results exceed the 2006 Update, but validates current TARPS forecast. TARPS forecast methodology: Constraint 20 Gates. Constraint Voluntary Curfew (17 hours of operation) Variable Aircraft size: assume , 137 seats. Note: American & Continental currently operate 50 seat Regional Jets. The forecast assumes greater demand for larger aircraft when all restrictions phase out in Variable Turns per Gate: 10 turns per gate (assumes min ground time per turn reasonable on consistent basis). 15 turns per gate (assumes 15 min ground time per turn achievable but not consistently) 30 30

32 Master Plan Major Findings & Recommendations Forecasts Design Level Consultation with airlines concerning these peak hour passenger levels indicate that they are within a reasonable range Love Field during the forecast period. FAA TAF validates the TARPS 10-turn per gate projection for post-wright Amendment conditions. However, it assumes on-going growth rate, which fails to recognize physical constraint of 20 gates and practical operating constraint of 10 turns per gate, as limiting factors on growth. TARPS projection for 10 turns in 2014 constitutes the design level of passenger enplanements. Design Level Enplanement Forecasts Historical Annual Peak Month Average Day Peak Hour ,439, ,032 10,033 1, % 31 Days 11.60% TAF Projected ,275, ,691 12,474 1, ,889, ,679 17,183 1, ,967, ,588 23,245 2, ,653, ,675 25,248 2, Turn Projected ,865, ,442 22,498 2,250 Compounded TAF Annual Growth Rate % 4.39% 4.39% 4.39% Sources: City of Dallas, Department of Aviation (historical annual activity) FAA Terminal Area Forecast (projected annual air carrier activity) Ricondo & Associates, Inc. (peak month and peak hour activity) Gresham, Smith and Partners (update and turn project activity) Prepared by: Ricondo & Associates, Inc, updated by Gresham, Smith and Partners 31 31

33 Master Plan Major Findings & Recommendations BASIS FOR 10-TURN SPACE PROGRAM CALCULATIONS DALLAS LOVE FIELD LANDSIDE TERMINAL BUILDING Key Type of space Units Sq.Ft. AIRLINE SPACE Airline Ticket Counter AS-2 Ticket counter agent positions 14 AS-2 Ticket counter ATMs 12 AS-2 Curbside counter agent positions 49 AS -2 Ticket counter (lineal feet) - 90 AS -3 Ticket counter (area) 1,454 AS -4 Ticket counter queuing area 7,938 AS -5 Ticket counter support office 2,250 AS -6 Baggage Makeup 2,250 93,000 Baggage Claim AS -7 Number of devices 5 AS -7a Total lineal feet 729 AS -8 Bag claim area 12,500 AS -8a Baggage Claim Input 10,400 AS -9 Holdrooms 87,841 AS -10 Clubrooms - AS -11 Airline Offices - Landside Terminal 7,512 AS -11a Airport Administration - Landside Terminal 35,000 AS -12 Airlines Offices - Airside Terminal 4,000 AS -13 Airline Operations 60,000 Subtotal 321,895 CONCESSIONS C -1 Food & beverage 53,518 C -2 Rental Car area 3,400 C -3 News/sundries (5% of Gross Terminal Area) 16,095 Subtotal 73,013 PUBLIC SPACE PS -1 Security Checkpoints 14 14,000 PS -1a TSA Administration 4,000 PS -2 Ticket Lobby 4,500 PS -3 Baggage Claim Lobby 9,200 PS -4 Restrooms 18,260 PS -5 Terminal Services 15,600 PS -6 Concourse Circulation 80,375 PS -7 Mechanical & Services 60,884 Subtotal 206,819 Curbside and Parking CS -1 Curbside - Departures 992 CS -2 Curbside - Arrivals 1,043 CS -3 Curbside - Shuttle 568 P-1 Employee Parking Spaces 1,000 Subtotal TOTAL 601,

34 Implementation & Project Delivery Project Development Agreement (PDA) An agreement between the City and Southwest Airlines specifying the goals and objectives of the LFMP and agreeing to the manner in which it will be developed, financed and operated. Scope of the Agreement: Intent of the Project Project scope Commitment to interests of each party Cooperation with other airlines Safety, security, maintenance of operations Program Management Team Consists of representatives for City and Southwest Responsibilities & authority defined Controls, reporting, costs, payments Program Description Individual projects comprising the LFMP Exclusions and interfacing projects FAA funding, standards, grant assurance conformance 33 33

35 Implementation & Project Delivery Project Development Agreement (PDA) (cont d.) Program Definition Manual Project planning & phasing Design Procurement & solicitation Construction, completion, acceptance City ordinances & requirements Codes, ordinances, Life Safety Master Plan Environmental remediation M/WBE, DBE participation Art in Public Places, LEED Certification Project labor agreement, wage rates Sales tax exemption, Record documents Construction staging and parking Dispute Resolution 34 34

36 Implementation & Project Delivery Project Development Agreement (PDA) (cont d.) Contract forms Contracting authority Design, Construction, Program/Construction Management Contract forms, bond/insurance requirements Project title Default Plan of Finance Sources of funds, schedules Grants, PFC, airport revenues, airline funds Financing obligations Requisition of funds Agreement on Rates & Charges 35 35

37 Implementation & Project Delivery Project Development Agreement (PDA) (cont d.) Effectiveness of agreement City, airline approvals FAA Record of Decision Indemnification Airline use and lease agreement / lease amendment Responsibilities of Agencies Department of Aviation Public Works TSA FAA Building Permits 36 36

38 Questions and Answers 37

39

40

41

Amended & Restated Lease of Terminal Building Premises (Airport Use & Lease Agreement)

Amended & Restated Lease of Terminal Building Premises (Airport Use & Lease Agreement) Amended & Restated Lease of Terminal Building Premises (Airport Use & Lease Agreement) Briefing to the Transportation and Environment Committee Department of Aviation October 27, 2008 Purpose Review 5-Party

More information

LOVE FIELD MODERNIZATION PROGRAM (LFMP)

LOVE FIELD MODERNIZATION PROGRAM (LFMP) LOVE FIELD MODERNIZATION PROGRAM (LFMP) April 29, 2015 DALLAS AIRPORT SYSTEM Three Facilities Dallas Love Field Dallas Executive Airport Downtown Vertiport $90 million City of Dallas Department Operated

More information

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES Over the term of the Master Amendment to the Airline Use and Lease Agreement, the Kansas City Aviation Department

More information

Tampa International Airport Master Plan Update. December 12, 2012

Tampa International Airport Master Plan Update. December 12, 2012 Tampa International Airport Master Plan Update December 12, 2012 1 Prior Presentation Consolidated rental car and people mover Decongest curbsides and roadways Enable rental car growth Gain long term parking

More information

TRACK: B TERMINAL/LANDSIDE

TRACK: B TERMINAL/LANDSIDE Salt Palace Convention Center TRACK: B TERMINAL/LANDSIDE WORKSHOP: 3 Title: Airlines and Airports Consolidation and Changing Faces Who is building the Terminals, Technology, and Flexibility? Moderator:

More information

SAN JOSÉ INTERNATIONAL AIRPORT

SAN JOSÉ INTERNATIONAL AIRPORT SAN JOSÉ INTERNATIONAL AIRPORT NEAR-TERM TERMINAL CAPACITY ANALYSIS AIRPORT COMMISSION AUGUST 14, 2017 August 14, 2017 AGENDA 1. Forecast Review (with 14 MAP High Case) 2. Gate Requirements and Aircraft

More information

AIRPORT MASTER PLAN UPDATE

AIRPORT MASTER PLAN UPDATE AIRPORT MASTER PLAN UPDATE PENSACOLA INTERNATIONAL AIRPORT Technical Advisory Committee Meeting #2 June 20, 2017 Agenda» Introduction» Facility Requirements Airside Terminal Landside General Aviation Cargo

More information

Love Field Customer Facility Charge Ordinance

Love Field Customer Facility Charge Ordinance Love Field Customer Facility Charge Ordinance Mobility Solutions, Infrastructure & Sustainability Committee August 28, 2017 Mark Duebner, Director Department of Aviation Overview Provide overview of Dallas

More information

Master Plan Phase 2 Workshop

Master Plan Phase 2 Workshop Master Plan Phase 2 Workshop Tampa Airport: A Legacy of Innovation and Convenience Tampa Airport: A legacy of Innovation and Convenience The world s first airport people mover Tampa Airport: A legacy of

More information

BNA Master Plan Update Public Meeting No. 2

BNA Master Plan Update Public Meeting No. 2 A Six Sigma Organization BNA Master Plan Update Public Meeting No. 2 September 18, 2012 Agenda BNA Master Plan Update Consultants Status of the BNA Master Plan Update Workstation Boards Forecasts of Aviation

More information

Brief Recap of Project to Date

Brief Recap of Project to Date CITY AND BOROUGH OF SITKA Rocky Gutierrez Airport (SIT) Terminal Improvements Project Brief Recap of Project to Date Schematic Design: Design Development Meetings June 26 & 27, 2018 Project Description

More information

City of Kansas City AIRPORT COMMITTEE BRIEFING. Major Renovation Evaluation for Kansas City International Airport.

City of Kansas City AIRPORT COMMITTEE BRIEFING. Major Renovation Evaluation for Kansas City International Airport. City of Kansas City AIRPORT COMMITTEE BRIEFING Major Renovation Evaluation for Kansas City International Airport February 2, 2016 1 Agenda Briefly review Exhibit K Process to establish Program Requirements

More information

BNA Master Plan Update Community Advisory Committee Meeting No. 5

BNA Master Plan Update Community Advisory Committee Meeting No. 5 A Six Sigma Organization BNA Master Plan Update Community Advisory Committee Meeting No. 5 September 19, 2012 Introductions MNAA Staff RW Armstrong Team Albersman & Armstrong, Ltd. Atkins North America,

More information

July 21, Mayor & City Council Business Session KCI Development Program Process Update

July 21, Mayor & City Council Business Session KCI Development Program Process Update July 21, 2015 Mayor & City Council Business Session KCI Development Program Process Update History of KCI 2 Airport Funding KCI Improvements are Funded by Airlines & Travelers City tax revenues do not,

More information

FORECASTING FUTURE ACTIVITY

FORECASTING FUTURE ACTIVITY EXECUTIVE SUMMARY The Eagle County Regional Airport (EGE) is known as a gateway into the heart of the Colorado Rocky Mountains, providing access to some of the nation s top ski resort towns (Vail, Beaver

More information

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018 NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PROPOSED PASSENGER FACILITY CHARGE APPLICATION NOVEMBER 9 TH, 2018 LAWTON-FORT SILL REGIONAL AIRPORT LAWTON, OKLAHOMA PASSENGER FACILITY CHARGE PROPOSED

More information

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER PETE FLAHERTY COMMISSIONER TOM FOERSTER CHAIRMAN DEPARTMENT OF AVIATION BARBARA HAFER COMMISSIONER STEPHEN A. GEORGE DIRECTOR ROOM M 134, TERMINAL BUILDING GREATER PITTSBURGH INTERNATIONAL AIRPORT PITTSBURGH,

More information

LOVE FIELD MODERNIZATION EVOLUTION

LOVE FIELD MODERNIZATION EVOLUTION LOVE FIELD MODERNIZATION EVOLUTION June 8, 2016 WRIGHT AMENDMENT MCI STL ELP ABQ LBB AM A MAF OKC DAL TUL LIT JAN BHM SAT AUS HOUIIAH MSY Passed in 1979 to protect DFW Airport Could only fly within Texas

More information

Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway

Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway Master Plan Advisory Committee (MPAC) Alternatives September 28, 2017 AGENDA Review of Previous Work Ultimate Land

More information

IAH Terminal Redevelopment Project. Memorandum of Agreement with United Airlines

IAH Terminal Redevelopment Project. Memorandum of Agreement with United Airlines IAH Terminal Redevelopment Project Memorandum of Agreement with United Airlines May 29, 2014 On April 24, HAS presented plans for a new Mickey Leland International Terminal (MLIT) Sufficient capacity for

More information

FUTURE PASSENGER PROCESSING. ACRP New Concepts for Airport Terminal Landside Facilities

FUTURE PASSENGER PROCESSING. ACRP New Concepts for Airport Terminal Landside Facilities FUTURE PASSENGER PROCESSING ACRP 07-01 New Concepts for Airport Terminal Landside Facilities In association with: Ricondo & Associates, TransSolutions, TranSecure RESEARCH Background Research Objective

More information

Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis

Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis ITB MAIN TERMINAL DEPARTURES LEVEL & BOARDING AREAS A & G ALTERNATIVES ANALYSIS

More information

? 0-? WA", ilp. Y ON 1Z Cond 1 0 AIRPORT COMMISSIONERS BOARD REPORT TO THE Los Angeles World Airports 0*1-

? 0-? WA, ilp. Y ON 1Z Cond 1 0 AIRPORT COMMISSIONERS BOARD REPORT TO THE Los Angeles World Airports 0*1- I 1 RW MT BOARD 0*1-.04 11 Los Angeles World Airports REPORT TO THE 0 AIRPORT COMMISSIONERS Meeting Date: Approved /by: Dave Jone - Airline Prop nd Concession Services ) 7/13/2017 Reviewed by:.',...ek

More information

Existing Conditions AIRPORT PROFILE Passenger Terminal Complex 57 air carrier gates 11,500 structured parking stalls Airfield Operations Area 9,000 North Runway 9L-27R 6,905 Crosswind Runway 13-31 5,276

More information

Dallas Love Field Update. Dallas City Council Briefing February 18, 2015

Dallas Love Field Update. Dallas City Council Briefing February 18, 2015 Dallas Love Field Update Dallas City Council Briefing February 18, 2015 Purpose Construction Update Impacts of Wright Amendment Repeal Increase in operations/passengers/ projections Concessions performance

More information

msp macnoise.com MSP Noise Oversight Committee (NOC) November 17, 2010

msp macnoise.com MSP Noise Oversight Committee (NOC) November 17, 2010 MSP Noise Oversight Committee (NOC) November 17, 2010 Operations Update Technical Advisor s Report Summary MSP Complaints September October 2010 3,025 3,567 2009 6,350 6,001 Total Operations September

More information

Kansas City Aviation Department. Airport Committee July 19, 2018

Kansas City Aviation Department. Airport Committee July 19, 2018 Kansas City Aviation Department Airport Committee July 19, 2018 AGENDA Labor Update Design Process General Updates Community Outreach LABOR UPDATE Overarching Goals: Labor Harmony on the project Ensure

More information

Feasibility Study Federal Inspection Service Facility at Long Beach Airport

Feasibility Study Federal Inspection Service Facility at Long Beach Airport Feasibility Study Federal Inspection Service Facility at Long Beach Airport 13 December 2016 Long Beach City Council PLEASE NOTE: The information, analysis, assessments and opinions contained in this presentation

More information

Chapter 1: Introduction Draft

Chapter 1: Introduction Draft Chapter 1: Draft TABLE OF CONTENTS 1... 4 1.6.1 Stakeholder Engagement Plan... 10 Chapter 1 Page 2 TABLE OF EXHIBITS Exhibit 1.1-1 ABIA Annual Growth Since 1993... 5 Exhibit 1.4-1: ABIA Location Map...

More information

RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan

RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan Project Schedule Today Slide 40 Project Vision To provide an achievable, flexible, fiscally, and environmentally

More information

Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport

Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport Re: Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport Los Angeles World Airports (LAWA) intends to submit

More information

FLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING

FLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY FLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING May 15, 2018 Master Plan Schedule Overview Progress Since Last Master Plan

More information

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201

More information

Kansas City Aviation Department. Update to Airport Committee Customer Service

Kansas City Aviation Department. Update to Airport Committee Customer Service Kansas City Aviation Department Update to Airport Committee Customer Service 1 Perspective An estimated 800,000 people participated in the Royals Word Series Parade On average 883,000 airline passengers

More information

Chapter 4 Terminal Facility Requirements and Alternatives

Chapter 4 Terminal Facility Requirements and Alternatives Chapter 4 Terminal Facility Requirements and Alternatives I. Terminal Facility Requirements Introduction This chapter of the master plan converts the forecasted passenger demand levels that were identified

More information

Chapter 1: Introduction

Chapter 1: Introduction Chapter 1: TABLE OF CONTENTS 1... 4 1.1 Master Plan Study Content... 4 1.2 Purpose and Scope of Master Plan Study... 4 1.3 Airport History and Role... 6 1.4 Airport Location and Service Area... 6 1.5 ABIA

More information

NORTHERN ROCKIES REGIONAL AIRPORT Terminal Expansion ANALYSIS 31 st August 2012

NORTHERN ROCKIES REGIONAL AIRPORT Terminal Expansion ANALYSIS 31 st August 2012 NORTHERN ROCKIES REGIONAL AIRPORT Terminal Expansion ANALYSIS 31 st August 2012 INTRODUCTION The purpose of this report is to analysis the current schedule of operations and assumptions within the 2010

More information

Forecast and Overview

Forecast and Overview Forecast and Overview DENVER INTERNATIONAL AIRPORT Overall goals of the (MPR): Work with DEN to refine the preferred airport development plan to guide the development over an approximate 25-year planning

More information

BOARD ITO Aide REPORT TO THE AIRPORT COMMISSIONERS

BOARD ITO Aide REPORT TO THE AIRPORT COMMISSIONERS 1 [1 11 BOARD ITO Aide 001:4 Los Angeles World Airports REPORT TO THE Approved by: Justin rbacci - hief Innovation and Commercial St tegy Officer (--(AtSotA_ /1//r/'(10 PV Reviewed by: Samson Mengistu

More information

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012 1. Introduction The Federal Aviation Administration (FAA) recommends that airport master plans be updated every 5 years or as necessary to keep them current. The Master Plan for Joslin Field, Magic Valley

More information

CHAPTER 4: ALTERNATIVES

CHAPTER 4: ALTERNATIVES MSP Long Term Comprehensive Plan Update Metropolitan Airports Commission 4.1 INTRODUCTION CHAPTER 4: ALTERNATIVES Several alternatives were developed and evaluated based on their capability to meet the

More information

Love Field Modernization Program Bond Financing Update

Love Field Modernization Program Bond Financing Update Love Field Modernization Program Bond Financing Update Briefing to the Transportation and Environment Committee Department of Aviation December 14, 2009 Purpose Review LFMP background and give status update

More information

Implications of Construction Cost Escalation

Implications of Construction Cost Escalation Implications of Construction Cost Escalation 2007 ACI-NA Economics and Finance Conference James Gill, CPA Deputy Airport Director Finance, Business & Administration Raleigh-Durham Airport Authority Presentation

More information

Terminal Space and Ratemaking

Terminal Space and Ratemaking Terminal Space and Ratemaking (Written by Dafang Wu on March 19, 2016; PDF version) This article discusses classification of terminal space and options for setting terminal rates and charges methodology.

More information

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257 Form PDES 8 THE CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257 Summary of Duties: A Senior Airport Engineer performs the more difficult and

More information

Kansas City Aviation Department. Community Listening Session

Kansas City Aviation Department. Community Listening Session Kansas City Aviation Department Community Listening Session Listening Session Purpose The Kansas City Aviation Department is moderating these community listening sessions in order to gather feedback from

More information

Fort Lauderdale Hollywood International Airport

Fort Lauderdale Hollywood International Airport ATLANTA, GEORGIA 1 2 ATLANTA, GEORGIA Fort Lauderdale Hollywood International Airport Master Plan to Master Plan Implementation Jamie McCluskie Director of Aviation Planning & Environmental Broward County

More information

The 14-Gate Replacement Terminal Project and Protections for Burbank

The 14-Gate Replacement Terminal Project and Protections for Burbank The 14-Gate Replacement Terminal Project and Protections for Burbank UNITED AIRPORT 1934 The Airport Needs A Safer, Modern, and More Convenient Replacement Terminal Why the Airport Needs a Replacement

More information

PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM

PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM FREQUENTLY ASKED QUESTIONS September 2017 Master Plan Update: 1. What is a Master Plan Update? The objective of a Master Plan Update (MPU)

More information

Westshore Development Forum Presented by: Alice J. Price, AICP, Senior Project Director

Westshore Development Forum Presented by: Alice J. Price, AICP, Senior Project Director Presented by: Alice J. Price, AICP, Senior Project Director Back In Time: 1946 Drew Field 1952 Main Terminal 1963 Study Terminal Design Goals: Human Values Airline economics Airport financial considerations

More information

Alternatives. Introduction. Range of Alternatives

Alternatives. Introduction. Range of Alternatives Alternatives Introduction Federal environmental regulations concerning the environmental review process require that all reasonable alternatives, which might accomplish the objectives of a proposed project,

More information

The CLE Master Plan Includes:

The CLE Master Plan Includes: The CLE Master Plan Includes: An inventory of existing conditions Forecasting future demand and analyzing future needs Evaluating alternative development scenarios Preparing the Airport Layout Plan Preparing

More information

PUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017

PUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017 PUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017 Agenda Overview of PFC Program at Spokane Airport (GEG) Proposed New PFC 11 Application Project

More information

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting August 23, 2016

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting August 23, 2016 PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting August 23, 2016 DATE: TO: FROM: Michael Ehl, Director, Airport Operations Wayne Grotheer, Director, Aviation Project

More information

14 C.F.R. Part 158. Passenger Facility Charge Program Logan International Airport. Public Notice

14 C.F.R. Part 158. Passenger Facility Charge Program Logan International Airport. Public Notice 14 C.F.R. Part 158 Passenger Facility Charge Program Logan International Airport Public Notice Summary of Proposed 2018 PFC Application PFC Project Descriptions and Justifications PFC Financial Plan Class

More information

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES

STUDY OVERVIEW MASTER PLAN GOALS AND OBJECTIVES INTRODUCTION An Airport Master Plan provides an evalua on of the airport s avia on demand and an overview of the systema c airport development that will best meet those demands. The Master Plan establishes

More information

TERMINAL DEVELOPMENT PLAN

TERMINAL DEVELOPMENT PLAN 5.0 TERMINAL DEVELOPMENT PLAN 5.0 TERMINAL DEVELOPMENT PLAN Key points The development plan in the Master Plan includes the expansion of terminal infrastructure, creating integrated terminals for international,

More information

Greater Orlando Aviation Authority

Greater Orlando Aviation Authority Greater Orlando Aviation Authority Orlando International Airport & Orlando Executive Airport Budgets Fiscal Year 2017-2018 Greater Orlando Aviation Authority Orlando, Florida Greater Orlando Aviation Authority

More information

Preliminary Draft Budget FY Airline Rates and Charges. Sea-Tac International Airport

Preliminary Draft Budget FY Airline Rates and Charges. Sea-Tac International Airport Draft Budget FY 2015 Airline Rates and Charges Sea-Tac International Airport Aviation Finance & Budget 2015 Budget Airline Rates and Charges TABLE OF CONTENTS Exhibit Contents 1 Aeronautical Revenue Summary

More information

Norfolk International Airport

Norfolk International Airport Norfolk International Airport Master Plan Update Technical Advisory Committee Meeting #1 Community Advisory Committee Meeting #1 January 24, 2018 Agenda Project Background Introductions Overview of Airport

More information

Greater Orlando Aviation Authority Orlando International Airport One Jeff Fuqua Boulevard Orlando, Florida Memorandum TO: FROM:

Greater Orlando Aviation Authority Orlando International Airport One Jeff Fuqua Boulevard Orlando, Florida Memorandum TO: FROM: Greater Orlando Aviation Authority One Jeff Fuqua Boulevard Orlando, Florida 32827-4399 Memorandum TO: FROM: Participating Airlines Phil Brown, Executive Director DATE: SUBJECT: Rate Methodology for FY

More information

GSP TERMINAL IMPROVEMENT PROGRAM PRESS KIT

GSP TERMINAL IMPROVEMENT PROGRAM PRESS KIT About GSP MISSION STATEMENT At Greenville-Spartanburg International Airport (GSP), we begin each day fully committed to finding new ways to achieve our mission to provide the citizens of Upstate South

More information

AIRPORT RATES AND CHARGES October 1, 2016 to September 30, 2017 SIGNATORY AIRLINE CHARGES

AIRPORT RATES AND CHARGES October 1, 2016 to September 30, 2017 SIGNATORY AIRLINE CHARGES AIRPORT RATES AND CHARGES October 1, 2016 to September 30, 2017 SIGNATORY AIRLINE CHARGES Landing Fees - per 1,000 lbs. of Maximum Gross Landed Weight Terminal Rental Rate - includes ATO, BSO, ticket counters,

More information

TABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary.

TABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary. TABLE OF CONTENTS Section Page Section Page 1.0 INTRODUCTION... 1 1.1 Purpose of an... 1 1.2 Goals and Objectives... 1 1.3 Mission Statement... 2 1.4 Stakeholder/Public Involvement... 2 1.5 Major Deliverables...

More information

Savannah / Hilton Head International Airport Master Plan Update

Savannah / Hilton Head International Airport Master Plan Update EXECUTIVE SUMMARY Savannah / Hilton Head International Airport Master Plan Update Prepared for: The Savannah Airport Commission Prepared by: URS Corporation In Association With: RS&H and Ruth and Associates,

More information

Love Field Modernization Program Special Facilities Revenue Bond Issue

Love Field Modernization Program Special Facilities Revenue Bond Issue Love Field Modernization Program Special Facilities Revenue Bond Issue Briefing to the Budget, Finance & Audit Committee Department of Aviation January 11, 2010 Purpose Review LFMP Bond Financing Program

More information

STUDY WORK GROUP MEETING No. 4. July 12, 2017

STUDY WORK GROUP MEETING No. 4. July 12, 2017 STUDY WORK GROUP MEETING No. 4 July 12, 2017 Agenda Welcome and introductions Update of project schedule Brief overview of previous SWG meeting Introduction to airport development alternatives Comments,

More information

Executive Summary This document contains the Master Plan for T. F. Green Airport. The goal of a master plan is to provide a framework of potential future airport development in a financially feasible manner,

More information

EXECUTIVE SUMMARY FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT (FLL) MASTER PLAN UPDATE PHASE 1

EXECUTIVE SUMMARY FORT LAUDERDALE-HOLLYWOOD INTERNATIONAL AIRPORT (FLL) MASTER PLAN UPDATE PHASE 1 Workshop Briefing Package Airport Master Plan Update, Phase I Fort Lauderdale-Hollywood International Airport October 18, 2005 Leigh Fisher Associates A Division of Jacobs Consultancy Inc. EXECUTIVE SUMMARY

More information

FLL Master Plan Update Technical Advisory Committee (TAC) Briefing #1. September 28, 2016

FLL Master Plan Update Technical Advisory Committee (TAC) Briefing #1. September 28, 2016 FLL Master Plan Update Technical Advisory Committee (TAC) Briefing #1 September 28, 2016 TAC Committee Role: Internal Stakeholders To provide input on the master planning analysis from the technical and

More information

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019

NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019 NOTICE OF OPPORTUNITY FOR PUBLIC COMMENT RELATED TO PASSENGER FACILITY CHARGE Posted March 25, 2019 The City of Atlanta is providing an opportunity for public comment until April 25, 2019 related to the

More information

Elevating the Upstate

Elevating the Upstate Greenville-Spartanburg Int l Airport Elevating the Upstate SC Economic Developers Association October 12, 2012 Introduction/Presentation Outline Introductions Airport Overview Air Service Terminal Improvement

More information

IRREGULAR OPERATIONS AIRPORT CONTINGENCY PLAN

IRREGULAR OPERATIONS AIRPORT CONTINGENCY PLAN IRREGULAR OPERATIONS AIRPORT CONTINGENCY PLAN.doc TABLE OF CONTENTS SAN Appendix 1 - DOT Required Contingency Plan Appendix 2 CBP Sterile Area Procedures.doc 1.0 Purpose 1.1. The purpose of the is to provide

More information

DRAFT. Airport Master Plan Update Sensitivity Analysis

DRAFT. Airport Master Plan Update Sensitivity Analysis Dallas Love Field Sensitivity Analysis PREPARED FOR: The City of Dallas Department of Aviation PREPARED BY: RICONDO & ASSOCIATES, INC. August 201 Ricondo & Associates, Inc. (R&A) prepared this document

More information

Birmingham Airport 2033

Birmingham Airport 2033 Over the next 15 years, we will expand and improve the Airport to maximise our potential as a single runway airport by investing 500 million in new development. Our plans take account of our forecasted

More information

The demand/capacity analysis was performed utilizing Federal Aviation Administration (FAA) publications, including the following:

The demand/capacity analysis was performed utilizing Federal Aviation Administration (FAA) publications, including the following: Chapter Three To properly plan for the future of Monterey Regional Airport, it is necessary to examine the capacities of the key airport systems. This chapter uses the results of the forecasts prepared

More information

BOARD OF AIRPORT COMMISSIONERS -

BOARD OF AIRPORT COMMISSIONERS - 0 OF1 Los Angeks World Airports REPORT TO THE BOARD OF AIRPORT COMMISSIONERS - Meeting Date: O'IAA.A.)1.Alk-Tort/uQA212J`s-- Approved by: Samantha Bricker - Deputy Executive Director 11/16/2017 11-Pleviewed

More information

Airport Rates & Charges Study Recommendations

Airport Rates & Charges Study Recommendations Airport Rates & Charges Study Recommendations Presented to the City Council Economic Development Committee Department of Aviation August 4, 2008 1 Purpose Ensure revenues are adequate to cover costs. Ensure

More information

EXHIBIT E to Signatory Airline Agreement for Palm Beach International Airport RATE AND FEE SCHEDULE

EXHIBIT E to Signatory Airline Agreement for Palm Beach International Airport RATE AND FEE SCHEDULE EXHIBIT E to Signatory Airline Agreement for Palm Beach International Airport RATE AND FEE SCHEDULE SECTION I - DEFINITIONS The following words, terms and phrases used in this Exhibit E shall have the

More information

Airport Rates & Charges Study Recommendations

Airport Rates & Charges Study Recommendations Airport Rates & Charges Study Recommendations Presented to the City Council Economic Development Committee Department of Aviation August 15, 2008 1 Purpose Ensure revenues are adequate to cover costs.

More information

Kansas City International Airport Airport Terminal Advisory Group Airport Benchmarking. February 11, 2014

Kansas City International Airport Airport Terminal Advisory Group Airport Benchmarking. February 11, 2014 Kansas City International Airport Airport Terminal Advisory Group Airport Benchmarking February 11, 2014 Presentation Agenda 1. Overview of Findings 2. Definitions 3. Airport Benchmarking Caveats 4. Benchmark

More information

Westover Metropolitan Airport Master Plan Update

Westover Metropolitan Airport Master Plan Update Westover Metropolitan Airport Master Plan Update June 2008 INTRODUCTION Westover Metropolitan Airport (CEF) comprises the civilian portion of a joint-use facility located in Chicopee, Massachusetts. The

More information

ENVISIONING AUSTIN s Airport of the Future

ENVISIONING AUSTIN s Airport of the Future ENVISIONING AUSTIN s Airport of the Future ABIA 2040 Master Plan Public Workshop #1 October 12, 2017 WHAT IS THE PURPOSE OF TODAY S WORKSHOP? Educate & Inform Solicit Input Answer Questions 2 WHAT IS A

More information

Meeting Presentation. Sacramento International Airport Master Plan Update October 30, 2012

Meeting Presentation. Sacramento International Airport Master Plan Update October 30, 2012 Meeting Presentation Master Plan Update October 30, 2012 Agenda We encourage open discussion during today s meeting Team Goals Background (Airport Master Plans) Areas of Emphasis Schedule Special Concerns

More information

Noise Oversight Committee

Noise Oversight Committee Noise Oversight Committee March 18, 2015 Audio recordings are made of this meeting Noise Oversight Committee March 18, 2015 Item 1 Review and Approve Draft Meeting Minutes Minutes from January 21, 2015

More information

Opening A New Airport Terminal

Opening A New Airport Terminal Opening A New Airport Terminal A Systematic Approach to Activation & Lessons Learned Leo Fermin Deputy Airport Director San Francisco International Airport Clearly Define Objectives Clearly define the

More information

ACI-NA BUSINESS TERM SURVEY APRIL 2017

ACI-NA BUSINESS TERM SURVEY APRIL 2017 ACI-NA BUSINESS TERM SURVEY APRIL 2017 Airport/Airline Business Working Group Randy Bush Tatiana Starostina Dafang Wu Assisted by Professor Jonathan Williams, UNC Agenda Background Rates and Charges Methodology

More information

Chapter 9: Financial Plan Draft

Chapter 9: Financial Plan Draft Chapter 9: Draft TABLE OF CONTENTS 9... 5 9.2.1 ABIA Accounting... 6 9.2.2 Legal Environment... 6 9.2.3 Governing Documents... 8 9.3.1 FAA AIP Grants... 13 9.3.2 Local ABIA Funds... 14 9.4.1 Defer or Delay

More information

PUBLIC SCOPING MEETING APRIL 2018

PUBLIC SCOPING MEETING APRIL 2018 Photo credit: Patrick Schneider PUBLIC SCOPING MEETING APRIL 2018 Welcome to the meeting! The Federal Aviation Administration (FAA) is preparing an Environmental Impact Statement (EIS) to evaluate the

More information

CHAPTER 1 EXECUTIVE SUMMARY

CHAPTER 1 EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY 1 1 EXECUTIVE SUMMARY INTRODUCTION William R. Fairchild International Airport (CLM) is located approximately three miles west of the city of Port Angeles, Washington. The airport

More information

RONALD REAGAN WASHINGTON NATIONAL AIRPORT NOVEMBER 2016

RONALD REAGAN WASHINGTON NATIONAL AIRPORT NOVEMBER 2016 2. Purpose and Need 2.1 Background The Metropolitan Washington Airports Authority (the Authority) is preparing an Environmental Assessment (EA) of potential environmental impacts associated with the proposed

More information

Greater Orlando Aviation Authority Board Meeting. Wednesday, January 17, 2018

Greater Orlando Aviation Authority Board Meeting. Wednesday, January 17, 2018 Greater Orlando Aviation Authority Board Meeting Wednesday, Award Recognition South Terminal Complex Phase 1 and Phase 2 Planning Overview Greater Orlando Aviation Authority AGENDA PASSENGER TRAFFIC

More information

COUNTY OF ORANGE, CALIFORNIA AIRPORT REVENUE BONDS, SERIES 2009 A & B ANNUAL REPORT FOR FISCAL YEAR ENDED JUNE 30, 2013

COUNTY OF ORANGE, CALIFORNIA AIRPORT REVENUE BONDS, SERIES 2009 A & B ANNUAL REPORT FOR FISCAL YEAR ENDED JUNE 30, 2013 COUNTY OF ORANGE, CALIFORNIA AIRPORT REVENUE BONDS, SERIES 2009 A & B ANNUAL REPORT FOR FISCAL YEAR ENDED JUNE 30, 2013 Dated: January 28, 2014 COUNTY OF ORANGE, CALIFORNIA AIRPORT REVENUE BONDS, SERIES

More information

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES

MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES MONTEREY REGIONAL AIRPORT MASTER PLAN TOPICAL QUESTIONS FROM THE PLANNING ADVISORY COMMITTEE AND TOPICAL RESPONSES Recurring topics emerged in some of the comments and questions raised by members of the

More information

Omaha Airport Authority Eppley Airfield

Omaha Airport Authority Eppley Airfield June 13, 2018 Omaha Airport Authority Eppley Airfield Terminal Development Program Industry Day Previous Master Plan Results 1996 2014 2 June 13, 2018 Eppley Airfield Terminal Development Program Industry

More information

Hartsfield Jackson Update prepared for:

Hartsfield Jackson Update prepared for: Hartsfield Jackson Update prepared for: September 6, 2013 Presented by: Shelley Lamar, Planning Manager Agenda ATL Overview Economic Impact Preparing for the Future Your Questions Airport overview Airport

More information

Stakeholders Meeting

Stakeholders Meeting Stakeholders Meeting for the Expansion of Runway 9R-27L, Terminal 4 Gate Relocation and Land Acquisition for Runway 9R-27L September 22, 2011 Stakeholders Meeting AGENDA Introduction FLL Airport Improvements

More information

BOARD OF AIRPORT COMMISSIONERS

BOARD OF AIRPORT COMMISSIONERS 1 8/17/2018 8/21/2018 8/16/2018 i ElY MY Y I : JH MT BY...01,, III1*.ji,"1.111Los Angeles World Airports REPORT TO THE BOARD OF AIRPORT COMMISSIONERS Meeting Date: la Approved by: e1. "ampbell, Chief Airports

More information

Aviation Operating Administration/Executive

Aviation Operating Administration/Executive Aviation Operating Administration/Executive To provide the executive and administrative support necessary to the Divisions within the Aviation Department to ensure continued efficiencies, effectiveness,

More information

Dallas Love Field Capital Program. September 16, 2015

Dallas Love Field Capital Program. September 16, 2015 Dallas Love Field Capital Program September 16, 2015 1 The Dallas Airport System Dallas Love Field, Dallas Executive Airport, Downtown Vertiport A $86 million City of Dallas enterprise Operated by the