Kansas City Aviation Department. August 25, 2015

Size: px
Start display at page:

Download "Kansas City Aviation Department. August 25, 2015"

Transcription

1 Kansas City Aviation Department August 25, 2015

2 KCI History Prior to the 1972 Charles B Wheeler Downtown Airport (MKC) was Kansas City s commercial airport Trans World Airlines (TWA) influenced the planning of the Kansas City International Airport (MCI/KCI) in the 1960s, designing it to be a gateway to the world for supersonic aircraft KCI opened in November 11, 1972 Do to a rapid increase in aircraft hijackings, the FAA mandated screening of airline passengers and carry-on bags on January 5, 1973 When KCI was designed/built there was no separation between secure and unsecure areas 2

3 Airport Master Plan (1992) Airports in the US are required to submit Master Plans to the FAA (10-20 years) KCI commissioned a Master Plan in 1992 with three primary objectives: 1. Establish plans that are flexible to meet unforeseen circumstances 2. Improve the level of service provided 3. Confirm the development plan is financially feasible Local citizens, community groups and government agencies participated in one of three committees established at the beginning of the process The plan recommended to construct a new terminal when the existing terminals reach the end of their useful life. Industry experts suggested a single terminal. 3

4 Terminal Improvement Program (TIP) Timeline: Following completion of the 1995 Airport Master Plan and approval by the FAA, the Terminal Improvement Program TIP was initiated : Project Development to determine specific extent of renovations to the three terminals and selection of the Architectural Team : Architectural and Engineering designs progress to preparation of construction bid documents and the Program Management Team is selected. Construction Phasing is determined through close coordination with Airlines and Tenants : TIP construction takes place in multiple phases in each of the three terminals. Program Costs total $258 million. 4

5 Asbestos Abatement 5

6 TIP Construction Complete Removal of Interior to Concrete Frame 6

7 TIP Construction Replace All Exterior Glass and Glazing 7

8 TIP Construction Raise Departure Lounge Separator Walls to 12 Feet Tall 8

9 TIP Construction Expand Certain Departure Lounges per Airline Requests 9

10 TIP Construction Replace All Interior Walls and Floor Finishes 10

11 Not Included in TIP Not all airlines service Kansas City requested gate area expansion Bathrooms were not included in the gate areas Terminal connectivity (mono rail) was not advanced due to funding Security walls (glass) were not raised to the full ceiling height Escalators/elevators not replaced Underground utilities not addressed 11

12 Landside Infrastructure Improvements Underground Utilities Replacement 12

13 Post 9-11 In-Line Checked Baggage Screening Install Explosive Detection Systems in the checked baggage handling systems for 6 of 10 Airlines 13

14 Airport Master Plan (2006) Seven Visioning Workshops were held in the fall of 2006 that included aviation officials, airlines, tenants, regional and local civic leadership, planning agencies, neighborhoods and other key stakeholders Several future terminal concepts were discussed A final terminal concept was chosen and the master plan was adopted by Kansas City Council - December

15 Short-List Terminal South Option 5 15

16 KCI Terminal Development Strategies Continue to infuse capital improvements into the existing three terminals and expand into a 4th new terminal Opened in 1972 (34 yrs. old in 2006, 53 yrs. old in 2025) $258M renovations in 2004 The very narrow dimension of the existing Drive to Your Gate terminals limit their ability to meet a variety of airline missions 4th Terminal location blocks potential of landside access from the south Renovate the existing terminal complex moving towards a single consolidated terminal for passenger processing Very difficult to construct while maintaining current operations Does not fix airside operational constraints Falls short of achieving an efficient operation or offering airline mission flexibility Develop a new single consolidated terminal / concourse facility Greenfield site with no operational impacts Increased operational flexibility and expansion capability 16

17 KCI Terminal Planning Considerations KCI Master Plan sets the long-range direction for the terminal complex which influences on-going planning and capital improvement decisions Terminal facilities influence airline decisions about whether their business model can efficiently operate from an airport like KCI Master Plan identifies a terminal complex solution with the flexibility to accommodate a variety of airline missions thereby ensuring Kansas City s economic future by providing efficient air service options Origin and Destination (O&D) service Hubbing operations Low Cost Carriers (LLC) International 17

18 Future Major Capital Work in Three Terminals Landside Infrastructure Replacement and Rehabilitation Improvements to Checked Baggage Screening Airside Infrastructure Replacement and Rehabilitations Improvements to Deicing Runoff Collection Systems Increase Capacity of Terminal Parking Garages Continue Preventive Maintenance and Monitoring Programs on Systems: Terminal Chillers Installed in 1996 Terminal Boilers Installed in 2000 Terminal Roofing Installed in

19 Decade of Airline Consolidation Alaska 2012 Spirit 2014 Allegiant

20 Advance Terminal Planning (2012) $3.4M FAA grant awarded for further study of terminal plan 20

21 Advance Terminal Planning (2012) 21

22 South Terminal Costs Avoided with a Northern Site (2012) MCI Terminal and Infrastructure Estimate Project Element South Cost Reduced Cost Savings Highway 152 $ 143,797,000 $ - $ 143,797,000 Landside $ 576,044,800 $ 353,129,200 $ 222,915,600 Airside $ 256,850,700 $ 205,255,700 $ 51,595,000 Architecture $ 653,920,000 $ 596,975,000 $ 56,945,000 Utilities $ 82,075,000 $ 29,882,000 $ 52,193,000 $ 1,712,687,500 $ 1,185,241,900 $ 527,445,600 22

23 Conceptual Site Plans (2015) Major Renovation: A New Terminal: A Major Renovation: B New Terminal: B 23

24 Initial Findings Airlines and KCAD concluded that major renovation alternatives presented significant shortfalls: Higher capital and ongoing operating cost Substandard operational performance More difficult and lengthy construction Limited options to improve customer convenience 24

25 Airline Recommendation The Airline-Airport Affairs Committee unanimously proposed tabling further study of major renovation options The Airline-Airport Affairs Committee will continue to review and refine new terminal options 25

26 Next Steps: Exhibit K Process Refine New Terminal Options Final Presentation to City Council & Mayor Design & layout Cost estimations Airline agreement 26

27 Kansas City Aviation Department August 25, 2015

July 21, Mayor & City Council Business Session KCI Development Program Process Update

July 21, Mayor & City Council Business Session KCI Development Program Process Update July 21, 2015 Mayor & City Council Business Session KCI Development Program Process Update History of KCI 2 Airport Funding KCI Improvements are Funded by Airlines & Travelers City tax revenues do not,

More information

FLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING

FLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING (PRELIMINARY DRAFT) WORK IN PROGRESS - FOR DISCUSSION PURPOSES ONLY FLL Master Plan Update BOARD OF COUNTY COMMISSIONERS BRIEFING May 15, 2018 Master Plan Schedule Overview Progress Since Last Master Plan

More information

City of Kansas City AIRPORT COMMITTEE BRIEFING. Major Renovation Evaluation for Kansas City International Airport.

City of Kansas City AIRPORT COMMITTEE BRIEFING. Major Renovation Evaluation for Kansas City International Airport. City of Kansas City AIRPORT COMMITTEE BRIEFING Major Renovation Evaluation for Kansas City International Airport February 2, 2016 1 Agenda Briefly review Exhibit K Process to establish Program Requirements

More information

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES

EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES EXHIBIT K TERMINAL PROJECT PROCEDURES PHASE I - DEVELOPMENT OF TERMINAL PROGRAM & ALTERNATIVES Over the term of the Master Amendment to the Airline Use and Lease Agreement, the Kansas City Aviation Department

More information

GSP TERMINAL IMPROVEMENT PROGRAM PRESS KIT

GSP TERMINAL IMPROVEMENT PROGRAM PRESS KIT About GSP MISSION STATEMENT At Greenville-Spartanburg International Airport (GSP), we begin each day fully committed to finding new ways to achieve our mission to provide the citizens of Upstate South

More information

Kansas City Aviation Department. Community Listening Session

Kansas City Aviation Department. Community Listening Session Kansas City Aviation Department Community Listening Session Listening Session Purpose The Kansas City Aviation Department is moderating these community listening sessions in order to gather feedback from

More information

TERMINAL DEVELOPMENT PLAN

TERMINAL DEVELOPMENT PLAN 5.0 TERMINAL DEVELOPMENT PLAN 5.0 TERMINAL DEVELOPMENT PLAN Key points The development plan in the Master Plan includes the expansion of terminal infrastructure, creating integrated terminals for international,

More information

Kansas City Aviation Department. Airport Committee July 19, 2018

Kansas City Aviation Department. Airport Committee July 19, 2018 Kansas City Aviation Department Airport Committee July 19, 2018 AGENDA Labor Update Design Process General Updates Community Outreach LABOR UPDATE Overarching Goals: Labor Harmony on the project Ensure

More information

Tampa International Airport Master Plan Update. December 12, 2012

Tampa International Airport Master Plan Update. December 12, 2012 Tampa International Airport Master Plan Update December 12, 2012 1 Prior Presentation Consolidated rental car and people mover Decongest curbsides and roadways Enable rental car growth Gain long term parking

More information

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257

CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257 Form PDES 8 THE CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION 5/12/11 SENIOR AIRPORT ENGINEER, CODE 7257 Summary of Duties: A Senior Airport Engineer performs the more difficult and

More information

Brief Recap of Project to Date

Brief Recap of Project to Date CITY AND BOROUGH OF SITKA Rocky Gutierrez Airport (SIT) Terminal Improvements Project Brief Recap of Project to Date Schematic Design: Design Development Meetings June 26 & 27, 2018 Project Description

More information

EXHIBIT K OVERVIEW KANSAS CITY INTERNATIONAL AIRPORT TERMINAL DEVELOPMENT PROGRAM PREPARED BY: April 2016

EXHIBIT K OVERVIEW KANSAS CITY INTERNATIONAL AIRPORT TERMINAL DEVELOPMENT PROGRAM PREPARED BY: April 2016 OVERVIEW April 2016 PREPARED BY:, Incorporated AirProjects, Inc. AvAirPros Connico Incorporated HNTB Corporation LeighFisher Inc. PGAL Ross & Baruzzini, Inc. SK Design Group, Inc. Vic Thompson Company

More information

Current and Forecast Demand

Current and Forecast Demand Existing Facilities Jacksonville International Airport (JIA) is served by a number of airside and landside facilities. There are two runways that serve the airport in an open V configuration. The Annual

More information

Executive Summary This document contains the Master Plan for T. F. Green Airport. The goal of a master plan is to provide a framework of potential future airport development in a financially feasible manner,

More information

Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport

Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport Re: Public Notice of Opportunity to Comment on Los Angeles World Airports Passenger Facility Charge Application at Los Angeles International Airport Los Angeles World Airports (LAWA) intends to submit

More information

Kansas City Aviation Department. Update to Airport Committee Customer Service

Kansas City Aviation Department. Update to Airport Committee Customer Service Kansas City Aviation Department Update to Airport Committee Customer Service 1 Perspective An estimated 800,000 people participated in the Royals Word Series Parade On average 883,000 airline passengers

More information

CHAPTER 4: ALTERNATIVES

CHAPTER 4: ALTERNATIVES MSP Long Term Comprehensive Plan Update Metropolitan Airports Commission 4.1 INTRODUCTION CHAPTER 4: ALTERNATIVES Several alternatives were developed and evaluated based on their capability to meet the

More information

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER

DEVELOPMENT OF TOE MIDFIELD TERMINAL IROJECT CAPACITY ENHANCEMENT REPORT DEPARTMENT OF AVIATION TOM FOERSTER CHAIRMAN BARBARA HAFER COMMISSIONER PETE FLAHERTY COMMISSIONER TOM FOERSTER CHAIRMAN DEPARTMENT OF AVIATION BARBARA HAFER COMMISSIONER STEPHEN A. GEORGE DIRECTOR ROOM M 134, TERMINAL BUILDING GREATER PITTSBURGH INTERNATIONAL AIRPORT PITTSBURGH,

More information

Port of Seattle Sea-Tac Airport Master Plan An Economic Engine for Washington State. Kurt Beckett Deputy Chief Executive Officer

Port of Seattle Sea-Tac Airport Master Plan An Economic Engine for Washington State. Kurt Beckett Deputy Chief Executive Officer Port of Seattle Sea-Tac Airport Master Plan An Economic Engine for Washington State Kurt Beckett Deputy Chief Executive Officer WA Ports A Unique Public Agency Mission: Create Jobs through Travel, Trade

More information

PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM

PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM PITTSBURGH INTERNATIONAL AIRPORT TERMINAL MODERNIZATION PROGRAM FREQUENTLY ASKED QUESTIONS September 2017 Master Plan Update: 1. What is a Master Plan Update? The objective of a Master Plan Update (MPU)

More information

Meeting Presentation. Sacramento International Airport Master Plan Update October 30, 2012

Meeting Presentation. Sacramento International Airport Master Plan Update October 30, 2012 Meeting Presentation Master Plan Update October 30, 2012 Agenda We encourage open discussion during today s meeting Team Goals Background (Airport Master Plans) Areas of Emphasis Schedule Special Concerns

More information

FLL Master Plan Update Technical Advisory Committee (TAC) Briefing #1. September 28, 2016

FLL Master Plan Update Technical Advisory Committee (TAC) Briefing #1. September 28, 2016 FLL Master Plan Update Technical Advisory Committee (TAC) Briefing #1 September 28, 2016 TAC Committee Role: Internal Stakeholders To provide input on the master planning analysis from the technical and

More information

Chapter 1: Introduction Draft

Chapter 1: Introduction Draft Chapter 1: Draft TABLE OF CONTENTS 1... 4 1.6.1 Stakeholder Engagement Plan... 10 Chapter 1 Page 2 TABLE OF EXHIBITS Exhibit 1.1-1 ABIA Annual Growth Since 1993... 5 Exhibit 1.4-1: ABIA Location Map...

More information

Fort Lauderdale Hollywood International Airport

Fort Lauderdale Hollywood International Airport ATLANTA, GEORGIA 1 2 ATLANTA, GEORGIA Fort Lauderdale Hollywood International Airport Master Plan to Master Plan Implementation Jamie McCluskie Director of Aviation Planning & Environmental Broward County

More information

ENVISIONING AUSTIN s Airport of the Future

ENVISIONING AUSTIN s Airport of the Future ENVISIONING AUSTIN s Airport of the Future ABIA 2040 Master Plan Public Workshop #1 October 12, 2017 WHAT IS THE PURPOSE OF TODAY S WORKSHOP? Educate & Inform Solicit Input Answer Questions 2 WHAT IS A

More information

Kansas City International Airport Airport Terminal Advisory Group Airport Benchmarking. February 11, 2014

Kansas City International Airport Airport Terminal Advisory Group Airport Benchmarking. February 11, 2014 Kansas City International Airport Airport Terminal Advisory Group Airport Benchmarking February 11, 2014 Presentation Agenda 1. Overview of Findings 2. Definitions 3. Airport Benchmarking Caveats 4. Benchmark

More information

BUSH INTERCONTINENTAL AIRPORT

BUSH INTERCONTINENTAL AIRPORT JULY 2014 BUSH INTERCONTINENTAL AIRPORT Project 500N-Terminal D, Phase III-Gate D9 A380 Conversion Project Manager: Randy Williams Everything is Bigger Terminal D at IAH The saying everything is bigger

More information

An Overview of GMR Megawide Consortium s Unsolicited Proposal. March 2018

An Overview of GMR Megawide Consortium s Unsolicited Proposal. March 2018 s An Overview of GMR Megawide Consortium s Unsolicited Proposal March 2018 1 Metro Manila requires a multi-airport system and NAIA shall continue to play an anchor role in this system. Multi-Airport system

More information

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012

JOSLIN FIELD, MAGIC VALLEY REGIONAL AIRPORT DECEMBER 2012 1. Introduction The Federal Aviation Administration (FAA) recommends that airport master plans be updated every 5 years or as necessary to keep them current. The Master Plan for Joslin Field, Magic Valley

More information

Existing Conditions AIRPORT PROFILE Passenger Terminal Complex 57 air carrier gates 11,500 structured parking stalls Airfield Operations Area 9,000 North Runway 9L-27R 6,905 Crosswind Runway 13-31 5,276

More information

Chapter 1: Introduction

Chapter 1: Introduction Chapter 1: TABLE OF CONTENTS 1... 4 1.1 Master Plan Study Content... 4 1.2 Purpose and Scope of Master Plan Study... 4 1.3 Airport History and Role... 6 1.4 Airport Location and Service Area... 6 1.5 ABIA

More information

The CLE Master Plan Includes:

The CLE Master Plan Includes: The CLE Master Plan Includes: An inventory of existing conditions Forecasting future demand and analyzing future needs Evaluating alternative development scenarios Preparing the Airport Layout Plan Preparing

More information

BNA Master Plan Update Public Meeting No. 2

BNA Master Plan Update Public Meeting No. 2 A Six Sigma Organization BNA Master Plan Update Public Meeting No. 2 September 18, 2012 Agenda BNA Master Plan Update Consultants Status of the BNA Master Plan Update Workstation Boards Forecasts of Aviation

More information

BURLINGTON INTERNATIONAL AIRPORT

BURLINGTON INTERNATIONAL AIRPORT BURLINGTON INTERNATIONAL AIRPORT VISION 2030 AIRPORT MASTER PLAN UPDATE Summary Presentation AIRPORT STAFF AND STUDY TEAM Robert McEwing, Director of Planning & Development Brad Worthen, Community Facilitator

More information

State of the Airport Robert S. Bowen, Executive Director October 18, 2018

State of the Airport Robert S. Bowen, Executive Director October 18, 2018 Robert S. Bowen, Executive Director October 18, 2018 A Year of Change The last year will be remembered as a period when the airlines, bolstered by a growing national economy, moderate fuel prices and changing

More information

RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan

RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan RNO Master Plan Approved Alternatives, Financial Analysis, and Facilities Implementation Plan Project Schedule Today Slide 40 Project Vision To provide an achievable, flexible, fiscally, and environmentally

More information

Birmingham Airport 2033

Birmingham Airport 2033 Over the next 15 years, we will expand and improve the Airport to maximise our potential as a single runway airport by investing 500 million in new development. Our plans take account of our forecasted

More information

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal

Airport Master Plan. Rapid City Regional Airport. October 2015 FAA Submittal Airport Master Plan Rapid City Regional Airport October 2015 FAA Submittal Rapid City Regional Airport Master Plan Update Table of Contents Executive Summary... i Scope & Timeline... i Forecasts... i Preferred

More information

Notice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application

Notice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application July 3, 2018 Notice and Opportunity to Comment on New Proposed Passenger Facility Charge (PFC) New Application The City of Kansas City (City), Missouri through its Aviation Department ( the Department

More information

TRACK: B TERMINAL/LANDSIDE

TRACK: B TERMINAL/LANDSIDE Salt Palace Convention Center TRACK: B TERMINAL/LANDSIDE WORKSHOP: 3 Title: Airlines and Airports Consolidation and Changing Faces Who is building the Terminals, Technology, and Flexibility? Moderator:

More information

KANSAS CITY INTERNATIONAL AIRPORT TRAFFIC AND OPERATIONS Jan-19 MONTH TO DATE MONTH TO DATE

KANSAS CITY INTERNATIONAL AIRPORT TRAFFIC AND OPERATIONS Jan-19 MONTH TO DATE MONTH TO DATE TRAFFIC AND OPERATIONS % Change from 2018 YEAR YEAR MONTH TO DATE MONTH TO DATE Scheduled Enplaned 413,708 413,708 2.01 2.01 Deplaned 413,956 413,956 1.95 1.95 Total 827,664 827,664 1.98 1.98 Charter Enplaned

More information

AEROVISION AUGMENTED REALITY AIRPORTS IN 3D Young Professionals Innovation Competition Daniel Schoenberg, RS&H Jill Geboy, Jacobs Engineering Daniel

AEROVISION AUGMENTED REALITY AIRPORTS IN 3D Young Professionals Innovation Competition Daniel Schoenberg, RS&H Jill Geboy, Jacobs Engineering Daniel AUGMENTED REALITY AIRPORTS IN 3D Young Professionals Innovation Competition Daniel Schoenberg, RS&H Jill Geboy, Jacobs Engineering Daniel Pruim, Horry County Department of Airports Challenges Explore Innovate

More information

KANSAS CITY INTERNATIONAL AIRPORT TRAFFIC AND OPERATIONS Dec-18 MONTH TO DATE MONTH TO DATE

KANSAS CITY INTERNATIONAL AIRPORT TRAFFIC AND OPERATIONS Dec-18 MONTH TO DATE MONTH TO DATE TRAFFIC AND OPERATIONS % Change from 2017 YEAR YEAR MONTH TO DATE MONTH TO DATE Scheduled Enplaned 477,661 5,930,388 3.52 3.23 Deplaned 469,187 5,910,901 3.77 2.85 Total 946,848 11,841,289 3.64 3.04 Charter

More information

Master Plan Update Community Advisory Committee Kick-off Meeting

Master Plan Update Community Advisory Committee Kick-off Meeting Nashville International Airport Master Plan Update Community Advisory Committee Kick-off Meeting September 13, 2018 Agenda Welcome and Introductions Master Plan Objectives Master Plan Process BNA Vision

More information

TABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary.

TABLE OF CONTENTS. Airport Master Plan Update Manchester-Boston Regional Airport. W:\ _Manchester\MPU\Final\Executive Summary. TABLE OF CONTENTS Section Page Section Page 1.0 INTRODUCTION... 1 1.1 Purpose of an... 1 1.2 Goals and Objectives... 1 1.3 Mission Statement... 2 1.4 Stakeholder/Public Involvement... 2 1.5 Major Deliverables...

More information

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport

Executive Summary. MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport Executive Summary MASTER PLAN UPDATE Fort Collins-Loveland Municipal Airport As a general aviation and commercial service airport, Fort Collins- Loveland Municipal Airport serves as an important niche

More information

What is the ABIA 2040 Master Plan?

What is the ABIA 2040 Master Plan? AUSTIN-BERGSTROM INTERNATIONAL AIRPORT What is the ABIA 2040 Master Plan? The ABIA 2040 Master Plan outlines the vision for how our airport will serve the expected 26+ million passengers by the year 2040.

More information

During Construction. Full Resident and Non-Resident Services. Contract Administration and Construction Supervision of Groundside and Airside Projects

During Construction. Full Resident and Non-Resident Services. Contract Administration and Construction Supervision of Groundside and Airside Projects Page 1 of 5 May 21, 2007 HOME PROFILE SECTORS & SERVICES CAREERS SEMINARS & PAPERS LINK airport development Description of Service transportatio services link Airport Developm Pre-Construction Area Development

More information

KCI New Terminal Update. Airport Committee Thursday, August 16, 2018

KCI New Terminal Update. Airport Committee Thursday, August 16, 2018 KCI New Terminal Update Airport Committee Thursday, August 16, 2018 AGENDA Design Progress Community Outreach General Updates Construction Phasing PROJECT TIMELINE Click to edit Master title style We are

More information

Los Angeles International Airport (LAX) Airside $907M

Los Angeles International Airport (LAX) Airside $907M Los Angeles International Airport (LAX) $3,948M Airside $907M Airfield Electrical Systems Rehabilitation Bradley West Core Renovation, East Ramp and Concourse Demolition Imperial Terminal Aircraft Parking

More information

FUTURE PASSENGER PROCESSING. ACRP New Concepts for Airport Terminal Landside Facilities

FUTURE PASSENGER PROCESSING. ACRP New Concepts for Airport Terminal Landside Facilities FUTURE PASSENGER PROCESSING ACRP 07-01 New Concepts for Airport Terminal Landside Facilities In association with: Ricondo & Associates, TransSolutions, TranSecure RESEARCH Background Research Objective

More information

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan

1.0 Project Background Mission Statement and Goals Objectives of this Sustainable Master Plan TABLE OF CONTENTS CHAPTER 1 INTRODUCTION 10 Project Background 1-1 11 Mission Statement and Goals 1-1 12 Objectives of this Sustainable Master Plan 1-2 CHAPTER 2 INVENTORY 20 Airport Background 2-1 201

More information

Tulsa Airports Improvement Trust Strategic Plan Update

Tulsa Airports Improvement Trust Strategic Plan Update Tulsa Airports Improvement Trust Strategic Plan Update 2016-2026 TABLE OF CONTENTS I. Background II. III. IV. Existing Conditions and Future Requirements Mission, Vision, & Goals Strengths, Weakness, Opportunities

More information

Casper/Natrona County International Airport Master Plan Update Technical Advisory Committee Meeting Two - October 14th, :30 PM

Casper/Natrona County International Airport Master Plan Update Technical Advisory Committee Meeting Two - October 14th, :30 PM Casper/Natrona County International Airport Master Plan Update Technical Advisory Committee Meeting Two - October 14th, 2014 1:30 PM Casper/Natrona County International Airport Master Plan Update Policy

More information

Funding Package TOTAL $15,172,000

Funding Package TOTAL $15,172,000 Funding Package ACT 13 $3,000,000 Transportation Capital Budget $5,000,000 Redevelopment Capital Program(RACP) $3,000,000 Passenger Facility Charge (PFC) $1,500,000 Multimodal Transportation (DCED) $1,500,000

More information

CASE STUDY The New Guayaquil International Airport

CASE STUDY The New Guayaquil International Airport www.jacobs.com worldwide CASE STUDY The New Guayaquil International Airport Prepared for ICAO Airport Planning Seminar for the SAM Region Lima, Peru 10-14 Sep. 2018 September 11, 2018 Outline Existing

More information

Planning, Development and Environment Committee

Planning, Development and Environment Committee Page 1 of 7 MEMORANDUM TO: Planning, Development and Environment Committee FROM: Neil Ralston, Airport Planner Airport Development (726-8129) SUBJECT: 2035 MSP LONG TERM COMPREHENSIVE PLAN FORECAST, FACILITY

More information

Frankfurt Airport Preparing for the Future!

Frankfurt Airport Preparing for the Future! SESSION 3. Aviation Demand & Capacity Expansion Frankfurt Airport Preparing for the Future! Pierre Dominique PRUEMM Senior Executive Vice President, Incheon, September 6, 2017 Frankfurt Airport Preparing

More information

The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands.

The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands. The implementation of this Master Plan will be undertaken in logical stages to meet passenger and workforce demands. Connecting People Building Opportunities 198 Brisbane Airport Corporation CHAPTER 10

More information

Preferred Alternative Summary

Preferred Alternative Summary Tacoma Narrows Airport Master Plan Update Preferred Alternative Summary The Preferred Alternative represents Pierce County s vision for the long-term development of the Tacoma Narrows Airport. This Alternative

More information

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project

PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project PULLMAN-MOSCOW REGIONAL AIRPORT Runway Realignment Project GENERAL AIRPORT INFORMATION AIRPORT USERS Airport ownership: Public, owned by the Pullman-Moscow Regional Airport Board Year opened: February

More information

Fort Wayne International Airport Master Plan Study. Executive Summary

Fort Wayne International Airport Master Plan Study. Executive Summary Fort Wayne International Airport Master Plan Study Executive Summary March 2012 Introduction Airport Background Forecast of Aviation Activity Development Plans Recommended Airfield & Access Development

More information

CVG Overview Connect with CVG March 29, 2017

CVG Overview Connect with CVG March 29, 2017 CVG Overview Connect with CVG March 29, 2017 Launching Point Strategic Plan CVG Launching Point Strategies for 2016 and Beyond Vision: Make travel through CVG and unforgettably positive experience Mission:

More information

Ronan Delaney. DELANEY_RONAN_AVIATION_JUN_2018.DOCX

Ronan Delaney.   DELANEY_RONAN_AVIATION_JUN_2018.DOCX Ronan Delaney Profession Structural Engineer Current Position Associate Principal Global Aviation Skills Leader Joined Arup 1988 Years of Experience 25+ Nationality Irish Qualifications Bsc (Eng), Dip

More information

75 YEARS OF EXPERIENCE 350+ AIRPORT PROJECTS AIRPORT TERMINAL ENGINEER (BUILDING DESIGN+CONSTRUCTION) AIRPORTS (ENR 2016)

75 YEARS OF EXPERIENCE 350+ AIRPORT PROJECTS AIRPORT TERMINAL ENGINEER (BUILDING DESIGN+CONSTRUCTION) AIRPORTS (ENR 2016) COMMERCIAL AVIATION #2 AIRPORT TERMINAL ENGINEER (BUILDING DESIGN+CONSTRUCTION) #3 AIRPORTS (ENR 2016) 75 YEARS OF EXPERIENCE 350+ AIRPORT PROJECTS PILOTING YOUR SUCCESS FROM THE GROUND UP Designing and

More information

RAPID CITY REGIONAL AIRPORT

RAPID CITY REGIONAL AIRPORT RAPID CITY REGIONAL AIRPORT Budget: $16,232,274 Full time Employees: 24 Mission Statement It is the mission of the Rapid City Regional Airport Board to provide safe, efficient, environmentally sensitive,

More information

DRAFT. Master Plan RESPONSIBLY GROWING to support our region. Summary

DRAFT. Master Plan RESPONSIBLY GROWING to support our region. Summary Master Plan GROWING 2017-2037 RESPONSIBLY to support our region Summary DRAFT 2 1 Introduction Over the next three decades, Southern Ontario is set to experience significant growth its population will

More information

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015

Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 Lake Tahoe Airport Master Plan Public Meeting March 16, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development plans

More information

Addendum - Airport Development Alternatives (Chapter 6)

Addendum - Airport Development Alternatives (Chapter 6) Bowers Field Addendum - Airport Development Alternatives (Chapter 6) This addendum to the Airport Development Alternatives chapter includes the preferred airside development alternative and the preliminary

More information

Lake Tahoe Airport Master Plan

Lake Tahoe Airport Master Plan Lake Tahoe Airport Master Plan City Council Briefing October 20, 2015 What is an Airport Master Plan? a comprehensive study of an airport [that] usually describes the short, medium, and long term development

More information

2018 Airport Master Plan Overview of Development Concepts. Greg Ballentine (WSP)

2018 Airport Master Plan Overview of Development Concepts. Greg Ballentine (WSP) 2018 Airport Master Plan Overview of Development Concepts Greg Ballentine (WSP) Thank You Stakeholder and community consultation has included discussions with over 40 stakeholder groups including airport

More information

Norfolk International Airport

Norfolk International Airport Norfolk International Airport Master Plan Update Technical Advisory Committee Meeting #1 Community Advisory Committee Meeting #1 January 24, 2018 Agenda Project Background Introductions Overview of Airport

More information

Chapter 2 FINDINGS & CONCLUSIONS

Chapter 2 FINDINGS & CONCLUSIONS Chapter 2 FINDINGS & CONCLUSIONS 2.01 GENERAL Dutchess County acquired the airport facility in 1947 by deed from the War Assets Administration. Following the acquisition, several individuals who pursued

More information

THE CASE OF A SUCCESSFUL PFC APPLICATION

THE CASE OF A SUCCESSFUL PFC APPLICATION THE CASE OF A SUCCESSFUL PFC APPLICATION 1 Chapter One: Scene of the case study 2 Chapter One: The Scene Spokane, WA Home of the RED TURF at Eastern WA University (and Gonzaga) 3 Chapter One: The Scene

More information

KANSAS CITY INTERNATIONAL AIRPORT TRAFFIC AND OPERATIONS Jun-18 MONTH TO DATE MONTH TO DATE

KANSAS CITY INTERNATIONAL AIRPORT TRAFFIC AND OPERATIONS Jun-18 MONTH TO DATE MONTH TO DATE TRAFFIC AND OPERATIONS % Change from 2017 YEAR YEAR MONTH TO DATE MONTH TO DATE Scheduled Enplaned 560,613 2,875,583 4.73 2.71 Deplaned 564,014 2,851,413 4.37 2.37 Total 1,124,627 5,726,996 4.55 2.54 Charter

More information

Roddy Boggus, Chair, ACC Board of Directors, Suffolk

Roddy Boggus, Chair, ACC Board of Directors, Suffolk Development at U.S. Airports: A Summary Look at Future Trends and Opportunities Speakers: Mark Ahasic, IATA AvMP, Arup Matthew Sheren, AICP, Arup Moderator: Roddy Boggus, Chair, ACC Board of Directors,

More information

2006 ANNUAL GENERAL MEETING

2006 ANNUAL GENERAL MEETING 2006 ANNUAL GENERAL MEETING Address by Garth F. Atkinson President and Chief Executive Officer April 19, 2006 Thank you Peter and good morning ladies and gentlemen and invited guests. Before proceeding

More information

City of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan. Public Workshop #2 April 19, 2018

City of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan. Public Workshop #2 April 19, 2018 City of Austin Department of Aviation Austin Bergstrom International Airport 2040 Master Plan Public Workshop #2 April 19, 2018 DISCUSSION TOPICS Introduction About the Master Plan Public Workshop #1 Recap

More information

Press Release March 1, Refer to: Anna Salgado

Press Release March 1, Refer to: Anna Salgado Press Release March 1, 2018 Refer to: Anna Salgado 63 917 5637629 asalgado@megawide.com.ph MEGAWIDE GMR offers an alternative solution to NAIA congestion Aligned with the government strategy to develop

More information

AirportInfo. Passenger Facility Charge

AirportInfo. Passenger Facility Charge AirportInfo Passenger Facility Charge May 2014 PFC A Cornerstone of Airport Capital Programs PFC user fees were first authorized by Congress in 1990 and are tied directly to local airport projects that:

More information

Pinellas Tourist Development Council

Pinellas Tourist Development Council Network USA 2013 Air Service Development Conference St. Pete Pride Parade National Tourism Week Tony Jannus Aviation Summit - 2013 Tampa International Airport Volunteer Ambassadors Air Service Development

More information

PUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017

PUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017 PUBLIC NOTICE AND OPPORTUNITY FOR COMMENT PASSENGER FACILITY CHARGE NEW PFC APPLICATION #11 JUNE 28, 2017 Agenda Overview of PFC Program at Spokane Airport (GEG) Proposed New PFC 11 Application Project

More information

Love Field Modernization Program Update: Master Planning Recommendations

Love Field Modernization Program Update: Master Planning Recommendations Love Field Modernization Program Update: Master Planning Recommendations Briefing to the Council Transportation and Environment Committee April 28, 2008 1 1 Briefing Objective Discuss the background and

More information

September 14, Dear Mr. Goyette:

September 14, Dear Mr. Goyette: September 14, 2004 Mr. Jacques Goyette Chairman of the Board Développement de l Aéroport Saint-Hubert de Longueuil 5700 Route de l Aéroport Saint-Hubert, Quebec J3Y 8Y9 Dear Mr. Goyette: On behalf of the

More information

Planning Advisory Committee November 20, 2014

Planning Advisory Committee November 20, 2014 Planning Advisory Committee November 20, 2014 Master Plan website up & running: www.flydurango.com Planning Advisory Committee (PAC) established & meeting Briefings provided to City Council, County Commissioners

More information

Beaver Island Airport Terminal Building Project Q & A Prepared by Mead & Hunt

Beaver Island Airport Terminal Building Project Q & A Prepared by Mead & Hunt Beaver Island Airport Terminal Building Project Q & A Prepared by Mead & Hunt About the Consultant Q What services do you (Mead & Hunt) provide as the Island s airport consultant? A Mead & Hunt provides

More information

Schiphol Group. Annual Report

Schiphol Group. Annual Report Schiphol Group Annual Report 2013 Business model Business model Schiphol Group distinguishes four core activities: Aviation, Consumer Products and Services, Real Estate, and Alliances and Participations.

More information

Airport Master Planning Process & Update

Airport Master Planning Process & Update Airport Master Planning Process & Update David Stewart ICAO Airport Master Planning Task Force Subgroup Leader ICAO Airport Planning Seminar for the SAM Region Lima, Peru 10-14 Sep. 2018 1 Speaker: David

More information

,~-- JOHN WAYNE AIRPORT, ORANGE COUNTY. Airline Competition Plan UPDATE. Barry A. Rondinella, A.A.E/C.A.E. Airport Director

,~-- JOHN WAYNE AIRPORT, ORANGE COUNTY. Airline Competition Plan UPDATE. Barry A. Rondinella, A.A.E/C.A.E. Airport Director JOHN WAYNE AIRPORT, ORANGE COUNTY Airline Competition Plan UPDATE JOrNVAYN. AIRPOITT O R A N GE COU N TY,~-- Barry A. Rondinella, A.A.E/C.A.E. Airport Director 3160 Airway Avenue Costa Mesa, CA 92626 January

More information

3.9 AIRPORT SUPPORT FACILITIES

3.9 AIRPORT SUPPORT FACILITIES 3.9 AIRPORT SUPPORT FACILITIES This section details additional airfield facilities that may be required over the next 20 years. 3.9.1 Airport Rescue and Fire Fighting (ARFF) Station GEG is certified under

More information

Sunshine Coast Airport Master Plan September 2007

Sunshine Coast Airport Master Plan September 2007 Sunshine Coast Airport Master Plan September 2007 Contents CONTENTS... I ACKNOWLEDGEMENT... II DISCLAIMER... III 1 EXECUTIVE SUMMARY...IV 1 INTRODUCTION... 1 2 AVIATION DEMAND FORECAST... 5 3 AIRCRAFT

More information

Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway

Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway Gerald R. Ford International Airport Authority Master Plan Update A World Class Gateway Master Plan Advisory Committee (MPAC) Alternatives September 28, 2017 AGENDA Review of Previous Work Ultimate Land

More information

Executive Biography. Jeffrey P. Fegan Chief Executive Officer JeffFegan.com

Executive Biography. Jeffrey P. Fegan Chief Executive Officer JeffFegan.com Executive Biography Jeffrey P. Fegan began his career in the Aviation Industry in 1978. In September 2013, Mr. Fegan retired from the Dallas Fort Worth International Airport (DFW) after serving 29 years:

More information

Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis

Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis Appendix F International Terminal Building Main Terminal Departures Level and Boarding Areas A and G Alternatives Analysis ITB MAIN TERMINAL DEPARTURES LEVEL & BOARDING AREAS A & G ALTERNATIVES ANALYSIS

More information

City of Tallahassee, FL Department of Aviation

City of Tallahassee, FL Department of Aviation City of Tallahassee, FL Department of Aviation Proposed Application to Federal Aviation Administration For Authority to Impose a Passenger Facility Charge (PFC) at Tallahassee International Airport and

More information

BNA Master Plan Update Community Advisory Committee Meeting No. 5

BNA Master Plan Update Community Advisory Committee Meeting No. 5 A Six Sigma Organization BNA Master Plan Update Community Advisory Committee Meeting No. 5 September 19, 2012 Introductions MNAA Staff RW Armstrong Team Albersman & Armstrong, Ltd. Atkins North America,

More information

AIRPORT MASTER PLAN UPDATE

AIRPORT MASTER PLAN UPDATE AIRPORT MASTER PLAN UPDATE PENSACOLA INTERNATIONAL AIRPORT Technical Advisory Committee Meeting #2 June 20, 2017 Agenda» Introduction» Facility Requirements Airside Terminal Landside General Aviation Cargo

More information

Implications of Construction Cost Escalation

Implications of Construction Cost Escalation Implications of Construction Cost Escalation 2007 ACI-NA Economics and Finance Conference James Gill, CPA Deputy Airport Director Finance, Business & Administration Raleigh-Durham Airport Authority Presentation

More information

Alexandria International Airport Emergency Contingency Plan for Excessive Tarmac Delays

Alexandria International Airport Emergency Contingency Plan for Excessive Tarmac Delays Alexandria International Airport Emergency Contingency Plan for Excessive Tarmac Delays Introduction Alexandria International Airport (AEX) has prepared this Emergency Contingency Plan pursuant to 42301

More information

Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport

Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport Notice of Intent to File an Application to Impose and Use a Passenger Facility Charge at Fort Lauderdale-Hollywood International Airport Pursuant to 14 CFR Part 158.24(a) (1) (III), the Broward County

More information