1 Southern African Power Pool Report to SADC By The SAPP Executive Committee arare, ZIMBABWE APRIL
2 CONTENTS 1. Status of the SAPP 2. Market Price Determination 3. SAPP Tariff Study 4. Diminishing Generation Surplus Capacity 5. Western Power Corridor Project 2
3 1. STATUS OF TE SAPP 1.1 Update on the SAPP IGMOU The Revised IGMOU was signed by Ministers responsible for energy in the SADC region on 23 February 2006 in Gaborone, Botswana. The Revised document took into account the following: Restructuring of the SADC Power sector reforms in SAPP member countries The SAPP-Zaire (DRC) Agreement Participation of other stakeholders, such as IPPs Membership of the SAPP All Member Countries have signed the Revised IGMOU. 3
4 1.2 Update on the SAPP IUMOU The following documents were circulated to SAPP Members in January 2007 for comments and approval: i. The Final Draft of the Revised IUMOU ii. iii. Membership Guidelines Membership Application Forms The SAPP EC had requested incorporating a clause on dispute resolution, and this has been done including a clause on confidentiality. In terms of SAPP governance, differentiation between CC Board and Management Committee has been made. The Revised IUMOU is now ready for signing. 4
5 1.3 SAPP-RERA MOU The SAPP-RERA MOU has been approved by both SAPP and RERA and both are ready to sign the document. SAPP and RERA have both recognized the benefits of working together to: Achieve their respective goals Ensure capacity building Ensure cooperation and harmonization in the region, and Keeping each other informed of their respective projects and actions. 5
6 1.4 ost Country Agreement On 13 March 2006, the Government of Zimbabwe and SAPP signed a ost Country Agreement for the hosting of the SAPP Coordination Centre in arare, Zimbabwe. The Agreement has given the SAPP a Diplomatic Status in Zimbabwe and has helped the SAPP to: To be fully recognized as a SADC Institution in Zimbabwe Achieve its stated aims, goals and objectives Reduce its operating costs and tax burden on member states, and Receive support and donations from cooperating partners without difficulties. The SAPP is grateful to the assistance given by the Government of Zimbabwe. 6
7 1.5 Revision of the 2001 Pool Plan The results of the SAPP 2001 Pool Plan were that: The estimated cost of the SAPP Integrated projects was USD 8 billion. The total sum of the individual country project was estimated at USD 11 billion. A potential saving of USD 3 billion could have been achieved if the projects were implemented in a coordinated manner. Unfortunately, due to the difficulty of getting funding, the implementation has not been achieved as previously planned. 7
8 1.5 SAPP Pool Plan - CONTD The current revision of the SAPP Pool Plan of 2001 is funded by a World Bank grant to the tune of US$1 Million. The revision is in line with the SAPP requirement of revising the plan every after 5 years. Work on the Pool Plan is expected to be completed in November The completed Pool Plan will provide input into the SADC Regional Infrastructure Development Master Plan. 8
9 SAPP Pool Plan Objectives To develop an Integrated Generation and Transmission Plan in order to take full advantage of the available power pooling opportunities. To ighlight the benefits that can be derived for members from a co-ordination of their individual expansion plans. To develop electricity supply systems providing least-cost to consumers and minimizing negative environmental impacts. To take into account energy security and requirements of member countries. 9
10 2. MARKET PRICE DETERMINATION 2.1 STEM Operations 2.2 Progression from STEM to Competitive Market 10
11 2.1 STEM Operations Supply and Demand 350, , ,000 Supply Demand Demand far much outstrips the supply. For 2006: Demand 1,705-GWh [MWh] 200, , ,000 50,000 - January March May July September November Supply 372-GWh Traded 217-GWh Data for 2005: Demand 3,857-GWh Supply 1,138-GWh Traded 291-GWh Month January-December 2006 Demand and supply reductions in
12 2.1.2 Actual Energy Prices 70,000 60,000 50,000 40,000 30,000 20,000 10,000 Energy Traded [M Wh] M onetary Value [x10 US$] Energy & Prices, 2006: Traded 217-GWh Prices USc/kWh Data for 2005: Traded 291-GWh Prices USc/kWh - January March May July Month September November Energy trading peaked from May-July 2006, corresponding to winter months. Trading during off peak Energy Traded & Monetary Value 12
13 2.2 STEM Progression to Competitive Market The STEM was introduced in April 2001 as a precursor to a full competitive market. The following members are current STEM Participants: BPC EDM Eskom CB NamPower SEB ZESA 13 In January 2004, the SAPP started the development of a competitive market with funding from Government of Norway and Sida.
14 Measures introduced to achieve reliability and security of supply: STEM contracts are all firm Non delivery penalties apply Security deposit required before Participants trade Shorter financial settlement periods, within 5 days Energy prices in the STEM are achieved by matching offers and bids using pay-as-bid method. The competitive market has been designed to use a uniform pricing method. The market is a day-ahead market (DAM). DAM Market trials started on 10 April 2007 and will be on for the next three months. 14 Market opening to be considered when governance issues are resolved with the SAPP.
15 3. TE SAPP TARIFF STUDY Following the Ad oc meeting held in Namibia in July 2004, it was resolved to: Implement cost reflective tariffs Adopt regulatory principles to enhance the tariffs The SAPP has initiated a Tariff Study and has appointed a Consultant. Key stakeholders such as RERA would be consulted 15 DBSA is funding the study which shall be completed in Aug 2007.
16 SAPP Tariff Study - CONTD The outcome of the Study will be to highlight: Cost reflectiveness of tariffs in Member countries Competitiveness regionally & internationally Implications of capacity expansion projects on tariffs Energy efficiency implications on tariffs Analyse and recommend best practices 16
17 3. DIMINISING GENERATION SURPLUS CAPACITY 3.1 Status of Power Supply Situation 3.2 Commissioned Generation Projects 3.3 Future Short & Long Term Generation Projects 3.4 Priority Transmission Projects 17
18 3.1 Power Supply and Demand No. Country Utility Installed Capacity [MW] Available Capacity [MW] 2006 Peak Demand [MW] 1 Angola ENE Botswana BPC DRC SNEL 2,442 1, Lesotho LEC Malawi ESCOM Mozambique EDM CB 2,250 2,075 7 Namibia NamPower South Africa Eskom 42,011 36,208 34,807 9 Swaziland SEB Tanzania TANESCO Zambia ZESCO 1,752 1,302 1, Zimbabwe ZESA 1,990 1,825 1,904 TOTAL 53,124 44,741 41,744 Non-coincidental 2006 peak demand for interconnected grid: 40,554 MW Available hydro capacity varies depending on season 18
19 60,000 SAPP Generation Vs SAPP Load Forecast Net Capacity Peak Demand 50,000 Capacity [MW} 40,000 30,000 20,000 10, Year The SAPP Planning Data is indicating that SAPP runs out of generation surplus capacity after the year
20 Load shedding in ZESA, ZESCO and NamPower in 2006 at peak periods Interruptible Load Contracts, Demand Market Participation and DSM utilised in ESKOM. (Experience in 2006) This demonstrated that supply was not adequate The forecast for 2007 indicates that actual generation reserve capacity would be lower than normally planned. Demand Side Management Initiatives have been initiated and supported 20
21 3.2 Commissioned Generation Projects [ ] Total Capacity Country Plant Capacity [MW] (MW) Commissioning Date Comment Angola Capanda 1 2 x New Tanzania Ubongo 2 x New Zambia Kariba North 1 x Uprating South AfricaCamden 2 x De-mothballed Zambia Kariba North Uprating South AfricaCamden De-mothballed South AfricaArnot 6 x Upgrade Swaziland Maguga New Zambia Kafue Gorge 2x Uprating Total 1140 Type Percentage ydro 35% Gas 7% Coal 58% 21
22 New Generation Projects in 2007 ESKOM commissioned 2 x 190 MW at Camden in 1 st quarter of ESKOM to commission 1050 MW Commercial Operation by May 2007 (OCGT). SEB to commission 20 MW at Maguga by July
23 Priority Projects The SAPP priority projects have been agreed as follows: 1. Rehabilitation & associated transmission projects. 2. Short-term generation projects Expected to be commissioned before 2010 Completed feasibility studies Approved Environmental Impact Assessment 3. Transmission projects 4. Medium to Long-term generation projects Expected to be commissioned after 2010 Most have no feasibility studies and EIA 23
24 3.3 Classification of Generation Projects No. Generation Project Category Capacity [MW] Estimated Cost [US$ Million] 1 Projects with secured funding 5,031 2,500 2 Rehabilitation 1, Short-term projects 11,206 7,880 4 Long-term projects 32,223 31,800 Total 50,250 43,132 24
25 Planned Rehabilitation & Short Term Generation Projects 2007 to 2010 Country Generation Capacity MW Angola 343 Botswana 600 DRC 1136 Lesotho 28 Malawi 104 Mozambique 912 Namibia 800 RSA 6639 Swaziland 20 Tanzania 260 Zambia 1350 Zimbabwe 1315 TOTAL Annual Average Planned New Generation Capacity = 3,327 MW Most Projects are on track to be commissioned before
26 Country Capacity Contribution GENERATION PROJECTS IN PROGRESS Country Capacity, MW Percentage Angola % South Africa 4, % Swaziland % Zambia % Zimbabwe % TOTAL 5, ydro 40% Gas 27% Coal 33% The above projects have secured funding and are currently in progress. They are expected to be commissioned before
27 REABILITATION & SORT TERM PROJECTS Country Capacity, MW Percentage Botswana % DRC 1, % Lesotho % Malawi % Mozambique % Namibia % South Africa 2, % Tanzania % Zambia 1, % Zimbabwe % TOTAL 8, The above projects are ready but have not reached financial closure. If funding was available, the should be commissioned by
28 SAPP Operating Members Only MW Year Capacity Planned Capacity Required Peak Demand forecast 28 Assumptions: Demand Growth = 3.6% Reserve Margin = 10.2 %
29 SAPP Members (All) Improved reserve margin if all members are interconnected MW Available & Planned Capacity Year Capacity Required Peak Demand forecast 29 Assumptions: Demand Growth = 3.6% Reserve Margin = 10.2 %
30 Priority Transmission Projects Transmission projects are divided as follows: i. Outstanding transmission interconnectors whose aim is to interconnect non-operating members of the SAPP: Malawi-Mozambique interconnector, Zambia-Tanzania-Kenya Interconnector, and Angolan interconnection to SAPP. ii. Transmission interconnectors aimed at relieving congestion on the SAPP grid, and iii. New transmission interconnectors aimed to evacuate power from generating stations to the load centres. 30
31 Gabon Congo Dem Rep of Congo Brazzaville Kinshasa Rwanda Burundi Tanzania Kenya Nairobi Luanda Dar es Salaam A total of USD 4.7 billion is required to develop the identified transmission projects Angola Namibia Botswana Zambia Lusaka T arare Malawi Lilongwe T Zimbabwe Mozambique SOUTERN AFRICAN GRID 31 Windhoek Cape Town T South Africa N P Gaborone Pretoria Johannesburg T T T T P Lesotho T T TT T T T T T T Maputo Mbabane Swaziland P T ydro station Pumped storage scheme Thermal Station
32 4. WESTERN POWER CORRIDOR PROJECT BACKGROUND WESTCOR consist of a renewable hydro power generation at Inga 3 comprising of VAC and VDC power transmission and broad band telecommunication. The five participating member utilities have each paid US$ for establishment of the project office in Gaborone. A procurement policy, code of ethics and General Conditions of Service have been approved. The Board of Directors is in the process of reviewing the draft Business Plan for approval. 32
33 4. WESTCOR (2) CONDUCTING TE STUDIES The first part has been completed and conclusion of the study is acceptable at this stage. The independent consultants to be sourced to conduct the studies for pre-feasibility, feasibility and solicitation phase. The estimated time to conduct these studies is 3-years. A management to be established under the leadership of the Chief Operating Offices, to coordinate and monitor the study. 33
34 4. WESTCOR (3) STUDY BUDGET, TIMELINE AND COST Pre-feasibility study US$4.5 Million (6 Months) Feasibility US$38 Million (12 months) Solicitation Phase US$2.4 Million (12 Months) Evaluation to be done after each stage. 34
35 5. ACIEVEMENTS [ ] i. DOCUMENTATION REVIEW The revised IGMOU was signed in February 2006 The IUMOU will be signed on 25 April ii. COMMISSIONED GENERATION PROJECTS The SAPP has commissioned a total of 1,140MW of power generation projects in various countries. iii. SAPP POOL PLAN REVIEW SAPP received a World bank grant to review the SAPP Pool Plan of Work shall be completed in Nov
36 iv. COMPETITIVE MARKET DEVELOPMENT Market specifications completed and approved. The market type is a day-ahead market (DAM). DAM Trading Platform delivered in Feb Traders training conducted in RSA, 6-10 Nov Market trials commenced from 10 April v. TRANSMISSION PRICING AND ANCILLARY SERVICES A method of loss compensation developed by a Consultant is under consideration by SAPP. The SAPP is also reviewing the wheeling charge methodology. 36
37 vi. REGIONAL ELECTRICITY INVESTMENT CONFERENCE (REIC) SAPP co-hosted with RERA the REIC in Namibia, Sept Over 250 delegates attended the conference. Aim was to attract investors into the SADC power sector iii. SAPP TARIFF STUDY SAPP has secured funding from DBSA to do the study. The study is from 10 April to 10 August vii. ENVIRONMENTAL GUIDELINES The SAPP approved the following guidelines: Guidelines on EIA for Thermal Power Plants EIA Guidelines for Transmission Lines within SAPP Guidelines on the Management of Oil Spills SAPP Position on Climate Change 37
38 TANK YOU 38
The Southern African Power Pool. Meeting growing power demands through Southern African regional integration
he Southern African Power Pool www.sapp.co.zw Meeting growing power demands through Southern African regional integration Johnson Maviya Southern African Power Pool SAREE/IRENA Workshop, Windhoek Namibia
More informationTrading in the Southern African Power Pool and possible coupling with the East African Power Pool
Trading in the Southern African Power Pool and possible coupling with the East African Power Pool Mr Willem Theron International Trader Manager Eskom, South Africa EAPIC 2007 Conference Addis Ababa, Ethiopia
More informationEast African Power Industry Convention 2007, Addis Ababa, ETHIOPIA
Pan African Electrical Interconnection and Power rade By Dr. Fatma Moustafa, Dr. Babiker Ibrahim, Dr. azem anafi, Mr. Jelal Shafi Eastern Nile echnical Regional Office Nile Basin Initiative East African
More informationSAPP DEMAND AND SUPPLY SITUATION
No. Country Utility YEAR 2007 STATISTICS Table 1 : Installed vs Peak Demand Survey SAPP DEMAND AND SUPPLY SITUATION Installed Capacity [MW] Available Capacity [MW] 2007 Peak Demand [MW] As at Feb 2008
More informationIntroduction to SAPP. Omar Vajeth Head SAPP: Project Advisory Unit. 23 June Snr. Transaction Advisor SOUTHERN AFRICAN POWER POOL
Introduction to SAPP Omar Vajeth ead SAPP: Project Advisory Unit Snr. Transaction Advisor 23 June 2016 1 Contents 1. Introduction to the SAPP 2. Project advisory unit 3. SADC market status 4. Current/planned
More informationRealistic Assessment of SADC Energy Demand and Supply Up to By Prof M Elmissiry ENERGY SECTOR NEPAD, Midrand South Africa
Realistic Assessment of SADC Energy Demand and Supply Up to 2015 By Prof M Elmissiry ENERGY SECTOR NEPAD, Midrand South Africa PRESENTATION OUTLINES 1-SAPP UTILITIES CURRENT SUPPLY /DEMAND SITUATION 2-PROJECTED
More informationENERGY INVESTMENT OPPORTUNITIES PRESENTATION. By Remmy Makumbe, Director, Infrastructure and Services
ENERGY INVESTMENT OPPORTUNITIES PRESENTATION By Remmy Makumbe, Director, Infrastructure and Services THE SCRUMBLE FOR TICAD IVPLEDGES THE SCRUMBLE FOR TICAD IV PLEDGES SWAPs typically have six components:
More informationPOTENTIAL FOR COMMERCIAL
POTENTIAL FOR COMMERCIAL WIND FARMS IN SAPP Cape Town, SOUTH AFRICA 12-14 May 2010 CONTENTS 1. Installed and Available Capacity 2. Power situation in SAPP 3. Generation options available 4. Wind Power
More informationEnergy opportunities in southern Africa. Wim Jonker-Klunne Programme Director Energy & Environment Partnership
Energy opportunities in southern Africa Wim Jonker-Klunne Programme Director Energy & Environment Partnership Introduction Global trends Regional trends Focus on South Africa Conclusions Global trends
More informationDeveloping a competitive market for regional electricity cross border trading: The case for the Southern African Power Pool
Developing a competitive market for regional electricity cross border trading: he case for the Southern African Power Pool Dr. L. Musaba, P. Naidoo, W. Balet and A. Chikova SAPP Coordination Centre, 17th
More informationPumped Storage Schemes & imported hydroelectricity
Pumped Storage Schemes & imported hydroelectricity Date 11 May 2011 Role of pumped storage Ingula Pumped Storage Scheme Some important design criteria ydropower potential in Southern Africa Frans Louwinger
More informationRestructuring of the Electricity Industry: Experience of Southern Africa
Restructuring of the Electricity Industry: Experience of Southern Africa By Nomalanga Sithole (Ms) Executive Manager, NERSA Elijah C. Sichone Executive Secretary, RERA 1 Presentation for the 3rd ECOWAS
More informationALAN GOLDING ANALYTIKA HOLDINGS (PTY) LTD. Exploration Management, BOTSWANA
ALAN GOLDING ANALYTIKA OLDINGS (PTY) LTD Exploration Management, BOTSWANA World Coal July 2014 The challenges in the development of Botswana s coal resources. Where is Botswana? Gabon Congo Dem Rep of
More informationMONTHLY REPORT Issue No. R02-18 February 2018
Southern African Power Pool Energising the region for economic development 1 MONTHLY REPORT Issue No. R02-18 February CONTENTS Meetings, Workshops and Conferences.. 1 50 th SAPP Management Committee Meetings...
More informationSADC Enabling Infrastructure Initiative. Infrastructure Support for Deepening Regional Integration and Poverty Reduction in the SADC Region
SADC Enabling Infrastructure Initiative Infrastructure Support for Deepening Regional Integration and Poverty Reduction in the SADC Region 1 SADC - JAPAN COOPERATION IN INFRASTRUCTURE DEVELOPMENT Together
More informationDEVELOPMENT. Challenges and Opportunities. 9/5/2008 eapic 2008 Nairobi 1
REGIONAL DEVELOPMENT INFRASTRUCTURE Challenges and Opportunities 9/5/2008 eapic 2008 Nairobi 1 CONTENTS Introduction Regional Cooperation Generation Resources Existing and Future Power Systems Implementation
More informationNational Accounts Workshop for SADC countries
ESA/STAT/AC.184/21 National Accounts Workshop for SADC countries 16-19 June 2009, Windhoek, Namibia Strengthening statistical capacity-building in support of progress towards the Internationally Agreed
More informationRegional Investment rules in Eastern and Southern Africa
Regional Investment rules in Eastern and Southern Africa : COMESA Common Investment Area (CCIA) towards the Tripartite COMESA-EAC-SADC and Pan African investment arrangements London, 14 September 2012
More informationJosephine Tsele Divisional Executive International Division
Josephine Tsele Divisional Executive International Division Transport more than a strategy.a development necessity.. Transport 15 landlocked countries with high transport costs. Missing Road connections
More informationEnergy Poverty in Africa
African Energy Commission (AFREC) Paper on Energy Poverty in Africa By Dr. Gilbert NZOBADILA Consultant Energy Policy- AFREC 1 1- Introduction: African background : The African Energy Commission (AFREC)
More informationREPUBLIC OF ZAMBIA SPEECH BY HER HONOUR THE VICE-PRESIDENT OF THE REPUBLIC OF ZAMBIA MRS. INONGE MUTUKWA WINA, MP
REPUBLIC OF ZAMBIA SPEECH BY HER HONOUR THE VICE-PRESIDENT OF THE REPUBLIC OF ZAMBIA MRS. INONGE MUTUKWA WINA, MP AT THE INVESTOR CONFERENCE FOR THE BATOKA GORGE HYDRO ELECTRIC SCHEME, HELD ON 30TH MARCH,
More information`Density of GDP TEXT BOX. GDP per square kilometre
`Density of GDP TEXT BOX GDP per square kilometre The world at night Light indicates development? Southern Africa State of Cities Finances 2007 Tshwane Ekurhuleni Johannesburg Mangaung Msunduzi ethekwini
More informationTrade Facilitation Conference on New Trends in Trade Facilitation. June 16, Dominique Njinkeu
Trade Facilitation Conference on New Trends in Trade Facilitation June 16, 2011 Dominique Njinkeu Structure Introduction: Connect to compete Performance measurement : Transport Corridors: observatory Border
More informationBenefits of Integrating into a Regional Power Pool
EASTERN AFRICA POWER POOL Benefits of Integrating into a Regional Power Pool Ephrem Tesfaye Power Economist Eastern Africa Power Pool (EAPP) ETHIOPIA The Eastern African Power Pool (EAPP) The Energy Ministers
More informationREPORT ON WHO STAFF IN THE AFRICAN REGION. Information Document CONTENTS
10 July 2009 REGIONAL COMMITTEE FOR AFRICA ORIGINAL: ENGLISH Fifty-ninth session Kigali, Republic of Rwanda, 31 August 4 September 2009 Provisional agenda item 9.5 REPORT ON WHO STAFF IN THE AFRICAN REGION
More informationASHGABAT, TURKMENISTAN
Republic of Zambia MINISTRY OF TRANSPORT AND COMMUNICATIONS STATEMENT BY H.E. BRIAN MUSHIMBA MINISTER OF TRANSOPORT AND COMMUNICATION, REPUBLIC OF ZAMBIA AND GLOBAL CHAIR OF THE GROUP OF LLDCS Delivered
More information4 th Africa Regional Meeting of the Collaborative Arrangement for the Prevention and Management of Public Health Events in Civil in Civil Aviation
International Civil Aviation Organization 4 th Africa Regional Meeting of the Collaborative Arrangement for the Prevention and Management of Public Health Events in Civil in Civil Aviation Ouagadougou,
More informationREPORT ON HUMAN RESOURCES IN WHO IN THE AFRICAN REGION. Information Document CONTENTS INTRODUCTION... 1
AFR/RC56/INF.DOC/3 12 July 2006 REGIONAL COMMITTEE FOR AFRICA ORIGINAL: ENGLISH Fifty-sixth session Addis Ababa, Ethiopia, 28 August 1 September 2006 Provisional agenda item 10.4 REPORT ON HUMAN RESOURCES
More informationCOMESA VACANCIES OFFICE OF THE SECRETARY GENERAL
COMESA VACANCIES OFFICE OF THE SECRETARY GENERAL VACANCY NOTICE I. EXECUTIVE SECRETARY OF COMESA CLEARING HOUSE II. DIRECTOR OF COMESA MONETARY INSTITUTE Background The Common Market for Eastern and Southern
More informationEconomic Partnership Agreements (EPA) Lucia BALOGOVA European Commission Directorate-General Trade
Economic Partnership Agreements (EPA) Lucia BALOGOVA European Commission Directorate-General Trade 1 Overview Background Ambitions and objectives Challenges Key development aspects EPA scope Alternatives
More informationCatchment and Lake Research
LARS 2007 Catchment and Lake Research Multilateral versus bilateral agreements for the establishment of river based organizations: comparison of legal, economic and social benefits in the Zambian experience.
More informationSTATUS OF THE COMESA SEED HARMONISATION PROGRAMME (COMSHIP) John Mukuka, COMESA Seed Development Expert. June, 2018
STATUS OF THE COMESA SEED HARMONISATION PROGRAMME (COMSHIP) John Mukuka, COMESA Seed Development Expert. June, 2018 COMESA COVERAGE Size: 11.6 Million sq. km Population: 510 million (2018) GDP: $950 billion
More informationAFSEC Workshop Johannesburg 27 March 2017
Evah Oduor IEC-AFRC Director AFSEC Workshop Johannesburg 27 March 2017 INTERNATIONAL ELECTROTECHNICAL COMMISSION About the IEC Africa Quality Infrastructure IEC-AFRC Mission Recommendations Conclusion
More informationMONITORING INFORMAL CROSS- BORDER TRADE IN STAPLE FOODS IN SOUTHERN AFRICA
MONITORING INFORMAL CROSS- BORDER TRADE IN STAPLE FOODS IN SOUTHERN AFRICA A collaborative activity between WFP and FEWS NET Presented at the FAO/University of Pretoria Workshop on Government and Private
More informationSADC Harmonised Consumer Price Indices (HCPI) February 2017
News Release Issue No. 66 SADC Harmonised Consumer Price Indices (HCPI) February 2017 SADC Secretariat Telephone: (267) 3951863 Directorate -Policy Planning and Resource Mobilization Telefax: (267) 3972848/3181070
More informationSADC Harmonised Consumer Price Indices (HCPI) March 2017
News Release Issue No. 67 SADC Harmonised Consumer Price Indices (HCPI) March 2017 SADC Secretariat Telephone: (267) 3951863 Directorate -Policy Planning and Resource Mobilization Telefax: (267) 3972848/3181070
More informationZambia by Numbers. Foreign Exchange Reserves $1.892 Billion (Dec.2013) Public Debt as a % of GDP 36% (2013)
. Area: 752,614km 2 (39 th ) Population: 14.1 million (71 st ) GDP (PPP): $24.714 billion Per Capita: $1,752 GDP Growth Rate 6.6% 2013 Trade Export: $10.434bn 2013 (f.o.b) Import: $9.414bn Foreign Exchange
More informationAfrica. Display Transparency 6 on the overhead. Explain to students that Africa is the
3S 4S 1S 2S 3N 4N Banjul Bissau SIERRA LEONE 5N MADEIRA IS. CANARY IS. (SPAIN) (disputed) Dakar Freetown (PORTUGAL) GAMBIA Bamako Conakry Monrovia Rabat BURKINA FASO 1W Accra Lomé ~ Niamey BENIN Algiers
More informationSADC Harmonised Consumer Price Indices (HCPI) September 2017
News Release Issue No. 73 SADC Harmonised Consumer Price Indices (HCPI) September 2017 SADC Secretariat Telephone: (267) 3951863 Directorate -Policy Planning and Resource Mobilization Telefax: (267) 3972848/3181070
More informationSTATEMENT FROM THE NINTH SOUTHERN AFRICA REGIONAL CLIMATE OUTLOOK FORUM (SARCOF-9) HELD IN HARARE, ZIMBABWE FROM 7 8 SEPTEMBER 2005.
STATEMENT FROM THE NINTH SOUTHERN AFRICA REGIONAL CLIMATE OUTLOOK FORUM (SARCOF-9) HELD IN HARARE, ZIMBABWE FROM 7 8 SEPTEMBER 2005. 1.0 SUMMARY During the period October to December 2005, northern DRC
More informationAfrica the potential for growth
Africa the potential for growth Ian Taylor President & CEO, Vitol March 2015 The oil price a long term view 2010 to date - $94 2000s - $49.6 1980s - $25.8 1990s - $18.3 1970s $10.5 1 Q1-14 Q2-14 Q3-14
More informationSevere weather in Africa and impact of current telecom capability on Early Warning Systems
WMO Severe weather in Africa and impact of current telecom capability on Early Warning Systems WMO African severe weather demonstration projects success and limitations Abdoulaye Harou (WMO)/ David Thomas
More informationThe Second Japan-Africa Business Forum TICAD and Business: Feedback from the Yokohama Action Plan to the Nairobi Declaration July 25, 2017
The Second Japan-Africa Business Forum TICAD and Business: Feedback from the Yokohama Action Plan to the Nairobi Declaration July 25, 207 Takeshi Osuga Ambassador, Assistant Minister, Director-General
More informationafrica s hospitality market
africa s hospitality market Year in Review 2016 Ghana Nigeria Ethiopia Addis Ababa Kenya In this issue 3 Introduction Windhoek Zambia Lusaka Gabarone Pretoria Dar es Salaam Hahare Namibia Zimbabwe Botswana
More informationREPORT ON WHO STAFF IN THE AFRICAN REGION. Information Document CONTENTS
6 September 2013 REGIONAL COMMITTEE FOR AFRICA ORIGINAL: ENGLISH Sixty-third session Brazzaville, Republic of Congo, 2 6 September 2013 Agenda item 20.1 REPORT ON WHO STAFF IN THE AFRICAN REGION Information
More informationTechnical Report: RERA Publication on Electricity Tariffs & Selected Performance Indicators for the SADC Region
Technical Report: RERA Publication on Electricity Tariffs & Selected Performance Indicators for the SADC Region SATH Submitted by: AECOM International Development Submitted to: USAID/Southern Africa August
More informationPower sector challenges and investment trends in Africa
Power sector challenges and investment trends in Africa Presentation to the Board of Norfund Cape Town 23 January 2015 Prof Anton Eberhard Graduate School of Business University of Cape Town @AntonEberhard
More information2015 CRS ICT4D CONFERENCE INTRODUCING THE BANDWIDTH AGGREGATION BUYING PROGRAM
2015 CRS ICT4D CONFERENCE INTRODUCING THE BANDWIDTH AGGREGATION BUYING PROGRAM InsideNGO and NetHope s first connectivity demand-aggregation program, implemented by Hutchison Global Communications (HGC)
More information182ND SESSION OF THE COUNCIL
International Civil Aviation Organization FI-WP/675 19/11/07 WORKING PAPER 182ND SESSION OF THE COUNCIL FINANCE COMMITTEE Subject No. 3 Financial matters for consideration and approval by the Finance Committee
More informationPRIORITIZED ROAD CORRIDOR TRANSPORT PROJECTS
PRIORITIZED ROAD CORRIDOR TRANSPORT PROJECTS Ali KIES African Development Bank ICA Senior Level Meeting January 18, 2007 Berlin, Germany Why Regional Transport Infrastructure? REGIONAL AND INTERNATIONAL
More informationData Limitations. Index Choices
Section 3. Annexes The Index is part of a central database and system for collecting data on regional integration. It will capture additional data for indicators that are not part of the Index but that
More informationResolving Non Tariff Barriers and Creating Transparency, Lessons Learnt from the Tripartite Experience
Resolving Non Tariff Barriers and Creating Transparency, Lessons Learnt from the Tripartite Experience Non Tariff Measures Week : MAST and VSS Meeting Presented by Vonesai Shuvirai Hove Tripartite NTBs/NTMs
More informationTanzania s Transport Hub: What Prospects for Regional Integration and Investment? 22 NOVEMBER 2016, JOHANNESBURG, CHELSEA MARKOWITZ
Tanzania s Transport Hub: What Prospects for Regional Integration and Investment? 22 NOVEMBER 2016, JOHANNESBURG, CHELSEA MARKOWITZ OUTLINE 1. Current Condition of Transport Infrastructure in Tanzania
More informationICAO/AFCAC Regional Symposium on Airport & Air Navigation Services Infrastructure Financing Maputo, Mozambique
ICAO/AFCAC Regional Symposium on Airport & Air Navigation Services Infrastructure Financing Maputo, Mozambique 29 Nov 1 Dec 2010 Session 3: International Cooperation COMESA-EAC- SADC Tripartite Experience
More informationSADC SELECTED ECONOMIC AND SOCIAL INDICATORS, 2016
SADC SELECTED ECONOMIC AND SOCIAL INDICATORS, 2016 1. INTRODUCTION This report is an attempt to provide data series and a brief trend analysis of the major socio-economic characteristics of SADC region
More informationMeeting of Energy Regulators for the Launch of the Association of Energy Regulators for Eastern and Southern Africa
Distr. LIMITED CS/ID/RAERESA/II/5 March 2009 Original: ENGLISH COMMON MARKET FOR EASTERN AND SOUTHERN AFRICA Meeting of Energy Regulators for the Launch of the Association of Energy Regulators for Eastern
More informationEARTHQUAKE HAZARD ZONES - AFRICA
GAP.15.2.3.1 A Publication of Global Asset Protection Services LLC EARTHQUAKE HAZARD ZONES - AFRICA Algeria Hazard Zones... 1,2,3,4,5,6 Algiers... 6 Oran... 5 Constantine... 5 100 Constitution Plaza, Hartford,
More informationBridging the Gap: Benchmarking Utilities in Africa
Bridging the Gap: Benchmarking Utilities in Africa Rosemary Rop World Water Week Stockholm, Focus Africa: August 23 rd 2011 Water and Sanitation Program Global Status: Water and Sanitation Access Gaps
More informationMonthly inflation rates (%) for SADC, April April 2012
Apr11 May11 Jun11 Jul11 Aug11 Sep11 Oct11 Nov11 Dec11 Jan12 Feb12 Mar12 Apr12 Monthly change (%) Stage I SADC Harmonised Consumer Price Indices (HCPI) April 2012 News Release Issue No. 9 SADC Secretariat
More informationCHINGOLA-SOLWEZI-JIMBE RAILWAY LINE
From a landlocked to a land linked Zambia CHINGOLA-SOLWEZI-JIMBE RAILWAY LINE Presented by Ministry of Transport Works Supply and Communications and October 2013 Presented to PUBLIC-PRIVATE DIALOGUE FORUM
More informationnortheast group, llc Sub- Saharan Africa Electricity Metering: Market Forecast ( ) May group.com
northeast group, llc Sub- Saharan Africa Electricity Metering: Market Forecast (2014 2024) May 2014 www.northeast- group.com Sub- Saharan Africa Electricity Metering: Market Forecast (2014-2024) Sub- Saharan
More informationMEETING OF SADC MINISTERS RESPONSIBLE FOR TRANSPORT & METEOROLOGY
MEETING OF SADC MINISTERS RESPONSIBLE FOR TRANSPORT & METEOROLOGY COMMUNIQUE LILONGWE, MALAWI 3 NOVEMBER 2017 Page1 1. Background The 2017 edition of the SADC meeting of Ministers responsible for Transport
More informationSTATEMENT FROM THE EIGHTEENTH SOUTHERN AFRICA REGIONAL CLIMATE OUTLOOK FORUM (SARCOF-18), WINDHOEK, NAMIBIA, AUGUST 2014.
STATEMENT FROM THE EIGHTEENTH SOUTHERN AFRICA REGIONAL CLIMATE OUTLOOK FORUM (SARCOF-18), WINDHOEK, NAMIBIA, 27 29 AUGUST 2014. SUMMARY Southern African Development Community (SADC) is likely to receive
More informationSupporting Road Infrastructure Development to Connect Africa: Actions to be taken under the TICAD Process and Japan s Initiatives
Supporting Road Infrastructure Development to Connect Africa: Actions to be taken under the TICAD Process and Japan s Initiatives Hajime Ueda Principal Deputy Director, Country Assistance Planning Division,
More informationUNCOVERING THE SADC RETAIL OPPORTUNITY. Vicus Bouwer Divisional Director Retail Leasing Africa Broll Property Group
UNCOVERING THE SADC RETAIL OPPORTUNITY Vicus Bouwer Divisional Director Retail Leasing Africa Broll Property Group OVERVIEW Despite an economic slowdown in Mozambique, Zambia, Botswana development in and
More informationJICA s activity in the Northern Economic Corridor. 7 Dec 2015, Nairobi
JICA s activity in the Northern Economic Corridor 7 Dec 2015, Nairobi Contents 1. Japan s commitment on corridor development 2. On-going support on corridor development 3. JICA s activity on Northern Economic
More informationHCPI COMESA Monthly News Release
HCPI COMESA Monthly News Release Is sue No. 84 March 2018 Common Market for Eastern and Southern Africa (COMESA) Macroeconomic Indicators COMESA region annual inflation rate stood at 19.4% in March 2018
More informationTHE TWENTY FIRST ANNUAL SOUTHERN AFRICA REGIONAL CLIMATE OUTLOOK FORUM
STATEMENT FROM THE TWENTY FIRST ANNUAL SOUTHERN AFRICAN REGIONAL CLIMATE OUTLOOK FORUM (SARCOF-21), MASA CONFERENCE CENTRE, GABORONE, BOTSWANA, 23 25 AUGUST 2017. SUMMARY The bulk of Southern African Development
More information1. International Conventions 2. South African Legislation 3. Swaziland Legislation
A. Legal context WATER FOR EVER 1. International Conventions 2. South African Legislation 3. Swaziland Legislation B. Evolution of KOBWA 1. Treaties 2. Evolution Stages 3. Main Objectives 4. Need for Bi-national
More informationEnsuring water and sanitation for all Where are we?
Ensuring water and sanitation for all Where are we? CABRI Peer Review Workshop (Anglophone) on WASH, June 2018 Cape Town Dr Nana Boateng, CABRI Goal 6: Ensure availability and sustainable management of
More informationSouthern African Development Community (SADC) Grain Trade What does the data say?
15 October 2015 Southern African Development Community (SADC) Grain Trade What does the data say? Tinashe Kapuya (Agbiz Head: International Trade and Investment) and Wandile Sihlobo (Economist at Grain
More informationAccelerating Economic Growth in Africa
Accelerating Economic Growth in Africa Japan International Cooperation Agency Africa Department Director General Kazunori Oshiyama Strategies for Accelerating Economic Growth Major Corridors and Japan
More informationINFRASTRUCTURE DEVELOPMENT IN TANZANIA
INFRASTRUCTURE DEVELOPMENT IN TANZANIA PROF JOSEPH MSAMBICHAKA MBEYA UNIVERSITY OF SCIENCE AND TECHNOLOGY 50 TH YEARS ERB ANNIVERSARY 5 TH TO 7 TH SEPTEMBER 2018 PRESENTATION LAYOUT 1. DEFINITION OF INFRASTRUCTURE
More informationTRIPARTITE FREE TRADE AREA: PROSPECTS AND CHALLENGES. 14 OCTOBER 2016 Presented by Fudzai Pamacheche
TRIPARTITE FREE TRADE AREA: PROSPECTS AND CHALLENGES 14 OCTOBER 2016 Presented by Fudzai Pamacheche Coverage Introduction Current State of Play in Each REC Current State of Play in Tripartite Prospects
More informationWALVIS BAY CORRIDOR GROUP
WALVIS BAY CORRIDOR GROUP CROSS BORDER INFRASTRUCTURE: Role of Transport Corridors in Deepening Integration SACU Conference JULY 2011 WALVIS BAY CORRIDOR GROUP Joint PPP of logistics providers REGIONAL
More informationECONOMIC PARTNERSHIP AGREEMENTS. Overview of State of Play
ECONOMIC PARTNERSHIP AGREEMENTS Overview of State of Play Following the expiry of the Cotonou trade regime and the WTO waiver which covered it on 31 December 2007, trade disruption for the ACP was minimised
More informationGermany s bilateral development cooperation with Sub-Saharan Africa: An Agenda for Reform
Germany s bilateral development cooperation with Sub-Saharan Africa: An Agenda for Reform Limited share of development cooperation in the context of donors ODA net payments (incl. debt r elief ) f or SSA
More informationSERENJE NAKONDE ROAD PROJECT PROJECT
SERENJE NAKONDE ROAD PROJECT PROJECT 2 nd German Africa Infrastructure Forum Munich 3 rd -4 th December 2014 Eng. Amos Phiri Contracts Manager (PPIU COMESA-EAC-SADC TRIPARTITE) Serenje Nakonde Road Project
More informationTrade Blocs, Development Hotspots and Changing Trade Patterns. Breakbulk Africa, 18 th February 2015
Trade Blocs, Development Hotspots and Changing Trade Patterns Breakbulk Africa, 18 th February 2015 Background Multiplicity of Trade Blocs in ever convergent economic spaces; Need for harmonisation of
More informationTHE MOST AND LEAST CHILD-FRIENDLY GOVERNMENTS IN AFRICA
The Most and Least Child-friendly Governments in Africa 5 THE MOST AND LEAST CHILD-FRIENDLY GOVERNMENTS IN AFRICA We must put the best interests of children at the heart of all political and business decision-making,
More informationOrgans of ARIPO Protocols Harare + Banjul Process of ARIPO joining Madrid Protocol Challenges Way Forward. Conclusion
Current status on Accession to the Madrid system for ARIPO. by F.K Mpanju Examiner, ARIPO Secretariat Presentation overview ARIPO Background Organs of ARIPO Protocols Harare + Banjul Process of ARIPO joining
More informationOSBP Development and Operationalization in Africa
4th WCO Global AEO Conference 15 March 2018, Kampala, Uganda OSBP Development and Operationalization in Africa Tomomi TOKUORI, TICAD Advisor assigned to DBSA Japan International Cooperation Agency (JICA)
More informationTHE AFRICAN DEVELOPMENT BANK GROUP. At the centre of Africa s transformation
THE AFRICAN DEVELOPMENT BANK GROUP At the centre of Africa s transformation African Development Bank Group At the centre of Africa s transformation The African Development Bank Group is a multilateral
More informationSouth-South cooperation in sub-saharan Africa: Lessons learned from the conservation / tourism trade dilemma
South-South cooperation in sub-saharan Africa: Lessons learned from the conservation / tourism trade dilemma South-South Cooperation Conference on SCP Brasília 6 April 2017 Manuel Bollmann South-South
More informationSpecial Note: Upcoming Group Visits:
Weekly Bulletin, 04 Special Note: Upcoming Group Visits: 05 October Richards Bay Day Visit 08 to 13 October Zambia Group Visit 12 to 17 Group Visit Angola US$97.9 million budgeted for Luanda and Benguela
More informationCURRENT STATUS OF CAPP PROJECTS
( C. A. P. P. ) A PECIALIZED BODY OF THE ECONOMIC COMMUNITY OF CENTRAL AFRICAN STATES (ECCAS) African Utility Week 18 22 May 2009 CTICC, Cape Town South Africa CURRENT STATUS OF CAPP PROJECTS By KAPANDJI
More informationTransCentury AGM Presentation 29 May 2014 INVESTING IN AFRICA
TransCentury AGM Presentation 29 May 2014 INVESTING IN AFRICA Where we are today: TransCentury s Infrastructure Focus What we achieved in 2013: Highlights and Financial Performance What has happened since
More informationAir Transport: An Engine to Prosperity
Air Transport: An Engine to Prosperity Mark Smyth Senior Economist, IATA To represent, lead and serve the airline industry Africa in a Global Economic Context Relatively low shares of GDP, trade and air
More informationCAPSCA Africa Achievements
International Civil Aviation Organization COOPERATIVE ARRANGEMENT FOR THE PREVENTION OF SPREAD OF COMMUNICABLE DISEASE THROUGH AIR TRAVEL (CAPSCA) Third Global Coordination and Fourth CAPSCA Americas Meetings
More informationOutlıne of the Presentatıon
Outlıne of the Presentatıon Background and Objectives What has been achieved National Perspective Regional Perspective Estimated Financing Requirements What is Needed Chingola-Solwezi-Jimbe Railway Line
More informationAIRLIFT STRATEGY PRESENTATION TO INDUSTRY GROWTH & SAFETY CONFERENCE: DATE: NOVEMBER 2014
AIRLIFT STRATEGY PRESENTATION TO INDUSTRY GROWTH & SAFETY CONFERENCE: DATE: 04-06 NOVEMBER 2014 Table of Contents Section 1 Section 2 Section 3 Section 4 INTRODUCTION & EXECUTIVE SUMMARY OBJECTIVES MANDATE
More informationReport on the 1st Year Activities. Sei KONDO Secretariat of the African Clean Cities Platform
Report on the 1st Year Activities Sei KONDO Secretariat of the African Clean Cities Platform Summary of the 1st Year Activities 1. Setting up the foundation The secretariat established, Action plan set
More informationEntrepreneurial Universities and Private Higher Education Institutions
Entrepreneurial Universities and Private Higher Education Institutions Professor Moses Oketch University College London, Institute of Education m.oketch@ucl.ac.uk Presentation at International Seminar
More informationSADC PPP Network PPPs in SADC
SADC PPP Network PPPs in SADC Kogan Pillay Head: SADC PPP Network German Africa Investment Conference Munich December 6 th, 2013 SADC DFRC, Botswana What is the SADC PPP Network» Created by the Ministers
More informationGlobal IP Infrastructure
Study Visit: Intellectual Property Focal Persons of the African Regional Economic Communities and Executive Bodies of the African Union Global IP Infrastructure Gregory Sadyalunda Project Manager IP Office
More informationTHE AFRICAN DEVELOPMENT BANK GROUP. At the centre of Africa s transformation
THE AFRICAN DEVELOPMENT BANK GROUP At the centre of Africa s transformation African Development Bank Group The African Development Bank Group is a multilateral development finance institution. It was established
More information2008 SADC Year of Free Trade
SADC 10.4 English 2/29/08 8:19 AM Page 1 POLICY 3 AFRICA 4 ENERGY 5-8 FLOODS 9 BUSINESS 10 EVENTS 11 HISTORY TODAY 12 Energy in southern Africa 4 AS THE demand for electricity in southern Africa surpasses
More informationTHE TWENTIETH ANNUAL SOUTHERN AFRICA REGIONAL CLIMATE OUTLOOK FORUM
STATEMENT FROM THE TWENTIENT ANNUAL SOUTHERN AFRICA REGIONAL CLIMATE OUTLOOK FORUM (SARCOF-20), HARARE INTERNATIONAL CONFERENCE CENTRE, HARARE, ZIMBABWE, 24 26 AUGUST 2016. SUMMARY The bulk of Southern
More informationFinancing Sustainable Transport in LLDCs in Africa High Level Meeting October Santa Cruz, Bolivia
Gylfi Palsson, Lead Transport Specialist and Acting Manager for the LAC Region, World Bank Financing Sustainable Transport in LLDCs in Africa High Level Meeting 13-14 October 2016 - Santa Cruz, Bolivia
More informationPPIAF Assistance in Swaziland
PPIAF Assistance in Swaziland July 2012 In 2002 PPIAF support was provided to the government of Swaziland to assess the regulatory, legal, and institutional framework necessary to concession Swaziland
More information