1 2.5 AVALANCHE MTGATON General considerations Several alternative forms of avalanche mitigation are in use around the world. The selection of the best form of avalanche protection in a given area depends on reliability, cost, and environmental factors. n summary, the various forms are listed below. a. Supporting structures. These are fences or rakes built in the avalanche starting zone on slopes steeper than 300. They anchor the snow to the ground and prevent avalanche release. They tend to be very expensive (> $300,000 per acre) and would'not be appropriate above Aspendell because of the very high cost of erecting structures in the remote starting zones. The upper starting zone area is estimated at approximately 30 acres, therefore total construction cost could be as high as $9,000,000..} " b. Deflecting structures. These are built in the upper runout zone and usually take the form of earthen or structural guide walls intended to change avalanche direction, generally through angles of less than 200. They could be used to reduce the hazard above the eastern portion of Aspendell where most damage has occurred historically, but they may increase the runout distance toward the Cardinal Road intersection and increase the hazard to buildings here. Therefore deflecting structures should not be used. c. Catching structures. These are usually earthen dams or fields of mounds built in a checker-board array i the upper runout zone. They are intended to reduce avalanche velocity and shorten the runout distance. With careful design they would be appropriate in reducing avalanche hazard above Aspendell. See Section for details. d. Direct-protection structures. These consist of reinforcing individual buildings for avalanche impact and deposition loads. They could be used at Aspendell, but design of such structures requires determination of expected avalanche forces and dimensions. They will increase construction costs by ail estimated lo-to-30 percent. See Section for details. e. Artificial avalanche release. This usually consists of delivering explosives to avalanche starting.. 13

2 zones and attempting to release avalanches in reduced volumes. The various explosives-release methods of controlling avalanches are not recommended above developed areas because of the uncertainties associated with this method. Sometimes they do not release avalanches at the time or size intended. Furthermore, avalanches released in this manner will sometimes be much larger than anticipated. Design of avalanche defenses depends on the design-avalanche characteristics. n general, knowledge of avalanche velocity, flow height, density, and impact pressure must be calculated in order to rationally design avalanche defenses. The two recommended forms of avalanche defenses which could be used at Aspendell, both of which depend on these parameters, are discussed below Catchinq structures Catching structures would be effective in reducing avalanche velocity and runout distance on the Aspendell alluvial fan. Figures 2-5 and 2-6 illustrate the locations and sizes of an array of earthen mounds and a catching dam. The proposed sizes and orientations of these structures would prevent avalanches similar to the 1986 event from reaching developed areas. However, an avalanche as large as the potential loo-year avalanche, although slowed considerably by the proposed structures, could overtop the barriers and reach buildings near Alpine Drive with reduced energy. An advantage to the mounddam array shown is the relatively low cost and the availability of local material in the alluvial fan for construction. Construction would, therefore, require no material to be transported to the site. Assuming, as shown on Figures 2-5 and 2-6, 36 mounds each 15 feet high and a 25-foot high dam 1,100 feet long, the approximate volume of earth moved for construction would be 30,000 cubic yards (20,000 yd3 for the dam and 10,000 yd3 for the 36 mounds). This volume estimate assumes a cut-and-fill geometry as indicated in Figure 2-6. Construction cost would depend primarily on local equipment operator rates. Final construction drawings should be completed bya local registered California engineer or surveyor as required by California law. Disadvantages include the obvious visual impact of such a large amount of earthwork immediately above town. Scars from mining activities throughout the mountains attest to the fact that construction activities may require long periods of time to revegette. Furthermore, the mounddam system will not effectively dissipate powder blast which will overrun the earthwork and may cause some damage within the developed area. 14

3 ..:..

4

5 -- (A) EARTHEN MOUNDS - - UNDSTURBED GROUND SURFACE FGURE 2-6. Earthen mounds and a catch dam as shown in (A) and (B) and located in Figure 2-5 would reduce the avalanche hazard at Aspendell by approximately 80%. Fast-moving dry-snowpowder.avalanches could overtop this proposed defense system and reach the upper part of town. Mounds must be built as close together as possible and must have an uphill. "crest-tc-..",t elevation difference of 15 feet. The dam must have an uphill elevation difference of 25 feet. A detailed engineering and soils investigation may be required in any final-design stage. 16

6 2.5.3 Direct-protection structures Direction-protection structures are built immediately up slope from buildings or are incorporated directly into. the design of the building. An example of one type of direct-protection structure at Ketchum, daho, is shown in Figure 2-7. Avalanches reach these duplex structures from the left and will flow up onto the "ramp roofs." The roofs have been specially designed for avalanche impact and deposition loads. This particular design is especially useful because large impact loads on flat surfaces are avoided and the avalanche flow will not be deflected laterally toward adjacent property. This type of design is definitely applicable at Aspendell. Many other forms of direct protection are used throughout the world. The "splitting wedge" design in which the flow energy is dissipated laterally has been used at many loctions where lateral deflection is not a problem. At other locations where avalanche energy is not large, such as the lower end of the runout zone at Aspendell, walls facing the flow can simply be reinforced for avalanche impact and depositional loads. Reinforcing buildings for avalanche loads requires detailed avalanche dynamics calculations and structural engineering design. Design parameters that must be known are a. Building location, shape, and orientation: b. Design-avalanche building site; velocity and energy at the c. The design-avalanche loads "b. " which depend on "a" and n general, design loads must be resolved into 3 mutually perpendicular directions in order for structural details to be specified. Figure 2-8 illustrates the elevation and plan view of a flat surface subject to avalanche loads and lists the factors that corol the magnitude of the avalanche loads. Design-avalanche energy densities are shown on Figure 2-9. The energy densities are equal to kinetic energy per unit volume of avalanche. This energy-density parameter has the units of pressure ([ft-lbs]ft3 = lbsft2), therefore the pressure isobars on Figure 2-9 give a rough idea of the pressure on a structure. We strongly emphasize that these isobar lines are not design pressures. Therefore,they cannot be used directly for design of defense structures or buildings. Figure 2-8 lists the most important factors that must be coidered in direct-protection design. Costs for design and construction of direct protection will consist of the initial avalanche analysis and engineering (an 17

7

8 (A) ELEVATON VEW (B) PLAN VEW A V ALAN CHE DRECTON FGURE 2-. Direct-protection design for avalanches must consider forces in J mutually-perpendicular directions. Pn(normal), Pv(vertical), and p s (lateral shear). n general, these forces will depend on the desinavalanche dynamics and the structure details. Factors that must be considered in design include: * Avalanche velocity; * flow density; * flow height; * deposit geometry; * Snowpack depth at structure; * Structure location; shape; " orientation to avalanche; and * Local terrain irregularities. Because these factors will vary from one case to another, they must always be considered on a site-specific basis. A registered engineer and or architect should be consulted in final design. Ramp structures such as shown in Figure 2-7 are efficient in dissipating avalanche energy, therefore design loads are minimized. Vertical walls normal to the flow generally receive maximum loads. 19

9 , (? 1.,,.., N.., ). J {:'.(, -, :, i!j i',.,. "')!.,"il,-'--, (.!i', ill " V.Ui V: irl {) "-J ', ), --.: "' -., ( ), lj -,,, 'cl, A"','i '. """'.'-"' (' '6, - (:{ 9''( C,, :..( J., i 'z" ; '1 : ' ' U,'-.( r, -) ' ' J, ::: -1,,, " 1. ' i,1 ' '. J.(..,. ' ) f C' '.,! J ", '!, ;,. ', {.f ', i '! 1" ' ( ;',. -; f ;-;. ;: J. : :;.-,... -,.1. (. r ;- )J,(.-",---V ',-, i, );!X fj ),;.. r,......:..7 (..)-, r.!:..:::r.1 f. ($ ') c! 1(!' ( r ' jr. ' r n.'., a '...'... ; r,., " : "., ) -'-1::,; '!,..,1 t i, ' }..0 ; '- ),.rl'.. " ' j -,., :.-!!1-; :,, -, ;., 4!!, f --,:, '.!.., Vn '., J,, ; :,.,),.,'.. i..., ()1,.:.-; V; t.,. 1'1-=-.:..:"-C-..V '?''.:.. 1., ('..,. ) --! ), f J,, i i ( 11! '' ' t l ;" il '",,,..r!,-.; 1, H ),!!,1 1 ( i,,,.!.'! ' ) J,, ) '" ; 1 1 t u ". (.,,. 8 l ',! ",., L. '.., -L "' c"-- :.r -., {.- ( ) 1- J -, ' '!, "-"'! )! -..,!:...-'... ), ' J ( C.-,..; r,.:- '; ;.!i:f(( }, t : ' ' J, ""' :,,! '; f;;,-, ; "",,, ' ""', '., J.) '! :, )!., ) """" i.'., J : li.',,.,., ' ', " ";"-,, J. i 9', ( 'lir((.,, '.- 1, ',,-. f'- ) - :., '"," ' J, 'f },. ;:J ;' 1' )! ',, l'ijj ".. ' 1, " '- 5&, '1, ', ' f (..j,. :if : 'J,J J' f! -,...,. ; c'"... " 1 '1 '.....) ', : "" V.! J.":,',, --,. ' 1 ;'' ), J,,..,,,:,'. ; ',. CJ 1? r ' ',. v..! (.., '11 r-(.j)--."..c' (,,,,... ( { i ', ' :0 A.;.r '!0.'. : c,j r--". )t :''.)' c '.;. ),,,.t( )!1 T - )i,...."",. ',.1.."",;,. '.. i F, " -.,.. :, :!'P x' ',",,,...'.J.',-..)'.,.'.) (..,,...,'.',,- -..'..., ",.,,...-- x.1 ',.,-,, -.,,.i '. )' ' 1,...,..,,;J.! ".",.. J --,.;'..,,, -- -:>,...r,." ',) r- " ' r '.. -,' '.,.r -, -.,- f,;""'" "... '!' ;.),(. '.,'.' ".. :1 : L;: '., 0', '.,...' '.-- -, " v'.' :! '. i.., " ",." ' r '". :,...' '..., f!".. ',. l.,6.-rl, :,.Dl 1,- ", ;:: v r(,.'5,;:', )0, ' : 1 i ("-;. (; :.J-l-' '.. r -- ) :.c,.,..> "' c n ;= r <., # " O u 10;..P.'...,..,. r: C - "' "'.,. -, -=.J, ' "",,='<..,...;!.-" -..;, - -.,,d"1- > <..." " c c < "1 ".,. -..c o..., a c,.. "1 "..= " ". "-..0." "..". c ". c... c c C' '1.-, o <,..c =.,..", " -c c-..'--="'1 0-"..c ::: )C :.. " "1 '<,. --"., a a "1... -" C' 0 O.." <, " " r:.,. ::-.. " - 0., C " '< n o o."',.., P C.. ::- C > - '<... " " ".. C,c. 'i " =. n..'1 " :....,. c.-c - 0 "!"... c c..= = ::- " 0 " -..2., ".,

10 ; engineer registered in California must be involved in design), and the additional construction costs. These costs will be highly dependent on the individual project, but may add lo-to-30% to the building cost... ") 21

a. The historic avalanche areas, or areas in which there exists clear evidence of previous avalanches, are mapped.

a. The historic avalanche areas, or areas in which there exists clear evidence of previous avalanches, are mapped. 1 OBJECTIVES AND LIMITATIONS OF STUDY ;J'-o~ 1 j 1.1 BACKGROUND AND STUDY OBJECTIVES The communities of Aspendell, Habegger's, and Sage Flat are located in the eastern Sierra Nevada west of the towns of

More information

DESIGN-MAGNITUDE AVALANCHE MAPPING AND MITIGATION ANALYSIS KIRKWOOD RESORT, CALIFORNIA -- AN UPDATED STUDY. Prepared For. Mr.

DESIGN-MAGNITUDE AVALANCHE MAPPING AND MITIGATION ANALYSIS KIRKWOOD RESORT, CALIFORNIA -- AN UPDATED STUDY. Prepared For. Mr. 0 ----- )11.eCtfS t QQ'7 0 f-ieceivel) P,mador County MAR 0 3 2003 PLANNING DEPARTMENT DESIGN-MAGNITUDE AVALANCHE MAPPING AND MITIGATION ANALYSIS KIRKWOOD RESORT, CALIFORNIA -- AN UPDATED STUDY Prepared

More information

SHEET PILE WALLS A SPACE-SAVING AVALANCHE DEFENCE STRUCTURE

SHEET PILE WALLS A SPACE-SAVING AVALANCHE DEFENCE STRUCTURE SHEET PILE WALLS A SPACE-SAVING AVALANCHE DEFENCE STRUCTURE ÁRNI JÓNSSON, ORION Consulting Engineers * ERIK HESTNES, Norwegian Geotechnical Institute** ABSTRACT: Steel sheet piles, primarily used as retaining

More information

Structural Avalanche Defenses Chris Wilbur, P.E. Wilbur Engineering, Inc. SW Colorado Chapter ASCE February 15, 2012

Structural Avalanche Defenses Chris Wilbur, P.E. Wilbur Engineering, Inc. SW Colorado Chapter ASCE February 15, 2012 Structural Avalanche Defenses Chris Wilbur, P.E. Wilbur Engineering, Inc. SW Colorado Chapter ASCE February 15, 2012 Outline Design Avalanche Types of Structures Deflecting/Diversion Dams & Retarders Snowsheds

More information

Section 3-04 Cross Sectional Elements TABLE OF CONTENTS. INTRODUCTION...3 General...3 Exhibit 1-Cross-Sectional Elements...3

Section 3-04 Cross Sectional Elements TABLE OF CONTENTS. INTRODUCTION...3 General...3 Exhibit 1-Cross-Sectional Elements...3 Section 3-04 Cross Sectional Elements TABLE OF CONTENTS INTRODUCTION...3 General...3 Exhibit 1-Cross-Sectional Elements...3 CROSS-SECTIONAL ELEMENTS...3 Traveled Way...3 Shoulder...3 Surfacing Taper...3

More information

Avalanche Protection. Safety without Compromise

Avalanche Protection. Safety without Compromise Avalanche Protection Safety without Compromise Photo: Adobe Stock jancsi hadik Photo: Adobe Stock wakr10 Trumer Schutzbauten designs, produces and sells solutions for protection against natural hazards

More information

Guidelines for Snow Avalanche Risk Determination and Mapping. David McClung University of British Columbia

Guidelines for Snow Avalanche Risk Determination and Mapping. David McClung University of British Columbia Guidelines for Snow Avalanche Risk Determination and Mapping David McClung University of British Columbia Why do we need guidelines? Costs: 14 fatalities/year, $0.5 M/year property damage, $10 M/year avalanche

More information

Proceedings, 2012 International Snow Science Workshop, Anchorage, Alaska

Proceedings, 2012 International Snow Science Workshop, Anchorage, Alaska I-90 SNOQUALMIE PASS: OPERATING A HIGHWAY AVALANCHE PROGRAM DURING A MAJOR CONSTRUCTION PROJECT John Stimberis, Washington State Department of Transportation ABSTRACT: Snoqualmie Pass, WA (921m) receives

More information

INTERACTION OF FLEXIBLE ROCKFALL BARRIERS WITH AVALANCHES AND SNOW PRESSURE. Stefan Margreth* 1 and Andrea Roth 2

INTERACTION OF FLEXIBLE ROCKFALL BARRIERS WITH AVALANCHES AND SNOW PRESSURE. Stefan Margreth* 1 and Andrea Roth 2 INTERACTION OF FLEXIBLE ROCKFALL BARRIERS WITH AVALANCHES AND SNOW PRESSURE Stefan Margreth* 1 and Andrea Roth 2 1 WSL Swiss Federal Institute for Snow and Avalanche Research (SLF), Davos Dorf, Switzerland

More information

THRESHOLD GUIDELINES FOR AVALANCHE SAFETY MEASURES

THRESHOLD GUIDELINES FOR AVALANCHE SAFETY MEASURES BRITISH COLUMBIA MINISTRY OF TRANSPORTATION & INFRASTRUCTURE AVALANCHE & WEATHER PROGRAMS THRESHOLD GUIDELINES FOR AVALANCHE SAFETY MEASURES British Columbia Ministry of Transportation & Infrastructure

More information

Submitted to: NYX CAPITAL CORP. 1131a Leslie Street, Suite 201 Toronto, Ontario M3C 3L8 Attention: Mr. Tim Jessop Development Manager

Submitted to: NYX CAPITAL CORP. 1131a Leslie Street, Suite 201 Toronto, Ontario M3C 3L8 Attention: Mr. Tim Jessop Development Manager New Development Setback Assessment in Proximity to Railway Corridor Orangeville Brampton Railway Proposed Residential Development at 12 Henderson Avenue, Brampton, Ontario Submitted to: NYX CAPITAL CORP.

More information

RESEARCH AND DEVELOPMENT PERTAINING TO STEEL WIRE ROPE NET SYSTEMS FOR THE PREVENTION OF SNOW AVALANCHES1. Robert A. Thommen, Jr.

RESEARCH AND DEVELOPMENT PERTAINING TO STEEL WIRE ROPE NET SYSTEMS FOR THE PREVENTION OF SNOW AVALANCHES1. Robert A. Thommen, Jr. RESEARCH AND DEVELOPMENT PERTAINING TO STEEL WIRE ROPE NET SYSTEMS FOR THE PREVENTION OF SNOW AVALANCHES1 Robert A. Thommen, Jr. 2 Avalanches are most effectively prevented using support structures installed

More information

OCCURRENCE CONDITIONS OFTWO CATASTROPHIC AVALANCHES AT CHAMONIX, FRANCE. Franyois RAPIN and Christophe ANCEy l Cemagref, France

OCCURRENCE CONDITIONS OFTWO CATASTROPHIC AVALANCHES AT CHAMONIX, FRANCE. Franyois RAPIN and Christophe ANCEy l Cemagref, France OCCURRENCE CONDITIONS OFTWO CATASTROPHIC AVALANCHES AT CHAMONIX, FRANCE Franyois RAPIN and Christophe ANCEy l Cemagref, France ABSTRACT: In February 1999, in Chamonix, France, a large avalanche destroyed

More information

Report Tómas Jóhannesson Þorsteinn Arnalds Leah Tracy. Results of the 2D avalanche model SAMOS for Ísafjörður and Hnífsdalur

Report Tómas Jóhannesson Þorsteinn Arnalds Leah Tracy. Results of the 2D avalanche model SAMOS for Ísafjörður and Hnífsdalur Report 02018 Tómas Jóhannesson Þorsteinn Arnalds Leah Tracy Results of the 2D avalanche model SAMOS for Ísafjörður and Hnífsdalur VÍ-ÚR13 Reykjavík June 2002 -3- BACKGROUND The 2D avalanche model SAMOS,

More information

Part 1: Introduction to Decision Making

Part 1: Introduction to Decision Making Part 1: Introduction to Decision Making 1.1 - Anatomy of a Decision ABOUT AIARE Learning Outcomes Identify that backcountry decision making involves five key components: Plan, Observe, Teamwork, Choose

More information

Wingsuit Design and Basic Aerodynamics 2

Wingsuit Design and Basic Aerodynamics 2 WINGSUIT DESIGN AND BASIC AERODYNAMICS 2 In this article I would like to expand on the basic aerodynamics principles I covered in my first article (Wingsuit Flying Aerodynamics 1) and to explain the challenges

More information

CATCODE ] CATCODE

CATCODE ] CATCODE Runways. FAC: 1111 CATCODE: 111111 OPR: AFCEC/COS OCR: AF/A3O-A 1.1. Description. The runway is the paved surface provided for normal aircraft landings and take offs. Runways are classified as either Class

More information

along a transportation corridor in

along a transportation corridor in Rockfall hazard and risk assessment along a transportation corridor in the Nera Valley, Central Italy Presentation on the paper authored by F. Guzzetti and P. Reichenbach, 2004 Harikrishna Narasimhan Eidgenössische

More information

Installation Instructions for the Rolltec Bravo Awning

Installation Instructions for the Rolltec Bravo Awning Installation Instructions for the Rolltec Bravo Awning Questions? Call Rolltec at 1-800-667-0474 Table of Contents Available installation brackets Side dimensions of various installations Determining installation

More information

PROPOSED AVALANCHE CONTROL ALTERNATIVES STANLEY AVALANCHE, BERTHOUD PASS, COLORADO' Horst Ueblacleer, P.E. 2 ABSTRACT

PROPOSED AVALANCHE CONTROL ALTERNATIVES STANLEY AVALANCHE, BERTHOUD PASS, COLORADO' Horst Ueblacleer, P.E. 2 ABSTRACT PROPOSED AVALACHE COTROL ALTERATIVES STALEY AVALACHE, BERTHOUD PASS, COLORADO' Horst Ueblacleer, P.E. 2 ABSTRACT This paper covers a study to compare the feasibility of constructing avalanche sheds and

More information

Safer Steps from Sloping Sidewalks

Safer Steps from Sloping Sidewalks PDHonline Course A126 (2 PDH) Safer Steps from Sloping Sidewalks Instructor: Kenneth LiDonnici, P.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088

More information

NOISE ABATEMENT PROCEDURES

NOISE ABATEMENT PROCEDURES 1. Introduction NOISE ABATEMENT PROCEDURES Many airports today impose restrictions on aircraft movements. These include: Curfew time Maximum permitted noise levels Noise surcharges Engine run up restrictions

More information

International Snow Science Workshop

International Snow Science Workshop PASSIVE AVALANCHE DEFENSE FOR A DOMESTIC TRANSPORTAION APPLICATION: THE MILEPOST 151 AVALANCHE, JACKSON, WYOMING Josh Hewes*, Northern Arizona University, Flagstaff, Arizona Rand Decker, Northern Arizona

More information

Post earthquake rockfall protection resilience for a lifeline transmission pylon in Christchurch

Post earthquake rockfall protection resilience for a lifeline transmission pylon in Christchurch Riding, J.P & Woods, D.J (2017) Post earthquake rockfall protection resilience for a lifeline transmission pylon in Christchurch Proc. 20 th NZGS Geotechnical Symposium. Eds. GJ Alexander & CY Chin, Napier

More information

SLOPE CALCULATION. Wilderness Trekking School 1

SLOPE CALCULATION. Wilderness Trekking School 1 SLOPE CALCULATION By Joe Griffith, February 2014 Objectives Upon completion of this chapter, you will be able to: Read the rise-over-run from a topographic map. Convert the rise-over-run into a slope angle

More information

FUTENMA REPLACEMENT FACILITY BILATERAL EXPERTS STUDY GROUP REPORT. August 31, 2010

FUTENMA REPLACEMENT FACILITY BILATERAL EXPERTS STUDY GROUP REPORT. August 31, 2010 FUTENMA REPLACEMENT FACILITY BILATERAL EXPERTS STUDY GROUP REPORT August 31, 2010 MANDATE AND SCOPE OF WORK: In order to achieve the earliest possible relocation of Marine Corps Air Station Futenma, the

More information

Introduction...COMB-2 Design Considerations and Examples...COMB-3

Introduction...COMB-2 Design Considerations and Examples...COMB-3 SECTION DIRECTORY General Information Introduction...COMB-2 Design Considerations and Examples...COMB-3 Combination Assembly Recommendations and Limitations Composite Configurations...COMB-4 Typical Sealant

More information

Installation Instructions for the Rolltec Physique XL Awning

Installation Instructions for the Rolltec Physique XL Awning Installation Instructions for the Rolltec Physique XL Awning Questions? Call Rolltec at 1-800-667-0474 General Tool Requirements Table of Contents Available installation brackets Side dimensions of various

More information

Avalanche Observations

Avalanche Observations Avalanche Observations Avalanche Observations 3.1 Introduction Observations of past and present avalanche activity are of the utmost importance for any avalanche forecasting operation. These data should

More information

URBAN DESIGN REPORT. Proposed Residential Development, Old Church Road, Caledon East

URBAN DESIGN REPORT. Proposed Residential Development, Old Church Road, Caledon East Proposed Residential Development, Old Church Road, Caledon East TABLE CONTENTS: 1.0 DEVELOPMENT 1.1 Introduction-Analysis of Guiding Principles and Documents 1.2 Community Design and Architectural Design

More information

A TECHNICAL MANUAL FOR ASSESSING, MAPPING AND MITIGATING SNOW AVALANCHE RISK

A TECHNICAL MANUAL FOR ASSESSING, MAPPING AND MITIGATING SNOW AVALANCHE RISK A TECHNICAL MANUAL FOR ASSESSING, MAPPING AND MITIGATING SNOW AVALANCHE RISK Bruce Jamieson 1*, Ryan Buhler 2, Cam Campbell 3, Michael Conlan 4, Brian Gould 3, Greg Johnson 5, Alan Jones 2, Grant Statham

More information

Reduction of Wave Runup on a Revetment by Addition of a Berm

Reduction of Wave Runup on a Revetment by Addition of a Berm REMR Technical Note CO-RR-1.3 (Supersedes CO-RR-1.3 1986) Reduction of Wave Runup on a Revetment by Addition of a Berm Purpose To provide design guidance for reducing wave runup on a riprap revetment by

More information

Natural Factors Affecting the Level of Osoyoos Lake

Natural Factors Affecting the Level of Osoyoos Lake Natural Factors Affecting the Level of Osoyoos Lake Background Osoyoos Lake is operated under conditions prescribed by the International Joint Commission (IJC) and Figure 1 shows the ranges within which

More information

Trail Phasing Plan. Note: Trails in the Clear Creek Canyon area (Segments will be finalized in the future to minimize wildlife impacts

Trail Phasing Plan. Note: Trails in the Clear Creek Canyon area (Segments will be finalized in the future to minimize wildlife impacts Note: Trails in the Clear Creek Canyon area (Segments 2 5 and a future JCOS connection) will be finalized in the future to minimize wildlife impacts Trail Phasing Plan P Parking 3 Easy Trail Intermediate

More information

Installation Instructions for the Rolltec Adalia X3M Extenda Awning

Installation Instructions for the Rolltec Adalia X3M Extenda Awning Installation Instructions for the Rolltec Adalia X3M Extenda Awning Questions? Call Rolltec at 1-800-667-0474 General Tool Requirements Table of Contents Available installation brackets Side dimensions

More information

Northeast Stoney Trail In Calgary, Alberta

Northeast Stoney Trail In Calgary, Alberta aci Acoustical Consultants Inc. 5031 210 Street Edmonton, Alberta, Canada T6M 0A8 Phone: (780) 414-6373, Fax: (780) 414-6376 www.aciacoustical.com Environmental Noise Computer Modelling For Northeast Stoney

More information

THOMPSON PASS AVALANCHE MITIGATION STUDY 138 KV TRANSMISSION LINE. Final FOR THE SOLOMON GULCH

THOMPSON PASS AVALANCHE MITIGATION STUDY 138 KV TRANSMISSION LINE. Final FOR THE SOLOMON GULCH THOMPSON PASS AVALANCHE MITIGATION STUDY FOR THE SOLOMON GULCH 138 KV TRANSMISSION LINE Final June 2011 Table of Contents Executive Summary... 2 Background and Objectives... 2 Mitigation Options... 6 Evaluation

More information

MEMORANDUM. Lynn Hayes LSA Associates, Inc.

MEMORANDUM. Lynn Hayes LSA Associates, Inc. MEMORANDUM To: Lynn Hayes LSA Associates, Inc. Date: May 5, 217 From: Zawwar Saiyed, P.E., Senior Transportation Engineer Justin Tucker, Transportation Engineer I Linscott, Law & Greenspan, Engineers LLG

More information

Excelsior Pass Avalanche Accident January 1, 2008

Excelsior Pass Avalanche Accident January 1, 2008 Excelsior Pass Avalanche Accident January 1, 2008 Accident Summary Time: 1 January 2008, approximately 13:00 hrs Location: Near Excelsior Pass to east of Church Mt, Northern Washington Cascades WA Activity:

More information

TUPPER DESIGNATED ACCESS ROUTE

TUPPER DESIGNATED ACCESS ROUTE TUPPER DESIGNATED ACCESS ROUTE 1 FOR ACCESS/EGRESS TO CONNAUGHT, LOOKOUT, STONE ARCH, PORTAL PATHS AND TUPPER TRAVERSE EGRESS Length: 2.6km Vertical Gain: +162m / -83m (Values are for access. For egress,

More information

GCAA ADVISORY CIRCULAR

GCAA ADVISORY CIRCULAR GUYANA CIVIL AVIATION AUTHORITY 73 High Street Kingston Georgetown GUYANA TEL. NOs: (592) 225 6822, 225 0778, 227 8111 FAX: (592) 225 6800 E-mail: director-general@gcaa-gy.org GCAA ADVISORY CIRCULAR AERODROME

More information

Henderson Mountain Avalanche Accident Two riders caught, one partially buried, one fully buried

Henderson Mountain Avalanche Accident Two riders caught, one partially buried, one fully buried Henderson Mountain Avalanche Accident Two riders caught, one partially buried, one fully buried Custer-Gallatin National Forest 28 November 2014 Synopsis A group of 6 or 7 snowmobilers (part of a larger

More information

Runway Roughness Evaluation- Boeing Bump Methodology

Runway Roughness Evaluation- Boeing Bump Methodology FLIGHT SERVICES Runway Roughness Evaluation- Boeing Bump Methodology Michael Roginski, PE, Principal Engineer Boeing Airport Compatibility Engineering ALACPA X Seminar, Mexico City, Mexico September 30-

More information

Airport Master Plan Update June 15, 2017

Airport Master Plan Update June 15, 2017 Airport Master Plan Update June 15, 2017 www.harveyfield.com The Master Plan is a 20-year plan to understand the needs of current and future users of the Airport. This is important to ensure that safe

More information

Airport Master Plan Update June 15, 2017

Airport Master Plan Update June 15, 2017 Airport Master Plan Update June 15, 2017 www.harveyfield.com The Master Plan is a 20-year plan to understand the needs of current and future users of the Airport. This is important to ensure that safe

More information

Runway Roughness Evaluation- Boeing Bump Methodology

Runway Roughness Evaluation- Boeing Bump Methodology FLIGHT SERVICES Runway Roughness Evaluation- Boeing Bump Methodology Michael Roginski, PE, Principal Engineer Boeing Airport Compatibility Engineering ALACPA X Seminar, Mexico City, Mexico September 3-

More information

American Avalanche Association Forest Service National Avalanche Center Avalanche Incident Report: Long Form

American Avalanche Association Forest Service National Avalanche Center Avalanche Incident Report: Long Form American Avalanche Association Forest Service National Avalanche Center Avalanche Incident Report: Long Form Please send to: CAIC; 325 Broadway WS1; Boulder CO 80305; caic@qwest.net; Fax (303) 499-9618

More information

MP : the top of the bottom switchback

MP : the top of the bottom switchback MP 237 238: the top of the bottom switchback For reference this section of U S Highway 40 has been called the top of the bottom switchback on the Grand County side of the Pass. It is here that the proposed

More information

International Snow Science Workshop

International Snow Science Workshop A PRACTICAL USE OF HISTORIC DATA TO MITIGATE WORKER EXPOSURE TO AVALANCHE HAZARD Jake Elkins Jackson Hole Mountain Resort, Teton Village, Wyoming Bob Comey* Jackson Hole Mountain Resort, Teton Village,

More information

Twin Lakes Avalanche Incident 1/31/2016

Twin Lakes Avalanche Incident 1/31/2016 Twin Lakes Avalanche Incident 1/31/2016 Location: Place State Published by: Dave Bingaman (PAC), George Halcom (PAC), and Kent May (PAC) Twin Lakes, Salmon River Mountains Idaho Date 01/31/2016 Time Summary

More information

Proceedings, International Snow Science Workshop, Banff, 2014

Proceedings, International Snow Science Workshop, Banff, 2014 AVALANCHE MITIGATION MEASURES FOR SIGLUFJÖRÐUR REALIZATION OF THE LARGEST PROJECT WITH SNOW SUPPORTING STRUCTURES IN ICELAND Stefan Margreth 1 *, Tómas Jóhannesson 2 and Hrafnkell Már Stefánsson 3 1 WSL

More information

NWAC Blog. Cornices - don't walk the line! Written by Robert Hahn on March 14, Last update on May 15, 2017.

NWAC Blog. Cornices - don't walk the line! Written by Robert Hahn on March 14, Last update on May 15, 2017. NWAC Blog Cornices - don't walk the line! Written by Robert Hahn on March 14, 2017. Last update on May 15, 2017. Human-triggered cornice fall avalanche from March 10th, 2017. The crown release exposed

More information

SYNOPSIS WEATHER AND SNOWPACK

SYNOPSIS WEATHER AND SNOWPACK Peak 6996 Avalanche Fatality Incident Report Glacier National Park, MT Date of Avalanche: 31 March 2010 Date of Investigation: 2 April 2010 Investigation Team: Erich Peitzsch (USGS), Ted Steiner (Chugach

More information

New PFC Application #13

New PFC Application #13 PUBLIC CONSULTATION New PFC Application #13 Buffalo, NY December 16, 2015 Agenda PFC Program at Notice to Carriers and Consultation Meeting Class of Carrier Not Required to Collect PFC Air Carrier Requirements

More information

Blocking Sea Intrusion in Brackish Karstic Springs

Blocking Sea Intrusion in Brackish Karstic Springs European Water 1/2: 17-23, 3. 3 E.W. Publications Blocking Sea Intrusion in Brackish Karstic Springs The Case of Almiros Spring at Heraklion Crete, Greece A. Maramathas, Z. Maroulis, D. Marinos-Kouris

More information

SNOW AVALANCHE AVOIDANCE POLICY 2011

SNOW AVALANCHE AVOIDANCE POLICY 2011 SNOW AVALANCHE AVOIDANCE POLICY 2011 BC Public Service Natural Resource Sector For General Wilderness Activities Acknowledgements: Kevin Fogolin R.P.F./Qualified Avalanche Planner (Island Alpine Consulting

More information

Aspen Skiing Company Policy for Use of Other Power-Driven Mobility Devices And Service Animals

Aspen Skiing Company Policy for Use of Other Power-Driven Mobility Devices And Service Animals Aspen Skiing Company Policy for Use of Other Power-Driven Mobility Devices And Service Animals Introduction New rules under the Americans with Disabilities Act (ADA), Titles II and III, went into effect

More information

Typical avalanche problems

Typical avalanche problems Typical avalanche problems The European Avalanche Warning Services (EAWS) describes five typical avalanche problems or situations as they occur in avalanche terrain. The Utah Avalanche Center (UAC) has

More information

Airport Obstruction Standards

Airport Obstruction Standards Airport Obstruction Standards Dr. Antonio Trani Department of Civil and Environmental Engineering Virginia Tech Outline of this Presentation Obstructions to navigation around airports Discussion of Federal

More information

2016 Snowcraft Course Information

2016 Snowcraft Course Information 2016 Snowcraft Course Information Dates Beginner 21 st 23 rd July, 28 th 30 th July, 18 th 20 th August Intermediate 18 th 20 th August, 25 th 27 th August Advanced 25 th 27 th August Beginner Course Information

More information

Montana Canvas Tent Structure Design

Montana Canvas Tent Structure Design Montana Tech Library Digital Commons @ Montana Tech Proceedings of the Annual Montana Tech Electrical and General Engineering Symposium Student Scholarship 2016 Montana Canvas Tent Structure Design Eric

More information

MP : Blue Hill and the Disney Avalanche Path

MP : Blue Hill and the Disney Avalanche Path MP 252-253: Blue Hill and the Disney Avalanche Path This section of the Auto Tour includes a portion of the wagon road, one of Colorado s most famous avalanches and the remains of an old dam. Route Mile

More information

AIRCRAFT ACCIDENT REPORT AND EXECUTIVE SUMMARY

AIRCRAFT ACCIDENT REPORT AND EXECUTIVE SUMMARY Section/division Accident and Incident Investigations Division Form Number: CA 12-12a AIRCRAFT ACCIDENT REPORT AND EXECUTIVE SUMMARY Aircraft Registration Type of Aircraft Reference: CA18/2/3/9350 ZU-UBB

More information

CFIT-Procedure Design Considerations. Use of VNAV on Conventional. Non-Precision Approach Procedures

CFIT-Procedure Design Considerations. Use of VNAV on Conventional. Non-Precision Approach Procedures OCP-WG-WP 4.18 OBSTACLE CLEARANCE PANEL WORKING GROUP AS A WHOLE MEETING ST. PETERSBURG, RUSSIA 10-20 SEPTEMBER 1996 Agenda Item 4: PANS-OPS Implementation CFIT-Procedure Design Considerations Use of VNAV

More information

When should a hazard map show the risk of small avalanches or snow gliding?

When should a hazard map show the risk of small avalanches or snow gliding? When should a hazard map show the risk of small avalanches or snow gliding? Stefan Margreth* WSL Institute for Snow and Avalanche Research SLF, Davos, Switzerland ABSTRACT: Avalanche hazard maps describe

More information

Tahoe National Forest Over-Snow Vehicle Use Designation

Tahoe National Forest Over-Snow Vehicle Use Designation Tahoe National Forest Over-Snow Vehicle Use Designation USDA Forest Service Tahoe National Forest February 20, 2015 Introduction The Forest Service, U.S. Department of Agriculture will prepare an Environmental

More information

Avalanche Protection for Construction Site

Avalanche Protection for Construction Site Avalanche Protection for Construction Site Thomas Rentsch 1 and Ruedi Stüssi 2 1 tytec AG, Ennenda, Switzerland 2 NOK, Linthal, Switzerland ABSTRACT: Linthal 2015 is as more than 1.5 billion project in

More information

BLASTING GLACIAL ICE AND SNOW ABSTRACT

BLASTING GLACIAL ICE AND SNOW ABSTRACT BLASTING GLACIAL ICE AND SNOW HERB BLEUER ABSTRACT This presentation, with the aid of slides, is about methods of blasting large quantities of glacial ice and snow. The project illustrated here involved

More information

Slot Couloir Accident, Snoqualmie Mt

Slot Couloir Accident, Snoqualmie Mt Body Page 1 Slot Couloir Accident, Snoqualmie Mt 4-27-14 Date and Time: estimated 12 pm, Sunday 4/27/14 Location: Slot Couloir, Snoqualmie Mt Number in Party: 2 backcountry skiers Number hurt: 1 backcountry

More information

I507 Devonport Naval Base Precinct

I507 Devonport Naval Base Precinct I507. Devonport Naval Base I507.1. Precinct Description The Devonport Naval Base precinct covers most of the land held by the Crown for the HMNZ Naval Base (south yard) in Devonport. It incorporates the

More information

Dallas Executive Airport

Dallas Executive Airport 648 DECLARED DISTANCE OPTION 1a DISPLACE 31 THRESHOLD BY 97 Considers RSA Limiting Factor No runway extensions 13 31 TORA 6,451 6,451 TODA 6,451 6,451 ASDA 5,958 6,451 LDA 5,958 6,354 Runway 17-35 (3,8

More information

Guidelines for Snowmobile Trail Signing and Placement STOP SLOW

Guidelines for Snowmobile Trail Signing and Placement STOP SLOW Guidelines for Snowmobile Trail Signing and Placement STOP SLOW Table of Contents 1.0 Introduction... 2 6.0 Examples of Sign Use...7 2.0 Purpose of this Document... 2 3.0 Trail Signing Guidelines... 2

More information

Guide Training Ski TAP APPLICATION PACKAGE. Hello and thank you for your interest in applying to the ACMG Training and Assessment Program (TAP).

Guide Training Ski TAP APPLICATION PACKAGE. Hello and thank you for your interest in applying to the ACMG Training and Assessment Program (TAP). Hello and thank you for your interest in applying to the ACMG Training and Assessment Program (TAP). As of April 30, 2018, the ACMG will be running the program for an undetermined period. For any courses

More information

Morning Star Peak Avalanche Accident

Morning Star Peak Avalanche Accident Morning Star Peak Avalanche Accident Saturday, December 4, 2010 Date: 2010-12-13 Submitted by: Oyvind Henningsen Everett Mountain Rescue and Mark Moore NWAC Place: Morning Star Peak, north-central WA Cascades

More information

5 MAP SPECIFICATION FOR SKI-ORIENTEERING

5 MAP SPECIFICATION FOR SKI-ORIENTEERING 5 MAP SPECIFICATION FOR SKI-ORIENTEERING 5.1 General Maps for ski orienteering are based on the specifications for foot-orienteering maps. However in order to meet the specific requirements put on the

More information

Avalanche Hazard Investigations, Zoning, and Ordinances, Utah, Part 2

Avalanche Hazard Investigations, Zoning, and Ordinances, Utah, Part 2 Avalanche Hazard Investigations, Zoning, and Ordinances, Utah, Part 2 David A. Scroggin, Jack Johnson Company L. Darlene Batatian, P.G., Mountain Land Development ABSTRACT: The Wasatch Mountains of Utah

More information

PBN ROUTE SPACING AND CNS REQUIREMENTS (Presented by Secretariat)

PBN ROUTE SPACING AND CNS REQUIREMENTS (Presented by Secretariat) International Civil Aviation Organization The First Meeting of South China Sea Major Traffic Flow Review Group (SCS-MTFRG/1) Kuala Lumpur, Malaysia, 19-20 January 2015 Agenda Item 5: Discuss strategy for

More information

City of Fort Lauderdale. Frequently Asked Questions. Proposed Sea Wall Ordinance

City of Fort Lauderdale. Frequently Asked Questions. Proposed Sea Wall Ordinance City of Fort Lauderdale Frequently Asked Questions Proposed Sea Wall Ordinance The City of Fort Lauderdale is considering amending the Unified Land Development Regulations of the City of Fort Lauderdale

More information

Wake Turbulence Research Modeling

Wake Turbulence Research Modeling Wake Turbulence Research Modeling John Shortle, Lance Sherry Jianfeng Wang, Yimin Zhang George Mason University C. Doug Swol and Antonio Trani Virginia Tech Introduction This presentation and a companion

More information

BUS 2 1. Introduction 2. Structural systems

BUS 2 1. Introduction 2. Structural systems BUS 2 1. Introduction 2. Structural systems 3. Staircases terminology, requirements 4. Staircases structures, historic review 5. Staircases 6. Expansion joints 7. Foundations terminology 8. Foundations

More information

Westover Metropolitan Airport Master Plan Update

Westover Metropolitan Airport Master Plan Update Westover Metropolitan Airport Master Plan Update June 2008 INTRODUCTION Westover Metropolitan Airport (CEF) comprises the civilian portion of a joint-use facility located in Chicopee, Massachusetts. The

More information

Group similar facilities together separate dissimilar facilities.

Group similar facilities together separate dissimilar facilities. Park design Principle #1 Group similar facilities together separate dissimilar facilities. Why do we do this? Safety Differences in admission fees Differences in seasonal use Reduce user conflicts Principle

More information

Going-to-the-Sun Road, Glacier National Park, MT, USA Avalanche Path Atlas

Going-to-the-Sun Road, Glacier National Park, MT, USA Avalanche Path Atlas Going-to-the-Sun Road, Glacier National Park, MT, USA Avalanche Path Atlas Erich H. Peitzsch Daniel B. Fagre USGS Northern Rocky Mountain Science Center West Glacier, MT, USA Introduction... 2 Overview

More information

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis

Appendix B Ultimate Airport Capacity and Delay Simulation Modeling Analysis Appendix B ULTIMATE AIRPORT CAPACITY & DELAY SIMULATION MODELING ANALYSIS B TABLE OF CONTENTS EXHIBITS TABLES B.1 Introduction... 1 B.2 Simulation Modeling Assumption and Methodology... 4 B.2.1 Runway

More information

2.08 AVALANCHE SEARCH AND RESCUE. Q: What is the process to provide feedback on the Interim Policy and Avalanche Safety Plan?

2.08 AVALANCHE SEARCH AND RESCUE. Q: What is the process to provide feedback on the Interim Policy and Avalanche Safety Plan? 2.08.1 RELATED DOCUMENTS 2.08 Avalanche Search and Rescue Policy 2.08 AVALANCHE SEARCH AND RESCUE 2.08.2 FREQUENTLY ASKED QUESTIONS AVALANCHE SAFETY PLANNING Q: Are SAR Groups required to develop their

More information

FORT YORK PEDESTRIAN & CYCLE BRIDGE

FORT YORK PEDESTRIAN & CYCLE BRIDGE FORT YORK PEDESTRIAN & CYCLE BRIDGE November 2006 urban design landscape architecture architecture DTAH This is a new concept for the Fort York Pedestrian and Cycle Bridge linking Stanley Park (South)

More information

City of Rolling Hills INCORPORATED JANUARY 24, 1957

City of Rolling Hills INCORPORATED JANUARY 24, 1957 City of Rolling Hills INCORPORATED JANUARY 24, 1957 NO. 2 PORTUGUESE BEND ROAD ROLLING HILLS, CA 90274 (310) 377-1521 FAX (310) 377-7288 INSTRUCTIONS FOR COMPLETION OF THE LOT COVERAGE FORMS TOTAL STRUCTURES

More information

Wing Taper Ratio. Wing Incidence. Wing Incidence

Wing Taper Ratio. Wing Incidence. Wing Incidence Wing Design II Lift surfaces/devices Control surfaces Ailerons Leading-edge slats Vertical Stabilizer Rudder Spoilers Elevators Flaps Horizontal Stabilizer Wing Wing-tip device Basic Configuration Choices

More information

Using of space technologies for glacierand snow- related hazards studies

Using of space technologies for glacierand snow- related hazards studies United Nations / Germany international conference on International Cooperation Towards Low-Emission and Resilient Societies Using of space technologies for glacierand snow- related hazards studies Bonn,

More information

Runway Roughness Evaluation- Boeing Bump Methodology

Runway Roughness Evaluation- Boeing Bump Methodology FLIGHT SERVICES Runway Roughness Evaluation- Boeing Bump Methodology Michael Roginski, PE, Principal Engineer Boeing Airport Compatibility Engineering ALACPA XI Seminar, Santiago, Chile September 1-5,

More information

Guide to Siting of Seawalls January 13, 2014 by Michael Walther, P.E., D.CE, President - Coastal Tech

Guide to Siting of Seawalls January 13, 2014 by Michael Walther, P.E., D.CE, President - Coastal Tech January 13, 2014 by Michael Walther, P.E., D.CE, President - Coastal Tech mwalther@coastaltechcorp.com Prepared for the Sea Turtle Conservancy http://www.conserveturtles.org/ Introduction Overview: This

More information

Session Best Practices Amendments From Annex14, Volume I Annex 15. Runway Incursions Runway Excursions

Session Best Practices Amendments From Annex14, Volume I Annex 15. Runway Incursions Runway Excursions Session Best Practices Amendments From Annex14, Volume I Annex 15 Runway Incursions Runway Excursions Annex 15 AIP - Member States Report: Installation of ARRESTOR SYSTEMS Location - Runway End Industry

More information

MEETING MINUTES Page 1 of 5

MEETING MINUTES   Page 1 of 5 Page 1 of 5 50178.000 May 26, 2009 PROJECT PROJECT NO. MEETING DATE ISSUE DATE Citizens Advisory Committee Meeting MEETING LOCATION MEETING PURPOSE Amy Eckland ISSUED BY SIGNATURE PARTICIPANT See attached

More information

International Symposium on Mitigation Measures against Snow Avalanches and other Rapid Gravity Mass Flows

International Symposium on Mitigation Measures against Snow Avalanches and other Rapid Gravity Mass Flows ASSOCIATION OF CHARTERED ENGINEERS IN ICELAND International Symposium on Mitigation Measures against Snow Avalanches and other Rapid Gravity Mass Flows Co-sponsored by: Icelandic Avalanche and Landslide

More information

Jumbo Glacier Resort Master Plan Appendix 2-A

Jumbo Glacier Resort Master Plan Appendix 2-A Jumbo Glacier Resort Master Plan Appendix 2-A Avalanche Studies and Reports prepared by P. Schaerer of Stetham & Associates Pheidias Project Management Corp. Copyright June, 2005 JUMBO

More information

PREFACE. Service frequency; Hours of service; Service coverage; Passenger loading; Reliability, and Transit vs. auto travel time.

PREFACE. Service frequency; Hours of service; Service coverage; Passenger loading; Reliability, and Transit vs. auto travel time. PREFACE The Florida Department of Transportation (FDOT) has embarked upon a statewide evaluation of transit system performance. The outcome of this evaluation is a benchmark of transit performance that

More information

DR1. OFFSET MEASUREMENTS OF DISPLACED FEATURES ALONG THE DENALI FAULT AND ERROR CALCULATIONS

DR1. OFFSET MEASUREMENTS OF DISPLACED FEATURES ALONG THE DENALI FAULT AND ERROR CALCULATIONS DR1. OFFSET MEASUREMETS OF DISPLACED FEATURES ALOG THE DEALI FAULT AD ERROR CALCULATIOS The Denali fault trace is marked by a red line in all the photos. Black and white air photos were taken during August

More information

Proceedings, International Snow Science Workshop, Banff, 2014

Proceedings, International Snow Science Workshop, Banff, 2014 TRAVEL ADVICE FOR THE AVALANCHE PROBLEMS: A PUBLIC FORECASTING TOOL Wendy Wagner 1 * and Drew Hardesty 2 1 Chugach National Forest Avalanche Center, Girdwood, Alaska 2 Utah Avalanche Center, Salt Lake

More information

Provincial Railway Technical Standards

Provincial Railway Technical Standards GENERAL: INDEX: The standards and requirements listed in this document are intended for use on provincially regulated railway public grade crossings. These standards are considered the minimum requirements

More information

APPENDIX D: SUSTAINABLE TRAIL DESIGN. APPENDICES Town of Chili Parks and Recreation Master Plan Update

APPENDIX D: SUSTAINABLE TRAIL DESIGN. APPENDICES Town of Chili Parks and Recreation Master Plan Update APPENDIX D: SUSTAINABLE TRAIL DESIGN APPENDICES Town of Chili Parks and Recreation Master Plan Update Sustainable Trail Construction Sustainable trails are defined by the US Forest Service as trails having

More information